HomeMy WebLinkAboutContract 45823-A2 CITY SECRETAY
CONTRACT N0-. `[ R �—A
TEXAS DEPARTMENT OF TRANSPORTATION
DFc 18 20�� AIRPORT PROJECT PARTICIPATION AGREEMENT
c/�S�C9Frg9y ry (Federally Assisted Airport Development)
TxDOT CSJ No.: 1402SPINK
TxDOT Project No.: AP SPINKS 2
TxDOT Contract No. :4XXAV081
Commission Approval: June 26,2014
NPE Funds Applied: FYI 3,FY 14,FY 15
DUNS:073170458
C.F.D.A.:20.106
Amendment No. 02 to the Agreement
Part I-Identification of the Project
TO: The City of Fort Worth,Texas
FROM: The State of Texas, acting through the Texas Department of Transportation
The City of Fort Worth, Texas, hereinafter referred to as the "Sponsor," and the Texas
Department of Transportation, hereinafter referred to as the "State," have entered into an Airport
Project Participation Agreement TxDOT CSJ Number 1402SPINK, executed by the Sponsor on
July 11, 2014, and by the State on July 18, 2014, for the development of the Fort Worth Spinks
Airport, hereinafter referred to as the "Airport".
The project is described as design and construction services to: reconstruct taxiway C, G
and H; construct temporary access to Runway at taxiway D; construct new parallel taxiway to C
to allow access to taxiway C; construct a new access taxiway at taxiway J; apron joint seal
replacement; construct northwest service road; drainage study at east side development area;
drainage improvements to Stone Road, Wing Way Road, building and auto parking at West side;
drainage improvements to ditches from terminal apron to south T-hangars; install strip drain East
edge apron; and install gate northwest perimeter fence and a drainage study at the Fort Worth
Spinks Airport.
It is in the mutual interest of the Sponsor and the State to increase the agreement by
$142,690 for design services for taxiway C,G and H improvements.
Part H- Offer of Financial Assistance, as changed by Amendment No. 01, estimates total
project costs to be $3,070,916; and financial assistance is currently limited to $2,780,770 in
federal funds and$568,223 in local sponsor funds.
Page 1 of 3 OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
The following amendment to the Airport Project Participation Agreement shall become
effective upon execution of this Amendment by the Sponsor and the State.
The Airport Project Participation Agreement is amended as follows:
1. On Part II, Item No. 2 of the Agreement, change Amount A, estimated total project
costs, and any further references in the Agreement to Amount A, to$3,213,606.
2. On Part II, Item No. 2 of the Agreement, change Amount B,estimated total project costs
eligible for federal financial assistance, and any further references in the Agreement to Amount
B,to$2,923,460.
3. On Part II, Item 3 of the Agreement, change Amount C, the maximum obligation of the
United States payable under this offer, and any further references in the Agreement to Amount
C, to$2,631,114.
4. On Part II, Item 4 of the Agreement, change Amount D, Sponsor's share of the estimated
construction costs, and any further references in the Agreement to Amount D, to $582,492.
$290,146 is 100%local.
All other terms and conditions of the agreement are unchanged and remain in full force
and effect.
This Amendment to the Airport Project Participation Agreement between the City of Fort
Worth,Texas,and the Texas Department of Transportation is mutually agreed to and accepted.
APPROVAL RECOMMENDED.
The City of Fort Worth,Texas
By:�C��, mac' __ Sponsor
Bill Welstead
Aviation Director �
Sponsor Signature
APPROVED AS TO FORM AND Assistant City Manager
LEGALITY
Sponsor Title
B .
Paige 4ehane
Assistant City Atto, Contract Compliance Manager:
ORT By signing,I acknowledge that I am the
O�:�`' � person responsible for the monitoring
ATT and administration of this contract,
T� IN
= including ensuring all performance and
M Ka ' �r reporting requirements.R
City Secretary
P Page 2 of 3
M&C: C-28484 �� • Aya Ealy
Administrati �RECORD
Date: 12/5/17 OiTy SECRETARY
FT.WORTHO TX
Execution by the State
Executed by and approved for the Texas Transportation Commission for the purpose and effect
of activating and/or carrying out the orders,established policies or work programs and grants
heretofore approved and authorized by the Texas Transportation Commission.
STATE OF TEXAS
TEXAS DEPARTMENT OF TRANSPORTATION
By: /
David S. Fulton
Director
Aviation Division
Texas Department of Transportatio.
Date: "t 1
OFFICIAL RECORD
CITY SECRETARY
Page 3 of 3 FT. !NORTH, TR
M&C Review Page 1 of 3
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA FoR N
COUNCIL ACTION: Approved on 12/5/2017 - Resolution No. 4867-12-2017 & Ordinance Nos.
23021-12-2017 & 23022-12-2017
DATE: 12/5/2017 REFERENCE NO.: **C-28494 LOG NAME: 55FWS TXDOT GRANT
2ND AMEND (00402)
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Amendment Two to a Grant Agreement with the Texas Department of
Transportation to Increase the Grant Amount by $142,690.00 for Design Services for
Taxiway Improvements at Spinks Airport and Authorize an Increase in Sponsor's Share in
the Amount of$14,269.00 for a Total Sponsor's Share of$582,492.00, Adopt Resolution
Providing for Same and Adopt Appropriation Ordinances (COUNCIL DISTRICT 6)
RECOMMENDATION:
It is recommended that the City Council:
1 Authorize an amendment to the Grant Agreement with the Texas Department of Transportation,
Aviation Division, to increase the grant by $142,690.00 and the sponsor's share by $14,269.00 for a
total sponsor's share of$582,492.00 for design services for taxiway C, G and H improvements at Fort
Worth Spinks Airport;
2. Authorize the use of revenue derived from mineral leases on City-owned airports and adopt the
attached appropriation ordinance increasing estimated receipts and appropriations in the Aviation
Gas Lease Capital Projects Legacy Fund in an amount up to $14,269.00 for the City's sponsor's
share;
3. Adopt the attached resolution, as required by the Texas Department of Transportation, providing
that an additional amount up to $14,269.00 in available gas well revenue funds will be available as
sponsor's share for design services for Taxiway C, G and H improvements at Fort Worth Spinks
Airport and authorizing the City Manager or his designee to execute all necessary contracts
associated with this project with the Texas Department of Transportation;
4. Authorize a transfer in an amount up to $14,269.00 from the Municipal Airports Gas Lease Project
Fund to the Airport Grants Fund for the City's sponsor's share; and
5. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in
the Municipal Airport Grants Fund in an amount up to $14,269.00.
DISCUSSION:
On April 22, 2014, Mayor and Council Communication (M&C C-26778), City Council authorized the
application and acceptance of a grant from the Texas Department of Transportation (TxDOT),
Aviation Division, for the construction of a North Service Road at Fort Worth Spinks Airport in an
amount up to $3,000,000.00. To date the City of Fort Worth has been awarded $2,780,770.00 in
federal funds. TxDOT has recently negotiated the fee for the design services for the reconstruction of
taxiways C, G and H and it is now necessary to increase the grant Agreement by $142,690.00 for this
work. Additionally. TxDOT is requesting an additional $14,269.00 to cover the City's share of the
design costs for taxiway improvements. This will increase the total sponsor's share to $582,492.00.
http://apps.cfwnet.org/council_packet/mc review.asp?ID=25399&councildate=12/5/2017 12/6/2017
M&C Review Page 3 of 3
Originating Department Head: Bill Welstead (5402)
Additional Information Contact: Aaron Barth (5434)
Aya Ealy (5403)
ATTACHMENTS
55FWS TXDOT GRANT 2ND AMEND (00402) 55003 A018.docx
55FWS TXDOT GRANT 2ND AMEND 00402 59302 A018 vl.docx
EAST SIDE AIRPORT TAXIWAYS-20171013-APPENDIX D.pdf
RESOLUTION N SERVICE RD Grant FWS.docx
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=25399&councildate=12/5/2017 12/6/2017
M&C Review Page 2 of 3
-Activity Amount
Preliminary Engineering Report $ 75.430.00
Field Investigation $ 10,165.00
Laboratory Investigation $ 8.005.00
Engineering Services $ 22,000.00
-Property Ma $ 3,400.00
Preliminary Design $ 49.013.00
Final Design $ 50,023.00
-Bidding Phase $ 9,961.00
Topographic/Design Services $ 56,000.00
Taxiway C, G and H Design $ 142,690.00
Design Sub otai $ 426.687.00
Construction $2,776,919.00
Drainage Study $ 10,000.00
Project Total $3,213,606.00
The project will not impact the department's operating budget. The City will use revenue derived from
gas well drilling on City owned airports for the sponsor's share.
This project is funded from the following sources:
Fund Amount
Airports Gas Lease Capital Project $ 582,492.00
Fund
Municipal Airports Grants Fund $2,631,114.00
Total _ $3,213,606.00,
The construction portion of this project will be funded by TxDOT in a separate grant. The
construction is estimated to start upon completion of design in 2018 and is scheduled for completion
in 2019.
Fort Worth Spinks Airport is located in COUNCIL DISTRICT 6.
This contract will be with a governmental entity, state agency or public institution of higher
education: Texas Department of Transportation, Aviation Division.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of
the attached appropriation ordinance, funds will be available in the current capital budget, as
appropriated, of the Aviation Gas Lease Capital Projects Legacy Fund and the Municipal Airport
Grants Fund. This is an advance grant.
TO
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year Chartfield 2
FROM
Fund Department Account Project Program Activity Budget Reference# I Amount
ID I I ID I Year Chartfield 2
Submitted for City Manager's Office by: Fernando Costa (6122)
http://apps.cfwnet.org/council_packet/mc review.asp?ID=25 3 99&councildate=12/5/2017 12/6/2017