HomeMy WebLinkAboutContract 49085-CO1 \ 4
CITY SECRETARY q q of S-co
FORT WORTH City of Fort Worth CONTRACT NO.
Change Order Request
Project Name VCWRF Service Waterline Improvemetns-Part A&B,16"&8"Service WL City Sec# 1 49085
Client Project#(s)l City Project#100512;Felix Job No 1837;
Project Village Creek Water Reclamation Facility(VCWRF)Service Waterline Improvements-Part A 16"WL in W 7771
Description and Part B 8"WL in W A Corder and M I Dick Street M&C C-28214;approved on 5/2/2017
Contractorl Felix Construction Company Change Order# Date 1 9/11/2017
City Project Mgr.1 Fadda Goderya,PE City Inspector F Robert walker/Ronald Nason
Dept. Water Totals Select Day Type
Original Contract Amount $562,201.00 $562,201.00 90
Extras to Date
Credits to Date $24,600.00 $24,600.00
Pending Change Orders(in M&C Process)
Contract Cost to Date $537,601.00 $537,601.00 90
Amount of Proposed Change Order $1,425.00 $1,425.00 10
Revised Contract Amount $539,026.00 $539,026.00 100
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $24,600.00 $24,600.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 4.12%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $702,751.25
JMF"T CSI!OMR
The City awarded the contract for$562,201 (M&C C-28214). As part of the original awarded contract,an alternative deduct of$24,600 was
provided to use PVC pipe in lieu of Ductile Iron Pipe(DIP)in the base bid. The City elected to go witth the deductive alternative,reducing the
contrct price to$537,601.
See attached sheets for various details on subsequent contract modifications requests(CMRs)(E, )M #3.
A s by. C-PnNkl-,J. Kayser, City Sec tary
NO M&C Ian UIRI D
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's 071M Name contractor
Felix Construction Company Scott McElwee/Matt Phillipa,-sem << - 10/03/2017
hwedor/Inspedm§g?2n1MDate Project MaiiagerflProgr'a"^r Man.—er, D*
Louis Hund(JQI) Farida Goderya
.a
i Assistant Director(Dept) Date Director, trac`n ent Det) �" ' Date
Chris Harder,PE Kara Shuror
Assistant Qt � Date AssistanI Call�
Doug Black / j Jesus J Chapa . — Q r�-
rtjif i ired)
M&C Number
N/A M&C Date Approved
m r OF'F'ICIAL �: )
CITY SECRETARY
o FT.
WORTH, TX
1
Fr»r NVOR M City of Fort Worth
- �- Change Order Additions
Project Name VCWRF Service Waterline Improvemetns-Part A&B,16"&8"Service WL City Sec# 49085
Client Project# Ci Pro ct#100512;Felix Job No 1837;
Project Description Village Creek Water Reclamation Facility,(VCWRF)Service Waterline Improvements-Part A 16"WL in W R Hardy Avenue and
Part B 8"WL in W A Conder and M I Dick Street(M&C C-28214;approved on 5/2/2017)
Contractor Felix Construction Company Change Order# Date 9I11I2017
City Project Mgr. r Fadda Goderya,PE CityInspector Robert Walker,/Ronald Nason
ADDITIONS
ITEM DEP I yn Units oa
Delete wo b dia an oes an appu enances from scrape of work a er LS -
MR# -Concrete encasement ot 1 PVC pipe for 41 LF Water
Additional Pavement cut work ater
Water 1,425.00
Sub otaAdditions
Change Order Additions Page 2 of 4
3
CMR #1
CITY OF FORT WORTH VILLAGE CREEK WATER RECLAMATION FACILITY
SERVICE WATERLINE IMPROVEMENTS
CITY PROJECT NO.100512
Louis Hund
From: Scott McElwee<scottm@felixconstruction.com>
Sent: Tuesday,June 20,2017 12:31 PM
To: Louis Hund
Cc: Godinez,Gonzalo;Goderya,Farida;Raj Mehta
Subject: VCWRF Service Waterline Improvements-PCO-1 Manhole Credit
Attachments: 1837-PCO 1.pdf
Follow Up Flag: Follow up
Flag Status: Flagged
Categories: VCWRF WL-taskl2
Louis,
Please find attached our credit for the elimination of 2 ea.5'diameter manholes and related materials.We have halved
the 12 x 48 x 72 Styro Poly Pads to compensate for the additional valve box,extension stem, concrete valve box rings,
and labor and equipment expended during the excavation around the chlorine lines and electric duct bank. I hope this
meets your satisfaction.
Should you have any questions or need further information please do not hesitate to call.
Regards,
Scott
Scott McElwee I Project Manager
Felix Construction Company
D: 623.223.5409 r5: 480.299.2967
0: 480.464.0011 F: 480.464.0078
E: scottm(@felixconstruction.com
1326 W.Industrial Dr,Coolidge,A7.95128(corporate)
11140 N.136th.Ave,Surprise,AZ 85379(satellite)
www.felixconstruction.com
1
Construction Cost Summary FELV version 04.15.2013
CONSTRUCTIQN CONAPANY
Project 1 Bid Name: � Company:JQ Engineering
VCWRF Service Waterline Owners Representative: Louis Hund
Improvements Address: 100 Glass Street
Proiect Number(FCC): Dallas,TX 75207
1837 Phone:817-505-4311
E-mail:Ihund(a)geng.com
Description of Work:
Delete 2 ea 5'Diameter Valve Manholes and appurtenances from Scope of work.
Assumptions: Exclusions:
Notes I Other: Owner to Provide:
A.Labor D.Materials
Cat o HoursRate Total Item Quant Cost Total
Principal $ $ From Worksheet 1 LS $ 6,005.60 $ 6,005.60
Project Manager $ $ $
Project Engineer $ $ $
Admin $ $ $
General Superintendent $ $ $
Project Superintendent $ $ Material Subtotal $ 6,005.60
Foreman $ $ Marko Factor 10% $
Craftsman $ $ MATERIAL TOTAL $ 6,005.60
Apprentice I Laborer 46.0 $ 28.50 $ 1,311.00 E.Subcontractors
Labor Subtotal $ 1,311.00 Discipline Quant Cost Total
Markoe Factor 0% $ From Worksheet 1 LS $ $
LABOR TOTAL $ 1,311.00 $ -
B.Felix E ui $
Unit Hours Rate Total Subcontractor Subtotal $
Pick-up $ $ Markup Factor A 0% $
Pick-up wl Tools $ $ ISUBCONTRACTOR TOTAL $
Flatbed Truck $ $ F.Other Direct
Back Hoe 1.0 $ 51.36 $ 51.36 Item Quant Cost Total
Boom Truck $ $ From Worksheet 1 LS $ $
Loader(CAT 950) - $ - $ - $
Dump Truck with driver 1.0 $ 63.36 $ 63.36 Other Subtotal 1 $
Excavator(CAT 325) 4.0 $ 142.94 $ 571.76 Markup Factor 0% $
Water Truck - $ - $ - OTHER DIRECT COST TOTAL $
Compactor CAT $ $ G.FCC Electrical
Ext Reach Forklift $ $ Discipline Quant Cost Total
Grading Tractor(Case 480) $ $ ,Felix Construction Electrical' 10-7s $
Water Wagon $ $ H.Pass Throu h
Jumping Jack $ $ Item Quant Cost Total
Misc Tools I Supplies $ $ From Worksheet 1 LS $ $
Job Trailer $ $ $
Misc Other $ $ Pass Through Subtotal $
Felix Equipment Subtotal $ 686.48
Markup Factor 0% $
FELIX EQUIPMENT TOTAL 1$ 686.48 Subtotal:A+B+C+D+E+F+G+H $ 8,003.08
C.Rental E ui
Unit Unit Rate Total 18ond Rate(%) 0.00% $
From Worksheet 1 LS $ $ Tax Rate % 0.00% $
$ I Credit Card Fee % 0.00% $
$
Rental Subtotal $ SUB TOTAL $ 8,003.08
Markup Factor ft 15% $
RENTAL EQUIPMENT TOTAL $ CONTINGENCY"
( GRAND TOTAL $ 8,003.08
Estimated Duration of Work(Working Days) + TBD
Scott McElwee I Project Manager
Felix Construction Company does not include it's Electrical Division's costs when calculating overall project overhead and marc-up.
DATE: "Work paid for out of Contingency funds will have tax,bond and mark-ups applied at the same rates noted above.
June 20,2017
FELIX CONMUC710N CO.
-�7
VW
QL
CMR #2
CITY OF FORT WORTH VILLAGE CREEK WATER RECLAMATION FACILITY
SERVICE WATERLINE IMPROVEMENTS
CITY PROJECT NO.100512
Louis Hund
From: Goderya,Farida <Farida.Goderya@fortworthtexas.gov>
Sent: Wednesday,September 13,2017 5:29 PM
To: Scott McElwee;Louis Hund
Cc: Walker,Robert;Nason,Ronald A
Subject: RE:VCWRF Service WL Imp-PCO-002 16"Pipe Encasement;OK**
Follow Up Flag: Follow up
Flag Status: Flagged
Categories: VCWRF WL-taskl2
Scott/Louis,
I am not sure, if I gave you my written/email approval for this PCO, nevertheless, here it is...
Summary for documentation purposes:
At one of the location,the newly installed 16" PVC service WL was crossing over the existing 84-inch pipe. The existing
field conditions(not having enough ground cover between pavement 16" pipe) and to maintain appropriate separation
between the two pipes (16" &84") demanded a closer look and field adjustment. The City, Engineer and the Contractor
looked at various options and finally decided to encase the 16" PVC with concrete. I have reviewed the price proposal
and in agreement with additional fund request for the concrete encasement.
Call or email with questions. Regards. Farida
----------------------------------------------------
Farido Goderya, PhD,PE
Senior Project Manager
Fort Worth Water Department
Office: 817-392-8214
Cell: 817-851-4910
Farida.Goderva@fortworthtexas.gov
From:Scott McElwee [mailto:scottm@felixconstruction.com]
Sent:Thursday,June 29,2017 3:03 PM
To: Louis Hund (Ihund@jgieng.com)<Ihund@jgieng.com>
Cc:Goderya, Farida<Farida.Goderya@fortworthtexas.gov>; Raj Mehta<rmehta@jgieng.com>; Godinez,Gonzalo
<Gonzalo.Godinez@fortworthtexas.gov>; Nason, Ronald A<Ronald.Nason@fortworthtexas.gov>
Subject:VCWRF Service Waterline Improvements-PCO-002 16" Pipe Encasement
Louis,
Attached is our change order request for the 16" pipe encasement.As I had mentioned we are not charging overhead
and profit on this work.
Regards,
Scott
Scott McElwee 1 Project Manager
Felix Construction Company
D: 623.223.5409 I M: 480.299.2967
0: 480.464.0011 I F: 480.464.0078
1
Louis Hund
From: Louis Hund
Sent: Friday,June 23,2017 11:09 AM
To: 'Godinez,Gonzalo';Goderya,Farida;Raj Mehta
Subject: RE:84-inch crossings
Attachments: D017-CONCRETE ENCASEMENT FOR UTILITY PIPES.pdf
Categories: VCWRF WL-task12
Gonzo,
Yes the entire 41.5 feet is encased
I have also attached city standard detail for encasement
THanks
Louis B. Hund, PE
ASSOCIATE/SENIOR PROJECT N
JQ Infrastructure 1 1301 West 7th Street,Suite 1418,Fort Worth,Texas 76102
817.505.4311 phone 817.707.3131 cell
Ihund@iaieng.com
iaieng.com I Linkedln I Facebook I Twitter I Instagram
The information in this e-mail is confidential and may be legally privileged.It is intended solely for the addressee.Access by any other person to this e-mail is not authorized.If
you are not the intended recipient,please delete this e-mail.Any disclosure of this e-mail or of the parties to it,any copying,distribution,or any action taken or omitted in
reliance on it is prohibited,and may be unlawful.
From:Godinez,Gonzalo [mailto:Gonzalo.Godinez@fortworthtexas.gov]
Sent: Friday,June 23, 2017 10:50 AM
To: Louis Hund<Ihund@jgieng.com>;Goderya, Farida<Farida.Goderya@fortworthtexas.gov>; Raj Mehta
<rmehta@jgieng.com>
Subject: RE:84-inch crossings
Louis,
Are we encasing the entire 41.5 feet stretch of pipe above the 84" lines?That is what I gathered from our conversation.
Please confirm.Thanks.
Gonzo
From: Louis Hund [mailto1hund(a>igiencl.com]
Sent: Thursday,June 22, 2017 2:37 PM
To: Goderya, Farida; Raj Mehta
Cc: Godinez, Gonzalo
Subject: RE: 84-inch crossings
Farida,
Pictures from Gonzo this morning show that PVC is installed in lieu of DIP
As discussed at the pre-con,the PVC should be concrete encased
Concrete should be that used for thrust blocking(3000 psi), no rebar is required.
Thanks
Louis B. Hund, PE
1
ASSOCIATE/SENIOR PROJECT MANAGER
JQ Infrastructure 11301 West 7th street,Suite 1416,Fort Worth,Texas 76102
817.505.4311 phone 817.707.3131 cell
Ihund@'ciieng.com
iaieng.com I Linkedln I Facebook I Twitter I Instaeram
The information in this e-mail is confidential and may be legally privileged.It is intended solely for the addressee.Access by any other person to this e-mail is not authorized.If
you are not the intended recipient,please delete this e-mail.Any disclosure of this e-mail or of the parties to it,any copying,distribution,or any action taken or omitted in
reliance on it is prohibited,and may be unlawful.
From:Goderya, Farida [mailto:Farida.Goderva@fortworthtexas.gov]
Sent:Wednesday,June 21, 2017 4:27 PM
To:Raj Mehta<rmehta@igieng.com>
Cc:Louis Hund <lhund@igieng.com>
Subject: RE:84-inch crossings
Hi Raj,
Do we need to change the 16" pipe from PVC to DIP over the 84" crossing? I bet it will be simpler and cheaper to put
concrete encasement around the PVC. Will the encasement require rebar?
Regards. Farida
----------------------------------------------------
Farida Goderya, PhD, PE
Senior Project Manager
Fort Worth Water Department
Office:817-392-8214
Cell: 817-851-4910
Farida.Goderva@fortworthtexas.gov
From: Raj Mehta [mailto:rmehta@jgieng.com]
Sent:Wednesday,June 21.2017 4:23 PM
To:Goderya, Farida <Farida.Goderva@fortworthtexas.gov>
Cc: Louis Hund<Ihund@igieng.com>
Subject:84-inch crossings
Farida:
In reference to your question regarding embedment of the 16-inch pipe over the twin 84-inch crossing:
1 have in my notes from the preconstruction meeting held on 5-16 that the decision was made by FWWD at that
meeting that contractor would install PVC as the alternate to the DIP shown on the plans.
• Louis Hund stated that he would prefer that DIP as opposed to PVC be installed over the crossing due to the
separation distance between the pipes.
• David Townsend stated that PVC could be used there,along with concrete encasement.
That ended the discussion of the crossing, but I think it is understood that since PVC is being used for the project and
that this portion of the work will require either DIP or encased PVC and that the contractor will be paid the additional
cost due for either installation.
JQ is fine with either approach. We can issue a field order and get pricing back. If FWWD does not have a preference,
we can get pricing on both and see what Felix comes back with.
2
Regards,
Raj
C. Raajan Mehta, PE
Partner
JQ Infrastructure 1 100 Glass street,Suite 201,Dallas,Texas 75207
972.392.7340 phone 972.603.6653 cell
rmehta@ioieng.com
ioieng.com I Linkedin I Facebook I Twitter I Instagram
The information in this e-mail is confidential and may be legally privileged.It is intended solely for the addressee.Access by any other person to this e-mail is not authorized.If
you are not the intended recipient,please delete this e-mail.Any disclosure of this e-mail or of the parties to it,any copying,distribution,or any action taken or omitted in
reliance on it is prohibited,and may be unlawful.
3
BACKFILL
II
6' MIN. - .� .` ° S • ! ' °
ts�v
° JQ OSP CONCRETE
I I ENCASEMENT PER
SECTION 33 05 10
` .'.. . • IIS
6" MIN. �. .�-•.t,i :.:•... •• .
1 h—I i I I I 1-'�'•I 11-1 I•I—I`I 1 '`I:I I III
8" MIN. TRENCH WALL
CLEARANCE (TYP.)
NOTE:
• DIMENSIONS SHOWN ARE
THE MINIMUM REQUIREMENT
FOR PAYMENT PURPOSES.
FORT WORTH CITY OF FORT WORTH,TEXAS REVISED:06-19-2013
CONCRETE ENCASEMENT
FOR UTILITY PIPES 33 05 10-DO17
Construction Cost Summary FELIX Version 04.15.2013
CONSTRUCTI}N COMPANY
Project I Bid Name: , Company:JQ Infrastructure
VCWRF Service Waterline Improvements Owners Representative:Louis Hund
Address: 100 Glass Street
Project Number(FCC): Dallas,TX 75207
1837 Phone:817-555-4311
E-mail:Ihund aaioeng.com
Description of Work:
Concrete encase 41 If of 16"PVC Pipe
Assum tions: Exclusions:
Concrete Testing
Notes/Other: Owner to Provide:
A.Labor D.Materials
Cate o Hours Rate Total Item Quant Cost Total
Principal $ $ From Worksheet 1 LS $ 1,536.00 $ 1,536.00
Project Manager $ $ $
Project Engineer $ $ $
Admin $ $ $
General Superintendent $ $ $
Project Superintendent $ $ Material Subtotal $ 1,536.00
Foreman 3.0 $ 48.75 $ 146.25Marku Factor 0% $
Craftsman 33.0 $ 34.50 $ 1,138.50 MATERIAL TOTAL $ 1,536.00
Apprentice I Laborer $ $ E.Subcontractors
Labor Subtotal $ 1,284.75 Discipline Quant Cost Total
Markup Factor 0% $ From Worksheet 1 LS $ $
LABOR TOTAL $ 1,284.75 $
B.Felix Equip $
Unit Hours Rate Total Subcontractor Subtotal $
Pick-up $ $ Markup Factor 0% $
Pick-up w/Tools $ $ SUBCONTRACTOR TOTAL $
Flatbed Truck $ $ F.Other Direct
Back Hoe $ $ Item Quant Cost Total
Boom Truck $ $ From Worksheet 1 LS $ $
Loader(CAT 950) $ $ $
Dump Truck(with driver) $ $ Other Subtotal $
Excavator(CAT 325) $ $ Markup Factor ft 0% $
Water Truck $ $ OTHER DIRECT COST TOTAL T$
--
Compactor CAT $ $ G.FCC Electrical
Ext Reach Forklift $ $ Disci line Quant Cost Total
Grading Tractor(Case 480) $ $ Felix Construction Electrical' 1.0 $ $
Water Wagon $ $ H.Pass Throu h
Jumping Jack $ $ Item Quant I Cost Total
Misc Tools I Supplies $ $ From Worksheet 1 LS $ $
Job Trailer $ $ $
Misc Other $ $ Pass Through Subtotal $
Felix Equipment Subtotal $
Markup Factor 0% $
FELIX EQUIPMENT TOTAL $ Subtotal:A+B+C+D+E+F+G+H $ 2,820.75
C.Rental Equi
Unit Unit Rate Total Bond Rate(%) 0.00% $
From Worksheet 1 LS $ $ Tax Rate % 0.00% 65.0% $
$ Credit Card Fee % 0.00% $
Rental Subtotal $ SUB TOTAL $ 2,820.75
Markup Factor 10% $
RENTAL EQUIPMENT TOTAL $ CONTINGENCY•'
GRAND TOTAL $ 2,820.75
Estimated Duration of Work(Working Days) + TBD
Scott McElwee/Project Manager
Felix Construction Company does not include its Electrical Division's costs when calculating overall project overhead and mark-up.
DATE: "Work paid for out of Contingency funds will have tax,bond and mark+rps applied at the same rates noted above.
June 31,2017
FELIX CONSTRUCTION CO. o.mrma w.n rAav w.�..�
CMR #3
CITY OF FORT WORTH VILLAGE CREEK WATER RECLAMATION FACILITY
SERVICE WATERLINE IMPROVEMENTS
CITY PROJECT NO. 100512
Y
Louis Hund
From: Goderya,Farida<Farida.Goderya@fortworthtexas.gov>
Sent: Friday,September 8,2017 5:17 PM
To: Louis Hund;Scott McElwee
Cc: Walker,Robert;Nason,Ronald A
Subject: RE:Additional Pavement Cutting Depth"
Follow Up Flag: Follow up
Flag Status: Flagged
Categories: VCWRF WL-task12
Hi Scott/Louis,
I have reviewed this request for additional compensation for pavement work.This pavement additional work was
necessitated by the existing pavement at the VCWRF site. I understand, this request includes all costs associated with
the pavement work and will not require any additional funds or time extension. I am in agreement with this CMR and it
will be included in the next Change Order(CO#1) paperwork. Please finalize the CMR document and include all the
related paperwork.
Call or email with questions. Regards. Farida
----------------------------------------------------
Farida Goderya, PhD,PE
Senior Project Manager
Fort Worth Water Department
Office:817-392-8214
Cell: 817-851-4910
Farida.Goderya@fortworthtexas.gov
From:Goderya, Farida
Sent:Wednesday,August 30,2017 12:02 PM
To: Louis Hund (Ihund@jqieng.com)(Ihund@jqieng.com)<Ihund@jgieng.com>;'Raj Mehta'<rmehta@jqieng.com>
Cc:Robert Walker(robert.walker@fortworthtexas.gov)<Robert.Walker@fortworthtexas.gov>;Nason, Ronald A
(Ronald.Nason@fortworthtexas.gov)<Ronald.Naso n @fortworthtexas.gov>
Subject: FW:Additional Pavement Cutting Depth, Internal
Louis/Raj,
See attached file and email below from Felix, asking additional amount for Pavement! What do you think? Is it
justified?
Robert/Ron,
Do you have any comments/input regarding this?
Regards. Farida
----------------------------------------------------
Farida Goderya, PhD, PE
Senior Project Manager
Fort Worth Water Department
Office:817-392-8214
Cell: 817-851-4910
Farida.Goderya@fortworthtexas.gov
1
From:Scott McElwee (mailto:scottm@felixconstruction.com)
Sent:Wednesday,August 30; 2017 11:18 AM
To:Goderya, Farida<Farida.God erya@fortworthtexas.gov>
Subject:Additional Pavement Cutting Depth
Hi Farida,
In our bid we estimated the existing pavement to be 6"thick. Based on the detail(attached)the pavement appears to be
about 4".The average thickness of the paving that we cut is actually about 10"thick. Our pavement cutting
subcontractor bid based on 6"with a .25/inch additional cost for each additional inch of thickness. I've attached their
purchase order and quotation.
Long story short,We spent over$15,000 on cutting and had$3,500 in our bid.We're asking for relief in the amount of
$6,607 if possible.We feel that we were diligent in assuming that the existing pavement was an average of 6"thick,
based on the detail.
Thanks,
Scott
Stott McElwee I Project Manager
Felix Construction Company
D: 623.223.5409 M: 480.299.2967
0: 480.464.0011 F: 480.464.0078
E: scottm@felixconstruction.com
1326 W.industrial Or,Coolidge,AZ 85128(corporate)
11140 N.136th Ave,Surprise,AZ 85379(satellite)
www.felixconstruction.com
2
VCWRF Service Waterline Improvements
Pavement Cutting Additional Cost Based on 6"Assumed Thickness of Existing Pavement
Ticket No. LF Cut Thickness Bid Thickness Addl.Thickness Cost/Inch Addl.Cost/LF Addl.Cost
141892 167 10 6 4 0.25 1 167
180 8 6 2 0.25 0.5 90
142001 567 10 6 4 0.25 1 567
363 10 6 4 0.25 1 363
141987 789 10 6 4 0.25 1 789
138785 290 10 6 4 0.25 1 290
142595 1156 7 6 1 0.25 0.25 289
142875 17 6 6 0 0.25 0 0
152 10 6 4 0.25 1 152
102 10 6 4 0.25 1 102
38 10 6 4 0.25 1 38
140399 555 12 6 6 0.25 1.5 832.5
366 12 6 6 0.25 1.5 549
432 8 6 2 0.25 0.5 216
170 15 6 9 0.25 2.25 382.5
138741 512 12 6 6 0.25 1.5 768
410 12 6 6 0.25 1.5 615
141843 240 12 6 6 0.25 1.5 360
37 10 6 4 0.25 1 37
6607
t
I
ASPHALT TO
SAW-CUT BE PLACED IN
(TYP,) T%o LFTS
EXISTING TREATEDSRfNCN REPAIR LIMITS HMAC
EXISTING
SUBGRADE(IF ANY) CONCRETE BASE MATERIAL I PAVEMENT
FOR TRENCH REPAIR PER PAVEMENT
TACK COAT SECTKIN 03 34 16
••�i4"^�} �.l_a.��I-,:f�.�+•:S:! Vii!? ^.1 + ^-�1 iJ''i 11 i
PROVIDE DENSITY AND
HICKNESS TESTING 1t � :- •�l ': .•�»•..�`_..-':'4.'I�' f, � +
T ,...j f_r
........... .I'
PER SECTION 32 12 16
PART 3.6 -"'ti'`•'"`"'k"'TM'^" -'' UNDISTURBED `
�� ^--. :r- -- �•-tir••-+1.: ("j: SUSCRADE
952 COMPACTION FINAL BACXFB.L
1 '-2%TO 4S OF OPTIMUM� �. <15'UNDER
MOISTURE CONTENT ^1 PAVEMENT
SELECT BACKFILLTE
ACCORDANCE MTHMA MAL IN
SECTION 33 05 10
6'MIN. AND ._J .. •. .. .• __
12 MAX. -FI '::::;:.•.:::,•:::• 1� Ij..:
INITIAL BACKFILL I ? `•b - ,mac J
TRENCH GEOTEXTILE
1 �! fABRIC
UTILITY SAND PERS
SECTION 33 05 10i M14 )+1
.�5 •K CRUSHED ROCK PER
SECTION 33 05 10 i
6'MIN. 3�.:1'.
