HomeMy WebLinkAboutContract 33120-A4 AMENDMENT No.4 CITY SECRETARY
CONTRACT NO. �3 00" "1
TO CITY SECRETARY CONTRACT No. 33120
WHEREAS, the City of Fort Worth (CITY) and Freese and Nichols, Inc. ,
(ENGINEER) made and entered into City Secretary Contract No. 33120, (the
CONTRACT) which was authorized by M&C #C-21234 on the 10th day of
January, 2006 in the amount of $ 189, 000; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment Number
1 in the amount of $314, 925 which was authorized by M&C #C-22994 on
August 26, 2008; Amendment Number 2 in the amount of $352, 698 which was
authorized by M&C #C-26245 on May 14, 2013; and Amendment Number 3 in the
amount of $48, 000 which was administratively authorized on December 21,
2016; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Central Arlington Heights Storm Drain Watershed Planning Study; and
WHEREAS, it has become necessary to execute Amendment No. ; to the
CONTRACT to include an increased scope of work and revised fee .
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the additional
engineering services specified in a proposal dated September 14, 2017, a
copy of which is attached hereto and incorporated herein. The cost to
City for the additional design services to be performed by Engineer
totals $37,000. (See Attached Funding Breakdown Sheet)
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $941, 623.
City of Fort Worth
Professional Services Agreement Amendment Template O"ICULL RECOF �
PMO Official Release 8/1/2012
Page 1 of 3 �,�SECRETARY
ft M "mo TX
3 .
Unless terminated pursuant to the terms herein, this Agreement shall
be for a term of 6 months, beginning upon the date of its execution, or
until the completion of the subject matter contemplated herein, whichever
occurs first.
4 .
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED:
City of Fort Worth ENGINEER
Freese and Nichols, Inc.
ALI
Jesus J. Chapa Scott Hub , P.E.
Assistant City Manager Associate
DATE: DATE: �—
APPR L RECOMMENDED:
Uk
—Doul Wiersig, P.E.
Direc o , Transportation and Public Works Department
APPROVED AS TO FORM AND LEGALITY: M&C : t'V/iQ•
Date:
Sr. Assistant City Attorney
ATT S ORT '
Par J. Kayser U? _
City Secretary
City of Fort Worth
7� x f
Professional Services A Amendment Tem r CSA , x
g p S
reement late $
PMO Official Release 8/1/2012
Page 2 of 3 °>
w �;�
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements .
'��AA j kk -�) M . Dl�
Jen er M. )Dyke
Sr. lanne
City of Fort Worth �
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012
Page 3 of 3 �
FUNDING BREAKDOWN SHEET
City Secretary No. 33120
Amendment No. 4
Department Fund-Account-Center Amount
0200431 52002-5330500-100091 $37 , 000 . 00
Total : $37, 000
City of Fort Worth
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012
Page 3 of 3
FREESE
4055 International Plaza,Suite 290 • fort Worth,Texas 76109 • 817-735-7300 • fax 817-735-7491
September 14, 2017
Ms.Jennifer Dyke,CFM
Sr. Planner
Transportation and Public Works Department
Stormwater Management Division
City of Fort Worth
200 Texas Street
Fort Worth,Texas 76102
Re: Proposal for Central Arlington Heights Watershed Planning Study Amendment#4
Dear Ms. Dyke:
In response to your request, Freese and Nichols, Inc. is pleased to present this scope of services for the
above referenced project. This proposal includes the following services and tasks:
Task Description Fee
1 Project Management and Meetings $5,000
2.1 Grant Applications(including$5,000 contingency) $20,000
3.2 Floodproofing $12,000
Total Proposed Amendment $37,000
The attached Scope of Services(Attachment A) includes a detailed description of the scope of work.
Thank you for the opportunity to assist the City on this project. If you have any questions, please call me
at(817) 735-7378.
Sincerely,
Freese and Nichols, Inc.
15—9�
Scott Hubley, P.E.,CFM
Associate
Project Manager
ATTACHMENT A
CENTRAL ARLINGTON HEIGHTS (CAH)
STORM DRAIN WATERSHED PLANNING STUDY AMENDMENT #4
CITY PROJECT NO. 00080
SCOPE OF WORK
PROJECT UNDERSTANDING
The Central Arlington Heights (CAH) watershed has experienced several flooding events in
recent years, both during and after the construction of the Ashland and Western capital projects.
While these projects were only intended to provide incremental flood benefits, the occurrence of
continuing floods has clearly demonstrated their limited nature. Historically, the neighborhood
has been strongly opposed to voluntary property acquisitions; however, several residents have
approached the City with an interest in selling their property. One grant application has already
been submitted and is pending review by the Texas Division of Emergency Management. The
purpose of this effort is to prepare additional grant applications for voluntary property
acquisitions along with performing the necessary engineering analyses and benefit cost
applications to support these applications. FNI will perform the following services. Each task
will be performed independently only upon written authorization from the City.
BASIC SERVICES
TASK 1. PROJECT MANAGEMENT AND MEETINGS
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use of
ENGINEER's and CITY's time and resources. ENGINEER will manage change, communicate
effectively, coordinate internally and externally as needed, and proactively address issues with
the CITY's Project Manager and others as necessary to make progress on the work.
1.1. Managing the Team
• Lead, manage and direct team activities
• Ensure quality control is practiced in performance of the work
• Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting
• Attend up to four(4) meetings to discuss the work effort with City staff
• Prepare and submit monthly progress reports in the format provided by the respective
CITY Department to accompany monthly invoices.
DELIVERABLES
A. Meeting summaries with action items
1
B. Monthly progress reports
C. Baseline project schedule
D. Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
TASK 2. VOLUNTARY PROPERTY ACQUISITION GRANT APPLICATIONS
2.1 Grant Application Assistance
• Update existing grant information and modeling to reflect property ownership
changes and project footprint changes.
• Prepare grant application for Flood Mitigation Assistance (FMA), Pre-Disaster
Mitigation Grant Program (PDM), or Hazard Mitigation Grant Program (HMGP) for up
to fifteen (15) properties. This scope assumes that previous HMGP grant application
will be used as basis and will be updated to include changes to the project.
• Up to two (2) different grant applications will be submitted.
• Respond to one (1) round of comments from state and one (1) round of comments
from FEMA for each application.
• A contingency of$5,000 has been included to accommodate potential future updates
to grant applications due to property owner turnover or other changes outside the
control of FNI.
• Utilize remaining funds from Amendment #3 to respond to comments from HMGP
application submitted in January 2017.
TASK 3. FLOOD MITIGATION ALTERNATIVES ANALYSIS
3.1 Elevating and Floodproofing
• Provide conceptual evaluation of elevating and floodproofing as mitigation measures
for single family residential, duplex, commercial, and apartment. Collect standard
FEMA reference materials and summarize ballpark costs for each method.
Document evaluation within a technical memorandum. Evaluation will be suitable as
a reference document and applicable for any elevating and floodproofing on a city-
wide basis.
• Identify candidate properties within CAH for elevations and/or floodproofing. Identify
these properties on a map and apply ballpark cost estimates to the candidate
properties.
• No detailed hydraulic modeling will be performed.
• Document analysis in a technical memorandum and update the memo once based
on 1 round of review comments from the City.
SPECIAL SERVICES:
ENGINEER will perform additional related tasks as directed by the City to potentially include but
not limited to meetings, coordination, public involvement, hydraulic analyses, and grant
applications. ENGINEER will not proceed with special services without written authorization
from the City.
2
ADDITIONAL SERVICES:
1. Preliminary or final design of recommended improvement alternatives
2. Assistance with real estate transactions or property acquisition
3. Evaluation of alternatives in addition to those listed above
4. Field survey
5. Coordination with individual property owners
6. Assistance with legal proceedings
7. Assistance with additional grant application cycles beyond those listed above
TIME OF COMPLETION:
FNI agrees to submit grant applications by FEMA established deadlines. FNI agrees to
complete Task 3 within 60 days of notice to proceed.
3
ATTACHMENT B
COMPENSATION
CENTRAL ARLINGTON HEIGHTS WATERSHED STUDY
CITY PROJECT NO. 00080
Time and Materials with Rate Schedule Project
I. Compensation
A. The ENGINEER shall be compensated for personnel time, non-labor expenses,
and subcontract expenses in performing services enumerated in Attachment A as
follows:
i. Personnel Time. Personnel time shall be compensated based upon hours
worked directly in performing the PROJECT multiplied by the appropriate
Labor Category Rate for the ENGINEER's team member performing the
work.
Labor Category Rate as presented in the rate schedule table below is the
rate for each labor category performing the work and includes all direct
salaries, overhead, and profit.
A summary of current hourly billing rates is provided below:
CAD Technician/Designer- 1 91
CAD Technician/Designer-2 117
CAD Technician/Designer-3 145
Construction Manager- 1 85
Construction Manager-2 111
Construction Manager-3 131
Construction Manager-4 164
Corporate Project Support- 1 87
Corporate Project Support- 2 105
Corporate Project Support- 3 139
Intern/Coop 53
Professional - 1 107
Professional -2 130
Professional -3 146
Professional -4 169
Professional -5 197
Professional -6 225
Technology Charge 8.50
ii. Non-Labor Expenses. Non-labor expenses shall be reimbursed as Direct
Expenses at invoice or internal office cost.
Direct Expenses (non-labor) include, but are not limited to, mileage, travel
and lodging expenses, mail, supplies, printing and reproduction services,
other direct expenses associated with delivery of the work; plus applicable
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 1 of 5
B-1
ATTACHMENT B
COMPENSATION
sales, use, value added, business transfer, gross receipts, or other similar
taxes.
iii. Subcontract Expenses. Subcontract expenses and outside services shall
be reimbursed at cost to ENGINEER plus a markup of ten percent (10%).
iv. Budgets. ENGINEER will make reasonable efforts to complete the work
within the budget and will keep the City informed of progress toward that
end so that the budget or work effort can be adjusted if found necessary.
ENGINEER is not obligated to incur costs beyond the indicated budgets,
as may be adjusted, nor is the City obligated to pay ENGINEER beyond
these limits.
If ENGINEER projects, in the course of providing the necessary services,
that the PROJECT cost presented in Article 2 of this Agreement will be
exceeded, whether by change in scope of the project, increased costs or
other conditions, the ENGINEER shall immediately report such fact to the
City and, if so instructed by the City, shall suspend all work hereunder.
When any budget has been increased, ENGINEER's excess costs
expended prior to such increase will be allowable to the same extent as if
such costs had been incurred after the approved increase.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. The ENGINEER shall be paid by the City based upon an invoice created on the
basis of statements prepared from the books and records of account of the
ENGINEER, based on the actual hours and costs expended by the ENGINEER in
performing the work.
B. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
C. ENGINEER shall prepare and submit invoices in the format and including content
as presented in Exhibit B-1.
D. Payment of invoices will be subject to certification by the City that such work has
been performed.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Transportation and Public Works Department monthly progress reports and
schedules in the format required by the City.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 2 of 5
B-2
IV. Summary of Total Project Fees
Firm Primary Responsibility Fee Amount %
Prime Consultant
Freese and Nichols, Inc. Engineering and PM $37,000 100%
MWBE Sub-Consultant
none
Non —M/WBE Consultants
none
TOTAL $37,000 100%
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 3 of 5
B-3