HomeMy WebLinkAboutOrdinance 22946-09-2017 Ordinance No. 22946-09-2017
AN ORDINANCE INCREASING APPROPRIATIONS IN THE AMOUNT OF $8,870,607.00
IN THE WATER AND SEWER DPN FUND, FROM AVAILABLE FUNDS, FOR SANITARY
SEWER MAIN 257 UPPER AND MIDDLE VILLAGE CREEK PARALLEL RELIEF MAIN,
PART 1 AND OTHER PROJECT COSTS; PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL
ORDINANCES IN CONFLICT HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2016-2017 in the
Budget of the City Manager, there shall also be increased appropriations in the amount of$8,870,607.00 in
the Water and Sewer DPN Fund,from available funds,for Sanitary Sewer Main 257 Upper and Middle Village
Creek Parallel Relief Main, Part 1 and other project costs.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion orjudgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 22394-09-2016 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETA
r `
DouglasW Black Warl J. a
Sr. Assistant City Attorney
ADOPTED AND EFFECTIVE: September 26, 2017
MAYOR AND COUNCIL COMMUNICATION MAP
60M257PI -SJ LOUIS
L JL
LON STEPHENSON RD
� Y
C $"
- a •ih 2. � 'Sg��k�
ARNOLD DRh d• :
D�L
E RD
NEVERA KE *
. ,
Ap
a
p
BLUEBELL DR 61R'ri �• ' t y
Z ' Q ZA
E ENON RD
m i r -
.
SHELBY'RDI e A,'
� - '. �� ��. may„ � _ .*� ;��_ k •s�q i- �' _ „ �.
k I
m
•4- S
rte« �*»M'�x olek s iY i... � "'� �A 1 rL� _ :.! E!` •!. ` �^°7 �. ��.
tv r w
ON R D
:'WILS
FORTWORTH
g,
1
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 9/26/2017 - Ordinance No. 22946-09-2017 7 Resolution No
4852-09-2017
DATE: Tuesday, September 26, 2017 REFERENCE NO.: C-28412
LOG NAME: 60M257P1-SJLOUIS
SUBJECT:
Authorize Execution of a Contract with S.J. Louis Construction of Texas Ltd., in the Amount of
$8,125,899.00 for Sanitary Sewer Main 257 Upper and Middle Village Creek Parallel Relief Main, Part 1,
Provide for Project Costs, Materials Testing and Contingencies for a Total Project Amount of
$8,870,607.00, Adopt Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of
Future Debt and Adopt Appropriation Ordinance (COUNCIL DISTRICT 8)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached resolution expressing official intent to Reimburse Expenditures with proceeds of
future debt for the Sanitary Sewer Main 257 Upper and Middle Village Creek Parallel Relief Main, Part 1
Project;
2. Adopt the attached appropriation ordinance increasing estimated appropriations in the Water and
Sewer DPN Fund in the amount of$8,870,607.00; and
3. Authorize execution of a contract with S.J. Louis Construction of Texas Ltd., Inc., in the amount of
$8,125,899.00 for Sanitary Sewer Main 257 Upper and Middle Village Creek Parallel Relief Main, Part 1.
(City Project No. 01226)
DISCUSSION:
Due to growth in the southeast part of Fort Worth and the wholesale customer cities of Burleson and
Crowley, additional wastewater capacity is required to meet the anticipated demand. The proposed
sanitary sewer main will begin north of Everman-Kennedale-Burleson Road and east of Anglin Drive and
end South of Shelby Road. The alignment generally follows Village Creek for approximately 11,300 linear
feet.
This project was advertised for bids on June 8, 2017 and June 15, 2017 in the Fort Worth Star-Telegram.
On July 27, 2017 the following bids were received:
Bidder _ Amount Time of Completion
S.J. Louis Construction of Texas, Ltd. $8,125,899.00 450 Calendar Days
Thalle Construction Company $8,491,950.40
Oscar Renda Contracting, Inc. $9,198,289.50
Circle C Construction Company $9,281,410.00
Logname: 60M257P1-SJL0UIS Page I of 3
Imountain Cascade of Texas, LLC $9,299,192.00
Ark Construction Services $9,976,343.00
JBar Constructors, Inc. $10,406,353.60
In addition to the contract amount, $582,190.00 is required for project management, material testing and
inspection and $162,518.00 is provided for project contingency.
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer Fund.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation
authority authorized under the Direct Purchase Note (DPN) Program will be used to provide interim
financing for this project until debt is issued. To the extent resources other than the Water and Sewer
portfolio are used to provide interim financing, the Water and Sewer Fund will be charged interest that is
equivalent to the overall rate of return being earned by the City portfolio (currently approximately one-
percent annually). Should the City's portfolio not support the liquidity needed to provide an interim short-
term financing source, another funding source will be required, which could mean issuance of securities
under the DPN Program or earlier issuance of Water and Sewer revenue bonds than is currently planned.
Once debt associated with this project is sold, bond proceeds will be used to reimburse the Water and
Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2017-2021 Five Year Capital Improvement
Plan on January 24, 2017, Mayor and Council Communication (M&C G-18927). This City Council adopted
plan includes this specific project, with funding identified through the DPN program to be reimbursed with
future revenue bonds. In accordance with the provisions of the Financial Management Policy Statement,
Staff anticipates presenting revenue-supported debt issuances to the City Council for consideration within
the next three years. This debt must be issued within approximately three years to provide reimbursement
for these expenses. If that does not occur, the costs will no longer be reimbursable by issuing tax-exempt
debt and the funding source will have to be made whole through budgetary methods. Adoption of this
resolution does not obligate the City to sell bonds, but preserves the ability to reimburse the City from tax-
exempt bond proceeds. associated with this project is sold, bond proceeds will be used to reimburse the
Water and Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement
Resolution.
Construction is anticipated to commence in November 2017 and be completed by February 2019. The
overall project budget is estimated to be $12,103,166.00. This project is part of the Water Department's
Sanitary Sewer Overflow Initiative Program. This project will have no impact on the Water Department's
Operating Budget when complete.
M/WBE OFFICE— S.J. Louis Construction of Texas, Ltd., is in compliance with City's BDE Ordinance by
committing to five percent MBE participation. The City's MBE goal on this project is five percent.
The project is located in COUNCIL DISTRICT 8.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in the Water& Sewer DPN Fund for this project.
The Water& Sewer DPN Fund includes authority of$100,000,000.00 for the purpose of providing interim
funding for Water and Sewer Capital Projects. After this transfer, the balance will be $91,129,393.00.
Funding for the Sanitary Sewer Main 257 Upper and Middle Village Creek Parallel Relief Main, Part 1
Project as depicted in the table below.
Logname: 60M257PI-SJLOUIS Page 2 of 3
Existing Additional
Fund Appropriations Appropriations FP roJect Total*
2016 Water and
Sewer Bond Fund $1,168,700.00 $0.00 $1,168,700.00
56005
Clean Water SRF $442,172.00 $0.00 $442,172.00
Fund 59602
Sewer Capital Fund - $1,621,687.00 $0.00 $1,621,687.00
Legacy 59607
Water & Sewer DPN $0.00 $8,870,607.00 I $8,870,607.00
Fund 56014
Project Total _ $3,232,559.00 F $8,870,607.00 $12,103,166.00
* Numbers rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID Year Chartfield 2
FROM
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID Year Chartfield 2
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Kara Shuror (8819)
Additional Information Contact: John Kasavich (8480)
Logname: 60M257P1-SJLOUIS Page 3 of 3