HomeMy WebLinkAboutContract 47858-CO1 FORT WORTH City of Fort Worth
Change Order Request CITY SECRETARY
CONTRACT NO. 4vl I
Project Name:1 Water and Sanitary Sewer Replacement Contract 2015 WSM-B,Pt.3 City Sec No.: 47858
Project No.(s): 59601/59607-0600430/070430-83 1 DOE No. 7435 City Proj.No.: 02436
Water and Sanitary Sewer Replacement on Schieffer Street, E.Mulkey Avenue, Colvin Avenue, E.Devitt Street,E.Cantey
Project Description: Street and Alleyway
Contractor:I Conatser Construction TX, LP Change Order# 0 Date: 7/24/2017
City Project Mgr.1 Walter Norwood City Inspector: I Edward Davila
Phone Number: 817-392-5026 Phone Number: 817-223-2268
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $787,321.00 $271,360.00 $1,058,681.00 160
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $787,321.00 $271,360.00 $1,058,681.00 160
Amount of Proposed Change Order $11,180.00 $13,208.00 $24,388.00 45
Revised Contract Amount $798,501.00 $284,568.00 $1,083,069.00 1205
Original Funds Available for Change Orders $52,079.00 $34,140.00 $86,219.00
Remaining Funds Available for this CO $52,079.00 $34,140.00 $86,219.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 2.30%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,323,351.25
Subsequent to water and sanitary sewer main installation on the alleyway, City staff decided to pulverize and overlay the entire street in lieu of
two permanent asphalt repair trenches.This change order will provide the necessary pay items for pulverization and overlay and also allow for
pay times for the deletion of the permanent asphalt repair.
Staff concurs with the contractor's request for 45 additional calendar days for the change order.
1:0l�rl2
� 9i01112gA� _ U'. ''0
A7}
Atm by•
CAS
as6o��ocQ PQy Miry J. ser, i tory
�b G�IG�yS Cb
�d Zt l4 0�6�
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Conaster Construction TX, LP Jesse Martinez
frupecto�,; .. Date Project Manager 4 Date
7 27 17
T (� $ S'
Adff
_ Date. Assistant t _ .
M&C Number NIA M&C Date Approv
H�
7
FORT IVU RT H City of Fort worth
Change Order Additions
Project Name Water and Sanitary Sewer Replacement Contract 2015 WSM-B, Pt.3 City Sec No.: 47858
Project No.(s): 59601/59607-0600430/070430-83 1 DOE No. 7435 City Proj. No.: 02436
Project Water and Sanitary Sewer Replacement on Schieffer Street, E.Mulkey Avenue,Colvin Avenue,E.Devitt Street,E.
Description Cantey Street and Alleyway
Contractor Conatser Construction TX, LP Change Order:=1 Date: 7/24/2017
City Project Mgr. Walter Norwood City Inspector Edward Davila
ADDITIONS
VESCRIFTION _ DEPT Qty Unit UnItCost T< 1
52 Pulverize 8"Asphalt and Stabilization Water 275.00 SY $14.00 $3,850.00
53 Haul Off of Excess Material Water 1.00 LS $4,500.00 $4,500.00
54 Asphalt Overlay 6" Water 275.00 SY $56.00 $15,400.00
55 Mobilization Water 1.00 LS $3,750.00 $3,750.00
27 Pulverize 8"Asphalt And Stabilization Sewer 275.00 SY $14.00 $3,850.00
28 Asphalt Overlay 6" Sewer 275.00 SY $56.00 $15,400.00
29 Mobilization Sewer 1.00 LS $3,750.00 $3,750.00
Water $27,500.00
Sewer $23,000.00
Page 2 of 4 Additions Sub Total 1$50,500.00
e
FORT WORTH City of Fort worth
Change Order Deletions
Project Name Water and Sanitary Sewer Replacement Contract 2015 WSM-B,Pt.3 City Sec No.: 47858
Project No.(s): 59601/59607-0600430/070430-83 DOE No. 7435 City Proj. No.: 02436
Project Description Water and Sanitary Sewer Replacement on Schieffer Street,E.Mulkey Avenue,Colvin Avenue,E.Devitt Street,E.
Cantey Street and Alleyway
Contractor Conatser Construction TX, LP Change Order: [i] Date 7/24/2017
City Project Mgr. Walter Norwood City Inspector: FEdward Davila
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
14 4'Wide Asphalt Pvmt Repair,Residential Water 340.00 LF $48.00 $16,320.00
9 4'Wide Asphalt Pvmt Repair,Residential Sewer 204.00 LF $48.00 $9,792.00
Water $16,320.00
Sewer $9,792.00
Page 3 of 4 Deletions Sub Total $26,112.00
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Page 4 of 4
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Walter Norwood
Name of Employee
Senior Professional Engineer
Title
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX