HomeMy WebLinkAboutContract 49967 ,� i t►►�wrr is rix:
CONTRACTOR
CITY SECRETARY
CITY SECRETARYG� SPONSORING DEPT
CONTRACT N0. _1
PROJECT MANAGER
IC'Sa'FILE COPY
THE CITY OF FORT WORTH, TEXAS pMa
WEST PATROL DIVISION
(JOYCE DRIVE POLICE STATION)
PMD2014-09
CITY PROJECT #100172
FQRTWORTH,H,
BETSY PRICE DAVID COOKE
MAYOR CITY MANAGER
.r►
Steve Cooke
Director, Property Management Department
Joel Fitzgerald
Chief, Police Department
Elements of Architecture
Balfour Beatty Construction, LLC
�. October 2417
t�
[LOPFICIALOR ARY TQC
M0
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 10/1712017
DATE: Tuesday, October 17, 2017 REFERENCE NO.: C-28440
— LOG NAME: 21WEST PATROL DIVISION CONSTRUCTION
SUBJECT:
Authorize Execution of Construction Contract with Balfour Beatty Construction, LLC, in the Amount of
$1,691,344.00, Including 7.5 Percent for the Owner's Construction Contingency Allowance for the New
West Patrol Division, a Remodel of an Existing Facility Located at 3532 Joyce Drive and Provide for
Administrative Costs in the Amount of$1,382,083.00 for a Total Project.Cost of$3,230,000.00 (CCPD
Funded) (COUNCIL DISTRICT 3)
.. RECOMMENDATION:
It is recommended that the City Council authorize the execution of a construction contract with Balfour
Beatty Construction, LLC, in the amount of$1,691,344.00, including 7.5 percent for the Owner's
.. Construction Contingency Allowance for the new West Patrol Division, a remodel of an existing facility
located at 3532 Joyce Drive and provide for administrative costs in the amount of$1,382,083.00 for a total
project cost of$3,230,000.00.
DISCUSSION:
The Police Department's West Patrol Division is currently housed in two facilities. Land and facilities
totaling 3.290 acres on Joyce Drive was purchased in March of 2014 (M&C C-26688) to provide for a new
West Division Headquarters. The City engaged Elements of Architecture through the annual architectural
Agreement to redesign the existing facility and to produce drawings and bid documents for the new
headquarters.
The City issued a Request for Proposals to prospective contractors on June 22 and 29, 2017. Pre-
proposal meetings and site visits were conducted with interested contractors. On August 4, 2017, the City
received eight responses from general construction contractors. Five of these firms provided the required
Post Proposal—Pre Award Submittals to be further evaluated by the City. Those firms were:
. Azteca Enterprises, Inc.
. Balfour Beatty Construction, LLC
. CPM Commercial Construction, Inc.
. Denco CS Corp
. RJM Contractors, Inc.
These proposals were reviewed by members of the Police Department, Office of Business Diversity and
the Property Management Department and were evaluated for best value based on the criteria set forth in
,. the Request for Proposals. The selection team recommends award of the construction contract to Balfour
Beatty Construction, LLC.
CPM
Logname: 21 WEST PATROL DIVISION CONSTRUCTION Page I of 3
i Balfour Beatty RJM Commercial Denco Azteca
!Criteria Construction, Contractors, Construction, CS Enterprises,
LLC Inc. Inc. Corp Inc.
I—'- [—
�—roposed—Price 60 59 59 55 49
[,M/WBE 6.0—F 6.5 6.5 7.0
Pr 5 4 10
Pro Schedule 7 5 F
I-Reputation/Experience 9-- 9 9 —8F 5
Citof Fort Worth �5 6
JPasy 5
t Relationship with
r 87.5 H.0
TOTAL 83.5 77.5 77.0
The overall project costs are expected to be as described in table below:
*- EST PATROL DIVISION PROJECT BUDGET
Architectural and, Engineering Design F$ 121,040.001
1Project Management, Existing Condition Survey, Bid Advertisement, i$
35,532.00
jetc.
Design Phase Total $ 156,572.00!
Construction Contract (Including Alternates 2, 3, 4, 5, 6 & 7 and 7.5
,percent of Base Bid as Owner's Construction Contingency $1,691,344.00
Allowance)
Project Administration Cost: IT, Security, Site Fencing, Project $1,382,084.00,
iManagement, Contingency, FFE, Etc.
Construction Phase Total $3,073,428.00
PROJECT TOTAL $3,230,000.00
In accordance with Chapter 7, Article 111, Section 747, Section 109.2.1 of the City Code, Building and
Trade Permit Fees are waived for this project.
Construction is anticipated to start in Fall 2017, with an anticipated completion date during the Summer of
2018.
FUNDING SOURCES - This project is funded through the CCPD Facility Budget FY15 and FY16.
M/WBE OFFICE - Balfour Beatty Construction, LLC is in compliance with the City's BDE Ordinance by
committing to 16 percent MBE participation on the base bid. The City's MBE goal on this project is 15
percent.
The West Patrol Division Office will be located in COUNCIL DISTRICT 3.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations, funds will be available
as appropriated of the CCPD Capital Projects Fund. Prior to an expenditure being made, the participating
department has the responsibility to validate the availability of funds.
Lognaine: 21 WEST PATROL DIVISION CONSTRUCTION Page 2 of 3
FUND IDENTIFIERS (FIDs):
TO
Fund Department ccoun Project Program ctivity Budget Reference # moun
i ID ID Year (Chartfield 2)
FROM
Fund, De __partment JAccoun Project Program ctivity Budget Reference#moun
j ID ID Year (Chartfield
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Steve Cooke (5134)
Additional Information Contact: Brian Glass (8088)
ATTACHMENTS
1. 170922 Balfour Beatty West Division ComplianceMemo.pdf (CFW Internal)
2. 21 WEST PATROL DIVISION CONSTRUCTION FID TABLE.pd (CFW Internal)
3. Form 1295 Balfour Beatty.pdf (Public)
4. SAM Balfour Beatty Construction LLC.pdf (CFW Internal)
5. West Patrol Division.pdf (Public)
Logname: 21 WEST PATROL DIVISION CONSTRUCTION Page 3 of 3
POLICE DEPARTMENT
WEST PATROL DIVISION
3532 JOYCE DRIVP
F I;.
till
i
k
s
.c q.
•_mak. n ;,. . .._
a
1
PROPOSED
CONSTRUCTION
SITE
T
Ask
n a ,
As,
,
a
r
2
41 k�,' , v° / ►
� nr.
yy
M1'.• � T qg t
'T` »• a ,+«... ..f
FORT WORTH.
PROPERTY MANAGEMENT DEPARTMENT
FACILITIES/ARCHITECTURAL SERVICES
BID TABULATION
Project: WEST PATROL DIVISION(JOYCE DRIVE POLICE STATION)
3532 JOYCE DRIVE
FORT WORTH Tabulated by:Vicki McDonald
Project#: 100172
PMD Project#:PMD2014-09 Eng.Estimate: $2,000,000.00
Bid Date: AUGUST 3,2017
Advertised: JUNE 22&29,2017 Addendums:2
1 2 3 4
Balfour Beatty Construction,LLC CMP Commercial Construction,Inc. RJM Contractors,Inc Cooper General Contractors
3100 McKinnon Street 1150 Martin Luther King Fuy 3629 Lovell Avenue 2560 Technology Drive,Ste 100
Dallas,Texas 76201 Fort Worth,Texas 78104 Fort Worth,Texas 76107 Plano,Texas 75074
214-068-4700 817-882-6594 817-377-0971 972-245-7960
817-882-6596 FAX 817-377-0973 FAX
kbolejack@balfourbeattyus.com shawnQcmp2013.com l peteCrnnp2013.com kbuyam@rkmilleccom gcooper@coopergwoon.wm
DESCRIPTION BID BID BID BID
Base Proposal $ 1,370,000.00 $ 1,384,975.00 $ 1,385,249.00 $ 1,461,570.00
Owner's General Contingency Allowance $ 102,750.00 $ 103,873.00 $ 103,894.00 $ 109,618.00
Base Proposal Plus Owner's $ 1,472,750.00 $ 1,488,848.00 $ 1,489,143.00 $ 1,571,188.00
General Contingency Allowance
ALLOWANCES
No.1 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 6,000.00
No.2 $ 4,000.00 $ 1,640.00 $ 2,000.00
ALTERNATES
Add Alternate#1 DELETED DELETED DELETED DELETED
Add Alternate#2 $ 62,766.00 $ 45,360.00 $ 76,000.00 $ 62,000.00
Add Alternate#3-Room 110 $ 91911.00 $ 18,292.00 $ 18,000.00 $ 5,500.00
Add Alternate#3-Rooms 121,129,&130 $ 15,218.00 $ 10,641.00 $ 5,000.00
Add Alternate#4 $ 10,989.00 $ 16,275.00 $ 18,000.00 $ 17,000.00
Add Alternate#5 $ 69,176.00 $ 32,130.00 $ 54,000.00 $ 91,000.00
Add Alternate#6 $ 24,076.00 $ 22,420.00 $ 19,000.00 $ 16,000.00
Add Alternate#7 $ 21,205.00 $ 24,081.00 $ 21,000.00
TOTAL ALTERNATES $ 203,343.00 $ 168,099.00 $ 185,000.00 $ 217,600.00
ADDENDUM'S: 2 2 2 2
CALENDAR DAYS: 119 180 180 180
PROPERTY MANAGEMENT DEPARTMENT
FACILITIES I ARCHITECTURAL SERVICES
BID TABULATION
5 6 7 8
DenCO CS Corp Azteca Enterprises,Inc. Basecom Inc. KHK Group,Ltd.
5525 Lyons Road 8205 Camp Borrie West,Suite 210 5209 Vesta Parlay Road 11255 Camp Borrie West Blvd
Garland,Teras 75D43 Fort Worth,Texas 76116 Fort Worth,Texas 76119 Fort Worth,Texas 76008
972-226-2609 817-244-0019 817-589-0050 817335-6129
972-226-0165 FAX 214-905-0828 FAX 817-486-2309 FAX 817-335-4146 FAX
ssmithCdencocs.com tenyc@aneca-omega.com ooaxaca@basewminc.mm hbiddle@khkgmup.net
DESCRIPTION BID BID BID BID
Base Proposal $ 1,497,399.21 $ 1,671,207.00 $ 1,720,800.00 $ 1,789,500.00
Owner's General Contingency Allowance $ 112,304.94 $ 125,341.00 $ 129,200.00 $ 134,202.00
Base Proposal Plus Owner's $ 1,609,704.15 $ 1,796,548.00 $ 1,850,000.00 $ 1,923,702.00
General Contingency Allowance
ALLOWANCES
No.1 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00
No.2 $ 1,800.00 $ 1,250.00 $ 3,000.00
ALTERNATES
Add Alternate#1 DELETED DELETED DELETED DELETED
Add Alternate#2 $ 42,896.00 $ 59,600.00 $ 87,790.00 $ 71,066.00
Add Alternate#3-Room 110 $ 4,850.00 $ 5,000.00 $ 9,320.00 $ 4,850.00
Add Alternate#3-Rooms 121,129,8 130 $ 3,190.00 $ 10,069.00 $ 3,190.00
Add Alternate#4 $ 8,000.00 $ 35,250.00 $ 28,750.00 $ 3,800.00
Add Alternate#5 $ 14,800.00 $ 12,500.00 $ 93,750.00 $ 31,000.00
Add Alternate#6 $ 29,384.00 $ 15,500.00 $ 19,375.00 $ 11,900.00
Add Alternate#7 $ 24,300.00 $ 17,000.00 $ 30,000.00 $ 13,500.00
TOTALALTERNATES $ 127,420.00 $ 144,850.00 $ 279,054.00 $ 139,306.00
ADDENDUM'S: 2 2 2 2
CALENDAR DAYS: 210 89 210 154
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
�0 RT WO ItTH
CITY OF FORT WORTH
PROPERTY MANAGEMENT DEPARTMENT
ADDENDUM NO. 1
WEST PATROL DIVISION (JOYCE DRIVE POLICE STATION)
*� Request for Proposals Submittal Date: August 3, 2017 (CHANGED)
The Request for Proposals for the above project is hereby revised and amended as follows:
1. The following paragraphs of the "NOTICE TO OFFERORS" in the "Instructions to Offerors"
are revised as noted:
"Proposals for the West Patrol Division (Joyce Drive Police Station), an interior renovation of an
existing building located at 3532 Joyce Drive in Fort Worth Texas will be received at the Purchasing
Office, City of Fort Worth, 200 Texas Street, Fort Worth, 76102, until 1:30 P.M on Thursday,August
3, 2017, and will be opened and publicly read aloud approximately thirty minutes later in the Council
Chambers."
.... "All questions will be answered by Addenda. The last day for questions from prospective Offerors is at
5:00 PM on Wednesday,July 26,2017."
2. The Pre-Proposal Conference and Walk-Through/Site Visit was held at 10:00 AM,
r' Wednesday, July 12, 2017 at the existing building project site located at 3532 Joyce Drive.
Refer to enclosed Pre-Proposal Attendees List. (Attachment No. 1)
3. The following paragraph of Section, 2. MINORITY BUSINESS ENTERPRISE (MBE) (Best
VALUE PROPOSAL), Minority Business Enterprise Provisions: of the "INSTRUCTIONS
TO OFFERORS'is revised as noted:
.. "The MBE goal on this project is 15%."
Acknowledge the receipt of this Addendum No. 1 on your Proposal.
.w
Steve Cook
Director, Property Management Department
By:
Alfonso Meza
Project Manager, Architectural Services
.r PMD, Facilities Division
817-392-8274, FAX 817-392-8488
Alfonso.Meza()fortworthtexas.gov
RELEASE DATE:July 14, 2017
Addendum No.1 Page 1 of 1
West Division—Joyce Drive Police Station July 2017
PAGE LEFT BLANK INTENTIONALLY
1 l 1 1 i i i M i I i 1 1 1 1 1 1 1 1
West Division (Joyce Drive Police Station) ">'
Pre-Bid Conference
12 July 2017,10:00AM a�€c�buM nig.
Name Organization Address Te!ephone&FAX Email
3C-C)BL3Kz. 1t i 1
t c-- t
titE — vxie�� �-0 til
S2 0 �sr- Fc a� Z
)JG-SC co•w"t vac. c
-wm
Zt
�OSP��'1 ��rTl�l$Z �enca Co�ts���a� �� � 41,�tR>, X72 -ZZ6 -2bp �'�.N'1�.-•�9.Mez fQ Qe�1CvCs •Co1�
L,Ae- /k yG/3S fs17��37-�1�J �f'y/D��/ ao/,eco
6719�f zt___,�V4
17,412 IRIwK.17,(
J�So� ali�t� �cmo CG>wt gn7alt Ty�
16,41. J5`7 0
rnie A47"-SrcJI'S/ e 3/0a Llvme Cc 17-653-JIOZ _S'� e �c��fi7`r is/tel tangy
i2G.frE: V�lif�
�4L �1d`��STiaFf 4.CC~ c2DC.t' c�:� _k &�-(,c O�cc� �kQAf�4� ctrc tz
�'�iGrt7 GL���cXL KEY Cct- 5r zT ZI14.7-Zb.8S8Z CC- eK_-
12Cd1 Wf'�Til -� c�
3r� fJ/�57�'L C�W fi,.w yard ,«'6✓aa /i-39���O a��JAsaEs,a�FsrF F.ar�.�ar,�Tfx .Gvv
I
City of Fort Worth
Property Management Department
Facilities DivisionfArchitectural Services
401 West 13th Street*Fort Worth,TX 76102 Page Of 9-
West Division (Joyce Drive Police Station)
Pre-Bid Conference
12 July 2017,10:00AM
Name Orcianization Address l Telephone&FAX Email 11
0
r ZOS U r�{„a
,r to4_gyg_�st
;s Fa B a
i431 (o il^ 5� rJ C.'303- 2 eO-82-18 L,+'�T7'rCa Ci b r�zoS V�� a tew
it
f r ` r UfrL�,a L 2 5 Ci{ 7M
200g P L'$zA 9K ?z St`I- '7(-23V.0 I_Vf?EV 63 f'1o01 fZucTRS Cain
�FK lob fZN CONT+"Cio2 ';EDFOtZD TX76aziF= `b(7-571 -5505
A-V t ril 3e33 cep �.�eL Z/5L S`f7' C—_
lZ/soh-vr�1
��d ��" Z>A_4_ f� �K.
'7T-. rJtJ?"
24v FC mr7>-2/ Iv1��e�rsr��J �?�1 w)
27g6 z' 6 LAO h"1 �fi 2i'f�d5`06)Z �ST;M t)��� jq
�`t'i/17�� �n�"-�vP'r�5-e5 �`.;,t„� ��r�.12- 7�4 3'� `�33dti� A2T��1�-0/�1�6 .�v✓�
City of Fort Worth
Property Management Department
Facilities Division/Architectural Services
401 West 13th Street*Fort Worth,TX 76102Page Z Of A,
West Division (Joyce Drive Police Station)
Pre-Bid Conference
12 July 2017,10:OOAM
Name Organization Address Telephone&FAX Email
'1�11t t I pv`~a;rc ,, 2 t�k �G 4�sD ree✓1 CCar�cin
��Zt eras a � � -76Z5rna �` c
�� ' ��ttc.o,� 1
150 3 �(Z"Y S7
ENn/t� --+r-_RV; 6Y75u& . 972.72./-/5-zz
54 l�
?M.
j
�PVi� qyyr C5�{ t>tr ��r7Z�I~Ot�l� rY 6Gt
GJ JNE,77 U t/ uLt-Lisl �(�� b�O"e'e_' 6akkvr "fit uS.GOm
W'11 I(C_jCAIN LI
Z�+(n0 'T¢c1 r�aj�OJt� teal @ Coo�,cy Cd{1,CcS�t
�b �t �eeclavl loo G-,.C. loo P1�nne T4 97o2- 7'fc -313
L � vbUr1 1�rr,7 tJor+a pa. bn (�F52-3�s- �3v2 �uteo�2u�nFcrrr,� C.
;nI
City of Fort Worth
Property Management Department
Facilities Division/Architectural Services
401 West 13th Street'Fort Worth,TX 76162 Page-3 of 4
West Division (Joyce Drive Police Station)
Pre-Bid Conference
12 July 2017,10:OOAM
Name Organization Address Telephone&FAX Email
�.`etlt�t� Bu er-s RuM �t-t 3�� 09-7f k—bU_Y--71� - r., M?tce Caw,
as.611v
(2MP L
rGf�t /
L. fle-leet f jlelk 9173 '!52W Gr9�J Jrf) t� tri f? % �.CUrY
'PA-"f, L-6v COz 7 S 9l7-Z39– ,953 d,vee c1tz5�cnterr zj.
cx--r"(C K I— &K-0 c/P Ej r 17 09t q,605— SMcc,.0 Fr t
71
V612-
!//u3O-5�w2LGK J /Jf�Z
City of Fart Worth
Property Management Department
Facilities Division/Architectural Services
401 West 13th Street*Fort Worth,TX 76102 Page of
QRT' 0RT
ow
CITY OF FORT WORTH
PROPERTY MANAGEMENT DEPARTMENT
ADDENDUM NO. 2
WEST PATROL DIVISION (JOYCE DRIVE POLICE STATION)
Request for Proposals Submittal Date: August 3, 2017 (NO CHANGE)
The Request for Proposals for the above project is hereby revised and amended as follows:
1. A revised"Proposal"is included as part of this addendum and dated, July 28, 2017.
(Attachment No. 1)
2. Elements of Architecture, Inc.Addendum No. 2 cover letter dated July 28, 2017 with attached
revised/added specifications and drawings, and responses to contractors' questions.
(Attachment No. 2)
Acknowledge the receipt of this Addendum No. 2 on your Proposal.
Steve Cook
Director, Property Management Department
By:
Alfonso Meza
Project Manager, Architectural Services
PMD, Facilities Division
817-392-8274, FAX 817-392-8488
Alfonso.Mezac@fortworthtexas.gov
RELEASE DATE:July 28, 2017
Addendum No.2 Page 1 of 1
West Division—Joyce Drive Police Station July 2017
so"
PAGE LEFT BLANK INTENTIONALLY
PROPOSAL(Rev.July 28,2017)
■w
T0: MR. DAVID COOKE
CITY MANAGER
ATTN: PURCHASING OFFICE
MR 200 TEXAS STREET
CITY OF FORT WORTH,TEXAS
FOR: West Patrol Division (Joyce Drive Police Station)
3532 Joyce Drive
Fort Worth,Texas
.. PMD2014-09
City Project#100172
Pursuant to the foregoing "Instructions to Offerors," the undersigned has thoroughly examined the plans,
* specifications and the site, understands the amount of work to be done, and hereby proposes to do all the
work and furnish all labor, equipment and materials necessary to fully complete all the work as provided
in the plans and specifications, and subject to the inspection and approval of the Director of
.. Transportation and Public Works of the City of Fort Worth.
Upon acceptance of this Proposal by the City Council, the bidder is bound to execute a contract and, if
the contract amount exceeds $25,000.00, furnish acceptable Performance and/or Payment Bonds
^� approved by the City of Fort Worth for performing and completing the Work within the time stated and for
the following sum,to wit:
DESCRIPTION OF ITEMS
$ Base Proposal
Calendar Days
Owner's Contingency Allowance (7.5%) added to Base
Proposal (This Allowance amount is not included in the Base Proposal but is added to the Base
Proposal. Only the Owner will approve the use of this Allowance during construction. Any
Allowance remaining at the end of construction will be retained by the City of Fort Worth).
Base Proposal Plus Owner's Contingency Allowance
ALLOWANCES
Allowance No. 1 —Irrigation System: Include a cash allowance of$5,000.00 for restoration of
existing irrigation system.
Allowance No. 2—Corner Guards:Contractor to provide a cash allowance of$
for material &labor for 40 corner guards as specified.
ALTERNATES
Add Alternate No. 1 —Roof Replacement: Provide new fluid applied protective membrane as
specified.
Add Alternate#1 DELETED—NOT APPLICABLE.
Instruction to Offerors(Feb 2017) Page 9 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 June 2017
Add Alternate No. 2—Lockers: Purchase and install new lockers in Room 110 as specified.
Add Alternate#2 $
Add Alternate No. 3—Lockers: Provide power to each locker with internal power outlets as shown
in the Electrical documents.
Add Alternate#3 $ Rooms 110.
$ Rooms 121, 129, & 130.
Add Alternate No. 4—Exterior Painting: Paint all exterior metal soffits,fasciae, &columns per
requirements outlined in specifications.
Add Alternate#4 $
Add Alternate No. 5—Gate Operators: In lieu of Owner-provided gate motors, Contractor to
purchase and install equipment. Contractor to coordinate installation with Owner's fencing
contractor.
Add Alternate#5 $ ..
Add Alternate No. 6—Ceilings: Existing ceilings in the following rooms are to be removed and
replaced with new ceilings as specified: Open Offices(104, 106, 113, 114, 136); Small Group
Training (135);Offices (137, 138, 139, 140, 144);Vestibule (141); Egress Corridor(142);Corridor
(145); and Copy(143).
Add Alternate#6 $ ,,..
Add Alternate No. 7—Solid Surfacing countertops: In lieu of plastic laminate countertops,
purchase and install solid surfacing countertops as specified.
Add Alternate#7 $
UNIT PRICES—N/A
The undersigned agrees to complete the Work within the calendar days specified above after the date of
Notice to Proceed. A Project Schedule will be submitted as required in the Instructions to Offeror.
The City reserves the right to accept or reject any and all bids or any combination thereof proposed for r..
the above work.
The undersigned assures that its employees and applicants for employment and those of any labor
organization, subcontractors or employment agency in either furnishing or referring employee applicants
to the undersigned are not discriminated against as prohibited by the terms of City Ordinance 7278 as
amended by City Ordinance 7400 (Fort Worth City Code Section 13A-21 through 13A-29).
Residency of Offerors: The 1985 Session of the Texas Legislature passed house Bill 620 relative to the
award of contracts to non-resident bidders. The law provides that, in order to be awarded a contract as
low bidder, non-resident bidders (out of state contractors whose corporate offices or principal place of
business are outside of the State of Texas) that bid projects for construction, improvements, supplies or
services in Texas at an amount lower than the lowest Texas resident bidder by the same amount that
Texas resident bidder would be required to underbid a non-resident bidder in order to obtain a
comparable contract in the state in which the non-resident's principal place of business is located. The
Instruction to Offerors(Feb 2017) Page 10 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 June 2017
appropriate blanks in Section A must be filled out by all non-resident bidders in order for your bid to meet
specifications.
The failure of out of state or non-resident bidders to complete the forms may disqualify that bidder.
Resident bidders must check the box in Section B.
.. A. 1_1 Non-resident vendors in (give state), our principal place of
business, are required to be percent lower than resident bidders by state
law.
LI Non-resident vendors in (give state), are not required to
underbid resident bidders.
B. I_I Our principal place of business or corporate offices are in the State of
..s Texas.
Within ten (10) days of receipt of notice of acceptance of this bid,the successful bidder will execute the
formal contract and will deliver approved Performance and Payment Bonds for the faithful performance of
this contact. The attached deposit check in the sum of
.. Dollars ($ ) is to become the property of the City of Fort Worth,Texas, or
the attached Bidder's Bond is to be forfeited in the event the contract and bonds are not executed within
the time set forth, as liquidated damages for delay and additional work caused thereby.
�* MINORITY BUSINESS ENTERPRISE (MBE): (For Proposals in excess of$50,000)
1 am aware that I must submit information to the Director, Property Management Department,
concerning the MBE participation within FIVE BUSINESS DAYS of submittal of this Proposal in order
to be considered RESPONSIVE.
Respectfully submitted,
Company Name
By:
Signature
Printed Name of Principal Title
Address:
�. Street
^� City Zip
Phone:
Fax:
Email:
Receipt is acknowledged of the following addenda:
Addendum No. 1: Addendum No.2:
Instruction to Offerors(Feb 2017) Page 11 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station), PMD2014-09,City Project#100172 June 2017
Addendum No.3: Addendum No.4:
Addendum No. 5: Addendum No. 6:
Addendum No. 7: Addendum No. 8:
Addendum No. 9: Addendum No. 10: .*
Instruction to Offerors(Feb 2017) Page 12 of 33 '"0
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 June 2017
ELEMENTS
of Architecture, Inc.
ADDENDUM No. 2
City of Fol Worth
401 W. 13''Street
Fort Worth,Texas 76102
Elements Project No. 14-1006.00
Date: 07/28/2017
..
TO THE BIDDERS OF RECORD:
This addendum forms a part of the Contract Documents, dated October 24, 2016,which supersedes and
supplements all portions of the documents with which it conflicts.
Bids remain due on August 3, 2017 as noted in Addendum No. 1. Note that only one original is required to
be submitted.
wir
The following refers to Addendum items, by number,to the Project Manual and/or Drawings and
attachments as indicated below:
Architectural
ADD 2/01 Roofing
Reference Sheet GO.1,A2.2,A9.3 Specification Section ALTERNATES 01 23 00 and 07 57
00 Fluid Applied Protective Membrane
Documents reflect recovering of the roof as Alternate#I. This work Is already in progress
and is to be deleted as an alternate under this project, delete specification 07 57 00 Fluid
s applied protective membrane in its entirety and delete details on A9.3:03,04,05, 06&07
and delete general roofing notes on A9.3.The roofing material being installed is US ply
torch down modified system(white in color). it is assumed that the roofing will be
completed by the time this contract is executed. The contractor shall only use the roofer
designated by the City of Ft.Worth for continuous Warranty for all roof curbs and other
work on the roof to complete the project such that the warranty is to be maintained and the
details for installation are as required for this roofing.The cost for all work associated with
roof work for this project is to be included in bids.Contractor for roofing is:Justin Laird,
RoofMart International,Cell: (979)204-9155 Office: (469)952-5842
Email: liaird@roofrmi.com Web:www.roofrmi.com
ADD 2/02 Lockers
Reference Sheet GO.1,A2.1, E3.1 and Specification Section METAL WARDROBE LOCKERS
Based bid is to be revised to include providing and installing lockers in rooms 121, 129 and
130 in lieu of owner furnished. Alternate#2 is to include providing and installing additional
lockers in room 110.
Alternate#3 is to provide the electrical for these lockers. Two line items are to be provided
that separate the electrical for lockers in Rooms 121, 129 and 130 as one cost and then
electrical for lockers in room 110 as the second line item. This should be reflected as
follows:
Provide electrical to lockers in Room 121, 129 and 130-$x.xx
Provide electrical to lockers in Room 110-$x.xx
These lockers are to be as shown on the drawings.All lockers are to be 18"wide and 2'
deep. Room 121 has 32 lockers+ 2 HC lockers =34 lockers total. Room 129 has 17 lockers
■. Addendum 2-Page 1 of 5
+ 3 HC lockers=20 lockers total. Room 130 has 31 lockers total.
Room 110 has 53 lockers+ 3 HC lockers=56 lockers total.
Changes to the locker information are to provide the internal components to be powder
coated steel to match the body material as noted and not stainless steel as per the
specifications. A sloped top is to be provided on all lockers and serve as a chase for the
electrical components. This is to be provided even if the alternate for the electrical is not
accepted.Given that an extended base drawer is to be provided, the 4"base should be
deleted except at the accessible locker locations were this base is still to be provided for
TAS compliance.
ADD 2/03 Irrigation and Landscaping ..■
Reference Sheet A1.1
All landscaping on site is to remain with no additional landscaping to be provided. If
construction damages any of the existing it will have to be replaced with the same species *�
and size. All landscaping to be protected during construction. As it is unknown the
condition of the existing irrigation system,for determining a cost associated with any work,
an allowance in the amount of$5,000.00 is to be included in the bid and reflected as
Allowance No. 1.
ADD 2/04 Drive-Thru Accessory Building
Reference Sheet Al.I
Any work illustrated to be performed on the accessory structures(s)to the north is to be
eliminated from the scope of the project. Note that the contractor is still responsible for all
work on the site and around these structures,just not the structures specifically.
ADD 2/05 Fencing,Gates,Access Control and Pavement Areas
Reference GO.1 GENERAL INFORMATION,A1.1 SITE PLAN and Specification Sections 32
21 11 GATE OPERATOR and 32 31 19 METAL FENCES AND GATES and 11 12 13 ACCESS
CONTROL
The City of Fort Worth has contracted with a separate vendor for providing and installing
the fencing,gates and operators that are illustrated within the documents.This includes w
demolition of the exiting fence on the west side of the property line where new gates are
being installed. Delete demo note#1 as all work to fencing is by Owner's Vendor.These
are shown for clarification as all electrical is to be included within the scope of this project
and as required for this work. The contractor is to coordinate with the city's vendor in all
aspects and to provide any support work associated with this installation, including but not
limited to patching of pavement,etc. Any patching of the pavement is to match the
existing. This includes the covering of the new waterline to the building. All access control
devices are to be provided and installed by the owner and are shown for clarification only ..
for the base bid of the project.
For Alternate#5,the contractor is to provide the cost for the equipment and the installation
for the gate motors and operators.
ADD 2/06 Casework
Reference GO.1,A5 series and A9 series drawings and specification sections 01 23 00
ALTERNATES, 06 41 00 ARCHITECTURAL WOOD CASEWORK and section 06 61 19 SOLID
SURFACING FABRICATIONS
Base Bid:All casework is plastic laminate as shown on cabinet sections.
Add Alternate#7: Price for Solid Surface to be used in lieu of plastic laminate for counter
tops.
ADD 2/07 Cast Stone Sealing
Reference specifications section 07 19 00 WATER REPELLENTS
This section is to be deleted in its in entirety.
Addendum 2 - Page 2 of 5
r
so
ON
ADD 2/08 Chair Rails and Comer Guards
r Reference specification section 10 26 00 WALL AND DOOR PROTECTION
Chair rails to be provided around the perimeter of the following rooms where walls are
gypsum board:Chair rail is to be"Pawlings", model #770 in lieu of the Koroguard C800 as
specified. No substitutions allowed.
Small Group Training 133
Break Room 126
Waiting 130
Interview Rooms 146-149
Roll Call &Training 112
Comer guards to be as noted in specifications with the exception of size.Comer guards to
be 4"x4 in lieu of 2"x2"as specified.
Comer guard locations to be determined. To determine pricing, provide an allowance for
providing and installing corner guards as specified for 40 outside comers. This is to be
reflected as Allowance No. 2.
ADD 2/09 Reference City of Ft.Worth Design Standards and General Conditions and Project
Management
(available on Buzzsaw)
Reference July 2017 updated Facilities Division Design Guidelines for New and Existing
Facilities.
Updated standards have been issued by the City of Fort Worth and can be found on the
city's Bi 177 site. All work as well as project management processes are to follow these
standards. Any discrepancies are to be brought to the attention of the Owner/Architect
with pricing for bidding purposes to assume the most costly and most restrictive.
Reference specifications section 01 31 00 PROJECT MANAGEMENTS AND COORDINATION
Progress meetings are to be held bi-monthly.
Reference specifications section 01 45 23 TESTING AND INSPECTION SERVICES
City of Fort Worth is Responsible for, not the General Contractor as specified, including any
w air quality testing if required.
Reference specifications section 01 50 00 TEMPORARY FACILITIES AND CONTROLS
The Contractor is responsible for all temporary utility usage costs.
wr
ADD 2/10 Interior Finishes and A2.4 Finish Schedules
09 30 00 Tiling—Item 2.01.B.2-Size and Shape of floor tile to be 4"in lieu of 2"as noted
in specifications.
w
09 5100 Acoustical Ceilings-item 2.01.C.1:ACT-1 to be Armstrong model #770 Cortega
24"x24" in lieu of 24"x48"
w 09 68 13 Tile Carpet:Change item 2.01.A.1 —Design to be based on Mannington
Commercial,style: Halftime, Color:Cobb in lieu of Shaw,
www.manningtoncommercial.com
Change item 2.02.B.1 a-q—to be Mannington Commercial,style: Halftime, Color:Cobb
09 91 00 Paints and Coatings:Change 2.04.A from latex to oil base with a semi-gloss
finish, 2 coats. Refer to Div 09 Finishes in City of Ft.Worth Design Guidelines July 2017 for
all interior door/frames/woodwork/trim-paint shall be oil base with semi-gloss finish
"r 12 24 13 Interior Light Control Fixed Window Shades
Item 2.01 Manufacturers Add A8. Draper Inc. Fixed Panel Flex Shades,www.drar)erinc.com
as an acceptable manufacture.
A2.4 Finish Schedule, refer to sketch A3
.w Addendum 2-Page 3 of 5
In Vest 101, Entry Corridor 102, Reception 103, Waiting 150 and Vest 141 existing terrazzo rr
floor to remain,and to be refinished, extents noted on Sheet AZ.1. Copy 143,Office 136,
Corridor Egress 142 and Office 105 all to receive new flooring per the finish schedule.The
existing terrazzo floor to remain when new finishes are applied per A1.3 Demolition Plan. .d
ADD 2/11 10 11 00 Visual Display Boards, 11 31 00 Residential Appliances, A2.1 Floor Plan,and
A5 Series Elevations
10 11 00-Delete specification Section in its entirety
Marker&Tack Boards are Owner furnished and Owner installed.
11 31 00 Residential Appliances, Delete section in its entirety
Owner to provide all Residential Appliances -
ADD 2/12 Toilet Partitions
Toilet partitions to be high density plastic in lieu of metal toilet partitions as specified.
Replace specification section 10 21 14 METAL TOILET COMPARTMETNS with 10 21 16
PLASTIC TOILET COMPARTMENTS, included in this addendum.
ADD 2/13 Miscellaneous Plan Changes
Reference A1.3 Demolition Plan and A2.1 Floor Plan
Attached plans are revised to reflect change in finishes and changes to address demolition
and repair work from asbestos abatement
For clarlfication,wall types are designated with letters as shown on GO.1 in the SYMBOLS
LEGEND
ADD 2/14 A2.3 Door S Window Schedules and A8.1 Sections and Details
Door 109 is to be modifled as follows: Existing vault door and frame is to be removed and
replaced with standard hollow metal frame and wood doors to match existing. Infill wall as
required to align with existing conditions. ..
New Door&Frame 109: Door Size 3x7/Door Type A/Door Material WD/ Door Finish ST/
Door Label-none/Frame Type B/Frame Material HM/Frame Finish PT/Hardware Set 12/
Details Head: 1/A8.1/jamb 2/A8.1/Sill 3/A8.1/Remarks-none
Door 110 is to be modified as follows: Existing vault door and frame is to be removed and
replaced with standard hollow metal frame and wood doors to match existing. Infill wall as
required to align with existing conditions.
New Door&Frame 1 10 to be: Door Size 3x7/Door Type A/Door Material WD/Door Finish
ST/Door Label-none/Frame Type B/Frame Material HM/Frame Finish PT/Hardware Set
12/Details: Headl7/A8.1/jamb 18/A8.1/Sill 3/A8.1 /Remarks—none. Add head
detail I7/A8.1 and jamb detail 18/A8.1, refer to attached sketches:Al &A2 ..,
Door 137 was removed during abatement and now needs to be replaced.
New Door 137 to be 3x7(Field Measure Existing Frame)and Door Type B/Door Material
WD/Door Finish PT/Hardware Set#3 .•
Door Schedule remarks: Delete Remark#I in its entirety as bank vault doors are being
removed.
Clarification:Door 151 is not a ballistic core door and refer to materials legend for ST
definition.
ADD 2/15 A6.1 Reflected Ceiling Plan
Office 137, 138, 139 & 144—to receive all new ceilings, refer A2.4 Finish Schedules
Add General Note 3: In all existing ceilings to remain, replace any missing, damaged or
stained ceiling tile. Fix any existing light fixtures to remain so they are set properly in the '®
ceiling grid&replace any bulbs/ballasts that are not working. Existing ceilings&grid to
remain will need to be cleaned.
Addendum 2-Page 4 of 5
wr
Alternate#6 is to replace all ceilings noted as remaining and is still to be priced.
■w ADD 2/16 Removal of Debris
Reference A1.3 Demolition Plan, Notes by symbol 30
The building has been used for temporary storage by Police for miscellaneous office fixtures,
equipment, boxes of files, etc.All is being removed by Police and will be removed by the
time the contract is awarded.All building elements that have been removed but stored on
site after abatement will still need to be removed and disposed of by General Contractor
with cost included in bid.
ADD 2/17 A2.2 Roof Plan
Construction Notes by Symbol. Revise Note 15 to Read: Line of existing windows and or
masonry walls below upper roof level, re-set and re-caulk existing upper fascia on travertine
— panels and/or windows per condition.
ADD 2/18 01 21 00 Allowances
Add section in its entirety,see attached specification.
Plumbing
ADD 2/19 P0.2 Plumbing Schedules
Reference'Thermostatic Mixing Valve Schedule'-change Model number from 320 to
"3208.
Electrical
ADD 2/20 E3.1 Power Plan -Electrical
Add panel LCP-1 adjacent and to the west of new panel C
Refer to specification section 260923, paragraph 2.1
Clarification:This project includes power and raceway provisions for card readers,gate
operators and other security devices. It does not include the security systems themselves,
including but not limited to security cameras, card readers and intercom system.These
systems will be provided by the city under a separate contract.
ADD 2/21 E4.1 Power Plan -Electrical
Add ID 103 to feeder schedule. Add "3#1,#8G,1-1/4"C"to corresponding description.
Panel DA contains circuit breakers that protect panels A and B. Both, protection,feeders
and panels are existing to remain.
ADD 2/22 ESA Schedules- Electrical
Panel schedule for panel DPF is shown on sheet E5.1. Include in bid, replacement of all
branch circuit breakers. Added circuits to existing panels. UL listed will likely not be
available. Used and reconditioned units may be the only option.This will be considered on
a case-by-case basis during construction.
END OF ADDENDUM—2
.r
Addendum 2- Page 5 of 5
OR
ow
ow
..
on
■.
PAGE LEFT BLANK INTENTIONALLY ..
r
SECTION 01 21 00
ALLOWANCES
PART 1 -GENERAL
1.01 SUMMARY
A. Section Includes:
1. Cash allowances.
2. Contingency allowance.
B. Related Sections
1. Section 012900-Payment Procedures.
2. Section 01 3216-Construction Progress Schedules.
3. Individual specification sections.
C. Include in Contract Sum cash allowances scheduled at end of Section
D. Designate in Construction Progress Schedule specified in Section 01 3216 delivery dates for products
under each allowance.
E. Designate in Schedule of Values specified in Section 01 2900 quantities of materials specified under unit
cost allowances.
1.02 CASH ALLOWANCES
A. General:
1. Purchase products under each allowance as directed by Architect.
2. Amount of allowance includes:
a. Net cost of product, less any applicable trade discounts.
b. Delivery to site.
c. Applicable taxes.
" d. Labor required under allowance, only when labor is specified to be included in allowance.
3. In addition to amounts of allowances, include in Contract Sum, Contractor's costs for:
a. Handling at site, including unloading, uncrating, and storing.
b. Protection from elements and from damage.
c. Labor required for installation and finishing, except where installation is specified to be part of
allowance.
d. Other expenses required to complete installation.
e. Overhead and profit.
B. Selection of Products:
1. Architect's Duties:
A. a. Consult with Contractor in consideration of products and suppliers.
b. Make selection; designate products to be used.
c. Prepare Change Orders.
2. Contractor's Duties:
a. Assist Architect in determining:
1) Supplier or installer, as applicable.
2) Cost, delivered and unloaded at site.
b. Obtain proposals from suppliers when requested by Architect.
c. Notify Architect of any effect anticipated by selection of product or supplier under consideration
on construction schedule or contract sum.
d. On notification of selection, enter into purchase agreement with designated supplier.
C. Delivery:
1. Contractor's Duties:
a. Arrange for delivery and unloading.
�.. b. Promptly inspect products for damage or defects.
c. Submit any claims for transportation damage.
D. Installation: Comply with requirements of referenced specification section.
" E. Adjustment of Costs:
City of Fort Worth Addendum 2-01 21 00- 1 ALLOWANCES
'� Joyce Drive Police Station
on
1. Should actual purchase cost be more or less than specified amount of allowance, Contract Sum will
be adjusted by Change Order equal to amount of difference.
2. Amount of Change Order will recognize any changes in handling costs at site, labor, installation
costs, overhead, profit, and other expenses caused by selection under allowance.
3. For products specified under unit cost allowance, unit cost shall apply to quantity listed in Schedule of
Values.
4. Submit invoices or other data to substantiate quantity actually used.
5. Submit any claims for additional costs at site or other expenses caused by selection under
allowances, prior to execution of work. Failure to do so will constitute waiver of claims for additional
costs.
PART 2-PRODUCTS -NOT USED ..
PART 3 -EXECUTION -NOT USED
3.01 ALLOWANCE SCHEDULE
A. Irrigation Allowance:
1. Include a cash allowance of$5,000.00, as noted in this addendum
B. Corner Guards
1. Price for 40 Corner Guards per specification section 10 26 00 WALL AND DOOR PROTECTION and
this addendum.
END OF SECTION
City of Fort Worth Addendum 2-01 21 00-2 ALLOWANCES
Joyce Drive Police Station
SECTION 10 16 00
PLASTIC TOILET COMPARTMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Solid plastic toilet compartments.
B. Urinal screens.
1.02 REFERENCE STANDARDS
A. ASTM A666-Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel
Sheet, Strip, Plate, and Flat Bar; current edition.
B. NFPA 286-Standard Methods of Fire Tests for Evaluating Contribution of Wall and Ceiling
Interior Finish to Room Fire Growth; current edition.
1.03 ADMINISTRATIVE REQUIREMENTS
A. Coordination: Coordinate the work with placement of support framing and anchors in walls and
ceilings.
1.04 SUBMITTALS
A. See Division 1 Sections, for submittal procedures.
B. Shop Drawings: Indicate partition plan, elevation views, dimensions, details of wall supports,
door swings.
C. Product Data: Provide data on panel construction, hardware, and accessories.
D. Samples: Submit two samples of partition panels, illustrating panel finish,color, and sheen.
E. Manufacturer's Installation Instructions: Indicate special procedures.
PART 2 PRODUCTS
2.01 MANUFACTURERS
— A. Basis of Design Manufacturer for Solid Plastic Toilet Compartments and Urinal Screens.
1. Scranton Products: www.scrantonproducts.com.
B. Other Acceptable Manufacturers
1. Metpar Corp: www.metpar.com.
2. Bradley Coporation: www.bradleycorp.com.
3. Substitutions: See Division 1 Sections for substitution procedures.
2.02 SOLID PLASTIC TOILET COMPARTMENTS
A. Basis of Design Product: Hiney Hiders, floor and ceiling anchored, manufactured by Scranton
Products.
B. Toilet Compartments: Factory fabricated doors, pilasters, and divider panels made of solid
molded high density polyethylene(HDPE), tested in accordance with NFPA 286, floor-mounted
unbraced.
1. Color: To be selected by Architect.
C. Doors:
1. Thickness: 1 inch.
2. Width: 24 inch.
3. Width for Handicapped Use: 36 inch, out-swinging.
4. Height: 55 inch.
D. Panels:
1. Thickness: 1 inch.
2. Height: 55 inch.
City of Fort Worth
Joyce Drive Police Station Addendum 2-10 16 00-1 Plastic Toilet Compartments
E. Pilasters:
1. Thickness: 1 inch.
2. Width: As required to fit space; minimum 3 inch.
F. Substitutions: See Division 1 Section for substitution procedures.
2.03 WALL HUNG URINAL SCREENS
A. Basis of Design Product: Manufactured by Scranton Products. .�.
1. Factory fabricated screens made of solid molded high density polyethylene(HDPE)
tested in accordance with NFPA 286.
B. Substitutions: See Division 1 Section for substitution procedures.
2.04 ACCESSORIES
A. Pilaster Shoes: Formed ASTM A666, Type 304 stainless steel with No. 4 finish, 3 in high,
concealing floor fastenings. —
1. Provide adjustment for floor variations with screw jack through steel saddles integral with
pilaster.
2. Provide ceiling attachment using two adjustable hanging studs, attached to above-ceiling
framing. —
B. Head Rails: Hollow anodized aluminum, 1 by 1-1/2 inch size,with anti-grip profile and cast
socket wail brackets.
C. Pilaster Brackets: Satin stainless steel.
D. Wall Brackets: Continuous type, satin stainless steel.
E. Attachments, Screws, and Bolts: Stainless steel ,tamper proof type.
1. For attaching panels and pilasters to brackets: Through-bolts and nuts ; tamper proof.
F. Hardware: Satin stainless steel:
1. Pivot hinges, gravity type, adjustable for door close positioning; two per door.
2. Nylon bearings. --
3. Door Latch: Slide type with exterior emergency access feature.
4. Door strike and keeper with rubber bumper; mounted on pilaster in alignment with door
latch.
5. Coat hook with rubber bumper; one per compartment, mounted on door.
6. Provide door pull for outswinging doors.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify correct spacing of and between plumbing fixtures.
C. Verify correct location of built-in framing, anchorage, and bracing.
3.02 INSTALLATION ...
A. Install partitions secure, rigid, plumb, and level in accordance with manufacturer's instructions.
B. Maintain 3/8 to 1/2 inch space between wall and panels and between wall and end pilasters.
C. Attach panel brackets securely to walls using anchor devices.
D. Attach panels and pilasters to brackets. Locate head rail joints at pilaster center lines.
E. Field touch-up of scratches or damaged finish will not be permitted. Replace damaged or
scratched materials with new materials.
3.03 TOLERANCES
A. Maximum Variation From True Position: 1/4 inch.
B. Maximum Variation From Plumb: 1/8 inch.
City of Fort Worth
Joyce Drive Police Station Addendum 2- 10 16 00-2 Plastic Toilet Compartments
3.04 ADJUSTING
A. Adjust and align hardware to uniform clearance at vertical edge of doors, not exceeding 3/16
inch.
B. Adjust hinges to position doors in partial opening position when unlatched. Return out-swinging
doors to closed position.
C. Adjust adjacent components for consistency of line or plane.
END OF SECTION
.Nr
w
City of Fort Worth
Joyce Drive Police Station Addendum 2-10 16 00-3 Plastic Toilet Compartments
PAGE LEFT BLANK INTENTIONALLY
< ELEMENTS
"v"i...........
i...........
-T------------ ----------------------------------
( CONFlOENIIPI MIO PROPRIEIPRY
------------------------I
FoRTWoRT
-----------------
CITY OF
----------- � �
------ FORT WORTH
----------------
I 1
Joyce Drive
080 Police Station
A0 r",
----------- - - ------------------ --------
`j Fon worth,nc psi s
.. . ...........
14
--- -------
Demolition Plan on 10
-DEMOLITIONS NOTES BY SYMBOL - .-LEGEND,'
(D
NE-RAL NOTES; Demolition Poan
=%x
I A1.3:: 'j
ELEMENTS
rnac;xnur.,rK.
_.., , , canrioEvnu ar;o aaoPR crnar
s
marirs orrsce office _
FoxT�WoxTxo
❑3 CITY OF
ro 7L d R O f Z� s FORT WORTH
; E `-" P x Joyce Drive
O - EPolice Station
- \� _. I , �•' _,. �—fnI1I nD OF] CE)Ii�L`?.I $1. y ti� \ i �i 3532 JOYce Odra
�'II Port Worth,TX]6t 16
5
"i.,"N�L11111LLW IC7 j _
❑ a is i
uo
❑ ._ _ +�g �,i 'i � worm
m
❑ —_
-
wmnoa
�m
r _ -
1 Ground Floor Plan
`<= a e• it u
GE�CONSTRUCTION-NOTES CE0EN0 J r CONSTRUCTION NOTES 9Y SYMBOL
El
wooEl
Floc Ian
F-1 El
X15TING INTERIOR WAL
EXSTI NG
BRICK WALL
WITH CMU
BACKING
NEW BRICK
LINTEL, REP.
5TRUCTURAL
t� 5EALANT
N=t EACH 51DE
Q
lu -H.M. FRAME
t�
DOOR A5
50HEDULED
21/411 5 3/4"
J
Head Detail
0 4" 8., V-0"
FORT11,
ADDENDUM 2 PAGE#:
TWOR LIENT/PROJECT NAME: ELEMENTS Al
Y City of Fort Worth o Architecture,Inc.
Joyce Drive Police Station Elements projec;914_10W00
X15TIN6 INTERIOR-HALL,,
EXSTI NG
BRICK WALL P
j WITH CMU
I BACKING
C
SEALANT
----------- ---------- EACH SIDE
JAMB ANCHOR
L--------------------------J 5 EA. JAMB
w
FRAME
-POOR AS
SCHEDULED w
2 1/4" 55/411
Jamb Detail 2
1 8 K
0 4' 8" 1'-0"
ADDENDUM 2 PAGE 4:
FORTWORT cu_vr,PROJECT NAr�F: ELEMENTS A2
City of Fort Worth
of Architecture,Inc.
W_
Joyce Drive Police Station Dements Project#:14-1006.00 July 27,[Ut7
ROOM FOW
w FILING
R ROOM HANE FLOOR y - FIEWJIKS
NORTH EABT 801IfH WE8T NORTH EAST 80Uili YVEBT} T 7 14:88 I
101 VMTIaLE --
� ;exlsr 813-1 EXIST RB-1 813-1 PI4 EXISTNr-I"I
En
ACT-[ i N;. ._�
107 ENTW CORRIDOR 1ST RB-I RS-I RB-I R6-1 I°iT'-1 PT-I ACT-1
109 REGIFTION EXIST RB-I REW RB-1 R3N PI'-N PT-1(04 OPEN OFFICE GPf-1 RB-1 RB-I RSI WA
106 OPBI OFFICE CpT-I RB-I EX15T exleTA-0-1 RS-1 PPI EXIST EXIST PT-1 EXIST EXIST
107 STORAGE GPT-I RB-1 RB-! Re-if R5-1 P'f-I Pr-I PT-1 PT-1 AGT-I Db'
IOD STORAGE GPT-I RB-I REA RB-I RB-1 Pf-I PT-I IFT-I Pr-I ACT-I b'-0'
0 109 VAIA.T SG RB-I RB-I RB-I R8-1 PT-I PT-1 FT-4 Pf-1 EXIST EXIST #[,05
IIAffgyp ST . 915 �IPr,;�. 9-I_-T
uD OPEN OFFICE GPT-1 R5-1 R15-•1 " RB-1 ST Pr-1 IF-1 Pr-1 ST EXIST EXIST ` w (Y 7 —
114 OPEN OFFICE c-r-1 RB 1 8134 RIS-1 Pr-1/ST Pr-1 PT-1 Pr-1 Pr-Var Ex1sr Ex15r N `�
115 LNISEX TOILET GT-I GT-1 CT-1 GT-1 GT-I GT-VPT-I GT-Wr-I GT-1/Pr-I GT-UPr-I A4T-2 9'-0' -_
Ila CORRIDOR CPPI RB-1 MIA RB-1 RB-1 PTH PPI PPI PT-1 ACT-I 9b' Na
IR CORRIDOR GPr-I RB-I REA RB-1 REA PT-I Pr-1 PM1I Pr-I ACT-I 9b' -- �
190 MENS LOGI®i5 II GT-I GT-1 6T-I GT-I GT-I G7-II1'r-I GT-IipT-1 GT-1/PT-1 GT-VPr-I ACT-2 9b'
IDI MENS SHOVER 1 07-1 GT-I GT-I GT-1 GT-1 GT-1/PT-1 GT-IAS I GT-VPr-I GT-VPr-1 SEWT 9'-0'
152 MENS SHOMR If GT-I GT-I GT-I GT-1 GT-1 GT-1A-T-I -UPT-4 GT-VPr-I GT-WT-I 66/YT 9b'
193 MECHANICAL EXIST EXIST EXIST EX15T EXIST EXIST EXIST EXIST EXIST EXIST EXIST
134 VESTIBULE VC-T-) RB-I RB-I RB-1 R5-I PT-1 PT-1 PPI Pr-1 ACT-1 9'-0'
199 SMALL GROUP TRAINING CPT-I EXIST EXIST MI5T/ST EXIST EXIST EXIST EXIST/5T EXIST EXIST EXIST 01,HSS,rtD
196 OPEN OFFICE CPT-I EXIST EXI9T/9T EXIST/37 Sr EXIST EXISTA3T EXIST)ST 9T 5 1ST 01,05
IDT OFFICE CPT-I EXI5Tl5T EXIST EXI57/ST,..T/5T E7CR9T/ST EXIST Pi-I E%15T/3T AGT-1 EXIST OS
NR IDD OFFICE Cpr--I MI5T/5T EXIST EXI5T/ST M,ST/sT Pr-I MIST Pf-f MiST/ST AGT-1 EXIST OS
199 OFFICE GPr-I CX15T/5T EXIST EX15T/5T EXIST/9T Pr-I EXIST PT-I EXIST/ST AGT-I EXIST 05
140 OFFICE GPT-I RB-I Fjt19T/ST RB-I RB-I PT-I EXIST/ST Pf-I Pf-! EXIST M5
141 VESTIBULE EXIST Exl9r/9r EXIST EXfST/ST EXIST EXIST/9T EXIST EXIST/ST EXIST EXIST EXIST of,02,
147 EGRP3S/GORRIDOR GPT-I MIST/ST EX19T RB- rj
I RB-I EXI5Th3T EXI5T PPI/9t Pr'-I EXIST EXIST W,MS 1
140 COPY GPT-I RB-I RB-I RB-I _1 -! PT-I PI'-I Pr-I -I 13T._ EX�B,T'" 2
144 OFFICE CPr-I RB-1 RB-I EXI5TA3% �RE-I Pr-1 PM1I EXIST/9 PT-I AG7-I 10'-0' Ir5 '
-.
149 coRwDOR CPT-I RB-I RB--I wA -Rer1 Pr-I Pr-) WA
146 INTERVIEW ROOM CPPI EXI5T/sT EXi5T/ST RB-I RB-1 EXIST/ST EXIST/ST PPI Pr-I AGT-I 8'-O' M9
14T INTrERVILW ROOM 0P1=1 RB-I EXI5Ti5T RB-I RB-I PM1I EXIST/5T PPI Pr-I ACT-! D'-O' 03
14D INr@iVIEW ROOM CA -I R194 PXIST/5T R13-f RS-1 PT-I EXIST/ST Pr-1 PPI ACT-1 D'-0' 05
144 INTERVIEW ROOM CPr--I RB-I EXISTAST EXIST/ST RS-I PT-I L°XIST/ST EXIST/ST PT-I ACT-I D'-0' MS
ISO WAITING EXIST EXIST EXIST RBA RB-I EXIST EXIST Pr-I Pr-I AGT-I Db' 01,02
M
rfpil14f7 REMMM
-
#I- VERIFY EXISTING CONDITIONS TO REMAIN AND PATCH,REPLACE,OR PAINT AS REWIR®TO BRING TO LII-Z NEW CONDITIONS
02- RInNISH EXISTING TERRA=FLOORING
MLi
MD- REMOVE ALL EXISTING FLOORING 4 ADHESIVES PRIOR TO SEALING FLOOR
04- MOLNT A 410'x ab x 5/4'(T)51-EEr OF PLYWOOD LENGTH WISE TO SOUTH WALL OF ROOM. CENTER ON WALL.MOUNT BOTTOM EDGE AT
42'ABOVE FINISHED FLOOR PAINT TO MATCH WALL COLOR.
MS- RESTAIN EXISTING HOOD PANELING TO MATCH EXISTING STAIN FINISH AND COLOR
Mw
06- FINISH INSIDE OF DRIWING RDl1NTAIN ALCOVE(ALL SIDES)WITH GT-I FLOOR BASE,MID WALL FINISH. CT--I TO BE Sb'NIGH,PPI ABOVE
*I- FRF-I FINISH TO RUN FULL HEIGHT OF WALL FINISH WIDTH AT NORTH WALL TO BE 4'-6'FROM INSIDE BACK CORNER OF FLOOR
Ma- LEVEL SLAB TO PREPARE FOR NEW FLOOR FINISH
09- PROVIDE MOP HOLDERISHELF(TOILET ACCESSORY'S').PROVIDE STAINLESS STEEL AT WAILS 56'ABOVE JANITOR SPEC
010-PROVIDE TRAN51TION AT FLOOR MATERIAL CHANGE PER 21M.5(SIM)
I 2
ADD WOOD PMSJNG INLY'ftTS TO MATCH EXISTING WOOD PANELING AT DOOR INFILL
ADDENDUM 2
FORIMORTH CLIENT/PROJECT NAME: ELEMENTSA3
City o f Fort
Worth
orth of Architecture,Inc.
Joyce Drive Police Station Elements Project#:14-1006.00 July 27,2017
TRIS COPY IS FOR:
CONTRACTOR
CITY SECRETARY
SPONSORING DEPT
PROJECT MANAGER
PMD FILE COPY
THE CITY OF FORT WORTH, TEXAS
WEST PATROL DIVISION
(JOYCE DRIVE POLICE STATION)
PMD2014-09
CITY PROJECT #100172
FORTWORTHC,,,
BETSY PRICE DAVID COOKE
M�A'Y`; R CITY MANAGER
Steve Cooke
Director, Property Management Department
Joel Fitzgerald
Chief, Police Department
Elements of Architecture
October 2017
Instruction to Offerors(Feb 2017) Page 1 of 33
Citv of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
NOTICE TO OFFERORS
Proposals for the West Patrol Division (Joyce Drive Police Station), an interior renovation of an
.� existing building located at 3532 Joyce Drive in Fort Worth Texas, will be received at the Purchasing
Office, City of Fort Worth, 200 Texas Street, Fort Worth, 76102, until 1:30 P.M on Thursday, July 27,
2017, and will be opened and publicly read aloud approximately thirty minutes later in the Council
Chambers.
After evaluating the Proposals submitted, the City shall select the Offeror that offers the Best Value to the
City and enter into negotiations with that Offeror. The City may discuss with the selected Offeror options
for a scope or time modification and any price change associated with such modification.
The last day for questions from prospective Offerors is at 5:00 PM on Wednesday,July 19, 2017
A Pre-Proposal Conference and Walk-Through/Site Visit will be held at 10:00 A.M.,Wednesday,July
12, 2017 at 3532 Joyce Drive.
The offers will be valid for NINETY (90) calendar days. Estimated construction cost is approximately
$2,000,000 Base Bid. There are several Alternates for this project.
The Offeror will add a 7.5% Owner's Contingency Allowance on a separate line item on the Proposal
form and only the Owner will approve the use of this allowance during construction. Any Allowance
remaining at the end of construction will be retained by the City of Fort Worth. This Allowance is not to be
included in the Base Proposal and will not be used in the Best Value selection process.
Refer to the evaluation matrix for the selection of the Best Value Offeror in the Instructions to Offerors.
Refer to the Request for Proposal documents for the Minority Business Enterprise (MBE) Information.
MBE participation will be evaluated in awarding this Contract. The MBE participation goal will be
established and included in Addendum No. 1. Offerors must submit the attached Best Value Utilization
.� Form within 5 business days of submitting their Best Value Proposal. Failure to document proposed
attainment will remove the Proposal from further consideration.
Also, Refer to Section 2. MINORITY BUSINESS ENTERPRISE (MBE) (BEST VALUE PROPOSAL) in the
Instructions to Offerors.
Offerors must submit a bid bond with their proposal. Offeror(s) to whom an award of contract(s) is made
will be required to provide Payment and Performance Bonds and provide Contractors General Liability
and Statutory Workers Compensation Coverage.
.� If you intend to submit a Proposal, request you inform the Project Manager or Architect/Engineer
who can then inform the interested subcontractors,
General Contractors and Suppliers may make copies of the Instructions to Offerors, General Conditions,
Drawings, and Specifications through their printer. The construction documents are not available at the City
but may be viewed and printed on-line by cutting and pasting the following link into your browser:
https://proiectpoint.buzzsaw.com/fortworthgov/PMD%20Projects/West%2OPatrol%2ODivision?public Contact
+� the Project Manager, Alfonso Meza, at (817) 392-8274 or email Alfonso.Meza(a fortworthtexas.gov for
assistance. For additional information contact the Architect, Debbie Fulwiler, at (817) 333-2880 or email
dfulwiler(a-)elementsofarc.com .
Advertisement: June 22, 2017
June 29,2017
Instruction to Offerors(Feb 2017) Page 2 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
®" TABLE OF CONTENTS
PROJECT COVER PAGE
• NOTICE TO OFFERORS
• TABLE OF CONTENTS
• INSTRUCTIONS TO OFFERORS
• PROPOSALFORM
• CONFLICT OF INTEREST AFFIDAVIT
• CONFLICT OF INTEREST QUESTIONAIRE (CIQ)
CONFLICT DISCLOSURE STATEMENT(CIS)
• TEXAS SALES AND USE TAX EXEMPTION CERTIFICATE
2013 PREVAILING WAGE RATES
• WEATHER TABLE
• GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
• CONSTRUCTION CONTRACT
• PAYMENT BOND
• PERFORMANCE BOND
• CERTIFICATE OF INSURANCE
• CONTRACTOR COMPLIANCE WITH WORKERS'COMPENSATION LAW
• PROJECT SIGN
is
Instruction to Offerors(Feb 2017) Page 3 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
r.
PAGE LEFT BLANK INTENTIONALLY ..
A
w.
INSTRUCTIONS TO OFFERORS
1. PROPOSAL REQUIREMENTS: The following requirements shall be used in the preparation of
.■ the response to this Request for Sealed Proposals:
• Use the Proposal Form provided below.
• Entries on the Proposal Form may be handwritten or typed.
• Write in contract duration if not specified.
• Acknowledge all addenda on the Proposal Form.
• Have a Principal sign the Proposal. If the Offeror is a corporation, the president or a vice-
president must sign the Proposal. If the Offeror is a partnership, then the person/entity who
is the managing/general partner must sign the proposal.
• Complete and submit the Conflict of Interest Affidavit form. (Also submit associated Form CIQ
and Form CIS if required.)
+� • Include cashier's check or an acceptable bidder's bond written by a corporate surety payable
to the City of Fort Worth, in an amount of not less than five (5%) per cent of the total of the
bid submitted.
• In order for a surety to be acceptable to the City, the surety must (1) hold a certificate of
authority from the United States Secretary of the Treasury to qualify as a surety on
obligations permitted or required under federal law; or(2) have obtained reinsurance for any
�., liability in excess of$100,000 from a reinsurer that is authorized and admitted as a reinsurer
in the state of Texas and is the holder of a certificate of authority from the United States
Secretary of the Treasury to qualify as a surety on obligations permitted or required under
federal law. Satisfactory proof of any such reinsurance shall be provided to the City upon
request. The City, in its sole discretion, will determine the adequacy of the proof required
herein.
w
1A. SELECTION OF CONTRACTOR:
The City shall select the Offeror that offers the best value based upon the following criteria and
on its ranking evaluation.
In determining the Best Value Offeror, the City will consider:
1. Proposed Price (60 points) — The lowest priced responsive Proposal will receive 60
points for this rating criterion. Higher priced proposals will receive proportionally lower
scores. When compared to the lowest price, the higher priced proposal will have its
score reduced by one percent(1 point)for every percent it is higher than the lowest price.
The score will be rounded to the nearest whole number.
"■ 2. Proposed level of MBE participation (10 points).
3. Proposed project schedule (10 points) —The proposal with the shortest schedule will
receive 10 points for this rating criterion. Longer schedules will receive proportionally
lower scores.
4. References/Experience (10 points) - References and experience of the Offeror as
demonstrated by listing past and current projects including references with names and
current telephone numbers; and, list of subcontractors if applicable.
•. 5. Past relationship with the City(10 points)—Offeror's past relationship with the City of Fort
Worth for "vertical" facilities projects shall receive up to 10 points for this rating criterion.
If the Offeror does not have a past relationship with the City of Fort Worth, the Offeror will
receive 5 points for this rating criterion.
Instruction to Offerors(Feb 2017) Page 4 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
■w
6. If the score for any individual rating criteria is rated as zero, this will result in the overall
score being zero regardless of how many points could have been earned in the other
categories.
After ranking the responses to the Request for Proposal (RFP), the City shall first attempt to
negotiate a contract with the selected Offeror. The City and its architect may discuss with the
selected Offeror options for a scope or time modification and any price change associated with
the modification.
If the City is unable to negotiate a contract with the selected Offeror, the City shall, formally and in
writing, end negotiations with that Offeror and proceed to the next Offeror in the order of the
selection ranking until a contract is reached or all proposals are rejected.
2. MINORITY BUSINESS ENTERPRISE(MBE) (BEST VALUE PROPOSAL)
Minority Business Enterprise Provisions:
As of June 1, 2012, The City of Fort Worth implemented a new Business Diversity Ordinance
(BDO) to reflect the City's availability and disparity study findings and recommendations. During
this transition period interested Offerors must obtain a MBE listing from the M/WBE Office. This
will ensure that MBE listings reflect only those currently certified by the North Central Texas
Regional Certification Agency (NCTRCA) located in the six (6)-count geographic marketplace
that have been accepted by the City. The City's geographic marketplace includes the counties of:
Tarrant, Dallas, Denton, Johnson, Parker and Wise. Offerors are strongly encouraged to confirm
that each MBE that it intends to use is located in the geographic marketplace that will be counted
towards the established goal.
All Offerors shall note that it is the policy of the City of Fort Worth to ensure the full and equitable
participation of Minority Business Enterprises (MBE) in the procurement of goods and services. If
the total dollar value of the contract is greater than $50,000, then an MBE subcontracting goal
may be applicable.
The MBE goal on this project is: TBD.
Offerors must submit a Utilization Plan within 5 business days of submitting their Best Value
Proposal. The information shall include: (1) the name, address and telephone number of each
MBE; (2) the description of the work to be performed by each MBE; and (3) the approximate
dollar amount/percentage of the participation. Refer to the attached City of Fort Worth Best Value
Utilization Form.
A Minority Business Enterprise is defined as a business concern located in the Marketplace
meeting the following criteria:
a. is at least 51 percent owned by one or more minority persons, or, in the case of any
publicly owned business, at least 51 percent of the stock is owned by one or more
minority persons; and
b. management and daily business operations are controlled by one or more minority
persons who own it.
The business must be certified prior to recommendation of award in order for the participation to
be counted towards the established goal.
Offerors must submit the best value utilization form within 5 business days of submitting their
Best Value Proposal.
Instruction to Offerors(Feb 2017) Page 5 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
If an Offeror is certified as a DBE, MBE, SBE or WBE firm, please be aware that the City's
Ordinance does not allow a certified company to count itself towards the established goal; the
goal represents subcontracting opportunities.
If an Offeror (regardless of certification status or if a non- D/M/S/BE), however, forms a joint
venture with one or more MBEs, the MBE joint venture percentage participation will be counted
towards the established goal. The appropriate City of Fort Worth Joint Venture form must be
■'"" submitted for review and approval in order for it to be counted. The City of Fort Worth strongly
encourages joint ventures.
If Offeror failed to meet the stated MBE goal, in part or in whole, then a detailed explanation must
be submitted to explain the Good and Honest Efforts your firm made to secure MBE participation.
Failure to submit the MBE participation information or the detailed explanation of the proposer's
*" Good and Honest Efforts to meet or exceed the stated MBE goal, may render the proposal non-
responsive. The MBE plan will be part of the final weighted selection criteria.
3. PROPOSAL SECURITY: Cashier's check or an acceptable Offeror's bond payable to the City of
Fort Worth, in an amount of five (5) per cent of the Proposal submitted (See paragraph 1 above).
The Proposal Security must accompany the Proposal and is subject to forfeit in the event the
successful Offeror fails to execute the contract documents within ten (10) days after the contract
has been awarded. The Proposal Security shall be included in the envelope containing the
Proposal. Failure to submit the Proposal Security will result in the Proposal not being considered
for this project. Offeror's bond will be returned if the City fails to award the contract within 90
4M calendar days of receipt of proposals, unless the Offeror agrees to an extension. The surety must
be licensed to do business in the state of Texas.
4. PAYMENT BOND AND PERFORMANCE BOND: For projects in excess of $25,000, the
successful Offeror entering into a contract for the work will be required to give the City surety in a
sum equal to the amount of the contract awarded. The form of the bond shall be as herein
provided and the surety shall be acceptable to the City. All bonds furnished hereunder shall meet
.■, the requirements of Texas Government Code Section 2253, as amended.
In order for a surety to be acceptable to the City, the surety must(1) hold a certificate of authority
from the United States Secretary of the Treasury to qualify as a surety on obligations permitted or
required under federal law; or (2) have obtained reinsurance for any liability in excess of
$100,000 from a reinsurer that is authorized and admitted as a reinsurer in the State of Texas
and is the holder of a certificate of authority from the United States Secretary of the Treasury to
qualify as a surety on obligations permitted or required under federal law. Satisfactory proof of
any such reinsurance shall be provided to the City upon request. The City, in its sole discretion,
will determine the adequacy of the proof required herein.
No sureties will be accepted by the City that are at the time in default or delinquent on any bonds
or which are interested in any litigation against the City. Should any surety on the contract be
determined unsatisfactory at any time by the City, notice will be given to the contractor to that
effect and the contractor shall immediately provide a new surety satisfactory to the City.
If the total contract price is $25,000 or less, payment to the contractor shall be made in one lump
.. sum. Payment shall not be made for a period of 45 calendar days from the date the work has
been completed and accepted by the City
If the contract is in excess of$25,000, a Payment Bond shall be executed, in the amount of the
contract, solely for the protection of all claimants supplying labor and materials in the prosecution
of the work.
If the contract amount is in excess of$100,000, a Performance Bond shall also be provided, in
the amount of the contract, conditioned on the faithful performance of the work in accordance with
the plans, specification, and contract documents. Said bond shall be solely for the protection of
., the City of Fort Worth.
Instruction to Offerors(Feb 2017) Page 6 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
5. PRE-PROPOSAL SITE INVESTIGATION: Prior to filing a response, the Offeror shall examine the
site(s) of the work and the details of the requirements set out in these specifications to satisfy
itself as to the conditions which will be encountered relating to the character quality, and quantity
of the work to be performed and materials and equipment required. The filing of a response by
the Offeror shall be considered evidence that it has complied with these requirements. ■'•
6. AMBIGUITY: In case of ambiguity or lack of clearness in stating prices in the proposal, the City
reserves the right to adopt the most advantageous construction thereof to the City or to reject the
proposal.
7. WAGE RATES: Not less than the prevailing wage rates set forth in the Contract Documents must
be paid on this project.
8. POST PROPOSAL - PREAWARD SUBMITTALS: Offerors are required to submit the following
information to the Architectural Services Office, 401 West 13th Street, Fort Worth, Texas 76102
(phone number 817-392-2586), within five business days subsequent to bid opening (normally
by 5:00 PM the next Thursday following a Thursday bid opening) in order to assist City staff in
determining the Contractor's capability of performing the work and in meeting City contract ^,
requirements:
• Minority Business Enterprise Documentation (for proposals in excess of$50,000)
• Contractors Qualification Statement(AIA Form A305), including client references
• Proposed Subcontractors and Suppliers
• Project Schedule
• Schedule of Values (Breakout by CSI Divisions) «�
• Proof of insurability for Statutory Workers Compensation Insurance
9. PROPOSED SUBCONTRACTORS: Acceptance of the Proposal in no way requires the City to
accept the qualifications of the subcontractors. The Subcontractor lists are for use by the City in
preparing recommendations for award of the contract. The Contractor must provide and use
subcontractors listed unless the City agrees to allow a substitute.
10. DISCREPANCIES AND ADDENDA:
Should an Offeror find any discrepancies in the drawings and specifications, or should it be in
doubt as to their meaning, it shall notify the City at once. If required, the City will then prepare a
written addendum that will be available to all Offerors at the place designated for distribution of
the Request for Proposal Documents by the Notice to Offerors. The Contractor is responsible for
determining if addenda are available and for securing copies prior to submitting a response to this
request for sealed proposals. Oral instructions or decisions unless confirmed by written addenda
will not be considered valid, legal or binding. No extras will be authorized because of failure of
the contractor to include work called for in the addenda.
Offeror must acknowledge addenda in the Proposal. Failure to acknowledge addenda may cause
the Proposal to be ruled non-responsive. It is the Contractor's responsibility to obtain Addenda
and include its information in the Proposal.
11 WORKERS COMPENSATION INSURANCE: Offerors will be required to demonstrate that
coverage is in effect at time of Award of Contract. Sample Certificate of Insurance, or other proof
that Workers Compensation Insurance will be obtained, must be submitted within five working
days of bid opening. --
12. TAXES: Equipment and materials not consumed by or incorporated into the work are subject to
State sales taxes under House Bill 11, enacted August 15, 1991.
Instruction to Offerors(Feb 2017) Page 7 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
13. PERMITS: Contractor shall apply for all City of Fort Worth Permits and for any other permits
required by this project. City of Fort Worth Building and Trade Permit fees are waived. Separate
permits may be required for each work location.
14. UTILITIES AND IMPACT FEES: The City will pay water and sewer utilities tap fees and impact
fees. Unless shown otherwise, the City will coordinate and pay for water and sewer taps and
meters to the property line. The Contractor will include all remaining fees from the electrical and
gas companies in the Base Proposal. The Contractor will be responsible for coordinating with
City and utility companies for installation of utilities. The Contractor will be responsible for all fees
for electrical, gas, and other utilities within the property line of the project. Unless indicated
*� otherwise on the plans, the contractor will be responsible for costs and installations from the
building side of the water meter and sewer tap.
15. BID DOCUMENTS: Hard copies of bidding documents may be downloaded and printed by the
Offeror.
16. MANUFACTURER'S REFERENCE: Catalog, brand names, and manufacturer's references are
descriptive, not restrictive. Use of brands of like nature and quality will be considered. Upon
request of the architect or contractor, the contractor will submit a full sized sample and/or detailed
information as required to allow the architect to determine the acceptability of proposed
w* substitutions. Where equipment has been listed as "no substitute accepted" the City will accept
no alternates to the specified equipment. Also, refer to specification's product requirements.
17. TESTING SERVICES: The City shall provide for, independently of the contractor, the inspection
services, the testing of construction materials engineering, and the verification testing services
necessary for the acceptance of the construction work.
18. PROJECT SCHEDULE: The Project Schedule to be submitted with the Qualification Statement
will, at the minimum, include the following: quality control submittals and approvals, mobilization,
site preparation, under slab utilities, foundation work, structural erection, interior finish,
•* commissioning, and closeout. The Schedule may be submitted as a table or PERT diagram.
19. STATE FORM 1295 "CERTIFICATE OF INTERESTED PARTIES": Texas Ethics Commission
regulations require that the business entity must fill out the Form 1295 on an electronic filing
application on the Texas Ethics Commission website (www.ethics.state.tx.us). The business
entity that wishes to enter into the contract must supply the completed, signed and notarized
Form 1295 to the City.
Instruction to Offerors(Feb 2017) Page 8 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09, City Project#100172 October 2017
■w
PROPOSAL(Rev.July 28,2017)
T0: MR. DAVID COOKE
CITY MANAGER
ATTN: PURCHASING OFFICE
200 TEXAS STREET
CITY OF FORT WORTH,TEXAS
FOR: West Patrol Division (Joyce Drive Police Station)
+ 3532 Joyce Drive
Fort Worth,Texas
PMD2014-09
City Project#100172
Pursuant to the foregoing "Instructions to Offerors,"'the undersigned has thoroughly examined the plans,
specifications and the site, understands the amount of work to be done, and hereby proposes to do all the
work and furnish all labor, equipment and materials necessary to fully complete all the work as provided
in the plans and specifications, and subject to the inspection and approval of the Director of
Transportation and Public Works of the City of Fort Worth.
Upon acceptance of this Proposal by the City Council, the bidder is bound to execute a contract and, if
the contract amount exceeds $25,000.00, furnish acceptable Performance and/or Payment Bonds
approved by the City of Fort Worth for performing and completing the Work within the time stated and for
the following sum,to wit:
DESCRIPTION OF ITEMS
.s
$ .11 -5 70 , oo O Base Proposal
�., ' t -1 Calendar Days
$ L 6 Z 1 T�O Owner's Contingency Allowance (7.5%) added to Base
Proposal (This Allowance amount is not included in the Base Proposal but is added to the Base
Proposal. Only the Owner will approve the use of this Allowance during construction. Any
Allowance remaining at the end of construction will be retained by the City of Fort Worth).
$ 1 �-17
, 2-1 -7S-0 Base Proposal Plus Owner's Contingency Allowance
,.� ALLOWANCES
Allowance No. 1 -Irrigation System: Include a cash allowance of$5,000.00 for restoration of
existing irrigation system.
Allowance No. 2-Corner Guards: Contractor to provide a cash allowance of$ H 11000, 00
for material &labor for 40 corner guards as specified.
ALTERNATES
Add Alternate No. 1 -Roof Replacement: Provide new fluid applied protective membrane as
specified.
Add Alternate#1 DELETED-NOT APPLICABLE.
Instruction to Offerors(Feb 2017) Page 9 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 June 2017
Add Alternate No. 2—Lockers: Purchase and install new lockers in Room 110 as specified.
Add Alternate#2 $ 6 1_0 7 6 6. 0 0
` Add Alternate No. 3—Lockers: Provide power to each locker with internal power outlets as shown
in the Electrical documents.
Add Alternate#3 $ 9 19. 11 - 00
(,�
1. 1 1 • 0 0 Rooms 110. --
$ 1 5. ?- I S. 0 0 Rooms 121, 129, & 130.
Add Alternate No. 4—Exterior Painting: Paint all exterior metal soffits,fasciae, &columns per
requirements outlined in specifications.
(� Q
Add Alternate#4 $ 0
Add Alternate No. 5—Gate Operators: In lieu of Owner-provided gate motors, Contractor to
purchase and install equipment. Contractor to coordinate installation with Owner's fencing -..
contractor. Q
Add Alternate#5 $ (7 ' —7 y. 0 0
Add Alternate No. 6—Ceilings: Existing ceilings in the following rooms are to be removed and
replaced with new ceilings as specified: Open Offices (104, 106, 113, 114, 136);Small Group
Training (135); Offices (137, 138, 139, 140, 144); Vestibule (141); Egress Corridor(142);Corridor
(145);and Copy(143).
Add Alternate#6 $ 2 07 9. 0 0
Add Alternate No. 7—Solid Surfacing countertops: In lieu of plastic laminate countertops,
purchase and install solid surfacing countertops as specified.
Add Alternate#7 $ 7. 1 10S. 00
UNIT PRICES—N/A
The undersigned agrees to complete the Work within the calendar days specified above after the date of
Notice to Proceed. A Project Schedule will be submitted as required in the Instructions to Offeror.
The City reserves the right to accept or reject any and all bids or any combination thereof proposed for
the above work.
The undersigned assures that its employees and applicants for employment and those of any labor .�.
organization, subcontractors or employment agency in either furnishing or referring employee applicants
to the undersigned are not discriminated against as prohibited by the terms of City Ordinance 7278 as
amended by City Ordinance 7400 (Fort Worth City Code Section 13A-21 through 13A-29).
Residency of Offerors: The 1985 Session of the Texas Legislature passed house Bill 620 relative to the
award of contracts to non-resident bidders. The law provides that, in order to be awarded a contract as
low bidder, non-resident bidders (out of state contractors whose corporate offices or principal place of ^•
business are outside of the State of Texas) that bid projects for construction, improvements, supplies or
services in Texas at an amount lower than the lowest Texas resident bidder by the same amount.that
Texas resident bidder would be required to underbid a non-resident bidder. in order to obtain a
comparable contract in the state in which the non-resident's principal place of business is located. The
Instruction to Offerors(Feb 2017) Page 10 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 June 2017
appropriate blanks in Section A must be filled out by all non-resident bidders in order for your bid to meet
specifications.
The failure of out of state or non-resident bidders to complete the forms may disqualify that bidder.
Resident bidders must check the box in Section B.
A. 1_1 Non-resident vendors in N/A (give state), our principal place of
business, are required to be N/A percent lower than resident bidders by state
law.
1_1 Non-resident vendors in N/A (give state), are not required to
underbid resident bidders.
B. 1X1 Our principal place of business or corporate offices are in the State of
Texas.
Within ten (10) days of receipt of notice of acceptance of this bid,the successful bidder will execute the
formal contract and will deliver approved Performance and Payment Bonds for the faithful performance of
this contact. The attached deposit check in the sum of See Bid Bond
Dollars ($ See Bid Bond ) is to become the property of the City of Fort Worth,Texas, or
the attached Bidder's Bond is to be forfeited in the event the contract and bonds are not executed within
the time set forth, as liquidated damages for delay and additional work caused thereby.
MINORITY BUSINESS ENTERPRISE (MBE): (For Proposals in excess of$50,000)
1 am aware that I must submit information to the Director, Property Management Department,
concerning the MBE participation within FIVE BUSINESS DAYS of submittal of this Proposal in order
to be considered RESPONSIVE.
Respectfully submitted,
Balfour Beatty Constr ion, LLC
Compan arne
By:
g e
yle Bolejack, Vice President of Operations
Printed Name of Principal Title
-- Address: 3100 McKinnon Street
Street
Dallas, TX 75201
City Zip
Phone: (214) 468-4700
Fax: N/A
Email: kbolejack@balfourbeattyus . com
Receipt is acknowledged of the following addenda:
Addendum No. 1:YES-07/14/2017 Addendum No. 2:YES-07/28/2017
Instruction to Offerors(Feb 2017) Page 11 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09, City Project#100172 June 2017
Addendum No.3: Addendum No. 4:
Addendum No. 5: Addendum No. 6:
Addendum No. 7: Addendum No. 8:
Addendum No. 9: Addendum No. 10:
—
Instruction to Offerors(Feb 2017) Page 12 of 33
City of Ft Worth--West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 June 2017
CONFLICT OF INTEREST AFFIDAVIT
Each bidder, offeror, or respondent (hereinafter also referred to as "you") to a City of Fort Worth
(also referred to as "Cit)(') procurement are.required to complete Conflict of Interest Questionnaire (the
attached CIQ Form) and Local Government Officer Conflicts Disclosure Statement (the attached CIS Form)
below pursuant to state law. This affidavit will certify that the Bidder has on file with the City Secretary the
required documentation and is eligible to bid on City Work. The referenced forms may be downloaded from the
website links provided below.
http://www.ethics.state.tx.us/forms/CIQ.12df
hqp://www.ethics,state,tx,us/fonns/CIS,pdf
,.. Q CIQ Form is on file with City Secretary
0 CIQ Form is being provided to the City Secretary
Q CIS Form is on File with City Secretary
CIS Form is being provided to the City Secretary
BIDDER:
Balfour Beatty Construction, LLC By; Kyle Bolejack
Company (Please Print)
3100 McKinnon Street Signature:
Address /77"
Dallas, TX 75201 Title:Vice President of Operations
City/State/Zip (Please Print)
Instruction to Offerors(Feb 2017) Page 12 of 32
City of Ft Worth West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 June 2017
No
.r
ON
mm
am
ow
PAGE LEFT BLANK INTENTIONALLY
e..
CONFLICT OF INTEREST QUESTIONNAIRE FORM CI
For vendor doing business with local governmental entity
This questionnaire reflects changes made to the law by H.B. 23, 84th Leg., Regular Session. OFFICEUSEONLY
This questionnaire is being filed in accordance with Chapter 176,Local Government Code,by a vendor who Date Received
has a business relationship as defined by Section 176.001(1-a) with a local governmental entity and the
vendor meets requirements under Section 176.006(a).
By law this questionnaire must be filed with the records administrator of the local governmental entity not later
than the 7th business day after the date the vendor becomes aware of facts that require the statement to be
filed. See Section 176.006(a-1),Local Government Code.
A vendor commits an offense if the vendor knowingly violates Section 176.006, Local Government Code. An
offense under this section is a misdemeanor.
1 Name of vendor who has a business relationship with local governmental entity.
BALFOUR BEATTY CONSTRUCTION, LLC
2 r
Check this box if you are filing an update to a previouslyfiled questionnaire.(The law requires that you file an updated
completed questionnaire with the appropriate filing authority not later than the 7th business day after the date on which
you became aware that the originally filed questionnaire was incomplete or inaccurate.)
3 Name of local government officer about whom the information is being disclosed.
NOT APPLICABLE
Name of Officer
Describe each employment or other business relationship with the local government officer,.or a family member of the
officer,as described by Section 176.003(a)(2)(A). Also describe any family relationship with the local government officer.
Complete subparts A and B for each employment or business relationship described. Attach additional pages to this Form
CIO as necessary.
A. Is the local government officer or a family member of the officer receiving or likely to receive taxable income,
.., other than investment income,from the vendor?
Yes Fx No
�. B. Is the vendor receiving or likely to receive taxable income,other than investment income,from or at the direction
of the local government officer or a family member of the officer AND the taxable income is not received from the
local governmental entity?
Yes a No
5 Describe each employment or business relationship that the vendor named in Section 1 maintains with a corporation or
other business entity with respect to which the local government officer serves as an officer or director,or holds an
ownership interest of one percent or more.
NOT APPLICABLE
._ s
F-1Check this box if the vendor has given the local government officer or a family member of the officer one or more gifts
as described in Section 176.003(a)(2)(B),excluding gifts described in Section 176.003(a-1).
------- AUGUS1 3, 20-, .
i !a Xc+fidor ddKg business with the governmental entity ate
IrusbxrotonGrp fih6)Commission www.ethics.state.tx.us Page 13 of 32 Revised 11/30/2015
City of Ft Worth est Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 June 2017
PART 1 - CONFLICT OF INTEREST QUESTIONNAIRE
For vendor doing business with local governmental entity
A complete copy of Chapter 176 of the Local Government Code may be found at
hftp://www.statutes.legis.state.tx.us/ Docs/LG/htm/LG.176.htm. For easy reference, below are some of
the sections cited on this form.
Local Government Code§176.001(1-a):'Business relationship"means a connection between two or more
parties based on commercial activity of one of the parties. The term does not include a connection based on:
(A) a transaction that is subject to rate or fee regulation by a federal,state,or local governmental entity or an
agency of a federal,state,or local governmental entity;
(B) a transaction conducted at a price and subject to terms available to the public;or
(C) a purchase or lease of goods or services from a person that is chartered by a state or federal agency and
that is subject to regular examination by,and reporting to,that agency. „
1 1 LOCAL GOVERNMENT CODE§176.003(A)(2)(A)AND(B):
(a) A local government officer shall file a conflicts disclosure statement with respect to a vendor if.
(2) the vendor:
(A) has an employment or other business relationship with the local government officer or
a family member of the officer that results in the officer or family member receiving
taxable income, other than investment income, that exceeds $2,500 during the 12-
month period preceding the date that the officer becomes aware that
(i) a contract between the local governmental entity and vendor has been
executed;or
(ii) the local governmental entity is considering entering into a contract with
the vendor,
(B) has given to the local government officer or a family member of the officer one or more
gifts that have an aggregate value of more than$100 in the 12-month period preceding the
date the officer becomes aware that:
(i) a contract between the local governmental entity and vendor has been executed;
or
(ii) the local governmental entity is considering entering into a contract with the
vendor.
1.2 LOCAL GOVERNMENT CODE§ 176.006(A)AND (A-1)
(a) A vendor shall file a completed conflict of interest questionnaire if the vendor has a business relationship
with a local governmental entity and:
(1) has an employment or other business relationship with a local government officer of that local
governmental entity,or a family member of the officer,described by Section 176.003(a)(2)(A);
(2) has given a local government officer of that local governmental entity,or a family member of the
officer,one or more gifts with the aggregate value specified by Section 176.003(a)(2)(B),excluding any
gift described by Section 176.003(a-1);or
(3) has a family relationship with a local government officer of that local governmental entity.
(a-1)The completed conflict of interest questionnaire must be filed with the appropriate records administrator not later
than the seventh business day after the later of:
(1) the date that the vendor:
(A) begins discussions or negotiations to enter into a contract with the local
governmental entity; or
(B) submits to the local governmental entity an application, response to a request for
proposals or bids, correspondence, or another writing related to a potential contract
with the local governmental entity;or
(2) the date the vendor becomes aware:
(A) of an employment or other business relationship with a local government officer,or a
family member of the officer,described by Subsection(a);
(B) that the vendor has given one or more gifts described by Subsection(a);or
(C) of a family relationship with a local government officer.
Instruction to Offerors(Feb 2017) Page 15 of 33 �•
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
.. CERTIFICATE OF INTERESTED PARTIES FORM 1295
10f1
.r Complete Nos.1-4 and 6 if there are interested parties. OFFICE USE ONLY
Complete Nos.1,2,3,5,and 6 if there are no interested parties. CERTIFICATION OF FILING
1 Name of business entity filing form,and the city,state and country of the business entity's place Certificate Number:
of business. ,;,I 49
Balfour Beatty Construction, LLC
Dallas,TX United States Date Filed:
2 Name of governmental entity or state agency that is a party to the contract for which the form is ('-,9/02/2017
being filed.
The City of Fort Worth,Texas ❑ate Acknowledged:
g Provide the identification number used by the governmental entity or state agency to track or identify the contract,and provide a
description of the services,goods,or other property to be provided under the contract.
PMD 2014-09
City Project#100172
4 Nature of interest -
Name of Interested Parry City,State,Country(place of business) (check applicable)
Controlling-1 Intermediary
Bolejack, Kyle Dallas,TX United 5taies
y` Ray,Elizabeth Austin,TX United States
Brannen,Jeffrey Dallas,TX United States
rsalfour Beatty Construction Group, Inc. Dallas,TX United States X
5 Check only if there is NO Interested Party. ❑
6 AFFIDAVIT I swear,or affirm,under penalty of p ' ry,that the above disclosure is true and correct.
SHERRY L. STEVENS
Notary Public,State of Texas
i.omm.Expires 01-09-2021
nature of authorized agent of contracting business entity
<<,,`` NotarvIn n751i?_3 7 9 9 tY
AFFIX NOTARY STAMP/SEAL ABOVi
Sworn to and subscribed before me,by the said this the day of G(S
7
20 �� ,to certify which,witness my hand and seal f office.
ffice.Sign �—
s
at of officer administering-oath Printed nam officer administering oath Title of officer administering oath
Forms provided by Texas Ethics Commission www.ethics.state.tx.us Version V1.0.883
w.
w
PAGE LEFT BLANK INTENTIONALLY
■r
LOCAL GOVERNMENT OFFICER FORM CIS
CONFLICTS DISCLOSURE STATEMENT
(Instructions for completing and filing this form are provided on the next page.)
�- This questionnaire reflects changes made to the law by H.B. 23, 84th Leg., Regular Session. OFFICE USEONLY
This is the notice to the appropriate local governmental entity that the following local
government officer has become aware of facts that require the officer to file this statement Date Received
—' in accordancewith Chapter 176,Local GovernmentCode.
1 Name of Local Government Officer
2 Office Held
3 Name of vendor described by Sections 176.001(7)and 176.003(a), Local Government Code
4 Description of the nature and extent of each employment or other business relationship and each family relationship
with vendor named in item 3.
�* 5 List gifts accepted by the local government officer and any family member, if aggregate value of the gifts accepted
from vendor named in item 3 exceeds $100 during the 12-month period described by Section 176.003(a)(2)(B).
�. Date Gift Accepted Descriptic of Gift
Date Gift Accepted Description of Gift
Date Gift Accepted Description of Gift
(attach additional forms as necessary)
6 AFFIDAVIT
I swear under penalty of perjury that the above statement is true and correct.I acknowledge
that the disclosure applies to each family member(as defined by Section 176.001(2), Local
Government Code) of this local government officer. I also acknowledge that this statement
covers the 12-month period described by Section 176.003(a)(2)(B),Local Government Code.
ow
MR Signature of Local Government Officer
AFFIX NOTARY STAMP / SEAL ABOVE
No
Sworn to and subscribed before me,by the said this the day
of 20 to certify which,witness my hand and seal of office.
No
Signature of officer administering oath Printed name of officer administering oath Title of officer administering oath
go II
Instruction to Offerors(Feb 2017) Page 16 of 33
CiFpafrfANzdbd4*iFet<ftE*msirssimnr o,f Drive Police Station),PMD9 .eEaicityslPaW-t;t. 00172 October 2017 Revised 11/30/2015
LOCAL GOVERNMENT OFFICER CONFLICTS DISCLOSURE STATEMENT
Section 176.003 of the Local Government Code requires certain local government officers to file this form. A "local
government officer"is defined as a member of the governing body of a local governmental entity; a director,superintendent,
administrator,president,or other person designated as the executive officer of a local governmental entity;or an agent of a
local governmental entity who exercises discretion in the planning,recommending,selecting,or contracting of a vendor.This
form is required to be filed with the records administrator of the local governmental entity not later than 5 p.m. on the
seventh business day afterthe date on which the officer becomes aware of the facts that require the filing of this statement.
A local government officer commits an offense if the officer knowingly violates Section"76.003,Local Government Code.An
offense under this section is a misdemeanor.
Refer to chapter 176 of the Local Government Code for detailed information regarding the requirement to file this form.
PART 2 - INSTRUCTIONS FOR COMPLETING THIS FORM
The following numbers correspond to the numbered boxes on the other side.
1. Name of Local Government Officer. Enter the name of the local government officer filing this statement.
2. Office Held. Enter the name of the office held by the local government officer filing this statement.
3. Name of vendor described by Sections 176.001(7)and 176.003(a), Local Government Code. Enter the
name of the vendor described by Section 176.001(7), Local Government Code, if the vendor: a) has an employment or
other business relationship with the local government officer or a family member of the officer as described by
Section 176.003(a)(2)(A), Local Government Code; b)has given to the local government officer or a family member of the
officer one or more gifts as described by Section 176.003(a)(2)(B), Local Government Code;or c)has a family relationship
with the local government officeras defined by Section 176.001(2-a),Local Government Code.
4. Description of the nature and extent of each employment or other business relationship and
each family relationship with vendor named in item 3. Describe the nature and extent of the employment or
other business relationship the vendor has with the local government officer or a family member of the officer as
described by Section 176.003(a)(2)(A),Local Government Code,and each family relationship the vendor has with the local
government officer as defined by Section 176.001(2-9),Local Government Code. �-
5. List gifts accepted, if the aggregate value of the gifts accepted from vendor named in item 3
exceeds $100. List gifts accepted during the 12-month period (described by Section 176.003(a)(2)(B), Local
Government Code)by the local government officer or family member of the officer from the vendor named in item 3 that in the
aggregate exceed$100 in value.
6.Affidavit. Signature of local government officer.
Local Government Code 4 176.001(2-a): "Family relationship" means a relationship between a person and
another person within the third degree by consanguinity or the second degree by affinity,as those terms are defined by
Subchapter B,Chapter573,Government Code.
PART 3- LOCAL GOVERNMENT CODE&176.003(A)(2)(A):
(a) A local government officer shall file a conflicts disclosure statement with respect to a vendor if:
(2) the vendor:
(A) has an employment or other business relationship with the local government
officer or a family member of the officer that results in the officer or family member
receiving taxable income, other than investment income, that exceeds $2,500 during
the 12-month period preceding the date that the officer becomes aware that:
(i) a contract between the local governmental entity and vendor has been
executed;or
(ii) the local governmental entity is considering entering into a contract with the
vendor
Instruction to Offerors(Feb 2017) Page 17 of 33 --
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
TEXAS SALES AND USE TAX EXEMPTION CERTIFICATE
Name of Purchaser, Firm or Agency: City of Fort Worth, Texas
Address(Street&Number, P.O.Box or Route Number): 1000 Throckmorton
City, State,Zip Code: Fort Worth,Texas 76102
Telephone: (817)392-8360
1,the purchaser named above,claim an exemption from payment of sales and use
taxes for the purchase of taxable items described below or on the attached order or
invoice from:
rill vE-1dor-,,
.. Description of the items to be purchased, or on the attached order or invoice:
All items except motor vehicles as listed below
Purchaser claims this exemption for the following reason:
Governmental Entity
I understand that I will be liable for payment of sales or use taxes which may become
due for failure to comply with the provisions of the state,city, and/or metropolitan transit
authority sales and use tax laws and comptroller rules regarding exempt purchases.
Liability for the tax will be determined by the price paid for the taxable items purchased
® or the fair market rental value for the period of time used.
I understand that it is a misdemeanor to give an exemption certificate to the seller for
taxable items which I know, at the time of purchase,will be used in a manner other than
expressed in this certificate and that upon conviction I may be fined not more than$500
per offense. (�
Purchaser:
Title: Purchasing Manager Date: February 1.2007
Note:This certificate cannot be issued for the purchase, lease or rental of a motor
vehicle.
THIS CERTIFICATE DOES NOT REQUIREA NUMBER TO BE VALID
Sales and Use Tax"Exemption Numbers"or`Tax Exempt'Numbers do not exist.
This certificate should be furnished to the supplier. Do not send the completed
.. certificate to the Comptroller of Public Accounts.
Instruction to Offerors(Feb 2017) Page 18 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
PM
oft
OR
PM
r
r..
PAGE LEFT BLANK INTENTIONALLY ..
.. 2013 PREVAILING WAGE RATES
Commercial Construction Projects
CLASSIFICATION DESCRIPTION Wage Ratew
AC Mechanic $
25.24
AC Mechanic Helper $
13.67
Acoustical Ceiling installer $
16.83
Acoustical Ceiling Installer Helper $
12.70
Bricklayer/Stone Mason
19.45
Bricklayer/Stone Mason Trainee $
13.31
Bricklayer/Stone Mason Helper $
10.91
Carpenter $
17.75
Carpenter Helper $
14.32
w $
Concrete Cutter/Sawer 17.00
Concrete Cutter/Sawer Helper 11.00
Concrete Finisher $
15.77
Concrete Finisher Helper $
11.00
Concrete Form Builder $
w 15.27
Concrete Form Builder Helper $
11.00
,., Drywall Mechanic $
15.36
Drywall Helper $
12.54
Drywall Taper $
15.00
Drywall Taper Helper $
r� 11.50
Electrician(Journeyman) $
19.63
Electrician Apprentice(Helper) $
15.64
Electronic Technician $
20.00
•w Floor Layer $
18.00
MW Floor Layer Helper $
10.00
Glazier $
21.03
Instruction to Offerors(Feb 2017) Page 19 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
wo
Glazier Helper $
12.81 on
Insulator $
16.59
Insulator Helper $ on
11.21
Laborer Common $
10.89
Laborer Skilled $
14.15
Lather $
12.99
Metal Building Assembler $
16.00
Metal Building Assembler Helper $
12.00
Metal Installer(Miscellaneous) 13.00
Metal Installer Helper(Miscellaneous) $
11.00
Metal Stud Framer 16.12 ..�
Metal Stud Framer Helper $
12.54
Painter $
16.44
Painter Helper $
9.98
Pipefitter $
21.22
Pipefitter Helper $
15.39
Plasterer $
16.17
Plasterer Helper $
12.85
Plumber 2 98 ,,•,
Plumber Helper $
15.85
Reinforcing Steel Setter $ ,.
12.87
Reinforcing Steel Setter Helper $
11.08
Roofer $
16.90
Roofer Helper $
11.15
Sheet Metal Worker $
16.3S
Sheet Metal Worker Helper $ ..
13.11
Sprinkler System Installer $
19.17
Sprinkler System installer Helper $
14.15
Instruction to Offerors(Feb 2017) Page 20 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
MR
ow Steel Worker Structural $
17.00
Steel Worker Structural Helper $
13.74
Waterproofer $
15.00
Equipment Operators
rrM $
Concrete Pump
18.50
.� Crane,Clamshell, Backhoe, Derrick, D'Line Shovel $
19.31
Forklift $
16.45
wr
Foundation Drill Operator $
22.50
Front End Loader $
16.97
Truck Driver $
16.77
■s Welder $
19.96
Welder Helper $
13.00
ruu
The prevailing wage rates shown for Commercial construction projects were based on a salary survey
conducted and published by the North Texas Construction Industry(Fall 2012)Independently compiled
by the Lane Gorman Trubitt,PLLC Construction Group. The descriptions for the classifications listed are
w provided on the TEXO's(The Construction Association)website.
www.texoassociation.org/Chapter/wagerates.asp
w
w
Instruction to Offerors(Feb 2017) Page 21 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
r.
..
on
PAGE LEFT BLANK INTENTIONALLY
..t
w.
CITY OF FORT WORTH
WEATHER TABLE
Average Days
Month of inches of Rainfall
Rain/Snowllce
iJanuary 6 2.51
February 7 2.23
�. March 9 3.49
pil 7 2.97
May 10 4.56
June 8 3.31
July 4 1.83
August 5 1.88
September 5 2.34
October — 7 -- 3.65
November 7 2.70
December 6 2.34
nually 81 33.81
(1)Mean number of days precipitation of 0.01'or more or 1 art"srKmAce
., (2)Average normal precolabon,in inch
This table is based on information Wrted from Dallas-Fort Worth International Airport,
Texas.Latitude 32 deg 54 min north,longitude 97 deg 02 min west;elevation(ground)551 ft.
Average number of days of rain,snow,and ice days are based on records covering 21 years-
Precipitation is based on recorded information from 1996 through 2016 pefiod.
This table is to be used as a baisis for calculation of excess rain or weather days for projects
with duration in calendar days.If the site records indicate that the Contractor was unable to
carry out operations due to weather,it is counted as a weather day-If the number of weather
days exoeeds the number of average rain days plus the snowfice days for the contract
duration,the contract will be adjusted by Change Order..
Fart Wanh Weather TaMe 24 April 2017
w�
Instruction to Offerors(Feb 2017) Page 22 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
City of Fort Worth, Texas
"® Property Management Department
Facilities Management Group/Architectural Services Division
GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
,. LUMP SUM CONTRACT
SECTION A
DEFINITIONS,PROCEDURES AND INTERPRETATIONS
A-1 CONTRACT DOCUMENTS: By the term Contract Documents is meant all of the written and drawn documents setting
forth or affecting the rights of the parties,including but not necessarily limited to,the Contract,Notice to Bidders,Proposal,General
Conditions, Special Conditions, Specifications, Plans, Bonds and all Addenda,Amendments signed by all parties, Change Orders,
written Interpretations and any written Field Order for a minor change in the Work.
A-2 ENTIRE AGREEMENT: The Contract Documents represent the entire agreement between the Parties, and no prior or
contemporaneous,oral or written agreements,instruments or negotiations shall be construed as altering the terms and effects of the
Contract Documents. After being executed, the Contract Documents can be changed only by a written Amendment signed by the
Contractor and the Owner,or Change Order,or by a written Field Order for a minor change.
A-3 WORK: By the term Work is meant all labor,supervision,materials and equipment necessary to be used or incorporated
,. in order to produce the construction required by Contract Documents.
A-4 EXECUTION OF THE CONTRACT DOCUMENTS: The Contract Documents shall be executed in six originals, with all
required attachments, including required bonds and insurance certificates,by the Contractor and the Owner in such form as may be
prescribed by law and returned to the Owner within ten business days of notification to Contractor. Failure to execute contracts and
provide required enclosures will be grounds for revocation of award and taking of Bid Bond.
A-5 FAMILIARITY WITH PROPOSED WORK: Before filing a Proposal, the Contractor shall examine carefully the, plans,
specifications,special provisions, and the form of contract to be entered into for the work contemplated. He shall examine the site
+ of work and satisfy himself as to the conditions that will be encountered relating to the character, quality and quantity of work to be
performed and materials to be furnished. The filing of a bid by the bidder shall be considered evidence that he has complied with
these requirements and has accepted the site as suitable for the work.
w,s Claims for additional compensation due to variations between conditions actually encountered in construction and as indicated by
the plans will not be allowed.
A-6 ONE UNIFIED CONTRACT: Insofar as possible, the Contract Documents will be bound together and executed as a
single unified Contract.The intention of the Contract Documents being to provide for all labor,supervision,materials,equipment and
other items necessary for the proper execution and completion of the Work. Words that have well-recognized technical or trade
meanings are used herein in accordance with such recognized meanings.
A-7 DIVISION OF WORK: The arrangement of Drawings and/or Specifications into Divisions, Sections, Articles, or other
Subdivisions shall not be binding upon the Contractor in dividing the work among Subcontractors or Trades.
A-8 INTERPRETATIONS: In the event of inconsistency in the contract documents,the following sequence for interpretation
shall be used in order of precedence: Change Orders and/or Field Orders (by date of issuance); Addenda (by date of issuance);
.. Drawings; Notes and dimensions on Drawings; Technical Specifications; Special Provisions; Supplementary General Conditions;
General Conditions;and Construction Contract.
The Architect will furnish such Interpretations of the Plans and Specifications as may be necessary for the proper execution or
progress of the work. Such Interpretations shall be furnished at the instance of the Architect or at the request of the Contractor,or
Owner, and will be issued with reasonable promptness and at such times and in accordance with such schedule as may be agreed
upon. Such Interpretations shall be consistent with the purposes and intent of the Plans and Specifications and may be effected by
Field Order. In the event of any dispute between any of the parties to the Contract and the Architect or each other involving the
interpretation of the Contract Documents,the evaluation of work or materials performed or furnished by the Architect Contractor,or
®, any subcontractor or materialsman,or involving any question of fault or liability of any party,the decision of the Owner shall be final
and binding.
A-9 CORRELATION AND INTENT: In general,the drawings indicate dimension, locations,positions,quantities,and kinds of
construction;the specifications indicate the quality and construction procedures required. Work indicated on the drawings and not
®" specified of vice-versa,shall be furnished as though set forth in both. Work not detailed, marked or specified shall be the same as
similar parts that are detailed,marked or specified. If the drawings are in conflict or conflict with the specifications the better quality
or greater quantity or work or materials shall be estimated and shall be furnished or included. Dimensions on drawings shall take
precedence over small-scale drawings. Drawings showing locations of equipment, piping,ductwork,electrical apparatus,etc., are
w diagrammatic and job conditions may not allow installation in the exact location shown. Relocation shall not occur without the
Architects approval.
General Conditions of the Contract for Construction Lump Sum Contract Page 1 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
A-10 COPIES OF WORKING DRAWINGS AND SPECIFICATIONS: The Architect will furnish to Contractor electronic working
Drawings and Specifications. Contractor shall pay the cost of reproduction for all other copies of Drawings and Specifications
furnished to him. •�
All Drawings, Specifications and copies thereof furnished by the Owner or the Architect are and shall remain the property of the
Owner. They are not to be used on any other project and,with the exception of one Contract set for each Party to the Contract,are
to be returned to the Owner on request at the completion of the work.
A-11 MINORITY BUSINESS ENTERPRISE (MBE) POLICY: As of June 1, 2012, The City of Fort Worth has implemented
Business Diversity Ordinance(BDO)to reflect the City's availability and disparity study findings and recommendations. During this
transition period, interested Offerors must obtain an MBE listing from the MNVBE Office at 817-212-2674. This will ensure that the
MBE listings reflect only those currently certified by the North Central Texas Regional Certification Agency(NCTRCA)located in the
six (6)-county geographic marketplace that have been accepted by the City. The City's geographic marketplace includes the
counties of:Tarrant, Dallas, Denton,Johnson, Parker and Wise. Offerors are strongly encouraged to confirm that each MBE that it
intends to use is located in the geographic marketplace that will be counted towards the established goal.
The City of Fort Worth has goals for the participation of Minority Business Enterprises(MBE)in City contracts. Compliance with the
policies designed to meet these goals is mandatory in order to be considered a responsive bidder. The City policy and procedures
to be followed in submitting proposals are included.
The City of Fort Worth MBE Program will take precedence over other subcontractor utilization programs on Block Grant and other
federally funded Projects.
A-12 AGE: In accordance with the policy("Policy")of the Executive Branch of the federal government, Contractor covenants
that neither it nor any of its officers, members, agents, employees, program participants or subcontractors, while engaged in
performing this contract, shall, in connection with the employment, advancement or discharge of employees or in connection with
the terms, conditions or privileges of their employment, discriminate against persons because of their age except on the basis of a
bona fide occupational qualification,retirement plan or statutory requirement.
Contractor further covenants that neither it nor its officers, members, agents, employees, subcontractors, program participants, or
persons acting on their behalf, shall specify, in solicitations or advertisements for employees to work on this contract, a maximum
age limit for such employment unless the specified maximum age limit is based upon a bona fide occupational qualification,
retirement plan or statutory equipment.
w
Contractor warrants it will fully comply with the Policy and will defend, indemnify and hold City harmless against any claims or
allegations asserted by third parties or subcontractor against City arising out of Contractor's and/or its subcontractors'alleged failure
to comply with the above referenced Policy concerning age discrimination in the performance of this agreement.
ein
A-13 DISABILITY: In accordance with the provisions of the Americans With Disabilities Act of 1990 ("ADA"), Contractor
warrants that it and any and all of its subcontractors will not unlawfully discriminate on the basis of disability in the provision of
services to the general public, nor in the availability,terms and/or conditions of employment for applicants for employment with, or
employees of Contractor or any of its subcontractors. Contractor warrants it will fully comply with ADA provisions and any other
applicable federal,state and local laws concerning disability and will defend,indemnify and hold City harmless against any claims or
allegations asserted by third parties or subcontractors against City arising out of Contractor's and/or its subcontractors' alleged
failure to comply with the above-referenced laws concerning disability discrimination in the performance of this agreement.
SECTION B
IDENTITY OF ARCHITECT
B-1 CONTRACT ADMINISTRATION. The Architect is the person or person lawfully licensed to practice architecture
identified as such in the Agreement. The Architect is retained by the Owner to prepare the construction documents and represent
the Owner during the construction phase as directed by the Owner.
B-2 DUTIES OF THE ARCHITECT: As used herein,the term Architect means the Architect or his authorized representative.
Nothing contained in these Contract Documents shall create any privity of Contract between the Architect and the Contractor.
B-3 ARCHITECT AS REPRESENTATIVE OF THE OWNER: The Architect will provide general administration of the Contract
on behalf of the Owner and will have authority to act as the representative of the Owner to the extent provided in the Contract
Documents unless changed in writing by the Owner. The Architect will be available for conferences and consultations with the �..
Owner or the Contractor at all reasonable times.
B-4 ACCESS TO JOB SITES: The Architect shall at all times have access to the Work whenever it is in preparation and
progress. The Contractor shall provide facilities for such access so the Architect may perform its assigned functions under the
Contract Documents. ...
The Architect will make periodic visits to the Site to familiarize himself with the progress and quality of the work and to determine if
the work is proceeding in accordance with the Contract documents. On the basis of on-site observations,the Architect will keep the
Owner informed of the progress of the Work and will endeavor to guard the Owner against defects and deficiencies in the Work of
the Contractor. Based upon such observations and the Contractor's applications for payments, the Architect will make
General Conditions of the Contract for Construction Lump Sum Contract Page 2 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
determinations and recommendations concerning the amounts owing to the Contractor and will issue certificates for payment
amounts.
B-5 INTERPRETATIONS: The Architect will be, in the first instance, the interpreter of the requirements of the Plans and
Specifications and the judge of the performance thereunder by the Contractor,subject to the final decision of the Owner.
The Architect's decisions in matters relating to artistic effect will be final if consistent with the intent of the Contract Documents.
B-6 AUTHORITY TO STOP WORK: The Architect will have authority to reject work that does not conform to the Plans and
Specifications. In addition,whenever, in its reasonable opinion,the Architect considers it necessary or advisable in order to insure
•- the proper realization of the intent of the Plans and Specifications,the Architect will have authority to require the Contractor to stop
the Work or any portion thereof,or to require special inspection or testing of the Work whether or not such Work be then fabricated,
installed or completed.
® B-7 MISCELLANEOUS
Shop Drawings. Submittals and Samples: The Architect will review Shop Drawings, Submittals and Samples. Two copies of each
approved Shop Drawing and submittal will be provided to the Owner by the Architect. Three copies will be returned to the
Contractor.
Change Orders. Change Orders and Field Orders for Minor Changes in the Work will be issued by the Owner through the Architect.
Guarantees. The Architect will receive all written guarantees and related documents required of the Contractor.Upon completion of
the project the Contractor shall provide the Owner three copies of each guarantee.
Inspections The Architect will conduct inspections for the purpose of determining and making his recommendations concerning the
dates of substantial completion and final completion. The Architect will conduct the final acceptance inspection and issue the
Certificate of Substantial Completion.
Operation and Maintenance Manuals The Architect will receive on behalf of the Owner two hard copies and one digital copy of all
applicable equipment installation,operation,and maintenance brochures and manuals required of the Contractor.
■. B-8 TERMINATION OF THE ARCHITECT: In case of the termination of the employment of the Architect by the Owner, the
Owner shall either assume the duties of the Architect through the Director of the Property Management Department,or shall appoint
a successor Architect against whom the Contractor makes no reasonable objection.
SECTION C
OWNER
C-1 IDENTIFICATION: By the term Owner is meant the City of Fort Worth acting herein by its duly authorized representatives
®' in the manner provided by law. Authorized representatives include the City Manager,Assistant City Manager, and Director of the
Property Management Department and members of the Facilities Management Division. A designated representative will be
identified from within the Facilities Management Division to act as a point of contact for day-to-day contract administration.
C-2 DUTIES OF THE OWNER: The Owner shall furnish surveys describing the physical characteristics,legal limits and utility
locations for the site of the Work;provided, however.,that the Contractor hereby covenants that he has inspected the premises and
familiarized himself therewith and that the locations of utilities and other obstacles to the prosecution of the Work as shown on the
Owner's survey are for information only, are not binding upon the Owner, and the Owner shall not incur any liability for loss or
damage by virtue of any inaccuracies or deficiencies in such surveys. The Owner shall secure and pay for title to the site and all
necessary permanent or construction easements. The Owner will cooperate with the Contractor in the prosecution of the Work in
such manner and to such extent as may be reasonable and shall furnish information under its control with reasonable promptness at
the request of the Contractor.
C-3 INSTRUCTIONS: The Owner shall issue all instructions to the Contractor through the Architect.
C-4 ACCESS TO JOB SITE: The Owner shall at all times have access to the Work whenever it is in preparation and
progress. The Contractor shall provide facilities for such access so the Owner may perform its assigned functions under the
Contract Documents.
C-5 PROGRESS INSPECTIONS: The Owner and Architect will make visits to the Site to familiarize themselves with the
progress and quality of the Work and to determine if the work is proceeding in accordance with the Contract Documents. On the
basis of on-site observations and reports concerning the progress and quality of the work,the Owner and Architect will approve and
authorize the Contractor's applications for payments.
C-6 AUTHORITY TO STOP WORK: The City will have authority to reject work that does not conform to the Plans and
Specifications. Whenever, in its reasonable opinion, the City considers it necessary or advisable in order to insure the proper
.r realization of the intent of the Plans and Specifications,the City will have authority to require the Contractor to stop the work or any
portion thereof, or to require special inspection or testing of the Work whether or not such Work be then fabricated, installed or
General Conditions of the Contract for Construction Lump Sum Contract Page 3 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
completed. The Contractor shall be responsible for the cost of special inspections and testing for work that is found not to comply
with the plans and specifications.
C-7 SUBSTANTIAL COMPLETION INSPECTION: Upon agreement of the Contractor and Architect that the Work is
substantially complete,the Owner will schedule a Substantial Completion Inspection to be conducted by the Architect and attended
by representatives of the Architect, Owner and Contractor. Items identified during this inspection as being incomplete, defective or
deficient shall be incorporated into a punch list and attached to the AIA document G704,which is to be prepared and signed by the
Contractor,and accepted,approved and signed by the Owner.
C-8 RIGHT TO AUDIT: Contractor agrees that the City shall, until the expiration of three years after final payment under this
contract, have access to and the right to examine any directly pertinent books, documents, papers and records of the Contractor
involving transactions relating to this contract. *■
Contractor further agrees to include in all his subcontracts hereunder a provision to the effect that the subcontractor agrees that the
City shall,until the expiration of three years after final payment under the subcontract, have access to and the right to examine any
directly pertinent books,documents, papers and records of such subcontractor, involving transactions to the subcontract. The term
"subcontract'as used herein includes purchase orders.
Contractor agrees to photocopy such documents as may be requested by the city. The city agrees to reimburse Contractor for the
costs of copies at the rate published in the Texas Administrative Code.
C-9 TERMINATION AND SUSPENSION OF WORK: The Owner has the right to terminate the Project for any reason. If the
project is terminated,the Contractor shall:
a) Stop work under the Contract on the date and to the extent specified on the notice of termination. +�
b) Place no further orders or subcontracts except as may be necessary for the completion of the work not terminated.
C) Terminate all orders and subcontracts to the extent that they relate to the performance of the work terminated by the _
notice of termination.
After termination as above,the City will pay the Contractor a proportionate part of the contract price based on the work completed;
provided, however, that the amount of payment on termination shall not exceed the total contract price as reduced by the portion
thereof allocable to the work not completed and further reduced by the amount of payments, if, any otherwise made. Contractor
shall submit its claim for amounts due after termination as provided in this paragraph within 30 days after receipt of such claim. In
the event of any dispute or controversy as to the propriety or allowability of all or any portion of such claim under this paragraph,
such dispute or controversy shall be resolved and be decided by the City Council of the City of Fort Worth, and the decision by the
City Council of the City of Fort Worth shall be final and binding upon all parties to this contract. ®„
SECTION D
CONTRACTOR
D-1 IDENTIFICATION: The Contractor is the person or organization identified as such in the Contract. The term Contractor
means the Contractor or his authorized representative.
D-2 INDEPENDENT CONTRACTOR: Contractor shall perform all work and services hereunder as an independent .■.
contractor, not as agent, or employee of the City. Contractor shall have exclusive control of and the exclusive right to control the
details of the Work and services performed hereunder,and all persons performing same,and Contractor shall be solely responsible
for the acts of its officers,agents, and employees. Nothing herein shall be construed as creating a partnership or joint enterprise
between City and the Contractor,its officers,agents and employees,and the doctrine of respondent superior shall not apply. ..
D-3 REVIEW OF CONTRACT DOCUMENTS: The Contractor shall carefully study and compare the Agreement, Conditions
of the Contract,Drawings,Specifications,Addenda and modifications and shall at once report to the Owner and to the Architect any
error, inconsistency or omission he may discover. The Contractor shall do no work without Drawings, Specifications and
Interpretations. "!
D-4 SUPERVISION: The Contractor shall supervise and direct the Work, using reasonable skill and attention. He shall be
solely responsible for all construction means, methods, safety, techniques, sequences and procedures and for coordinating all
portions of the Work under the Contract Documents.
D-5 LABOR AND MATERIALS: Unless otherwise specifically noted, the Contractor shall provide and pay for all labor,
materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation and other facilities and
services necessary for the proper execution and completion of the Work.
The Contractor will use its reasonable best efforts to hire local laborers,workmen and materialmen.The general condition is not to
be constructed as limiting the right of the Contractor to employee laborers,workmen or materialmen from outside local area.
The Contractor shall at all times enforce strict discipline and good order among his employees, and shall not employ on the Work
any unfit person or anyone not skilled in the task assigned to him.
«sw
General Conditions of the Contract for Construction Lump Sum Contract Page 4 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
D-6 COMPLIANCE WITH AND ENFORCEMENT OF PREVAILING WAGE RATE
Duty to pay Prevailina Wage Rates. The Contractor shall comply with all requirements of Chapter 2258,Texas Government Code
(Chapter 2258), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the
prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these contract documents.
'® Penalty for Violation. A contractor or any subcontractor who does not pay the prevailing wage shall, upon demand made by the
City, pay to the City$60 for each worker employed for each calendar day or part of the day that the worker is paid less than the
prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative
costs,pursuant to Texas Government Code 2258.023.
Complaints of Violations and City Determination of Good Cause. On receipt of information, including a complaint by a worker,
concerning an alleged violation of 2258.023, Texas Government Code, by a contractor or subcontractor, the City shall make an
initial determination, before the 31`'day after the date the City receives the information,as to whether good cause exists to believe
that the violation occurred. The City shall notify in writing the contractor or subcontractor and any affected worker of its initial
determination. Upon the City's determination that there is good cause to believe the contractor or subcontractor has violated
Chapter 2258,the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and
wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final
determination of the violation.
Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023, Texas Government
Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the
Texas General Arbitration Act(Article 224 et seq., Revised Statutes)if the contractor or subcontractor and any affected worker do
.. not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to paragraph
(c)above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the
arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of
competent jurisdiction.
Records to be Maintained. The Contractor and each subcontractor shall, for a period of three (3) years following the date of
acceptance of the Work,maintain records that show(i)the name and occupation of each worker employed by the Contractor in the
construction of the Work provided for in this contract;and(ii)the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of the Audit section of these contract documents shall pertain
to this inspection.
Pay Estimates. With each partial payment estimate or payroll period, whichever is less, the Contractor shall submit an affidavit
stating that the Contractor has complied with the requirements of Chapter 2258,Texas Government Code.
Posting of Wage Rates. The Contractor shall post the prevailing wage rates in a conspicuous place at the site of the project at all
times.
Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its subcontractors to
comply with paragraphs(a)through(g)above.
On projects where special wage rates apply(e.g.Davis-Bacon)the Contractor agrees to meet all requirements of such programs.
D-7 WARRANTY: The Contractor warrants to the Owner and the Architect that all materials and equipment furnished under
this Contract will be new unless otherwise specified, and that all work will be of good quality, free from faults and defects, and in
conformance with the Contract Documents. All work not so conforming to these standards may be considered defective. If required
by the Architect or the Owner the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and
equipment.
Prior to occupancy of the Project by the Owner,the Contractor warranties and obligations to correct defective Work exclude remedy
for damage or defect caused by (i) abuse by the Owner's separate contractors, or (ii) modifications made by the Owner or the
Owner's separate contractors. After occupancy of the Project by the Owner, the Contractor warranties and obligations to correct
defective Work exclude remedy for damage or defect caused by (i) abuse, (ii) modifications not executed by the Contractor, (iii)
improper or insufficient maintenance, (iv)improper operation,(v)normal wear and tear,or(vi)normal usage.
The warranty provided in this Section shall be in addition to and not in limitation of any other warranty or remedy provided by law or
the Contract Documents.
D-8 TAXES: The Contractor is exempt from State Sales Tax on material incorporated into the finished construction, Excise
and Use Tax.Equipment and materials not consumed by or incorporated into the work are subject to State sales taxes under House
Bill 11,enacted August 15, 1991.
D-9 LICENSES, NOTICES AND FEES: The Contractor shall obtain all Permits, Licenses, Certificates, and Inspections,
whether permanent or temporary, required by law or these Contract Documents. The City of Fort Worth Building and Trade Permit
*• fees are waived. Separate permits may be required for each work location.If the Contractor allows any permit to expire,he shall be
responsible for all renewals including any associated fees.
General Conditions of the Contract for Construction Lump Sum Contract Page 5 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
The Contractor shall give all Notices and comply with all Laws, Ordinances, Rules, Regulations and Orders of any public authority
bearing on the performance of the Work. If the Contractor observes or becomes aware that any of the Contract Documents are at
variance therewith in any respect, he shall promptly notify the Architect and Owner in writing and any necessary changes will be ..�
made. If the Contractor performs any Work knowing that it is in violation of, or contrary to, any of such Laws, Statutes, Charter,
Ordinances, Orders or Directives, or Regulations without furnishing Notice to the Architect and Owner, the Contractor will assume
full responsibility therefore and bear all costs attributable thereto.
D-10 CASH ALLOWANCES: The Contractor shall include in the Contract Sum all allowances stated in the Contract
Documents.These allowances shall cover the net cost of the materials and equipment delivered and unloaded at the site, and all
applicable taxes. The Contractor's handling costs on the site, labor, installation costs, overhead, profit and other expenses
contemplated for the original allowance shall be included in the Contractor Sum and not in the allowance. The Contractor shall
cause the Work covered by these allowances to be performed for such amounts and by such persons as the Owner may direct, but r`
he will not be required to employ persons against whom he makes a reasonable objection. If the cost, when determined, is more
than or less than the allowance, the Contract Sum shall be adjusted accordingly by Change Order which will include additional
handling costs on the site, labor, installation costs,field overhead, profit and other direct expenses resulting to the Contractor from
any increase over the original allowance.
D-11 SUPERINTENDENT: The Contractor shall employ a competent superintendent and necessary assistants who shall be in
attendance at the Project site during the progress of the Work. The superintendent shall be satisfactory to the Owner. The
superintendent shall represent the Contractor and all communications given to the superintendent shall be binding as if given to the
Contractor. Important communications will be confirmed in writing. Other communications will be so confirmed on written request in
each case.
D-12 RESPONSIBILITIES FOR EMPLOYEES AND SUB-CONTRACTORS: The Contractor shall be responsible to the Owner
for the acts and omissions of all his employees and all Sub-contractors, their agents and employees, and all other persons �^
performing any of the Work under a contract with the Contractor.
D-13 FAILURE TO COMMENCE WORK: Should the Contractor fail to begin the Work herein provided for within the time
herein fixed or to carry on and complete the same according to the true meaning of the intent and terms of said Plans,Specifications
and Contract Documents,then the Owner shall have the right to either demand the surety to take over the Work and complete same
in accordance with the Contract Documents or to take charge of and complete the Work in such a manner as it may deem proper,
and if, in the completion thereof, the cost to the said City shall exceed the contract price or prices set forth in the said plans and
specifications made a part hereof, the Contractor and/or its Surety shall pay said City on demand in writing, setting forth and
specifying an itemized statement of the total cost thereof,said excess cost.
D-14 PROGRESS SCHEDULE: The Contractor, immediately after being awarded the contract, shall prepare and submit for
the Architect's and Owner's approval, an estimated progress schedule for the Work. The progress schedule shall be related to the
entire Project and indicate critical path.This schedule shall indicate the dates for the starting and completion of the various states of ..�
construction and shall be revised as required by the conditions of the Work,subject to the Architect's approval. It shall also indicate
the dates for submission and approval of shop drawings and submittals as well as the delivery schedule for major pieces of
equipment and/or materials.
The Contractor shall submit an updated progress schedule to the Architect and Owner at least monthly for approval along with the
Contractor's monthly progress payment requests.
D-15 DRAWINGS AND SPECIFICATIONS AT THE SITE: The Contractor shall maintain at the site for the Owner one copy of
all Drawings, Specifications, Addenda, approved Shop Drawings, Change Orders, and other Changes and Amendments in good
order and marked to record all changes made during construction. These shall also be available to the Architect. The Drawings,
marked to record all changes made during construction,shall be delivered to the Owner upon completion of the Work. The Architect
will prepare,and provide to the Owner,one complete set of reproducible record drawings of the Work.
D-16 SHOP DRAWINGS AND SAMPLES: Shop Drawings are drawings, diagrams, illustrations, schedules, performance
charts, brochures and other data which are prepared by the Contractor or any Subcontractor, manufacturer„supplier or distributor,
and which illustrate some portion of the Work.These may be provided in an electronic format acceptable to the Architect.
Samples are physical examples furnished by the Contractor to illustrate materials, equipment or workmanship, and to establish
standards by which the Work will be judged.Three copies of all physical examples shall be provided.
The Contractor shall review, approve, and submit,with reasonable promptness and in orderly sequence so as to cause no delay in
the Work or in the work of any other contractor, normally within the first 90 days of the work, six copies of all shop Drawings and
Samples required by the Contract Documents or subsequently by the Architect as covered by changes or amendments. Shop
Drawings and Samples shall be properly identified as specified, or as the Architect may require. At the time of submission the
Contractor shall inform the Architect in writing of any deviation in the Shop Drawings or Samples from the requirements of the
Contract Documents. ..
By approving and submitting Shop Drawings and Samples, the Contractor thereby represents that he has determined and verified
all field measurements, field construction criteria, materials, catalog numbers and similar data, and that he has checked and
coordinated each shop drawing given in the Contract Documents. The Architect's approval of a separate item shall not indicate
approval of an assembly in which the item functions. r.
General Conditions of the Contract for Construction Lump Sum Contract Page 6 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
The Architect will review and approve Shop Drawings and Samples with reasonable promptness so as to cause no delay, but only
for conformance with the design concept of the Project and with the information given in the Contract Documents.The Architect's
approval of a separate item shall not indicate approval of an assembly in which the item functions.
The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of
Shop Drawings or new Samples until approved. The Contractor shall direct specific attention in writing or on resubmitted Shop
Drawings to revisions other than the corrections requested by the Architect on previous submissions.
The Architect's approval of Shop Drawings or Samples shall not relieve the Contractor of responsibility for any deviation from the
requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of
submission and the Architect has given written approval to the specific deviation. Architect's approval shall not relieve the
•• Contractor from responsibility for errors or omissions in the Shop Drawings or Samples.
No portion of the Work requiring a Shop Drawing or Sample submission shall be commenced until the Architect has approved the
submittal.All such portions of the Work shall be in accordance with approved Shop Drawings and Samples.
D-17 SITE USE: The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits and the
Contract Documents and shall not unreasonably encumber the site with any materials or equipment. Until acceptance of the Work
by the City,the entire site of the Work shall be under the exclusive control,care and responsibility of the Contractor. Contractor shall
take every precaution against injury or damage to persons or property by the action of the elements or from any other cause
whatsoever.The Contractor shall rebuild,repair,restore and make good at his own expenses all injuries or damages to any portions
of the Work occasioned by any of the above,caused before acceptance.
D-18 CUTTING AND PATCHING OF WORK: The Contractor shall do all cutting, fitting or patching of his Work that may
require making its several parts fit together properly, and shall not endanger any Work by cutting, excavating or otherwise altering
the Work or any part of it.
D-19 CLEAN UP: The Contractor at all times shall keep the premises free from accumulation of waste materials or rubbish.At
.� the completion of the Work he shall remove all his waste materials and rubbish from and about the Project as well as all his tools,
construction equipment,machinery and surplus materials,and shall clean all glass surfaces and leave the Work"Broom-clean"or its
equivalent,except at otherwise specified. In addition to removal of rubbish and leaving the buildings"broom-clean",Contractor shall
clean all glass, replace any broken glass, remove stains,spots,marks and dirt from decorated work,clean hardware, remove paint
spots and smears from all surfaces,clean fixtures and wash all concrete,tile and terrazzo floors.
If the Contractor fails to clean up,the Owner may do so,and the cost thereof shall be charged to the Contractor.
D-20 COMMUNICATIONS: As a general rule, the Contractor shall forward all communications to the Owner through the
Architect.
D-21 CONTRACTOR REQUIREMENTS ON FEDERALLY FUNDED PROJECTS: Contractor shall observe and comply with
the requirements of the City of Fort Worth Fiscal Department, Intergovernmental Affairs and Grants Management as outlined in the
Supplemental Conditions contained in the Project Manual.
SECTION E
SUBCONTRACTORS
rw
E-1 DEFINITION: A Subcontractor is a person or organization that has a direct contract with the Contractor to perform any of
the Work at the site. The term Subcontractor is referred to throughout the Contract Documents as if singular in number and
masculine in gender and means a Subcontractor or his authorized representative.
Nothing contained in the Contract, Documents shall create any contractual relation between the Owner and the Architect and any
subcontractor or any of his sub-subcontractors or materialmen.
E-2 AWARD OF SUBCONTRACTS: The Contractor shall furnish a list of the names of the subcontractors or other persons
or organizations (including those who are to furnish materials or equipment fabricated to a special design) proposed for such
portions of the Work as may be designated in the bidding requirements,or if none is so designated in the bidding requirements,the
names of the Subcontractors proposed for the principal portions of the Work. Prior to the award of the Contract,the Architect shall
notify the successful bidder in writing if either the Owner or Architect,after due investigation,has reasonable objection to any person
or organization on such list. Failure of the Owner and Architect to make an objection to any person or organization on the list prior to
the award of this Contract shall not constitute acceptance of such person or organization.
If,prior to the award of the Contract,the Owner or Architect has an objective to any person or organization on such list,and refuses
to accept such person or organization, the apparent low bidder may, prior to the award, withdraw his bid without forfeiture of bid
security. If such bidder submits an acceptable substitute, the Owner may, at its discretion, accept the bid or he may disqualify the
bid. If, after the award, the Owner or Architect objects in writing to any person or organization on such list, the Contractor shall
provide an acceptable substitute.
•. The Contractor shall not make any substitution for any Subcontractor or person or organization that has been accepted by the
Owner and the Architect,unless the substitution is also acceptable to the Owner and the Architect.
General Conditions of the Contract for Construction Lump Sum Contract Page 7 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
E-3 TERMS OF SUBCONTRACTS: All work performed for the Contractor by a Subcontractor shall be pursuant to an
appropriate agreement between the Contractor and the Subcontractor(and where appropriate between Subcontractors and Sub-
subcontractors)which shall contain provisions that: ..
1, Preserve and protect the rights of the Owner and the Architect under the Contract with respect to the Work to be performed
under the subcontract so that the subcontracting thereof will not prejudice such rights;
2. Require that such Work be performed in accordance with the requirements of the Contract Documents;
3. Require submission to the Contractor of applications for payment under each subcontract to which the Contractor is a party,in
reasonable time to enable the Contractor to apply for payment;
4. Require that all claims for additional costs,extensions of time,damages for delays or otherwise with respect to subcontracted �+
portions of the Work shall be submitted to the Contractor(via any Subcontractor or Sub-subcontractor where appropriate) in
the manner provided in the Contract Documents for like claims by the Contractor upon the Owner;
5. Waive all rights the contracting parties may have against one another for damages caused by fire or other perils covered by the
property insurance,except such rights,if any,as they may have to proceeds of such insurance held by the Owner, and,
6. Obligate each Subcontractor specifically to consent to the provisions of this Section
All of the provisions set out in this section shall be deemed to have been included in every subcontract,and every subcontract shall
be so construed and applied as to the Owner and the Architect, whether or not such provisions are physically included in the sub-
contract.
E-4 MINORITY BUSINESS ENTERPRISE (MBE): Should the base proposal be $50,000 or less, the requirements of this
section do not apply.
As of June 1, 2012, The City of Fort Worth is implemented a new Business Diversity Ordinance (BDO) to reflect the City's
availability and disparity study findings and recommendations. During this transition period, interested Offerors must obtain a MBE
listing from the MAYBE Office. This will ensure that MBE listings reflect only those currently certified by the North Central Texas
Regional Certification Agency(NCTRCA)located in the six(6)-county geographic marketplace that have been accepted by the City.
The City's geographic marketplace includes the counties of: Tarrant, Dallas, Denton, Johnson, Parker and Wise. Offerors are
strongly encouraged to confirm that each MBE that it intends to use is located in the geographic marketplace that will be counted
towards the established goal. ...
In accordance with City of Fort Worth Diversity Business Ordinance (BDO) No 20020-12-2011 (the "Ordinance"), the City of Fort
Worth sets goals for the participation of Minority Business Enterprises(MBE) in City contracts. Ordinance No 20020-12-2011 is
incorporated in these General Conditions by reference. A copy of the Ordinance may be obtained from the Office of the City
Secretary. Failure to comply with the Ordinance shall be a material breach of contract. •■*
Prior to Award: The MBE documentation required by the procurement solicitation must be submitted within five city business days
after the proposals are opened. Failure to comply with the City's Business Diversity Ordinance, or to demonstrate a "good faith
effort",shall result in a bid being considered non-responsive.
During Construction: Contractor shall provide copies of subcontracts or cosigned letters of intent with approved MBE
subcontractors and or suppliers prior to issuance of the Notice to Proceed. Contractor shall also provide monthly reports on
utilization of the subcontractors to the MAYBE Office and the Building Construction Manager. Contractor must provide the City with
complete and accurate information regarding actual work performed by an MBE on the contract and proof of payment thereof. "^
Contractor further agrees to permit an audit and/or examination of any books, records or files in its possession that will substantiate
the actual work performed by an MBE. The misrepresentation of facts and/or the commission of fraud by the Contractor will be
grounds for termination of the contract and/or initiating action under appropriate federal,state,or local laws or ordinances relating to
false statement. An Offeror who intentionally and/or knowingly misrepresents material facts shall be determined to be an
irresponsible Offeror and barred from participating in City work for a period of time of not less than three(3)years. The failure of an
Offeror to comply with this ordinance where such non-compliance constitutes a material breach of contract as stated herein, may
result in the Offeror being determined to be an irresponsible Offeror and barred from participating in City work for a period of time of
not less than one(1)year.
The Contractor may count toward the goal any tier of MBE subcontractors and/or suppliers. The Contractor may count toward its
goal a portion of the total dollar amount of the contract with a joint venture equal to the percentage of the MBE participation in the
joint venture for a clearly defined portion of the work to be performed. All subcontractors used in meeting the goals must be certified
prior to the award of the Contract. —
Change Orders: Whenever a change order affects the work of an MBE subcontractor or supplier, the MBE shall be given an
opportunity to perform the work. Whenever a change order is$50,000 or more,the MAYBE Office Coordinator shall determine the
goals applicable to the work to be performed under the change order.
During the term of the contract the Contractor shall:
1 Make no unjustified changes or deletions in its MBE participation commitments submitted with the bid/proposal or during
negotiation,without prior submission of the proper documentation for review and approval by the MAYBE Office.
w
General Conditions of the Contract for Construction Lump Sum Contract Page 8 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
am
MR
2. If substantial subcontracting and/or supplier opportunities arise during the term of any contract when the Contractor
ON represented in its bid/proposal to the City that it alone would perform the subcontracting/supplier opportunity work, the
Contractor shall notify the City before subcontracts for work and/or supplies are awarded and shall be required to comply with
subsections of the O0rdinance,exclusive of the time requirements stated in such subsections.
3. The Contractor shall submit to the M/WBE Office for approval an MBE REQUEST FOR APPROVAL OF CHANGE FORM, if,
during the term of any contract,the Contractor wishes to change or delete one or more MBE subcontractors or suppliers.
Justification for change of subcontractors may be granted for the following:
irw 1. An MBE's failure to provide Workers'Compensation Insurance evidence as required by state law;or
2. An MBE's-failure to provide evidence of general liability or other insurance under the same or similar terms as contained in the
Contract Documents with limits of coverage no greater than the lower of 1)the limits required of the Contractor by the City;or
s� 2)the limits contained in the Contractor's standard subcontract or supply agreements used on other projects of similar size and
scope and within the Contractor's normal business practice with non-MBE subcontractors/sub consultant's or suppliers;or
3. An MBE's failure to execute the Contractor's standard subcontract form, if entering a subcontract is required by the Contractor
in its normal course of business, unless such failure is due to:
a) A change in the amount of the previously agreed to bid or scope of work;or
b) The contract presented provides for payment once a month or longer and the Contractor is receiving
we payment from the City twice a month;or
c) Any limitation being placed on the ability of the MBE to report violations of the Ordinance or any other
ordinance or violations of any state or federal law or other improprieties to the City or to provide notice
of any claim to the Contractor's surety company or insurance company.
d) Mediation shall be a consideration before the request for change is approved.
4. An MBE defaults in the performance of the executed subcontract. In this event,the Contractor shall:
a) Request bids from all MBE subcontractors previously submitting bids for the work,
b) If reasonably practicable,request bids from previously non-bidding MBEs,and
w
C) Provide to the MNVBE Office documentation of compliance with(a)and(b)above.
5. Any reason found to be acceptable by the MNVBE Office in its sole discretion.
Within ten days after final payment from the City the Contractor shall provide the MNVBE Office with documentation to reflect final
participation of each subcontractor and supplier,including non-MBEs, used on the project.
E-5 PAYMENTS TO SUBCONTRACTORS: The Contractor shall pay each Subcontractor, upon receipt of payment from the
an Owner an amount eaual to the percentage of completion allowed to the Contractor on account of such Subcontractor's Work. The
Contractor shall also require each Subcontractor to make similar payments to his subcontractors.
If the Owner refuses to issue a Certificate for Payment for any cause which is the fault of the Contractor and not the fault of a
particular subcontractor,the Contractor shall pay that Subcontractor on demand,made at any time after the Certificate for Payment
would otherwise have been issued,for his Work to the extent completed,less the retained percentage.
The Contractor shall pay each Subcontractor a just share of any insurance monies received by the Contractor,and he shall require
each Subcontractor to make similar payments to his Subcontractors.
w
The Owner may, on request and at its discretion,furnish to any Subcontractor, if practicable, information regarding percentages of
completion certified to the Contractor on account of Work done by such Subcontractors.
Neither the Owner nor the Architect shall have any obligation to pay or to see to the payment of any monies to any Subcontractor.
E-6 _SUBCONTRACTOR REQUIREMENTS FOR ECONOMIC DEVELOPMENT ADMINSTRATION (EDA) FUNDED
PROJECTS: The Contractor will cause appropriate provisions to be inserted in all subcontracts to bind subcontractors to FDA
contract requirements as contained herein and to 15 CFR 24 or OMB Circular A-110,as appropriate.
Each subcontractor must agree to comply with all applicable Federal, State, and local requirements in addition to those set forth in
this section.
No subcontractor will be employed on this Project, except as specifically approved by the City, who is contained in the listing of
contractors debarred, ineligible, suspended or indebted to the United States from contractual dealings with Federal government
General Conditions of the Contract for Construction Lump Sum Contract Page 9 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
departments. The work performed by any such contractor or subcontractor will be ineligible for reimbursement wholly or partially
from EDA grant fluids.
r
All subcontracts in excess of$10,000 shall include, or incorporate by reference, the equal opportunity clause of Executive Order
11246.
All subcontracts must contain a nondiscrimination clause.
Each subcontract must contain a requirement for compliance with the Davis-Bacon and related acts.
Each subcontractor must submit weekly each weekly payroll record and a weekly statement of compliance. These documents will
be submitted to the prime contractor who will compile them and submit to the City.The subcontractor can satisfy this requirement by �^
submitting a properly executed Department of Labor Form WH-347.
Each subcontract with every subcontractor must contain a clause committing the subcontractor to employment of local labor to the
maximum extent possible. ...
All subcontractors who employ more than 50 employees, and is a prime or first tier subcontractor, and has a subcontract or
purchase order of$50,000 or more must submit a completed Standard Form 100(Compliance Report)by March 30 of each year.
Subcontractors performing work in areas covered by published goals for minorities will be required to report monthly on Form CC-
257.
SECTION F �..
SEPARATE CONTRACTS
F-1 OWNER'S RIGHT: The Owner reserves the right to award separate contracts in connection with other portions of the
Work. When separate contracts are awarded for other portions of the Work, "the Contractor' in the Contract Documents in each �.
case shall be the contractor who signs each separate contract.
F-2 MUTUAL RESPONSIBILITY OF CONTRACTORS: The Contractor shall afford other contractors reasonable opportunity
for the introduction and storage of their materials and equipment and the execution of their work, and shall properly connect and
coordinate his work with theirs.
If any part of the Contractor's Work depends for proper execution or results upon the work of any other separate contractor, the
Contractor shall inspect and promptly report to the Owner any apparent discrepancies or defects in such work that render it
unsuitable for such proper execution and results.Failure of the Contractor to inspect and report shall constitute an acceptance of the
other contractors work as fit and proper to receive his Work, except as to defects which may develop in the other separate
contractor's work after the execution of the Contractor's Work.
Should the Contractor cause damage to the work or property of any separate contractor on the site,the Contractor shall, upon due
notice,settle with such other contractor by agreement,if he will so settle. If such separate contractor sues the Owner on account of
any damage alleged to have been so sustained, the Owner shall notify the Contractor who shall defend against such suit at the
Contractors expense, and if any judgment against the Owner arises therefrom, the Contractor shall pay or satisfy such judgment
and shall reimburse the Owner for all attorney's fees, court costs and expenses which the Owner has incurred in connection with
such suit.
F-3 CUTTING AND PATCHING UNDER SEPARATE CONTRACTS: The Contractor shall do all cutting,fitting or patching of
his Work that may be required to fit it to receive or be received by the work of other contractors shown in the Contract Documents.
The Contractor shall not endanaer any work or any other contractors by cutting,excavating or otherwise altering any work and shall
not cut or alter the work of any other contractor except with the written consent of the Architect.
Any costs caused by defective or ill-timed work shall be borne by the party responsible therefor.
F-4 OWNER'S RIGHT TO CLEAN UP: if a dispute arises between the separate contractors as to their responsibility for
cleaning up, the Owner may clean up and charge the cost thereof to the several contractors as the Director of the Project
Management Department shall determine to be just.
SECTION G ...
MISCELLANEOUS PROVISIONS
G-1 CONFLICT OF LAWS: The law of the place where the site is located shall govern the Contract. The Contractor must
familiarize himself and strictly comply with all Federal,State,and County and City Laws,Statutes,Charter,Ordinances,Regulations,
or Directives controlling the action or operation of those engaged upon the work affecting the materials used.He shall indemnify and
save harmless the City and all of its officers and agents against any claim or liability arising from or based on the violation of any
such Laws,Statutes,Charter,Ordinances,Regulations,or Directives,whether by himself,his employees,agents or subcontractors.
G-2 GOVERNING LAWS: It is mutually agreed and understood that this agreement is made and entered into by the parties ..
hereto with reference to the existing Charter and Ordinances of the City of Fort Worth and the laws of the State of Texas with
General Conditions of the Contract for Construction Lump Sum Contract Page 10 of
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
reference to and governing all matters affecting this Contract, and the Contractor agrees to fully comply with all the provisions of the
same.
G-3 PERSONAL LIABILITY OF PUBLIC OFFICIALS: In performing their duties under the Statutes of the State of Texas and
the Charter and Ordinances of the City of Fort Worth in connection with this Contract,or in exercising any of the powers granted the
Owner herein, the officers, agents and employees of the City of Fort Worth are engaged in the performance of a governmental
function and shall not incur any personal liability by virtue of such performance hereunder, except for gross negligence or willful
wrong.
G-4 COMPLIANCE WITH LAWS. Contractor agrees to comply with all laws, Federal,state and local,including all ordinances,
ww rules and regulations of the City of Fort Worth,Texas. Materials incorporated into the finished Project are not subject to State Sales
Tax.
The Owner is responsible for obtaining the Building Permit. The Contractor and the appropriate subcontractor are responsible for
�r obtaining all other construction permits from the governing agencies. Contractor shall schedule all code inspections with the Code
Inspection Division in accordance with the permit requirements. Building, plumbing,electrical and mechanical building permits are
issued without charge. Water and sewer tap, impact & access fees will be paid by the City. Any other permit fees are the
responsibility of the Contractor
G-5 INDEMNIFICATION: Contractor covenants and agrees to indemnify City's engineer and architect, and their
personnel at the project site for Contractor's sole negligence. In addition,Contractor covenants and agrees to indemnify,
hold harmless and defend,at its own expense,the Owner,its officers,servants and employees,from and against any and
all claims or suits for property loss, property damage, personal injury, including death, arising out of,or alleged to arise
out of, the work and services to be performed hereunder by Contractor, its officers, agents, employees, subcontractors,
licensees or invitees, whether or riot any such injury, damage or(loath is caused, in whole or in part, bit the neglig nce or
alleged negligence of Owner,its officers servants or employees. Contractor likewise covenants and agrees to indemnify
and hold harmless the Owner from and against any and all injuries to Owner's officers,servants and employees and any
r damage, loss or destruction to property of the Owner arising from the performance of any of the terms and conditions of
this Contract, whether or not any such injury or damage is caused in whole or in part by the negligence or alleged
negliqence of Owner,its officers,servants or employees.
In the event Owner receives a written claim for damages against the Contractor or its subcontractors prior to final
payment,final payment shall not be made until Contractor either(a)submits to Owner satisfactory evidence that the claim
has been settled and/or a release from the claimant involved,or(b)provides Owner with a letter from Contractor's liability
insurance carrier that the claim has been referred to the insurance carrier.
,.. The Director may, if he deems it appropriate, refuse to whom a claim for damages is outstanding as a result of work
performed under a City Contract.
G-6 SUCCESSORS AND ASSIGNS: Except as provided in Paragraph E-2,this contract shall be binding upon and insure to
the benefit of the parties hereto,their Successors or Assigns. Contractor shall not assign or sublet all or any part of this Contract or
his rights or duties hereunder without the prior written consent of the Owner.Any such purported assignment or subletting without
the prior written consent of Owner shall be void.
G-7 WRITTEN NOTICE: Written Notice shall be deemed to have been duly served if delivered in person to the individual or
member of the firm or to an officer of the corporation for whom it was intended, or if delivered at or sent by registered or certified
mail to the last business address known to him who gives the notice.
G-8 SURETY BONDS: Surety Bonds are required on all City contracts in excess of$25,000. The Contractor agrees, on the
submittal of his Proposal to make, execute and deliver to said City of Fort Worth good and sufficient surety bonds for the faithful
performance of the terms and stipulations of the Contract and for the payment to all claimants for labor and/or materials furnished in
the prosecution of the Work,such bonds being as provided and required in Article 5160 of the Revised Civil Statutes of Texas, as
amended, in the form included in the Contract Documents,and such bonds shall be 100 percent of the total contract price, and the
said surety shall be a surety company duly and legally authorized to do business in the State of Texas,and acceptable to the City
Council of the City of Fort Worth.
Bonds shall be made on the forms furnished by or otherwise acceptable to the City. Each bond shall be properly executed by both
the Contractor and the Surety Company. Bonds required by the City shall be in compliance with all relevant local,state and federal
statutes.
To be an acceptable surety on the bond the name of the surety should be included on the current U. S.Treasury List of Acceptable
Securities[Circular 570],and must be authorized to do business in Texas. Sureties not listed in Circular 570 may write performance
and payment bonds on a project without reinsurance to the limit of 10 percent of its capital and surplus.
Such a surety must reinsure any obligation over 10 percent.The amount in excess of 10 percent must be reinsured by reinsurers
who are duly authorized,accredited,or trusteed to do business in the State of Texas.
.. Should any surety for the contracted project be determined unsatisfactory at any time during same,the Contractor shall immediately
provide a new surety bond satisfactory to the City.
General Conditions of the Contract for Construction Lump Sum Contract Page 11 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
If the contract amount is$25,000 or less,payment to the Contractor shall be made in one lump sum.Payment shall not be made for
a period of 45 calendar days from the date the work has been completed and accepted by the City.
G-9 OWNER'S RIGHT TO CARRY OUT THE WORK: If the Contractor defaults or neglects to carry out the Work in
accordance with the Contract Documents or fails to perform any provision of the Contract,the Owner may,without prejudice to any
other remedy he may have, enter the site and make good such deficiencies. In such case an appropriate Change Order shall be
issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies,including the cost rr
of the Architect's additional services made necessary by such default, neglect or failure. If the payments then or thereafter due the
Contractor are not sufficient to cover such amount,the Contract shall pay the difference to the Owner.
G-10 ROYALTIES AND PATENTS: The Contractor shall pay all royalties and license fees. He shall defend all suits or claims
for infringement of any patent rights and shall save the Owner harmless from loss on account thereof and shall be responsible for all
such loss when a particular design,process or the product of a particular manufacturer or manufacturers is specified;however,if the
Contractor has reason to believe that the design,process or product specified is an infringement of a patent, he shall be responsible
for such loss unless he promptly gives such information to Owner.
G-11 TESTS: If the Contract Documents, Laws, Ordinances, Rules, Regulations or Orders of any public authority having
jurisdiction require any Work to be inspected,tested or approved,the Contractor shall give the Owner timely notice of its readiness
and the date arranged so the Architect may observe such inspection, testing or approval. The Owner shall bear all costs of such
inspection,tests and approvals unless otherwise provided. .�
If after the commencement of the Work, the Owner determines that any work requires special inspection, testing or approval not
included above, the Architect, upon written authorization from the Owner, will instruct the Contractor to order such special
inspection, testing or approval, and the Contractor shall give notice as required in the preceding paragraph. If such special
inspection or testing reveals a failure of the Work to comply(1)with the requirements of the Contract Documents or(2)with respect
to the performance of the Work, with Laws, Statutes, Charter, Ordinances, Regulations or Orders of any public authority having
jurisdiction, the Contractor shall bear all costs thereof, including the Architect's additional services made necessary by such costs;
otherwise the Owner shall bear such costs,and an appropriate Change Order shall be issued.
The Contractor shall secure certificate of inspection, testing or approval, and three copies will be promptly delivered by him to the
Architect.The Architect will review the certificates and forward one copy of each with his recommendation(s)to the Owner.
If the Owner wishes to observe the inspections, tests or approvals required by this Section, they will do so promptly and, where
practicable,at the source of supply.
Neither the observations of the Architect or the Owner in their administration of the Construction Contract, nor inspections,tests or
approvals by persons other than the Contractor shall relieve the Contractor from his obligations to perform the Work in accordance
with the Contract Documents. ■""
G-12 INTERRUPTION OF EXISTING UTILITIES SERVICES: The Contractor shall perform the Work under this Contract with a
minimum of outage time for all utilities. Interruption shall be by approved sections of the utility. In some cases,the Contractor may
be required to perform the Work while the existing utility is in service. The existing utility service may be interrupted only when
approved by the Owner.When it is necessary to interrupt the existing utilities,the Contractor shall notify the Owner in writing at least
ten days in advance of the time that he desires the existing service to be interrupted. The interruption time shall be kept to a
minimum.Depending upon the activities at an existing facility that requires continuous service from the existing utility,an interruption
may not be subject to schedule at the time desired by the Contractor In such cases,the interruption may have to be scheduled at a
time of minimum requirements of demand for the utility.The amount of time requested by the Contractor of existing utility services
shall be as approved by the Owner.
G-13 LAYING OUT WORK: The Contractor shall verify dimensions and elevations indicated in layout of existing work.
Discrepancies between Drawings, Specifications, and existing conditions shall be referred to the Architect for adjustment before ,..
work affected is performed. Failure to make such notification shall place responsibility upon Contractor to carry out work in
satisfactory workmanlike manner at the Contractor's sole expense.
The Contractor shall be held responsible for the location and elevation of all the construction contemplated by the Construction
Documents.
Prior to commencing work, the Contractor shall carefully compare and check all Architectural, Structural, Mechanical an Electrical
drawings; each with the other that in any affects the locations or elevation of the work to be executed by him, and should any
discrepancy be found, he shall immediately report the same to the Architect for verification and adjustment.Any duplication of work
made necessary by failure or neglect on his part to comply with this function shall be done at the Contractor's sole expense.
G-14 MEASUREMENTS: Before ordering any material or doing any work,the Contractor shall verify all measurements at the
site or at the building and shall be wholly responsible for the correctness of same.
No extra charge or compensation will be allowed on account of any difference between actual dimensions and dimensions indicated
on the drawings. Any difference that may be found shall be submitted to the Architect for consideration and adjustment before
proceeding with the project.
G-15 EXISTING OVERHEAD OR UNDERGROUND WORK: The Contractor shall carefully check the site where the project is
to be erected and observe any existing overhead wires and equipment.Any such work shall be moved, replaced or protected, as
required,whether or not shown or specked at the Contractor's sole expense.
General Conditions of the Contract for Construction Lump Sum Contract Page 12 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
Attention is directed to the possible existence of pipe and other underground improvements that may or may not be shown on the
M Drawings.All reasonable precautions shall be taken to preserve and protect any such improvements whether or not shown on the
Drawings.
Location of existing underground lines, shown the Drawings are based on the best available sources, but are to be regarded as
approximate only.Exercise extreme care in locating and identifying these lines before excavation in adjacent areas.
G-16 ALIGNMENT OF JOINTS IN FINISH MATERIALS: It shall be the responsibility of the Contractor to make certain in the
installation of jointed floor,wall and ceiling materials that:
..w 1 Preserve and protect the rights of the Owner and the Architect under the Contract with respect to the Work to be performed
under the subcontract so that the subcontracting thereof will not prejudice such rights;
2. Place joints to relate to all opening and breaks in the structure and be symmetrically placed wherever possible.This includes
heating registers,light fixtures,equipment,etc.
If because of the non-related sizes of the various materials and locations of openings, etc., it is not possible to accomplish the
above, the Contractor shall request the Architect to determine the most satisfactory arrangement. The Contractor shall establish
centerlines for all trades.
G-17 INTEGRATING EXISTING WORK: The Contractor shall protect all existing street and other improvements from
damages.
Contractors operations shall be confined to the immediate vicinity of the new work and shall not in any interfere with or obstruct the
ingress or egress to and from existing adjacent facilities.
Where new site work is to be connected to existing work,special care shaft be exercised by the Contractor not to disturb or damage
the existing work more than necessary.All damaged work shall be replaced, repaired and restored to its original condition at no cost
40 to the Owner
G-18 HAZARDOUS MATERIAL CERTIFICATION: It is the intent of the contract documents,whether expressly stated or not,
that nothing containing hazardous materials,such as asbestos,shall be incorporated in to the project. The Contractor shall exercise
every reasonable precaution to ensure that asbestos-containing materials are not incorporated into any portion of the project,
including advising all materials suppliers and subcontractors of this requirement. The Contractor shall verify that components
containing lead do not contact the potable water supply.
G-19 LOCATION OF EQUIPMENT AND PIPING: Drawing showing location of equipment, piping, ductwork, etc, are
wr diagrammatic and job conditions may not always permit their installation in the location shown.When this situation occurs,it shall be
brought to the Architect's attention immediately and the relocation determined in a joint conference. The Contractor will be held
responsible for the relocating of any items without first obtaining the Architect's approval. He shall remove and relocate such items
at his own expense if so directed by the Architect. Where possible, uniform margins are to be maintained between parallel lines
r�
and/or adjacent wall,floor or ceiling surfaces.
G-20 OVERLOADING: The Contractor shall be responsible for loading of any part or parts of structures beyond their safe
carrying capacities by placing of materials, equipment, tools, machinery or any other item thereon. No loads shall be placed on
floors or roofs before they have attained their permanent and safe strength.
w
G-21 MANUFACTURER'S INSTRUCTIONS: Where it is required in the Specifications that materials, products, processes,
equipment, or the like be installed or applied in accordance with manufacturer's instructions,direction or specifications,or words to
this effect, it shall be construed to mean that said application or installation shall be in strict accordance with printed instructions
rr furnished by the manufacturer of the material concerned for use under conditions similar or those at the job site.Six copies of such
instructions shall be furnished to the Architect and his approval thereof obtained before work is begun.
G-22 CLEANING UP: The Contractor shall keep the premises free from accumulation of waste material or rubbish caused by
employees or as a result of the Work.
At completion of work,the General Contractor shall, immediately prior to final inspection of complete building,execute the following
final cleaning work with trained janitorial personnel and with material methods recommended by the manufactures of installed
materials.
rMw
1. Sweep and buff resilient floors and base,and vacuum carpeting.
2. Dust all metal and wood trim and similar finished materials.
3. Clean all cabinets and casework.
4. Dust all ceilings and walls.
5. Dust,and if necessary wash,all plumbing and electrical fixtures.
w
6. Wash all glass and similar non-resilient materials.
General Conditions of the Contract for Construction Lump Sum Contract Page 13 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
7. All hardware and other unpainted metals shall be cleaned and polished and all equipment and paint or decorated work shall be
cleaned and touched-up if necessary, and all temporary labels,tags, and paper coverings removed throughout the buildings.
Surfaces that are waxed shall be polished. ■.,
8. The exterior of the building,the grounds, approaches,equipment,sidewalks, streets,etc.shall be cleaned similar to interior of
buildings and left in good order at the time of final acceptance. All paint surfaces shall be clean and unbroken, hardware shall
be clean and polished,all required repair work shall be completed and dirt areas shall be scraped and cleared of weed growth.
9. Clean all glass surfaces and mirrors of putty, paint materials, etc.,without scratching or injuring the glass and leave the work
bright,clean and polished.Cost of this cleaning work shall be borne by Contractor.
10. Cleaning, polishing, scaling,waxing and all other finish operations indicated on the Drawings or required in the Specifications
shall be taken to indicate the required condition at the time of acceptance of all work under the Contract.
11. Burning:Burning of rubbish on the premises will not be permitted.
G-23 DUST CONTROL: Precaution shall be exercised at all times to control dust created as a result of any operations during
the construction period. If serious problems or complaints arise due to air-borne dust,or when directed by the Architect, operations
causing such problems shall be temporarily discontinued and necessary steps taken to control the dust.
G-24 FIRE PROTECTION: The Contractor shall at all times maintain good housekeeping practices to reduce the risk of fire
damage or injury to workmen.All scrap materials, rubbish and trash shall be removed daily from in and about the building and shall
not be permitted to be scattered on adjacent property.
Suitable storage space shall be provided outside the immediate building area for storing flammable materials and paints;no storage +.
will be permitted in the building.Excess flammable liquids being used inside the building shall be kept in closed metal container and
removed from the building during unused periods.
A fire extinguisher shall be available at each location where cutting or welding is being performed.Where electric or gas welding or w.
cutting work is done, interposed shields of incombustible material shall be used to protect against fire damage due to sparks and hot
metal.When temporary heating devices are used,a watchman shall be present to cover periods when other workmen are not on the
premises.
The Contractor shall provide fire extinguishers in accordance with the recommendations and NFPA Bulletins Nos. 10 and 241.
However,in all cases a minimum of two fire extinguishers shall be available for each floor of construction.
G-25 CUTTING AND PATCHING: Wherever cutting and removal of portions of the existing work is indicated,such work shall
be neatly sawed or cut by Contractor in a manner that will produce a neat straight line, parallel to adjacent surfaces or plumb for
vertical surfaces.Care should be exercised not to damage any work that is to remain.
At no time shall any structural members be cut without written consent from the Architect.
G-26 PROJECT CLOSEOUT
Final Inspection, Record Drawings: Attention is called to General Conditions Section entitled, "Substantial Completion and Final
Payment".
Maintenance Manual:Sheets shall be 8'/"x 11",except pull out sheets may be neatly folded to 8'/z"x 11".Manuals shall be bound
in plastic covered,3 ring, loose leaf binder with title of project lettered on front and shall contain:
1) Name,address and trade of all sub-contractors. ..
2) Complete maintenance instructions; name, address, and telephone number of installing Contractor, manufacturer's local
representative,for each piece of operative equipment.
3) Catalog data on plumbing fixtures, valves, water heaters, heating and cooling equipment, temperature control, fan, electrical
panels,service entrance equipment and light fixtures.
4) Manufacturer's name,type,color designation for resilient floors,windows,doors,concrete block,paint,roofing,other materials.
Submit three digital electronic copies of Maintenance Manuals,prior to request for final payment. .�.
Operational Inspection and Maintenance Instruction: The Contractor shall provide at his expense, competent manufacturer's
representatives to completely check out all mechanical and electrical systems and items covered by the Drawings and
Specifications. This requirement shall be scheduled just prior to and during the initial start-up. After all systems are functioning
properly the representatives shall instruct maintenance personnel of the Owner in the proper operation and maintenance of each
item.
General Conditions of the Contract for Construction Lump Sum Contract Page 14 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
G-27 GUARANTEE AND EXTENDED GUARANTEE: Upon completion of the Project, prior to final payment, guarantees
required by technical divisions of Specifications shall be properly executed in quadruplicate by subcontractors and submitted
through the Contractor to Architect.Delivery of guarantees shall not relieve Contractor from any obligation assumed under Contract.
The Contractor shall guarantee the entire Project for one year. In addition,where separate guarantees,for certain portions of work,
are for longer periods, General Contractor's guarantee shall be extended to cover such longer periods. Manufacturer's extended
warrantees shall be included in this contract.
Guarantees shall become valid and operative and commence upon issuance of Certificate of Inspection and Acceptance by Owner..
Guarantees shall not apply to work where damage is result of abuse,neglect by Owner or his successor(s)in interest.
The Contractor agrees to warrant his work and materials provided in accordance with this contract and the terms of the Technical
Specifications contained herein. Unless supplemented by the Technical Specifications or the manufacturer's normal extended
warrantees,the Contractor shall warrant all work materials, and equipment against defects for a period of one year from the date of
final acceptance. The Contractor further agrees to bear all costs of making good all work that is found to be defective or not
provided in accordance with the Contract Documents. Additionally if the facility or contents are damaged due to defective materials
or workmanship of the Contractor, the Contractor further agrees to bear all cost of repairing and/or replacing damaged items and
components to bring such items back to at least their original condition.
G-28 RECORD DRAWINGS: Upon completion of the Work and prior to application for final payment, one print of each of the
drawings accompanying this specification shall be neatly and clearly marked in red by the Contractor to show variations between the
construction actually provided and that indicated or specified in the Contract Documents. The annotated documents shall be
delivered to Architect. Where a choice of materials and/or methods is permitted herein and where variations in the scope or
character of the work from the entire work indicated or specified are permitted either by award of bidding items specified for that
purpose, or by subsequent change to the drawings, the record drawings shall define the construction actually provided. The
representation of such variations shall conform to standard drafting practice and shall include supplementary notes, legends and
details which may be necessary for legibility and clear portrayal of the actual construction. The record drawings shall indicate, in
.rw
addition,the actual location of all sub-surface utility lines,average depth below the surface and other appurtenances.
G-29 CONSTRUCTION FENCE: The Contractor shall provide a substantial chain-link construction fence around all or a part of
the site. The fences and gates must be maintained throughout the construction period. Remove the fences and gates upon
completion of the Project and restore the site to the required original or contract condition.
G-30 PRODUCT DELIVERY,STORAGE, HANDLING: The Contractor shall handle,store and protect materials and products,
including fabricated components, by methods and means which will prevent damage, deterioration and loss, including theft (and
resulting delays), thereby ensuring highest quality results as the work progresses. Control delivery schedules so as to minimize
unnecessary long-term storage at project site prior to installation.
G-31 REMOVAL OF SALVAGED MATERIAL: The Contractor shall remove salvaged material and equipment from the Project
site and dispose of it in accordance with the law. Equipment or material identified in the Specifications or Plans for Owner salvage
shall be carefully removed and delivered to the Owner at any location in within the City limits as directed by the City.
G-32 MANUFACTURER'S REFERENCE: Catalog, brand names, and manufacturer's references are descriptive, not
restrictive. Bids on brands of like nature and quality will be considered.Contractor shall inform the City of any substitutions intended
for the project within 5 business days of bid opening. Failure to inform the City of substitute projects will obligate the Contractor to
.� provide the specified material if awarded the contract. Within 14 days after bid opening and upon request of the Contractor, the
Contractor will submit a full sized sample and/or detailed information as required to allow the architect to determine the acceptability
of proposed substitutions. Where equipment has been listed as"no substitute accepted", the City will accept no alternates to the
specified equipment.
SECTION H
CONTRACT TIME
rs H-1 DEFINITIONS
The Contract Time is the period of time allotted in the Contract Documents for completion of the Work and is the number of calendar
days elapsing between the date of commencement and the date of Substantial Completion plus additional days assessed for failure
to complete punch list items from the Final Inspection in a timely manner and additional weather days beyond what is allotted in the
contract.
The Date of Commencement of the Work is the date established in the Notice to Proceed.If there is no notice to proceed,it shall be
the date of the Agreement or such other date as may be established therein.
■ww
The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Architect with the approval
of the Owner that construction is sufficiently complete, in accordance with the Contract Documents, so the Owner may occupy the
Work or designated portion thereof for the use for which it is intended. Final acceptance of the completed work or any portion
aa. thereof can be made only by the Director of the Property Management Department,and no other form of acceptance will be binding
upon the Owner.
General Conditions of the Contract for Construction Lump Sum Contract Page 15 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
A Calendar Da v constitutes 24 hours of time and is any one of the seven days of a week, including Sunday, regardless of whether a
'Working Day"or not,and regardless of weather conditions or any situation which might delay construction.An extension of contract
time shall be in accordance with this Section. Extensions of time will be as recommended by the Architect with final approval by City ..
of Fort Worth.
A Working Day is defined as a calendar day, not including Saturdays, Sundays, and legal holidays, in which weather or other
conditions not under the control of the Contractor permit the performance of work for a continuous period of not less than seven
hours between 7:00 a.m. and 6:00 p.m. However„ nothing in these Contract Documents shall be construed as prohibiting the
Contractor from working on Saturdays if he so desires. Legal holidays for the City of Fort Worth are defined as being New Year's
Day, Independence Day, Labor Day, Thanksgiving Day, the day after Thanksgiving, Christmas Day, Memorial Day and Martin
Luther King Jr.Day.
H-2 PROGRESS AND COMPLETION: All the time limits stated in the Contract Documents are of essence to the Contract.
The Contractor shall begin the Work on the date of commencement as defined in this Section. He shall carry the Work forward
expeditiously with adequate forces and shall complete it within the Contract Time.
H-3 DELAYS AND EXTENSIONS OF TIME: If the Contractor is delayed at any time in the progress of the Work by any act or
neglect of the Owner or the Architect, or by any employee of the Owner, or by any separate contractor employed by the Owner, or
by changes ordered in the Work, or by labor disputes, fire, unusual delay in transportation, unavoidable casualties or any causes
beyond the Contractor's control,or by any cause which the Architect determines may justify the delay,then the contract time may be
extended by Change Order for such reasonable time as recommended by the Architect and approved by the Owner. When the
Contractor is delayed due to abnormal weather conditions,the weather table provided as WT-1 in these Contract Documents shall
be used as the basis for providing a fair and equitable adjustment of the contract time.
All claims for extension of time shall be made in writing to the Architect no more than fifteen days after the occurrence of the delay;
otherwise they shall be waived.
If no schedule or agreement is made stating the dates upon which written interpretations shall be furnished,then no claim for delay
shall be allowed on account of failure to furnish such interpretation until fifteen days after demand is made for them, and not then
unless such a claim is reasonable.
H-4 NO DAMAGE FOR DELAY: No payment, compensation or adjustment or any kind (other than the extensions of time
provided for)shall be made to the Contractor for damages because of hindrances or delays from an cause in the progress of the
work, whether such hindrances or delays be avoidable or unavoidable, and the Contractor agrees that he will make no claim for
compensation,damages or mitigation of liquidated damages for any such delays, and will accept in full satisfaction for such delays
said extension of time.
SECTION I
PAYMENTS AND COMPLETION
1-1 CONTRACT SUM: The Contract Sum is stated in the contract and is the total amount payable by the Owner to the
Contractor for the performance of the Work under the Contract Documents.
1-2 SCHEDULE OF VALUES: Before the first Applicable for Payment, the Contractor shall submit to the Architect a
Schedule of Values of the various portions of the Work, including quantities if required by the Architect, aggregating the total --
Contract Sum,divided so as to facilitate payments to Sub-contractors,prepared in such form as specked or as the Architect and the
Contractor may agree upon, and supported by such data to substantiate its correctness as the Architect may require. Each item in
the Schedule of Values shall include its proper share of overhead and profit.This Schedule,when approved by the Architect and the
Owner,shall be used as a basis for the Contractor's Applications for Payment.
1-3 ADJUSTMENT OF QUANTITIES(NOT USED)
1-4 PROGRESS PAYMENTS: On the first day of each month after the first month's work has been completed,the Contractor
will make current estimates in writing for review by the Architect and Owner of materials in place complete and the amount of work ^'
performed during the preceding month or period and the value thereof at the prices contracted for as shown on the approved
Schedule of Values and Progress Schedule.
If payments are to be made on account of materials or equipment not incorporated in the Work but delivered and suitably stored at .�
the site or in an independent, bonded warehouse such payments shall be conditioned upon submission by the Contractor of bills of
sale or such other procedures satisfactory to the Owner to establish the Owner's title to such materials or equipment or otherwise
protect the Owner's interest including applicable insurance and transportation to the site.
The Contractor warrants and guarantees that title to all Work, materials and equipment covered by an Application for Payment,
whether incorporated in the Project or not,will pass to the Owner upon the receipt of such payment by the Contractor„free and clear
of all liens, claims,security interests or encumbrances hereinafter referred to as"liens"; and that no Work, materials or equipment
covered by an Application for Payment will have been acquired by the Contractor, or by any other persons performing the Work at
the site or furnishing materials and equipment for the Work, subject to an agreement under which an interest therein or an .*•
encumbrance thereon is retained by the seller or otherwise imposed by the Contractor or such other person.
r
General Conditions of the Contract for Construction Lump Sum Contract Page io or 26
City of Ft Worth-West Division,PMD2014-09,City Project#100172 October 2017
The Contractor shall prepare each application for payment on AIA Document G702, "Application and Certificate for Payment", and
attached thereto AIA Document G703, "Continuation Sheet", to indicate the progress made to date and the period or month for
which payment is requested for each Item listed in the Schedule of Values. A copy of the revised monthly work progress schedule
must be attached before the pay request can be accepted.
1-5 CERTIFICATES FOR PAYMENT: If the Contractor has made Application for Payment as above,the Architect will,with
reasonable promptness but not more than seven days after the receipt of the Application, prepare a Certificate of Payment,with a
copy to the Contractor,for such amount determined to be properly due,or state in writing reasons for withholding a Certificate.
The issuance of a Certificate for Payment will constitute a representation by the Owner,based on the Architect's observations at the
site and the data comprising the Application for Payment,that the Work has progressed to the point indicated;that the quality of the
Work is in accordance with the Contract Documents(subject to an evaluation of the Work as a functioning whole upon Substantial
Completion, to the results of any subsequent tests required by the Contract Documents, to minor deviations from the Contract
Documents correctable prior to completion,and to any specific qualifications stated in the Certificate);and recommendations to the
Owner that the Contractor be paid in the amount certified. In addition,the Architect's approval of final payment assures the Owner
that the conditions precedent to the Contractor's being entitled to final payment as set forth in this Section have been fulfilled.
After the Architect has issued a Certificate for Payment, the Owner shall approve or disapprove same within ten days after it has
been delivered to the Director of the Property Management Department. For contracts less than$400,000,Owner shall pay 90%of
the approved estimate to the Contractor within seven days after its approval, and the remaining 10%of each such estimate will be
retained by the Owner until the final estimate is approved and the Work is accepted by the City Council of the City of Fort Worth.For
contracts in excess of$400,000, the Owner will retain only 5% of each estimate until the final estimate is approved and work
accepted by the City Council of the City of Fort Worth.
r
No Certificate for a progress payment, nor any progress payment, nor any partial or entire use or occupancy of the Project by the
Owner, shall constitute an acceptance of any Work not in accordance with the Contract Documents, or relieve the Contractor of
liability in respect to any warranties or responsibility for faulty materials or workmanship.The Contractor shall promptly remedy any
defects in the Work and pay for any damage to other work resulting therefrom that shall appear within a period of one year from the
date of final acceptance of the Work unless a longer period is specified.
1-6 PAYMENTS WITHHELD: The Architect may decline to approve an Application for Payment and may withhold his
Certificate in whole or in part if in his opinion he is unable to make the representations to the Owner as provided in this Section.The
ww Architect may also decline to approve any Applications for Payment or, because of subsequently discovered evidence or
subsequent inspections,may nullify the whole or any part of any Certificate for Payment previously issued to such extent as may be
necessary in his opinion to protect the Owner from loss because of:
1) Defective work not remedied;
w
2) Claims filed or reasonable evidence indicating probable filing of claims;
3) Failure of the Contractor to make payments properly to Subcontractors,or for labor,materials or equipment;
4) Reasonable doubt that the Work can be completed for the unpaid balance of the Contract Sum;
5) Damage to another contractor;
6) Reasonable indication that the Work will not be completed within the Contract Time;or
7) Unsatisfactory prosecution of the Work by the Contractor.
When such grounds for the refusal of payment are removed, payment shall be made for amounts withheld because of them.The
Owner reserves the right to withhold the payment of any monthly estimate, without payment of interest, if the Contractor fails to
iw perform the Work in accordance with the specifications.
1-7 NOT USED
1-8 LIQUIDATED DAMAGES: The deduction for liquidated damages shall be as follows:
Amount of Contract Liquidated Damages Per Day
$15,000 or less $45
ow $15,001 to $25,000 $63
$25,001 to $50,000 $105
$50,001 to $100,000 $154
$100,000 to $500,000 $210
$500,001 to$1,000,000 $315
$1,000,001 to$2,000,000 $420
$2,000,001 to$5,000,000 $630
$5,000,001 to$10,000,000 $840
over$10,000,000 $980
General Conditions of the Contract for Construction Lump Sum Contract Page 17 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
1-9 FAILURE OF PAYMENT: If,without fault on the part of the Contractor,the Architect should fail to issue any Certificate
for Payment within seven days after receipt of the Contractor's Application for Payment,if the Contractor's Application for Payment,
or if,without fault on the part of the Contractor,the Owner should fail to approve such estimate or to pay to the Contractor 90%or
95% (as applicable) of the amount thereof within the period of time specified, then the Contractor may, upon seven (7) days
additional written notice to the Owner and to the Architect,stop the Work until payment of the amount owing has been received.
1-10 SUBSTANTIAL COMPLETION AND FINAL PAYMENT: Prior to the request for final payment,the Contractor must meet
all provisions for Project Closeout.
When the Contractor determines that the Work is substantially complete,the City shall inspect the project with the Contractor and
the contractor will prepare a"Preliminary Punch List".
MW
When the Architect, on the basis of a subsequent inspection, determines that the Work is substantially complete, he then will
prepare a Certificate of Substantial Completion(G704)which,when approved by the Owner, shall allow the Contractor to request a
Certificate of Occupancy which will establish the Date of Substantial Completion. The Certificate of Final Completion shall state the
responsibilities of the Owner and the Contractor for maintenance,heat,utilities,and insurance,shall set forth the remaining work as
a"final punch list".The Contractor shall complete the remaining work listed therein within 60 calendar days. When the Certificate of
Occupancy has been issued,the retainage may be reduced to 4%.
Upon completion of the work listed on the final punch list to the satisfaction of the City of Fort Worth,the retainage may be reduced
to 2.5%.
Should the Contractor fail to complete all contractual requirements of the contract, including submittals and final pay request within
the fixed time,the contract time will again commence. Should the Contractor fail to complete the work within the contract duration,
liquidated damages will be assessed
Upon receipt of written notice that the Work is ready for final inspection,the City will conduct a joint inspection and certify completion
of the final punch list by cosigning it with the Contractor.
The Contractor shall submit the following items to the City prior to requesting final payment: ..
1) Contractor's Affidavit of Payment of Debts and Claims (G706)stating that all payrolls, bills for materials and equipment, and
other indebtedness connected with the Work for which the Owner or his property might in any way be responsible, have been
paid or otherwise satisfied, +
2) Consent of Surety to Final Payment(G707),if any,to final payment,
3) Contractor's Affidavit of Release of Liens(G706A),and,
4) Other data establishing payment or satisfaction of all such obligations, such as receipts, releases, and waivers of liens arising
out of the Contract,to the extent and in such form as may be designated by the Owner.
5) Contractor's Warranty
6) Statement that all outstanding work has been completed
7) Issuance of the Final Certificate of Substantial Completion
8) Final acceptance by the City of Fort Worth.
If any Subcontractor, materialman or laborer refuses to furnish a Contractor's Affidavit of Release of Liens, the Contractor may, at
the election of the Owner,furnish a bond satisfactory to the Owner to indemnify him against any right,claim or lien which might be
asserted by such Subcontractor, materialman or laborer. If any such right, claim or lien remains unsatisfied after all payments are
made.The Contractor shall refund to the Owner all monies that the latter may be compelled to pay to discharging such right,claim ..
or lien,including all costs and reasonable attorney's fees.
The Contractor may then request final payment. The acceptance of final payment shall constitute a waiver of all claims by the
Contractor except those previously made in writing and still unsettled.
The Contractors one-year warranty will commence upon final acceptance of the Project by the City of Fort Worth.
The designated representative of the City of Fort Worth will make final acceptance and no other form of acceptance will be binding
upon the Owner.. �^^
1-11 FINAL PAYMENT FOR UN-BONDED PROJECTS: Final payment will not be made for a period of 30 calendar days and
until all requirements have been met,with the exception of Consent of Surety for Final Payment.
SECTION J
PROTECTION OF PERSONS AND PROPERTY
J-1 SAFETY PRECAUTIONS AND PROGRAMS: The Contractor shall be responsible for initiating, maintaining and
supervising all safetv precautions and programs in connection with the Work.The Contractor shall designate a responsible member
of his organization at the site whose duty shall be the prevention of accidents.This person shall be the Contractors superintendent
unless otherwise designated in writing by the Contractor to the Architect.
General Conditions of the Contract for Construction Lump Sum Contract Page 18 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
J-2 SAFETY OF PERSONS AND PROPERTY: The Contractor shall take all reasonable precautions for the safety of, and
shall provide all reasonable protection to prevent damage,injury or loss to:
(1) All employees on the Work and all other persons who may be affected thereby;
(2) All the Work and all materials and equipment to be incorporated therein,whether in storage on or-off the site, under the care,
custody or control of the Contractor or any of his Subcontractors or Sub-contractors;and
(3) Other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures and
utilities not designated for removal,relocation or replacement in the course of construction.
Until acceptance of the Work, it shall be under the charge and care of the Contractor, and he shall take every precaution against
injury or damage to the Work by the action of the elements or from any other cause whatsoever,whether arising from the execution
or from the non-execution of the Work.The Contractor shall rebuild, repair, restore and make good, at his own expense, all injuries
w or damages to any portion of the Work occasioned by any of the above,caused before its completion and acceptance.
The Contractor shall comply with all applicable Laws, Ordinances, Rules, Regulations and Orders of any public authority having
jurisdiction for the safety of persons or property or to protect them from damage, injury or loss. He shall erect and maintain, as
required by existing conditions and progress of the Work, all reasonable safeguards for safety and protection, including posting
danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent
utilities.
When the use or storage of explosives or other hazardous materials or equipment is necessary for the execution of the Work, the
Contractor shall exercise the utmost care and shall carry on such activities under the supervision of properly qualified personnel.
All damage or loss to any property referred to in the preceding paragraphs caused in whole or in part by the Contractor, any
Subcontractor, or anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable,
shall be remedied by the Contractor,including damage or loss attributable to faulty Drawings or Specifications and acts or omissions
of the Architect or anyone employed by him or for whose acts he may be liable,and not attributable to the fault or negligence of the
Contractor or anyone claiming through the Contractor for such damage or loss.
The Contractor shall not load or permit any part of the Work to be loaded so as to endanger its safety.
■rr J-3 HARD HATS: Hard Hats will be required at all construction sites included in this Contract from start to completion of
work. Each Contractor, employee and visitor at any construction site included in the Contract will be required to wear a hard hat.
The Contractor shall enforce the wearing of hard hats by Contractor, employees and visitors.Contractor shall provide hard hats for
use by the consulting Architects and Engineers and visitors.
J-4 EMERGENCIES: In any emergency affecting the safety of persons or property,the Contractor shall act at his discretion
to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on
account of emergency work shall be determined as provided in Changes in the Work.
•* J-5 SAFE WORK PRACTICES: The Contractor shall employ safe practices in handling materials and equipment used in
performing required work so as to insure the safety of his workmen, City employees and the public. The Contractor shall keep the
premise free at all times from accumulation of waste materials or rubbish. At the completion of the work, the Contractor shall
remove all his wastes and rubbish from and about the work area, as well as his tools,equipment and surplus materials and shall
w leave the area as clean and free of spot,stains,etc.,as before the work was undertaken.
J-6 TRENCH SAFETY: The Contractor shall be responsible for all design and implementation of trench shoring and
stabilization to meet regulatory requirements. If the Proposal requires,the Contractor shall include a per-unit cost for trench safety
measures in his bid. If not included in the Proposal, the Contractor shall include a cost for trench safety measures for all trenches
over 5 feet in depth in his Schedule of Values.
SECTION K-INSURANCE
w
K-1 INSURANCE REQUIRED: The Contractor shall not commence work under this Contract until he has obtained all
insurance required under this Section and such insurance has been approved by the City of Fort Worth, nor shall the Contractor
allow any Subcontractor to commence work to be performed under this Contract until all similar insurance of the Subcontractor has
been so obtained and approved. The City of Fort Worth will be listed as an "additional insured" on all policies except Worker's
Compensation.
K-2 WORKERS'COMPENSATION INSURANCE
® 1) General:
a) Contractor's Worker's Compensation Insurance. Contractor agrees to provide to the Owner(City) a certificate showing
that it has obtained a policy of workers compensation insurance covering each of its employees employed on the project
in compliance with state law. No Notice to Proceed will be issued until the Contractor has complied with this section.
General Conditions of the Contract for Construction Lump Sum Contract Page 19 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
b) Subcontractor's Worker's Compensation Insurance. Contractor agrees to require each and every subcontractor who will
perform work on the project to provide to it a certificate from such subcontractor stating that the subcontractor has a policy
of workers compensation insurance covering each employee employed on the project. Contractor will not permit any ...
subcontractor to perform work on the project until such certificate has been acquired. Contractor shall provide a copy of
all such certificates to the Owner(City).
c) By signing this Contract or providing or causing to be provided a certificate of coverage,the Contractor is representing to
the City that all employees of the Contractor who will provide services on the project will be covered by worker's
compensation coverage for the duration of the project,that the coverage will be based on proper reporting of classification
codes and payroll amounts, and that all coverage agreements will be filed with the appropriate insurance carrier or, in the
case of a self-insured, with the Texas Worker's Compensation Commission's Division of Self-Insurance Regulation.
Providing false or misleading information may subject the Contractor to administrative penalties, criminal penalties, civil
penalties or other civil actions.
d) The Contractor's failure to comply with any of these provisions is a breach of contract by the Contractor which entitles the
City to declare the contract void if the Contractor does not remedy the breach within ten days after receipt of notice of
breach from the City.
2) Definitions:
a) Certificate of Coverage("certificate"). A copy of a certificate of insurance,a certificate of authority to self-insure issued by
the Texas Workers'Compensation Commission, or a coverage agreement(TWCC-81, TWCC-82, TWCC-83, or TWCC- ,�..
84), showing statutory workers' compensation insurance coverage for the person's or entity's employees providing
services on a project,for the duration of the project.
b) Duration of the Project. Includes the time from the beginning of the work on the project until the Contractor's/person's
work on the project has been completed and accepted by the City.
c) Persons providing services on the project("subcontractor"in section 406.096)-includes all persons or entities performing
all or part of the services the Contractor has undertaken to perform on the project, regardless of whether that person
contracted directly with the Contractor and regardless of whether that person has employees. This includes, without
limitation, independent contractors, subcontractors, leasing companies, motor carriers, owner-operators, employees of
any such entity,or employees of any entity which furnishes persons to provide services on the project. "Services"include,
without limitation, providing, hauling, or delivering equipment or materials, or providing labor, transportation, or other
services related to a project. "Services" does not include activities unrelated to the project, such as food/beverage
vendors,office supply deliveries,and delivery of portable toilets. ...
3) Requirements:
a) The Contractor shall provide coverage,based on proper reporting of classification codes and payroll amounts and filing of
any coverage agreements, which meets the statutory requirements of Texas Labor Code, Section 401.011(44) for all
employees of the Contractor providing services of the project,for the duration of the project.
b) The Contractor must provide a certificate of coverage to the governmental entity prior to being awarded the contract.
c) If the coverage period shown on the Contractor's current certificate of coverage ends during the duration of the project, �.
the Contractor must, prior to the end of the coverage period,file a new certificate of coverage with the City showing that
coverage has been extended.
d) The Contractor shall obtain from each person providing services on a project,and provide to the City:
I) a certificate of coverage, prior to that person beginning work on the project, so the governmental entity will have on
file certificates of coverage showing coverage for all persons providing services on the project;and
ii) no later than seven days after receipt by the Contractor, a new certificate of coverage showing extension of
coverage, if the coverage period shown on the current certificate of coverage ends during the duration of the project. •—
e) The Contractor shall retain all required certificates of coverage for the duration of the project and for one year thereafter.
f) The Contractor shall notify the City in writing by certified mail or personal delivery,within ten(10)days after the Contractor
knew or should have known, of any change that materially affects the provision of coverage of any person providing �.
services on the project.
g) The Contractor shall post on each project site a notice, in the text, form and manner prescribed by the Texas Worker's
Compensation Commission, informing all persons providing services on the project that they are required to be covered,
and stating how a person may verify coverage and report lack of coverage.
h) The Contractor shall contractually require each person with whom it contracts to provide services on a project,to:
I) provide coverage, based on proper reporting on the classification codes and payroll amounts and filing of any
coverage agreements,which meets the statutory requirements of Texas labor Code,Section 401.011(44)for all of its �+
employees providing services on the project,for the duration of the project;
ii) provide to the Contractor, prior to that person beginning work on the project, a certificate of coverage showing that
coverage is being provided for all employees of the person providing services on the project,for the duration of the
project;
General Conditions of the Contract for Construction Lump Sum Contract Page 20 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
li
7
iii) provide the Contractor, prior to the end of the coverage period, a new certificate of coverage showing extension of
coverage, if the coverage period shown on the current certificate of coverage ends during the duration of the project;
iv) obtain from each other person with whom it contracts,and provide to the Contractor:
(1) a certificate of coverage,prior to the other person beginning work on the project;and
(2) a new certificate of coverage showing extension of coverage, prior to the end of the coverage period, if the
coverage period shown on the current certificate of coverage ends during the duration of the project;
v) retain all required certificates of coverage on file for the duration of the project and for one year thereafter.
vi) notify the City in writing by certified mail or personal delivery, within ten (10) days after the person knew or should
have known,of any change that materially affects the provision of coverage of any person providing services on the
project;and
vii) contractually require each person with whom it contracts, to perform as required by paragraphs h-i)-vii), with the
certificates of coverage to be provided to the person for whom they are providing services.
4) Posting of Required Worker's Compensation Coverage:
a) The Contractor shall post a notice on each project site informing all persons providing services on the project that they are
required to be covered,and stating how a person may verify current coverage and report failure to provide coverage.This
notice does not satisfy other posting requirements imposed by the Texas Worker's Compensation Act or other Texas
Worker's Compensation Commission rules. This notice must be printed with a title in at least 30 point bold type and text
in at least 19-point normal type,and shall be in both English and Spanish and any other language common to the worker
.w population. The text for the notices shall be the following text,without any additional words or changes:
"REQUIRED WORKER'S COMPENSATION COVERAGE
The law requires that each person working on this site or providing services related to this construction project
�.. must be covered by worker's compensation insurance. This includes persons providing, hauling, or delivering
equipment or materials, or providing labor or transportation or other service related to the project, regardless of
the identity of their employer or status as an employee".
Call the Texas Worker's Compensation Commission at 512-440-3789 to receive information on the legal
wrr requirement for coverage,to verify whether your employer has provided the required coverage,or to report an
employer's failure to provide coverage."
K-3 LIABILITY INSURANCE: The Contractor shall procure and maintain during the term of this Contract such Liability
Insurance as shall protect him,the City of Fort Worth and any Subcontractor performing work covered by this Contract,from claims
of damage which may arise from operations under this Contract, including blasting,when blasting is done on, or in connection with
the Work of the Project,whether such operations be by himself or by any Subcontractor or by anyone directly or indirectly employed
by either of them and the limits of such insurance shall be not less than the following:
ire 1 Automobile Liability: $1,000,000 each accident or reasonably equivalent split limits for bodily injury and property damage.
Coverage shall be on "any auto"including leased, hired, owned, non-owned and borrowed vehicles used in connection with
this Contract.
wrr 2) Commercial General Liability: $1,000,000 each occurrence. Coverage under the policy shall be as comprehensive as that
provided in a current Insurance Services Office (ISO) policy form approved for use in Texas and the policy shall have no
exclusions by endorsement unless such are approved by the City.
3) Asbestos Abatement Liability Insurance:When the Project specifically requires the removal of Asbestos Containing Materials,
the Contractor,or subcontractor performing the removal,shall be required to maintain Asbestos Abatement Liability Insurance
as follows: $1,000,000 per occurrence; $2,000,000 aggregate limit. The coverage shall include any pollution exposure,
including environmental impairment liability, associated with the services and operations performed under this contract in
addition to sudden and accidental contamination or pollution liability for gradual emissions and clean-up costs.
+rw
K-4 BUILDER'S RISK INSURANCE: Unless stated otherwise in the Proposal or Invitation,the Contractor shall procure,pay
for and maintain at all times during the term of this Contract, Builder's Risk Insurance against the perils of fire, lightning,windstorm,
hurricane, hail, riot, explosion,civic commotion,smoke, aircraft, land vehicles,vandalism, and malicious mischief, at a limit equal to
rs
100%of the Contract Sum.
The policy shall include coverage for materials and supplies while in transit and while being stored on or off site. If specifically
required in the Instructions to Bidders, the policy shall include coverage for flood and earthquake. Different sub-Limits for these
coverages must be approved by the City.
■w
Consequential damage due to faulty workmanship and/or design performed by the Contractor or his agents shall be covered.
Upon completion of the Work,the Contractor shall notify the City of Fort Worth in writing before terminating this insurance.
ow K-5 PROOF OF CARRIAGE OF INSURANCE: The Contractor shall provide a certificate of insurance documenting the
Property Management Department. City of Fort Worth as a "Certificate Holder" and noting the specific project(s) covered by the
General Conditions of the Contract for Construction Lump Sum Contract Page 21 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
om
..
Contractor's insurance as documented on the certificate of insurance. More than one certificate may be required of the Contractor
depending upon the agents and/or insurers for the Contractor's insurance coverages specified for the project(s).
K-6 OTHER INSURANCE RELATED REQUIREMENTS
1) The City of Fort Worth shall be an additional insured,by endorsement,on all applicable insurance policies.
2) Applicable insurance policies shall each be endorsed with a waiver of subrogation in favor of the City of Fort Worth.
3) Insurers of policies maintained by Contractor and its subcontractor(s), if applicable, shall be authorized to do business in the
State of Texas,or otherwise approved by the City of Fort Worth,and such shall be acceptable to the City of Fort Worth insofar
as their financial strength and solvency are concerned. Any company through which the insurance is placed must have a
rating of at least A:VII, as stated in current edition of A. M. Best's Key Rating Guide. At the City's sole discretion, a less
favorable rate may be accepted by the City.
4) Deductible limits on insurance policies and/or self-insured retentions exceeding $10,000 require approval of the City of Fort
Worth as respects this Contract.
5) The City of Fort Worth shall be notified in writing a minimum of thirty days prior to an insurer's action in the event of
cancellation or non-renewal in coverage regarding any policy providing insurance coverage required in this Contract.
6) Full limits of insurance shall be available for claims arising out of this Contract with the City of Fort Worth. *•
7) The Contractor shall provide certificates of insurance to the City prior to commencement of operations pursuant to this
Contract. Any failure on part of the City of Fort Worth to request such documentation shall not be construed as a waiver of
insurance requirements specified herein.
8) The City of Fort Worth shall be entitled, upon request and without incurring expense,to review the insurance policies including
endorsements thereto and,at its discretion,to require proof of payment for policy premiums.
9) The City of Fort Worth shall not be responsible for paying the cost of insurance coverages required herein.
10) Notice of any actual or potential claim and/or litigation that would affect insurance coverages required herein shall be provided
to the City in a timely manner.
11) "Other insurance"as referenced in any policy of insurance providing coverages required herein shall not apply to any insurance
policy or program maintained by the City of Fort Worth.
12) Contractor shall agree to either require its subcontractors to maintain the same insurance coverages and limits thereof as
specified herein or the Contractor shall provide such coverage on the Contractor's subcontractors.
SECTION L
CHANGES IN THE WORK .r
L-1 CHANGE ORDER: The Owner, without invalidating the Contract, may order Changes in the Work within the general
scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and the Contract Time being adjusted
accordingly. All Such Changes in the Work shall be authorized by Change Order, and shall be executed under the applicable
conditions of the Contract Documents.
A Change Order is a written order to the Contractor signed by the Contractor,Owner and the Architect, issued after the execution of
the Contract,authorizing a Change in the Work or adjustment in the Contract Sum or the Contract Time. The Contract Sum and the
Contract Time may be changed only by Change Order.
Any changes in work required due to changed or unforeseen conditions, or by request of either the Contractor or the City,shall be
coordinated with the Director, Property Management Department. A change order must be written and duly negotiated and
executed prior to performing changed work. .®
The cost or credit to the Owner resulting from a Change in the work shall be determined in one or more of the following ways:
1) by mutual acceptance of a lump sum property itemized,including the allowance to Contractor for overhead and profit stipulated
in the original contract proposal;
2) by unit prices stated in the Contract Documents or subsequently agreed upon;or
3) by cost and a mutually acceptable fixed or percentage fee.
If none of the methods set forth herein above is agreed upon,the Contractor. provided he receives a Change Order,shall promptly
proceed with the Work involved. The cost of such work shall then be determined on the basis of the Contractor's reasonable
expenditures and savings, including a reasonable allowance for overhead and profit as indicted in the original contract proposal. In
such cases, the Contractor shall keep and present, in such form as the Architect shall prescribe, an itemized accounting together
General Conditions of the Contract for Construction Lump Sum Contract Page 22 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
with appropriate supporting data. Pending final determination of cost to the Owner„ payments on account shall be made on the
Architect's Certificate of Payment as approved by the Owner.
If after the Contract has been executed,the Architect,requests a price proposal from the Contractor for a proposed change in scope
of the work, Contractor shall process such proposal within seven days of receipt and return the price quote to the Architect in writing.
The Architect shall review the price quotation and if approval is recommended, forward the proposed change order request and
price proposal to the Owner for approval. If approval is not recommended,the Architect will attempt to negotiate with Contractor to
revise the proposal to a figure which is fair and reasonable and forward it on to the Owner for approval. If the negotiations do not
result in an equitable solution, the Architect shall prepare a cost-plus type Change Order with a price-not-to-exceed figure for
approval by the City and require specific documentation to be provided by Contractor in accordance with the paragraph above.
■w
Contractor is advised that according to City of Fort Worth Charter,that,the City Council must approve all Change Orders and Work
Orders which results in an increase in cost of the contract amount by over$100,000. Normal processing time for the City Staff to
obtain City Council approval, once the recommended change order has been received at the City, is approximately thirty days.
an Owner and Contractor shall endeavor to identify Change Order items as early in the Construction process as possible to minimize
their impact on the construction schedule.
If unit prices are stated in the Contract Documents or subsequently agreed upon,and if the quantities originally contemplated are so
changed in a proposed Change Order that application of the agreed unit prices to the quantities of Work proposed will create a
w hardship on the Owner or the Contractor,the applicable unit prices shall be equitably adjusted to prevent such hardship.
If the Contractor claims that additional cost or time is involved because of(1)any written interpretation issued pursuant to Section A,
(2) any order by the Architect or Owner to stop the Work pursuant to Section B, where the Contract was not at fault, or(3) any
written order for a minor change in the Work,the Contractor shall make such claim.
rww
L-2 CLAIMS FOR ADDITIONAL COST OR TIME: If the Contractor wishes to make a claim for an increase in the Contract
Sum or an extension in the Contract Time, he shall give the Architect written notice thereof within a reasonable time after the
occurrence of the event that gave rise to such claim.This notice shall be given by the Contractor before proceeding to execute the
Work,except in an emergency endangering life or property in which case the Contractor shall proceed in accordance with Section J.
No such claim shall be valid unless so made. Any change in the Contract Sum or Contract Time resulting from such claim, if
approved by the Owner shall be authorized by Change Order.
L-3 OVERHEAD ALLOWANCES FOR CHANGES: Should any change in the work or extra work be ordered,the following
w applicable percentage shall be added to Material and Labor costs to cover overhead and profit:
1. Allowance to the Contractor for overhead and profit for extra work performed by the Contractor's own forces shall not exceed
fifteen percent1( fj).
2. Allowance to the Contractor for overhead and profit for extra work performed by a Subcontractor and supervised by the
Contractor shall not exceed ten percent1( 0%).
L-4 MINOR CHANGES IN THE WORK: The Architect shall have authority to order minor changes in the Work not involving
an adjustment in the Contract Sum or an extension of the Contract Time and not inconsistent with the intent of the Contract
Documents. Such changes may be effected by Field Order or by other written order. Such changes shall be confirmed in writing by
the Architect and shall be binding on the Owner and the Contractor.
L-5 FIELD ORDERS: The Architect may issue written Field Orders which interpret the Contract Documents, or which order
minor changes in the Work without change in Contract Sum or Contract Time. The Contractor shall carry out such Field Orders
promptly.
.. SECTION M
UNCOVERING AND CORRECTION OF WORK
M-1 UNCOVERING OF WORK: If any Work should be covered contrary to the request of the Owner, it must be uncovered for
observation and replaced.at the Contractor's expense.
If any other work has been covered which the Owner has not specifically requested to observe prior to being covered,the Architect
or the Owner may request to see such work and it shall be uncovered by the Contractor. If such Work be found in accordance with
.w the Plans and Specifications,the cost of uncovering and replacement shall,by appropriate Change Order,be charged to the Owner.
If such work be found not in accordance with the Plans and Specifications,the Contractor shall pay such costs unless it is found that
this condition was caused by a separate contractor employed by the Owner.
M-2 CORRECTION OF WORK: The Contractor shall promptly correct all work rejected by the Architect or Owner as defective
or as failing to conform to the Plans and Specifications whether observed before or after Substantial Completion and whether or not
fabricated, installed or completed. The Contractor shall bear all costs of correcting such rejected Work, including the cost of the
Architect's additional service thereby made necessary.
ur If,within one year after the Date of Substantial Completion or within such longer period of time as may be prescribed by law or by
the terms of any applicable special guarantee required by the Contract Documents,any of the work is found to be defective or not in
accordance with the Contract Documents,the Contractor shall correct it promptly after receipt of a written notice from the Owner to
General Conditions of the Contract for Construction Lump Sum Contract Page 23 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
do so, unless the Owner has previously given the Contractor a written acceptance of such condition,describing same specifically
and not generally.The Owner shall give such notice promptly after discovery of the condition.
All such defective or non-conforming work under the preceding paragraphs shall be removed from the site where necessary and the
work shall be corrected to comply with the Contract Documents without cost to the Owner.
Defective or non-conforming work shall be completed in a timely manner. The Contractor shall respond and/or repair any work that
is deemed an emergency by the City within 48 hours. The Contractor shall respond and/or repair any other defective or non-
conforming work within seven days.
The Contractor shall bear the cost of making good all work of separate contractors destroyed or damaged by such removal or
correction.
If the Contractor does not remove such defective or non-conforming work within a reasonable time fixed by written notice from the
Owner,the Owner may remove it and may store the materials or equipment at the expense of the Contractor If the Contractor does
not pay the cost of such removal and storage within ten days thereafter,the Owner may upon ten additional days'written notice sell
such work at auction or at private sale and shall account for the net proceeds thereof,after deducting all the costs that should have
been borne by the Contractor including compensation for additional architectural services. If such proceeds of sale do not cover all
costs that the Contractor should have borne, the difference shall be charged to the Contractor and an appropriate Change Order
shall be issued. If the payments then or thereafter due the Contractor are not sufficient to cover such amount,the Contractor shall
pay the difference to the Owner.
If the Contractor fails to correct such defective or non-conforming work,the Owner may correct it in accordance with Section G.
The obligation of the Contractor under this Section shall be in addition to and not in limitation of any obligations imposed upon him
by special guarantees required by the Contract Documents or otherwise prescribed by law.
M-3 ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK: If the Owner prefers to accept defective or non-
conforming work, he may do so instead of requiring its removal and correction, in which case a Change Order will be issued to
reflect an appropriate reduction in the Contract Sum, or if the amount is determined after final payment, it shall be paid by the .�
Contractor.
SECTION N
TERMINATION OF THE CONTRACT
N-1 TERMINATION BY THE CONTRACTOR: If the work is stopped for a period of 30 days under an order or any court or
other public authority having jurisdiction,through no act or fault of the Contractor or a Subcontractor or their agents or employees or
any other persons performing any of the work under a contract with the Contractor,or if the work should be stopped for a period of
30 days by the Contractor for the Owner's failure to make payment thereon as provided in Section I,then the Contractor may after
the end of such period of 30 days and upon seven additional days'written notice to the Owner,terminate the Contract.
N-2 TERMINATION BY THE OWNER: If the Contractor is adjudged as bankrupt,or if he makes a general assignment for the
benefit of his creditors, or if a receiver is appointed on account of his insolvency, of if the Contractor refuses, except in cases for
which extension of time is provided, to supply enough properly skilled workmen or proper materials, or if he fails to make prompt
payment to Subcontractors or for materials or labor or fails to comply with all Laws, Statutes, Charter, Ordinances, Regulations or
Orders of any public authority having jurisdiction, or otherwise is guilty of a substantial violation of a provision of the Contract *—
Documents, then the Owner, on its own initiative that sufficient cause exists to justify such action, may, without prejudice to any
rights or remedy and after giving the Contractor and his surety, if any, seven (7)days'written notice,terminate the employment of
the Contractor and take possession of the site and of all materials,equipment,tools,construction equipment and machinery thereon
owned by the Contractor and may finish the work by whatever method he may deem expedient. In such case the Contractor shall
not be entitled to receive any further payment until the Work is finished.
If the costs of finishing the Work, including compensation for the Architect's additional services. exceed the unpaid balance of the
Contract,the Contractor shall pay the difference to the Owner.
The City of Fort Worth may terminate this contract in whole, or from time to time, in part, whenever such termination is in the best
interest of the City. Termination will be effected by delivering to the Contractor a notice of termination specifying to what extent
performance of the work of the contract is being terminated and the effective date of termination. After receipt of termination the
Contractor shall: .®.
a) Stop work under the Contract on the date and to the extent specified on the notice of termination.
b) Place no further orders or subcontracts except as may be necessary for the completion of the work not terminated. _
c) Terminate all orders and subcontracts to the extent that they relate to the performance of the work terminated by the notice of
termination.
After termination as above,the City will pay the Contractor a proportionate part of the contract price based on the work completed;
provided, however, that the amount of payment on termination shall not exceed the total contract price as reduced by the portion
General Conditions of the Contract for Construction Lump Sum Contract Page 24 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
w
thereof allocable to the work not completed and further reduced by the amount of payments, if, any otherwise made. Contractor
® shall submit its claim for amounts due after termination as provided in this paragraph within 30 days after receipt of such claim. In
the event of any dispute or controversy as to the propriety or allowability of all or any portion of such claim under this paragraph,
such dispute or controversy shall be resolved and be decided by the City Council of the City of Fort Worth, and the decision by the
City Council of the City of Fort Worth shall be final and binding upon all parties to this contract.
w
SECTION O
SIGNS
wr The Contractor shall construct and install the project designation sign as required in the Contract Documents and in strict
accordance with the Specifications for"Project Designation Signs."This sign shall be a part of this Contract and shall be included in
the Contractor's Base Bid for the Project.
w
SECTION P
TEMPORARY FACILITIES
P-1 SCOPE: The Contractor shall furnish, erect, and maintain facilities and perform temporary work required in the
performance of this Contract,including those shown and specified.
P-2 USE OF TEMPORARY FACILITIES: All temporary facilities shall be made available for use by all workmen and
subcontractors employed on the project, subject to reasonable directions by the Contractor as to their proper and most efficient
utilization.
P-3 MAINTENANCE AND REMOVAL: The Contractor shall maintain temporary facilities in a proper, safe operating and
sanitary condition for the duration of the Contract. Upon completion of the Contract, all such temporary work and facilities shall be
removed from the premises and disposed of unless otherwise directed or specified hereunder.
P-4 FIELD OFFICES AND SHED: The Contractor is not required to provide a temporary field office or telephone for projects
under$1,000,000. Contractor shall equip the Project Superintendent with a pager and provide 24-hour contacts to the City.
w The Contractor shall provide a temporary field office building for himself, his subcontractors and use by the Architect and Owner.
For construction contracts with a bid price in excess of$1,000,000.00, the Contractor shall provide a separate field office for the
City's field representative(but the separate office may be in the same structure). The buildings shall afford protection against the
weather, and each office shall have a lockable door,at least one window, adequate electrical outlets and lighting,and a shelf large
enough to accommodate perusal of the project drawings. Openings shall have suitable locks. Field offices shall be maintained for
the full time during the operation of the work of the Contract. During cold weather months,the field offices shall be suitably insulated
and equipped with a heating device to maintain 70 degree Fahrenheit temperature during the workday. During warm weather the
offices shall be equipped with an air conditioning device to maintain temperature below 75 degrees F. Upon completion of the work
of the Contract, the Contractor shall remove the building from the premises. In addition to the drawing shelf, provide for the City
field representatives office: one desk,four chairs, plan rack and a four drawer filing cabinet(with lock). Each office shall contain not
less than 120 square feet of floor space.
The Contractor shall provide and maintain storage sheds,other temporary buildings or trailers on the project site as required for his
use.Location of sheds and trailers shall be as approved by the Owner.Remove sheds when work is completed,or as directed.
P-5 WIRELESS CONNECTION: The Contractor shall provide and pay for wireless internet connection(WIFI)for the City and
Architect.
P-6 TOILET FACILITIES: The Contractor shall provide proper, sanitary and adequate toilet facilities for the use of all
workmen and subcontractors employed on the project.
P-7 UTILITIES: Contractor shall make all necessary arrangements and provide for temporary water and electricity required
■* during the construction. Contractor shall provide and install temporary utility meters during the contract construction period. These
meters will be read and the Contractor will be billed on this actual use. The Contractor shall provide all labor and materials required
to tap into the utilities. The Contractor shall make the connections and extend the service lines to the construction area for use of all
trades. Upon completion of the work all utility lines shall be removed and repairs made to the existing lines. Only utilities at existing
voltages,pressures,frequencies,etc.will be available to the Contractor.
Water. Provide an ample supply of potable water for all purposes of construction at a point convenient to the project or as shown on
the Drawings. Pipe water from the source of supply to all points where water will be required.
Provide sufficient hose to carry water to every required part of the construction and allow the use of water facilities to subcontractors
engaged on the work, Provide pumps,tanks and compressors as may be required to produce required pressures.
Electric Service. Provide adequate electric service for power and lighting to all points where required. Temporary,electric service
shall be of sufficient capacity and characteristics to supply proper current for various types of construction tools, motors, welding
w machines,lights,heating plant,air conditioning system,pumps,and other work required.Provide sufficient number of electric outlets
so that 50 foot long extension cords will reach all work requiring light or power.
General Conditions of the Contract for Construction Lump Sum Contract Page 25 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
wr
Lighting. Supply and maintain temporary lighting so that work of all trades may be properly and safely performed,in such areas and
at such time that day-lighting is inadequate. Provide at least 0.75 watts of incandescent lighting per squgr4e foot and maintain a
socket voltage of at least 110 volts. Use at least 100-watt lamps. In any event, the lighting intensity shall not be less than 5 foot
candles in the vicinity of work and traffic areas.
P-8 HEATING: Heating devices required under this paragraph shall not be electric. The Contractor shall provide heat,
ventilation, fuel and services as required to protect all work and materials and to keep the humidity down to the extent required to
prevent corrosion of any metal and to prevent dampness or mildew which is potentially damaging to materials and finishes. All such
heating,ventilation and services shall be provided and maintained until final acceptance of all work. In addition,the Contractor shall
provide heat ventilation prior and during the following work operations as follows:
a) At all times during the placing, setting and curing of concrete provide sufficient heat to insure the heating of the spaces
involved to not less than 40 F.
b) From the beginning of the application of drywall and during the setting and curing period, provide sufficient heat to produce a
temperature in the spaces involved of not less than 55 F.
c) For a period of seven (7)days previous to the placing of interior finish materials and throughout the placing of finish painting,
decorating and laying of resilient flooring materials,provide sufficient heat to produce a temperature of not less than 60 F.
P-9 TEMPORARY CONSTRUCTION, EQUIPMENT AND PROTECTION: The Contractor shall provide, maintain, and
remove upon completion of the work all temporary rigging, scaffolding, hoisting equipment, rubbish chutes, ladders to roof,
barricades around openings, and all other temporary work as required to complete all work of the Contract. Contractor shall
coordinate the use and furnishing of scaffolds with his sub-contractors.
The Contractor shall provide, maintain, and remove upon completion of the work, or sooner, if authorized by the Owner, all fences, ^
barricades, lights, shoring, pedestrian walkways, temporary fire escapes, and other protective structures or devices necessary for
the safety of workmen,City employees,equipment,the public and property.
All temporary construction and equipment shall conform to all regulations, ordinances, laws and other requirements of the �.
authorities having jurisdiction,including insurance companies,with regards to safety precautions,operation and fire hazard.
The Contractor shall provide and maintain pumping facilities, including power, for keeping the site, all times, whether from
underground seepage,rainfall,drainage of broken lines.
The Contractor shall maintain provision for closing and locking the building at such time as possible to do so. If this is not feasible,
maintain a night
The Contractor shall provide and maintain all barricades or enclosures, required to protect the work in progress from outside w.
elements, dusts, and other disturbances as a result of work under this Contract. Such protection shall be positive, shall meet the
approval of the Owner and shall be maintained for the duration of the construction period or as required to provide for the protection
as specified.
P-10 PROJECT BULLETIN BOARD: The Contractor shall furnish, install and maintain during the life of the project a weather-
tight bulletin board approximately 3 feet high by 5 feet wide having not less than two hinged or sliding glass doors with provisions for
locking. The bulletin board shall be mounted where and as approved by the Owner, in a prominent place accessible to employees
of the Contractor and sub-contractors, and to applicants for employment. The bulletin board shall remain the property of the
Contractor and shall be removed by him upon completion of the Contract work. The following information which will be furnished by
the City to the Contractor shall be posted on the bulletin board and shall be maintained by the Contractor in easily readable
condition at all times for the duration of the Contract.
a. The Equal Opportunity Poster and Notice Nondiscrimination of Employment(Standard Form 38). ,..,
b. Wage Rate Information Poster(Form SOL 155), with the Contract Schedule of minimum wage rates as required by the
Davis-Bacon Act.
C. Safety Posters.
w
SECTION Q
VENUE
Should any action arise out of the terms and conditions of this contract,venue for said action shall lie in Tarrant County,Texas.
General Conditions of the Contract for Construction Lump Sum Contract Page 26 of 26
City of Ft Worth—West Division,PMD2014-09,City Project#100172 October 2017
an
CITY OF FORT WORTH, TEXAS
..
CONSTRUCTION CONTRACT (LUMP SUM)
.. THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
This agreement made and entered into this the 17th day of October
+ A.D., 2017, by and between the CITY OF FORT WORTH, a municipal corporation of Tarrant County,
Texas, organized and existing under and by virtue of a special charter adopted by the qualified voters
A within said City on the 11th day of December, A.D. 1924, under the authority (vested in said voters by the
"Home Rule" provision) of the Constitution of Texas, and in accordance with a resolution duly passed at a
regular meeting of the City Council of said City, hereinafter called OWNER, and Balfour Beatty
Construction, LLC of the City of Dallas , County of Dallas , State of Texas, hereinafter called
CONTRACTOR.
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned to
" be made and performed by the Owner, and under the conditions expressed in the bond bearing even
date herewith, the said Contractor hereby agrees with the said Owner to commence and complete the
construction of certain improvements described as follows:
City of Fort Worth
West Patrol Division (Joyce Drive Police Station)
.. 3532 Joyce Drive
Fort Worth, Texas
PMD2014-09
City Project#100172
That the work herein contemplated shall consist of furnishing as an independent contractor all labor,
tools, appliances and materials necessary for the construction and completion of said project in
accordance with the Plans and Specifications and Contract Documents adopted by the City Council of the
City of Fort Worth, which Plans and Specifications and Contract Documents are hereto attached and
made a part of this contract the same as if written herein.
The Contractor hereby agrees and binds himself to commence the construction of said work within ten
(10) days after being notified in writing to do so by the Owner.
City agrees and binds itself to pay, and the said Contractor agrees to receive, for all of the aforesaid work,
and for stated additions thereto or deductions there from, the price shown on the Proposal submitted by
the successful bidder hereto attached and made a part hereof. Payment will be made in monthly
w installments upon actual work completed by contractor and accepted by the Owner and receipt of invoice
from the Contractor.
The agreed upon total contract amount shall be $1,685,093.00
including the Base Proposal ($1,370,000.00), Owner's Contingency Allowance ($102,750.00), Allowances
Nos. 1 &2 ($9,000.00), and Add Alternate Nos. 2 through 7($203,343.00).
Insurance Requirements:
A
The Contractor shall not commence work under this contract until it has obtained all insurance
required under the Contract Documents, and the Owner has approved such insurance. The
Contractor shall be responsible for delivering to the Owner the sub-contractors' certificates of
insurance for approval. The Contractor shall indicate on its certificate of insurance included in the
documents for execution whether or not its insurance covers subcontractors. It is the intention of
the Owner that the insurance coverage required herein shall include the coverage of all
subcontractors.
.w. Instruction to Offerors(Feb 2017) Page 23 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station), PMD2014-09,City Project#100172 October 2017
MW
a. WORKER'S COMPENSATION INSURANCE: •
• Statutory limits.
• Employer's liability:
• $100,000 disease each employee.
• $500,000 disease policy limit.
• $100,000 each accident.
b. COMMERCIAL GENERAL LIABILITY INSURANCE:
The Contractor shall procure and shall maintain during the life of this contract public
liability insurance coverage in the form of a Commercial General Liability insurance policy
to cover bodily injury, including death, and property damage at the following limits:
$1,000,000 each occurrence and $2,000,000 aggregate limit.
• The insurance shall be provided on a project specific basis and shall be endorsed
accordingly.
• The insurance shall include, but not be limited to, contingent liability for independent
contractors, XCU coverage, and contractual liability.
C. BUSINESS AUTOMOBILE LIABILITY:
• $1,000,000 each accident.
• The policy shall cover any auto used in the course of the project.
d. BUILDER'S RISK OR INSTALLATION FLOATER:
This insurance shall be applicable according to the property risks associated with the
project and commensurate with the contractual obligations specified in the contract
documents.
e. EXCESS LIABILITY UMBRELLA:
• $1,000,000 each occurrence; $2,000,000 aggregate limit.
• This insurance shall provide excess coverage over each line of liability insurance
required herein. The policy shall follow the form(s) of the underlying policies.
f. SCOPE OF INSURANCE AND SPECIAL HAZARD:
The insurance required under the above paragraphs shall provide adequate protection for
the Contractor and its subcontractors, respectively, against damage claims which may
arise from operations under this contract, whether such operations be by the insured or
by anyone directly or indirectly employed by it, against any insurable hazards which may
be encountered in the performance of the Contract.
g. PROOF OF CARRIAGE OF INSURANCE:
The Contractor shall furnish the owner with satisfactory proof of coverage by insurance
required in these Contract Documents in the amounts and by insurance carriers
satisfactory to the Owner. The form to be used shall be the current Accord certificate of
insurance form or such other form as the Owner may in its sole discretion deem
acceptable. All insurance requirements made upon the Contractor shall apply to the sub-
contractors, should the Contractor's insurance not cover the subcontractor's work
operations performed in the course of this contracted project.
Instruction to Offerors(Feb 2017) Page 24 of 33 *�
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
ADDITIONAL INSURANCE REQUIREMENTS:
a. The Owner, its officers, employees and servants shall be endorsed as an additional
insured on Contractor's insurance policies excepting employer's liability insurance
coverage under Contractor's workers'compensation insurance policy.
b. Certificates of insurance shall be delivered to the City of Fort Worth, contract
administrator in the respective department as specified in the bid documents, 200
Texas Street, Fort Worth, TX 76102, prior to commencement of work on the
contracted project.
C. Any failure on part of the Owner to request required insurance documentation shall
not constitute a waiver of the insurance requirements specified herein.
d. Each insurance policy shall be endorsed to provide the Owner a minimum thirty days
notice of cancellation, non-renewal, and/or material change in policy terms or
coverage. A ten days notice shall be acceptable in the event of non-payment of
premium.
e. Insurers must be authorized to do business in the State of Texas and have a current
A.M. Best rating of A:VII or equivalent measure of financial strength and solvency.
f. Deductible limits, or self-funded retention limits, on each policy must not exceed
$10,000.00 per occurrence unless otherwise approved by the Owner.
g. In lieu of traditional insurance, Owner may consider alternative coverage or risk
treatment measures through insurance pools or risk retention groups. The Owner
must approve in writing any alternative coverage.
h. Workers'compensation insurance policy(s)covering employees employed on the
.w project shall be endorsed with a waiver of subrogation providing rights of recovery in
favor of the Owner.
i. Owner shall not be responsible for the direct payment of insurance premium costs for
contractor's insurance.
j. Contractor's insurance policies shall each be endorsed to provide that such
insurance is primary protection and any self-funded or commercial coverage
maintained by Owner shall not be called upon to contribute to loss recovery.
k. In the course of the project, Contractor shall report, in a timely manner, to Owner's
officially designated contract administrator any known loss occurrence which could
give rise to a liability claim or lawsuit or which could result in a property loss.
I. Contractor's liability shall not be limited to the specified amounts of insurance
required herein.
M. Upon the request of Owner, Contractor shall provide complete copjes pf•all insurance
policies required by these contract documents. ' '
If this Contract is in excess of$25,000, the Contractor shall provide a Payment Bond in the full amount of
the contract. If the contract is in excess of $100,000 Contractor shall provide both Payment and
Performance Bonds for the full amount of the contract. Contractor shall apply for all City of Fort Worth
Permits and for any other permits required by this project. City of Fort Worth Permit fees are waived.
�., Separate permits will be required for each facility.
,.. Instruction to Offerors(Feb 2017) Page 25 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
If the Contractor should fail to complete the work as set forth in the Plans and Specifications and Contract
Documents within the time so stipulated, plus any additional time allowed as provided in the General ..
Conditions, there shall be deducted from any monies due or which may thereafter become due him, the
liquidated damages outlined in the General Conditions, not as a penalty but as liquidated damages, the
Contractor and his Surety shall be liable to the Owner for such deficiency. ..
IN WITNESS WHEREOF, the City of Fort Worth has caused this instrument to be signed in four
counterparts in its name and on its behalf by the City Manager and attested by its Secretary, with the
corporate seal of the City of Fort Worth attached. The Contractor has executed this instrument through its
duly authorized officers in four counterparts with its corporate seal attached.
�XXIuuuu►►►►1i 00 ••
`p0`�(`( Q Y ort Worth, Texas, this the 2 day of Noue-i?(3,eZ2 A.D., 2017.
i
LLQsEAL Af
2001 Bur Beatty Construction, LL APPROL:
%� '• I Y O FORT W R H
Y.
K I ack esu J. Chaps
i -President of Operations Assistant City Manager
APPR RECORDED: O
COMM D:
By: By:
low
4,C6 Stev9 Cooke Mary J. Kays `• . ;�'�,
Director, Property Management Dept. City Secretary
AS
/ APPROVED AS TO FORM AND LEGALITY: M&C Reference No.: C-28440
M&C Date: October 17, 2017
By: Contract Authorization
Jon B. Strong
Assistant City Attorney
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible for the monitoring and administration of this
contract, including ensuring all performance and reporting requirements.
By: �G 0. G&49
Brian R. Glass, AIA
Architectural Services Manager
OLFMIAL RECORD
FT. TX
Instruction to Offerors(Feb 2017) Page 26 of 33 w
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
Bond# 106813943
.. PAYMENT BOND
THE STATE OF TEXAS §
®, § KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
*• That we, Balfour Beath` Construction. LLC known as "Principal" herein, and
Travelers Casualty and Surety Company a corporate
surety(sureties), duly authorized to do business in the State of Texas,known as "Surety"herein(whether
one or more), are held and firmly bound unto the City of Fort Worth, a municipal corporation created
pursuant to the laws of the State of Texas, known as"City"herein, in the penal sum of, One Million,Six
w
Hundred Ei4hty-Five Thousand,Ninety-Three Dollars( $1,685,053.00 ), lawful money of the United
States, to be paid in Fort Worth, Tarrant County,Texas, for the payment of which sum well and truly be
made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and
severally, firmly by these presents:
WHEREAS, Principal has entered into a certain written Contract with City, awarded the 171
day of October ,2017,which Contract is hereby referred to and made a part hereof for all purposes as
if hilly set forth herein,to furnish all materials,equipment, labor and other accessories as defined by law,
in the prosecution of the Work as provided for in said Contract and designated as West Patrol Division
(.Ioyice Drive Police Station) located at 3532 Joyce Drive. Fort Worth, Texas (PMD2014-09. City
Project#100I72).
NOW, THEREFORE, 1-14E CONDITION OF THIS OBLIGATION is such that if Principal
shall pay all monies owing to any(and all)payment bond beneficiary(as defined in Chapter 2253 of the
Texas Government Code, as amended) in the prosecution of the Work under the Contract, then this
obligation shall be and became null and void; otherwise to remain in full force and effect.
.r
This bond is made and executed in compliance with the provisions of Chapter 2253 of the Texas
Government Code,as amended,and all liabilities on this bond shall be determined in accordance with the
provisions of said statute.
.r
.a
Instruction to Offerors(Feb 2017) Page 27 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station) PMD2014.09,City Projec1#100172 October 2017
wir
w
IN WITNESS WHEREOF, the Principal and Stu-ety Have each SIGNED and SCAT F;D this
instrument by duly authorized agents and officers on this the 3rd day of November .2017.
Pl;IXTr'TD A I.:
\\\\IIIIII1111//`l
Balfour Beatty Ck RVZOA.
,�
p s LIT
t Y
-_.a.._...„. Jam;��1-.•n...,.�.----`-'���G
A T `EST: BY. _ + 04�
-'
i l�LAUU.
(P 'n ip tt e ry Name and Title
MM
Address: 3100 McKinnon Street
Dallas,TX 75201
Witness as to Principal
SURETY:
Travelers Casualty and Surety Company
all
ATTEST: BY: % 1� �,•� —�
7 Signature
Noah William Pierce,Attorney-in-Fad
t iiSBat Jo ua Sanford,witness Name and`Title
.® Address: One Tower Square
Hartford,CT 06183
Witn , as to St Ct Bethany Stevenson
Telephone Number: (8W)277-0111
*Notc- if signed by an officer of the Surety, there must be on file a certified extract from the bylaws sho\\ging
that this:person has authority to sign such obligation. If Surety's physical address is different from its mailing
address,both must be provided. The date of the bond shall not be prior to the date the Contract is awarded.
4
7
7
Instruction to Offerors(Feb 2017) Page 28 of 33
City of Ft Worth-K West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Proles#100172 October 2017
Bond# 106813943
•.
PERFORMANCE BOND
THE STATE OF TEXAS §
�. § KNOW ALL BY THESE PRESENTS:
COUNTY OF TARILANT §
That we, Balfour Beatty Construction.LLC , known as"Principal"herein and
Travelers Casualty and Surety Company ____,a corporate surety
(sureties;if more than one)duly authorized to do bttsivess in the State of Texas,known as"Surety"herein
(whether one or more),are held and firmly bound unto the City of Port Worth,a municipal corporation
created pursuant to the laws of Texas,known as"City"herein, in the penal sum of, One Million,
Six Hundred Eighty-Five Thousand.Ninety-Three Dollars(S1.685.093.00), lawful money
of the United States, to be paid in Fort Worth,Tarrant County,Texas for the payment of which sum well
.. and truly to be made,we bind ourselves,our heirs,executors,administrators,successors and assigns,
jointly and severally, firmly by these presents.
r.
WHEREAS,the Principal has entered into a certain written contract with the City awarded the
17'h day of October ,2017,which Contract is hereby referred to and made a pant hereof
No for all purposes as if fully set forth herein,to furnish all materials,equipment labor and other accessories
defined by law,in the prosecution of the Work, including any Change Orders,as provided for in said
an Contract designated as Nest Patrol Division(Joyce Drive Police SWtion)located at 3532 Joyce Drive,
Fort Worth.Texas(PMD2014-09,Citv Proiect#100172).
NOW,THEREFORE,the condition of this obligation is such that if the said Principal shall
faithfully perform it obligations under the Contract and shall in all respects duly and faithfully perform
the Work, including Change Orders,under the Contract;according to the plans,specifications,and
contract documents therein referred to,and as well during any period of extension of the Contract that
.., may be granted on the part of the City,then this obligation shall be and become null and void,otherwise
to retrain in full force and effect,
PROVIDED FURTHER,that if any legal action be filed on this Bond,venue shall lie in Tarrant
County,Texas or the United States District Court for the Northern District ofTexas,Fort Worth Division.
MW
This bond is made and executed in compliance with the provisions of Chapter 2253 of the Texas
Government Code,as amended,and all liabilities on this bond shall be determined in accordance with the
on
provisions of said statue.
an
Instruction to Offerors(Feb 2017) Page 29 of 33
Gply of Ft Worth_West Patrol Divalon(Joyce Drive Police Station),PMD2014-09,City Project 4100172 October 2017
in
IN WITNESS WHEREOF,the Principal and the Surety have SIGNED and SEAL[-D this
instrument by duly authorized agents and officers on this the 3rd day of, November 2017.
PM''CIPAL:
Balfour Bea +ion LLC
\\11111411 t!!!!!1!
i
Sign'"vire =O 1 SEAL
Z4.� 2004 i
---.- TD>�-.�d� ��_...���✓'.,.SFO..••' ��.
(PrikilAA Saaetar \lame and Title 4� �AIWR1\���``
U �e Address:3100 McKinnon Street
Dallas,TX 75201
.s
Witness as to Principal
.■ SURETY:
Travelers Casualty and Surety Company
BY:
w Signature
Noah William Pierce,Attorney-In-Fad
Name and Title
Address: One Tower Square
MR Hartford,CT 01683
1•'4'ilne as to Sure Y Bethany Stevenson Telephone Number: (860)277-0111
*Note: If signed by an officer of the Surety Company, there must be on File a certified extract from the by-laws
showing that this person has authority to sign such obligation. If Surety's physical address is different from its
mailing address,both must be provided.'rhe date of the bond shall not be prior to the date the Contract is awarded.
.w
r.r4
Instruction to Offerors(Feb 2017) Page 30 of 33
arM!
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09 Cly Project#100172 October 2017
pp WARNING:THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
" k 4
.dW POWER OF ATTORNEY i
t TRAVELERS
Farmington Casualty Company St.Paul Mercury Insurance Company
Fidelity and Guaranty Insurance Company Travelers Casualty and Surety Company
Fidelity and Guaranty Insurance Underwriters,Inc. Travelers Casualty and Surety Company of America
St.Paul Fire and Marine Insurance Company United States Fidelity and Guaranty Company
St.Paul Guardian Insurance Company
Attorney-In Fact No. 232531 Certificate No. 007399044
KNOW ALL MEN BY THESE PRESENTS: That Farmington Casualty Company, St. Paul Fire and Marine Insurance Company,St. Paul Guardian Insurance
Company,St.Paul Mercury Insurance Company,Travelers Casualty and Surety Company,Travelers Casualty and Surety Company of America,and United States
Fidelity and Guaranty Company are corporations duly organized under the laws of the State of Connecticut,that Fidelity and Guaranty Insurance Company is a
corporation duly organized under the laws of the State of Iowa,and that Fidelity and Guaranty Insurance Underwriters,Inc.,is a corporation duly organized under the
laws of the State of Wisconsin(herein collectively called the"Companies"),and that the Companies do hereby make,constitute and appoint
Stacy Rivera,Donna M.Planeta,Joshua Sanford,Aimee R.Perondine,Aiza Lopez,Keri Ann Smith,Brian Peters,Danielle D.Johnson,Stephani A.
Trudeau,Michelle Anne McMahon,Cavel Dixon-Rubeor,Noah William Pierce,and Saykham Chanthasone
a
of the City of Hartford -,State of Connecticut ,their true and lawful Attorney(s)-in-Fact,
each in their separate capacity if more than one is named above,to sign,execute,seal and acknowledge any and all bonds,recognizances,conditional undertakings and
other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons,guaranteeing the performance of
R contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
IN WITNESS WHEREOF,the Companies have caused this instrument to be signed and their corporate seals to be hereto affixed,this 4th
day of October 2017
Farmington Casualty Company St.Paul Mercury Insurance Company
Fidelity and Guaranty Insurance Company Travelers Casualty and Surety Company
Fidelity and Guaranty Insurance Underwriters,Inc. Travelers Casualty and Surety Company of America
St.Paul Fire and Marine Insurance Company United States Fidelity and Guaranty Company
St.Paul Guardian Insurance Company
GAS(:, �r p\RE 6 N �X /• 1NS \,tY 4
,a>nn((, � 4 0��.-.-...SG,➢ JPS......�'P4 �o� A'OP /ib�u9th• W}iYAyp
02 O"�YJ.!- � 4� 6 P tCp NPDXAr�i
Yz on19�8 2s��;0 y4�rc 19'�f� INC1OBPO5NA1TEO P 'z "a��i.SEW$Lj�om"3 P'aQ�
im:�'S-8RALr Et
a: f3P:g �P HARTFORD,Ly@,pl'FumFbgq[`
<
F�
\
tass
y
CONN. o° �• R N �
6 a �r2 0' �'•.. j �a, u
State of Connecticut By:
City of Hartford ss. Robert L.Raney,Senior Vice President
On this the 4th day of October 2017,before me personally appeared Robert L.Raney,who acknowledged himself to
be the Senior Vice President of Farmington Casualty Company, Fidelity and Guaranty Insurance Company,Fidelity and Guaranty Insurance Underwriters,Inc.,St.Paul
Fire and Marine Insurance Company,St.Paul Guardian Insurance Company,St.Paul Mercury Insurance Company,Travelers Casualty and Surety Company,Travelers
Casualty and Surety Company of America,and United States Fidelity and Guaranty Company,and that he,as such,being authorized so to do,executed the foregoing
instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer.
G•T�R.t�
In Witness Whereof,I hereunto set my hand and official seal.
My Commission expires the 30th day of June,2021. Ik AL�Gir ASa>?e C.Tetreault,Notary Public
58440-5-16 Printed in U.S.A.
WARNING:THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
WARNING:THIS POWER OF AT rORNEY IS INVALID WITHOUT THE RED BORDER
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of Farmington Casualty Company,Fidelity
and Guaranty Insurance Company,Fidelity and Guaranty Insurance Underwriters,Inc.,St. Paul Fire and Marine Insurance Company,St.Paul Guardian Insurance
Company,St.Paul Mercury Insurance Company,Travelers Casualty and Surety Company,Travelers Casualty and Surety Company of America,and United States
Fidelity and Guaranty Company,which resolutions are now in full force and effect,reading as follows:
RESOLVED,that the Chairman,the President,any Vice Chairman,any Executive Vice President,any Senior Vice President,any Vice President,any Second Vice
President,the Treasurer,any Assistant Treasurer,the Corporate Secretary or any Assistant Secretary may appoint Attorneys-in-Fact and Agents to act for and on behalf w
of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the
Company's seal bonds,recognizances,contracts of indemnity,and other writings obligatory in the nature of a bond,recognizance,or conditional undertaking,and any
of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her;and it is
s
FURTHER RESOLVED,that the Chairman,the President,any Vice Chairman,any Executive Vice President,any Senior Vice President or any Vice President may i
delegate all or any part of the foregoing authority to one or more officers or employees of this Company,provided that each such delegation is in writing and a copy
thereof is filed in the office of the Secretary;and it is
FURTHER RESOLVED,that any bond,recognizance,contract of indemnity,or writing obligatory in the nature of a bond,recognizance,or conditional undertaking
shall be valid and binding upon the Company when(a)signed by the President,any Vice Chairman,any Executive Vice President,any Senior Vice President or any Vice
President,any Second Vice President,the Treasurer,any Assistant Treasurer,the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the
Company's seal by a Secretary or Assistant Secretary;or(b)duly executed(under seal,if required)by one or more Attorneys-in-Fact and Agents pursuant to the power ion
prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED,that the signature of each of the following officers:President,any Executive Vice President,any Senior Vice President,any Vice President,
any Assistant Vice President,any Secretary,any Assistant Secretary,and the seal of the Company may be affixed by facsimile to any Power of Attorney or to any w
certificate relating thereto appointing Resident Vice Presidents,Resident Assistant Secretaries or Attorneys-in-Fact for purposes only of executing and attesting bonds
and undertakings and other writings obligatory in the nature thereof,and any such Power of Attorney or certificate bearing such facsimile signature or facsimile seal
shall be valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on
the Company in the future with respect to any bond or understanding to which it is attached.
I,Kevin E.Hughes,the undersigned,Assistant Secretary,of Farmington Casualty Company,Fidelity and Guaranty Insurance Company,Fidelity and Guaranty Insurance
Underwriters,Inc.,St.Paul Fire and Marine Insurance Company,St.Paul Guardian Insurance Company,St.Paul Mercury Insurance Company,Travelers Casualty and
Surety Company,Travelers Casualty and Surety Company of America,and United States Fidelity and Guaranty Company do hereby certify that the above and foregoing
is a true and correct copy of the Power of Attorney executed by said Companies,which is in full force and effect and has not been revoked.
IN TESTIMONY WHEREOF,I have hereunto set my hand and affixed the seals of said Companies this � day of d e- 20
A.
Kevin E.Hughes,Assistant�tay
t".
49
FY 9Q;r••'y\PORq °P 9� � ,W_ _vi �
•{i lm•tp�_ f.�"'- �� „� � rtp�
2 1 9 8 2 0 1�� �: P i n; m NANTFOaO, < r tiFRTFOFq � f 896
EALonof CONN. ° ` CONN �q as
SEAL3
d1.....•�a a.••.. .%aa° ad �s
s. �
To verify the authenticity of this Power of Attorney,call 1-800-421-3880 or contact us at www.travetersbond.com.Please refer to the Attorney-In-Fact number,the
above-named individuals and the details of the bond to which the power is attached.
IM
PM
r
WARNING:THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER
Travelersi
IMPORTANT NOTICE
TO OBTAIN INFORMATION OR MAKE A COMPLAINT:
You may contact Travelers Casualty and Surety Company of America,.Travelers
Casualty and Surety Company, The Travelers Indemnity Company, Standard Fire
"* Insurance Company and/or Farmington Casualty Company for information or to make a
complaint at:
Travelers Bond
Attn: Claims
.� 1500 Market Street
West Tower, Suite 2900
Philadelphia,PA 19102
(267)675-3057
(267)675-3107 Fax
w
You may contact the Texas Department of Insurance to obtain the information on
companies, coverages, rights or complaints at:
Texas Department of Insurance
.■ P.O.Box 149104
Austin, TX 78714-9104
w (800) 252-3439
ATTACH THIS NOTICE TO YOUR BOND. This notice is for information only and
does not become a part or a condition of the attached document and is given to comply
with Section 2253-021, Government Code, and Section 53.202, Property Code, effective
September 1, 2001.
w
...
Notification to Others of Cancellation, Nonrenewal ZURICH
or Reduction of Insurance
Policy No. Eff. Date of Pol. Exp. Date of Pol. Eff.Date of End. Producer No. Add'I.Prem Return Prem.
LO 647668403 10/1/2016 10/1/2017
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
This endorsement modifies insurance provided under the:
Commercial General Liability Coverage Part
Liquor Liability Coverage Part
Products/Completed Operations Liability Coverage Part
A. If we cancel or non-renew this Coverage Part(s) by written notice to the first Named Insured for any reason other than
nonpayment of premium,we will mail or deliver a copy of such written notice of cancellation or non-renewal:
1. To the name and address corresponding to each person or organization shown in the Schedule below; and
2. At least 10 days prior to the effective date of the cancellation or non-renewal, as advised in our notice to the first
Named Insured, or the longer number of days notice if indicated in the Schedule below.
B. If we cancel this Coverage Part(s) by written notice to the first Named Insured for nonpayment of premium, we will
mail or deliver a copy of such written notice of cancellation to the name and address corresponding to each person or
organization shown in the Schedule below at least 10 days prior to the effective date of such cancellation.
C. If coverage afforded by this Coverage Part(s) is reduced or restricted, except for any reduction of Limits of Insurance
due to payment of claims, we will mail or deliver notice of such reduction or restriction:
1. To the name and address corresponding to each person or organization shown in the Schedule below; and
2. At least 10 days prior to the effective date of the reduction or restriction, or the longer number of days notice if
indicated in the Schedule below.
D. If notice as described in Paragraphs A., B. or C. of this endorsement is mailed, proof of mailing will be sufficient proof
of such notice.
SCHEDULE
Name and Address of Other Person(s)1 Number of Days Notice:
Organization(s):
City of Fort Worth Texas
PER SCHEDULE ON FILE WITH CARRIER 30
All other terms and conditions of this policy remain unchanged.
U-GL-1447-A CW(05/10)
Page 1 of 1
Includes copyrighted material of Insurance Services Office,Inc.,with its permission.
Notification to Others of Cancellation ZURICH
Policy No. Eff. Date of Pol. Exp. Date of Pol. Eff.Date of End. Producer No. AddT Prem Return Prem.
AP 6476683-03 [10/1/2016 110/1/2017
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
This endorsement modifies insurance provided under the:
Commercial Automobile Coverage Part
A. If we cancel this Coverage Part by written notice to the first Named Insured for any reason other than nonpayment of
premium,we will mail or deliver a copy of such written notice of cancellation:
1. To the name and address corresponding to each person or organization shown in the Schedule below; and
2. At least 10 days prior to the effective date of the cancellation, as advised in our notice to the first Named Insured,
or the longer number of days notice if indicated in the Schedule below.
B. If we cancel this Coverage Part by written notice to the first Named Insured for nonpayment of premium, we will mail
or deliver a copy of such written notice of cancellation to the name and address corresponding to each person or
organization shown in the Schedule below at least 10 days prior to the effective date of such cancellation.
C. If notice as described in Paragraphs A. or B. of this endorsement is mailed, proof of mailing will be sufficient proof of
such notice.
SCHEDULE
Name and Address of Other Person(s)0 Number of Days Notice:
Organ izations :
PER SCHEDULE ON FILE WITH CARRIER 30
All other terms and conditions of this policy remain unchanged.
U-CA-812-A CW(05/10)
Page 1 of 1
Includes copyrighted material of Insurance Services Office,Inc.,with its permission.
WORKERS COMPENSATION AND EMPLOYERS LIABILITY INSURANCE POLICY WC 99 06 33
NOTIFICATION TO OTHERS OF CANCELLATION ENDORSEMENT
This endorsement is used to add the following to Part Six of the policy.
PART SIX
CONDITIONS
A. If we cancel this policy by written notice to you for any reason other than nonpayment of premium,we will mail
or deliver a copy of such written notice of cancellation to the name and address corresponding to each person
or organization shown in the Schedule below. Notification to such person or organization will be provided at
least 10 days prior to the effective date of the cancellation, as advised in our notice to you, or the longer
number of days notice if indicated in the Schedule below.
B. If we cancel this policy by written notice to you for nonpayment of premium,we will mail or deliver a copy of
such written notice of cancellation to the name and address corresponding to each person or organization
shown in the Schedule below at least 10 days prior to the effective date of such cancellation.
C. If notice as described in Paragraphs A.or B. of this endorsement is mailed, proof of mailing will be sufficient
proof of such notice.
SCHEDULE
Name and Address of Other Person(s)/
Number of Days Notice:
Organ ization(s):
PER SCHEDULE ON FILE WITH CARRIER 30
All other terms and conditions of this policy remain unchanged.
This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated.
(The Information below Is required only when this endorsement Is issued subsequent to preparation of the policy.)
Endorsement Effective Policy No. WC 6476685-03 Endorsement No.
Insured. Balfour Beatty Construction, LLC Premium$
Insurance Company:Zurich American Insurance Company
WC 99 06 33
(Ed. 05-10) Includes copyrighted material of National Council on Compensation Insurance,Inc.with its permission. Page 1 of 1
Blanket Notification to Others of Cancellation or ZURICH
Nonrenewal
Policy No. Eff.Date of Pd. Exp.Date of Pol. Eff.Date of End. Producer Add'I Prem. Return Prem.
... AUC 0184602-01 10/01/2016 10/01/2017 10/01/2016
Named Insured and Mailing Address: Producer:
Balfour Beatty Construction,LLC
Central Division
3100 McKinnon, 7th Floor
Dallas,TX 75201
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
The following is added to Paragraph A. of SECTION VI. CONDITIONS:
Blanket Notification to Others of Cancellation or Nonrenewal
a. If we cancel or non-renew this policy by written notice to the first Named Insured, we will mail or deliver notification
that such policy has been cancelled or non-renewed to each person or organization shown in a list provided to us by
the first Named Insured if you are required by written contract or written agreement to provide such notification.
However, such notification will not be mailed or delivered if a conditional notice of renewal has been sent to the first
Named Insured. Such list:
(1) Must be provided to us prior to cancellation or non-renewal;
(2) Must contain the names and addresses of only the persons or organizations requiring notification that such policy
has been cancelled or non-renewed;and
(3) Must be in an electronic format that is acceptable to us.
b. Our notification as described in Paragraph a. above will be based on the most recent list in our records as of the date
the notice of cancellation or non-renewal is mailed or delivered to the first Named Insured. We will mail or deliver
such notification to each person or organization shown in the list:
(1) Within seven days of the effective date of the notice of cancellation, if we cancel for non-payment of premium;or
(2) At least 30 days prior to the effective date of:
(a) Cancellation, if cancelled for any reason other than nonpayment of premium;or
(b) Non-renewal, but not including conditional notice of renewal.
c. Our mailing or delivery of notification described in Paragraphs a. and b. above is intended as a courtesy only. Our
failure to provide such mailing or delivery will not:
(1) Extend the policy cancellation or non-renewal date;
_. (2) Negate the cancellation or non-renewal;or
(3) Provide any additional insurance that would not have been provided in the absence of this endorsement.
U-UMB-722-A CW(01A3)
Page 1 of 1
Includes copyrighted material of Insurance Services Office,Inc.,with its permission.
d. We are not responsible for the accuracy, integrity, timeliness and validity of information contained in the list provided
to us as described in Paragraphs a. and b. above.
ALL OTHER TERMS AND CONDITIONS OF THE POLICY SHALL APPLY AND REMAIN UNCHANGED.
U-UMB-722-A CW(01/13)
Page 2of2
Includes copyrighted material of Insurance Services Office,Inc.,with its permission.
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it provides
worker's compensation insurance coverage for all of its employees employed on City Project, West
Patrol Division (Joyce Drive Police Station) located at 3532 Joyce Drive, Fort Worth, Texas
(PMD2014-09, City Proiect#100172). Contractor further certifies that, pursuant to Texas Labor Code,
Section 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with
,■, worker's compensation coverage.
CONTRACTOR:
•p n
pO fl bU lr? 9f,---krV'� l:�,r&Wucyv,4J 4 By: 41-c-
.r� Company (Please Print)
_ g1Cb Allc C1rZpjj&J S'C Signature:
Address
pwu-/kc. 7-�S S2b I Title: d icC- F° eS►DC;kil- --b P EtZAl o A5
City/State/Zip (Please Print)
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
BEFORE- the under ' ed authority, o this day personally appeared
known to me
to be the p son whose name is subscribed to the foregoing, instrument, and ac/I owied ed to me that
he/she executed the same as the act and deed of C�1 I� L drlS C�
l
for the purposes and consideration therein expressed and in the capacity they1n stated.
17
GIVEN UNDER MY HAND AND SEAL OF OFFICE this qday of2017.
pa`ava�@4, SHERRY L. STEVENS
••� �i: Y s Notary Public,State of Texas
E � Comm. Expires 01-09-2021
- Nota Pu is in and for the State of Texas
Q10SO1� Notsry f7 11'
Instruction to Offerors(Feb 2017) Page 32 of 33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station),PMD2014-09,City Project#100172 October 2017
PAGE LEFT BLANK INTENTIONALLY ,,.,,
2)—O') 2)-0"
CENTERLINE OF
SIGN, LOGO &
TEXT INFORMATION
FORT 01PT
. He
Project Title
0
4
Architect:
T Architect's Name
Contractor:
G Contractor's Name
FUNDED BY
(List Bond Fund,etc.)
SCHEDULED COMPLETION DATE
YEAR
� s
SIGN COLOR & FONT:
BACKGROUND - WHITE
BORDER- 5118"WIDE, 3"RADIUS CORNERS, PMS 288 (BLUE)
TEXT - HELVETICA or ARIAL, PMS 288 (BLUE)
FORT WORTH LOGO COLORS & FONT:
FORT WORTH - PMS 288 (BLUE), CHELTENHAM BOLD
LONGHORN LOGO - PMS 725 (BROWN)
PROJECT DESIGNATION SIGN
Instruction to Offerors(Feb 2017) 33 -33
City of Ft Worth—West Patrol Division(Joyce Drive Police Station), PMD2014-09,City Project#100172
PAGE LEFT BLANK INTENTIONALLY ,