12'MIH. AND 1B'
MAX. TRENCH WALL
CLEARANCE(TYP.)
TRENCH DEPTH TRENCH DEPTH
LESS THAN OR GREATER THAN 15'.
EQUAL TO W. GROUND WATER
AND NO PRESENT,OR BURIED
GROUND WATER STEEL PIPE PER
PRESENT SECTION 33 11 14
1
I
t
S
PAVEMENT REPAIR, BACKFILL,
AND EMBEDEMENT DTEAILS
-Kl�
SCALE: NTS
FEEL PURCHASE ORDER
Show this Purchase Order Number 1837107
1326 W. Industrial Dr.Coolidge,AZ 85128(Corporate) Amendment Number
1313 Valwood Parkway, Ste. 320, Carrollton,TX 75006
www.felixcoiistruction.com
Phone (480)464-0011 (469)458-0011 (TX) Aft.A Ann.Agmt. Subcontract other Other
Fax (480)464-0078 0 ❑ ❑ ❑ ❑
VENDOR INFORMATION MMMMOMM' (.2UI5 10 NO.
Vendor. Associated Cutting Inc 5/30/17 10-1837-02-400-4115
Address: PO Box 541224 PROJECT: Village Creek Reclamation Facility
Dallas, TX 75354-1224 ADDRESS. 4500 Wilma Lane, Arlington TX 76012
DIRECTIONS (click here for Google Map to site)
ATTENTION: Scott McElwee
Office: 214-350-4436 Cell: 214-622-3101 SHIP TO: Jobsite
Contact: Andy (click here for Google Map to SHIP TO location)
n E-mailed ❑Faxed ❑Mailed PROJECT DOCUMENTS: Click Here to Download Plans
Routing: contact email address here Click Here to Download Specs
REQUISITIONED BY ?^!HEN SHIP SHIP VIA FOB POINT TERMS
Scott McElwee asap Jobsite Net 30
ITEM CITY UNIT DESCRIPTION UNIT PRICE TOTAL
1 1 EA 24"Core Droll @ 22 degree angle $ 600.00 $ 600.00
2 3000 If 6"Pavement Saw Cut $ 1,25 $ 3,750.00
3 $ -
4 $ -
1. No work activities will be permitted on-site until Felix has your companies CERTIFICATES OF INSURANCE on file. Please email
certificates to Felix PRIOR to beginning work on-site.
2. All invoices MUST reference this Purchase Order number in order to be paid in a timely manner.
3. Please mail all invoice to the attention of ACCOUNTS PAYABLE. Emailed invoices should be directed to
ap@felixconstruction.com.
4. Contact Scott McElwee 480-299-2967,24 HRS Priorto delivery,NO EXCEPTIONS.
5. Submittal packages less than 100 total pages may be submitted in ORIGINAL pdf format via email to
scottm@felixconstruction.com.Your submittal(s)MUST include a copy of the applicable specification section and any
referencing section(s)associated with the materials and or equipment you are supplying. The specification copy shall be
complete with each paragraph check-marked(Green Check)to indicate specification compliance or marked(PI,-_;;,)to
indicate requested deviations from specification requirements.Check-marks shall denote full compliance with a paragraph as
a whole.If deviations from the specifications are indicated,each deviation shall be underlined and denoted by a number in
the margin to the right of the identified paragraph. The submittal shall be accompanied by a detailed,written justification for
each deviation(on your company letterhead).Failure to include a copy of the marked-up specification sections,along with
justification(s)for any requested deviations to the specification requirements,with the submittal shall be sufficient cause for
rejection of entire submittal.
6. Safety Data Sheets(SDS)MUST accompany any materials classified as toxic or hazardous substances. Deliveries of these
materials that are not accompanied by an SDS shall be sufficient cause rejection of the delivery.
7. Persuant to State of Texas Tax Code,Section 151.309-this contract is issued by an agency that is exempt from sales tax on
materials that are incorporated into the real property of project listed above.
Click Here to Download Tax Exemption Certificate TOTAL $ 4,350.00
AUTHORIZED BY: DATE: Tuesday,May 30,2017
Scott McElwee
scottmna.felixconstruction.com
m:480-299-2967
AUTHORIZED BY: DATE:
Authorized Representative Signature
FEL 1 Village Creek Water ATTACHMENT "A"
Reclamation Facility
PURCHASE ORDER 1837107
9
TION DATE �EQ9IICITIaNNVQ.
Vendor: Associated Cutting
[::0:/30/17 10-1896-02-400-4115
ITEM DESCRIPTION NOTES BY VENDOR OTHER
FCC BY OTHER N/A
1 Cutting Services per attached Associated Cutting Inc
2 Estimate 69801
3
4 6" Minimum.Additional thickness is .25/inch.
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20 Specifics
21
22
23 Provide Insurance Cerrtificate
24
25 Prevailin Wage Rates Apply per GC 6.07 Wage Rates
26
27
28
29
30
31
32
33
-- 34
35 This project is Tax Exempt-See FCC Project
36 Tax Exempt form link on P1 of this Punchase Order
37 _
38 Exclusions
39
40
41
42
43
44
45
ASSOCIATED CUTTING, INC. Estimate
PO Box 541224
Dallas, Tx 75354-1224 DATE ESTIMATE#
214 350 4436 5/23/2017 69801
NAME/ADDRESS Ship To
FELIX CONSTRUCTION CO FORT WORTH
1326 W INDUSTRIAL DR SCOTT
COOLIDGE, AZ 85128
P.O. NO. TERMS PROJECT
C.O.D.
ITEM DESCRIPTION QTY COST TOTAL
CD CORE DRILLING -- 241N DIAMETER 1 600.00 600.00T
X 121N THICK WALL AT 22 DEGREE
ANGLE
SS SLAB SAWING -- 3000LF X 61N 3,000 1.25 3,750.00T
THICK PAVING
Exclusions/Conditions:
* Not responsible for layout or anything
located in or beneath the surface of the
concrete
* If there is post tension cable in the
slab, customer assumes all
responsibility
* Work to be done during normal
business hours unless otherwise
stated
* Quantities are estimated, invoice will
reflect actual quantities
* Fees, permits, inspections, one call
locates, lifts, scaffolding, cap, cover,
protect openings shall be done by
others unless otherwise stated
* Cleanup is limited to vacuuming
slurry (inside only), slurry on exterior
projects will be pushed onto concrete
scheduled for removal
PLEASE CALL ANDY AT (214) 622-3101 WITH ANY
QUESTIONS. THANK YOU TOTAL
Page 1
ASSOCIATED CUTTING, INC. Estimate
PO Box 541224 DATE ESTIMATE#
Dallas, Tx 75354-1224
214 350 4436 5/23/2017 69801
NAME/ADDRESS Ship To
FELIX CONSTRUCTION CO FORT WORTH
1326 W INDUSTRIAL DR SCOTT
COOLIDGE, AZ 85128
P.O. NO. TERMS PROJECT
C.O.D.
ITEM DESCRIPTION QTY COST TOTAL
* This estimate does not include
powerwashing after work is complete
*Any and all items not expressly
itemized in this estimate, if ordered, will
be billable with or without a change
order
*All visits to jobs must overcome
minimum charges or minimum rates
will apply
* Estimates do not include grade
beams or voided floors unless
otherwise stated
*Associated Cutting, Inc., reserves all
lien rights
*This estimate is to become a part of
any contract for this job and language
in this document supercedes any
language to the contrary in said
contract
* Bobcats are skid steers by definition
and as such do leave tire marks
behind, cleanup of tire marks is not
included in this price
* Customer is responsible for
determining whether tax should be
PLEASE CALL ANDY AT (214) 622-3101 WITH ANY
QUESTIONS. THANK YOU TOTAL
Page 2
ASSOCIATED CUTTING, INC. Estimate
PO Box 541224
Dallas, Tx 75354-1224 DATE ESTIMATE#
214 350 4436 5/23/2017 69801
NAME/ADDRESS Ship To
FELIX CONSTRUCTION CO FORT WORTH
1326 W INDUSTRIAL DR SCOTT
COOLIDGE, AZ 85128
P.O. NO. TERMS PROJECT
C.O.D.
ITEM DESCRIPTION QTY COST TOTAL
added to price during bidding process.
Please verify and add tax if necessary
* Lab testing and permits for concrete
work is excluded from this estimate
* This estimate assumes no cables in
concrete or cables are to be scanned,
located, and tension released by
others
* Concrete work is always estimated as
place and finish only and as such does
not include backfill unless otherwise
stated
* Concrete work does not include
cutting of control joints or sealing of
joints unless otherwise specified
Approved:
Title:
Sales Tax 8.25% 358.88
PLEASE CALL ANDY AT (214) 622-3101 WITH ANY TOTAL
QUESTIONS. THANK YOU $4,708.88
Page 3
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all erformance and reporting requirement.
Signature / =Gr,L, � �o� � Date
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX.