HomeMy WebLinkAboutContract 48870-CO1 CITY SECRETARY FORT WORTH. City of Fort Worth CONTRACT NO. Change Order Request Breakdown ProjectNamel CONCRETE RESTORATION(2017-2)AT VARIOUS LOCATIONS CitySec# 1 48870 Client Project#(s)l100631 Cgntractorl Westhill Construction,Inc. PM Tariquel Islam Inspector Ronnie Davis Change Order Submittal# 0 Date 11/7/2017 Dept. TPW Contract Time Totals CD Original Contract Amount $750,838.98 $750,838.98 150 Extras to Date Credits to Date Pending Change Orders(in M&C Process' Contract Cost to Date $750,838.98 $750,838.98 150 Amount of Proposed Change Order $46,765.16 $46,765.16 40 Revised Contract Amount $797,604.14 $797,604.14 190 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(if necessary) $46,765.16 546.765.16 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 6.23% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $938,548.73 The reason for this change order is to fund the remaining pavement repair on the southbound lanes of Randol Mill Road between John T.White Rd and Racquet Club Rd. The original estimated quantity for Cooks Lane overran by approximately 1528 S.Y. Therefore the funds that remained only were enough to partially repair the southbound Randol Mill.This change order will bring the southbound to completion. The time requested of forty days will allow for the repairs to be made;plus allow for the delayed time from the work being stopped(10-13-2017)until the contract can resume and finish. b S Secretary -�OF FO�Q�, V O SAS OFFICIAL RECORD CITY SECRETARY FT.WORTH,TX City of Fort worth Change Order Additions Project Name I CONCRETE RESTORATION(2017-2)AT VARIOUS LOCATIONS City Sec# 48870 Client Project# I 100631 Contractor Westhill Construction,Inc. PMJ Tariquel Islam Inspector Ronnie Davis Change Order Submittal# 0 Date 11(712017 ADDITIONS —ITEM DESGRIP I ION DEPT Qt) emove Concrete and replace vn Concrete avemen r..; 32110122 Flex Base.TY A, R- W P G Y. _____T4UT eognd Tensar AX 140-475)or approve Equal TP 0 S.00 T_9999.0000 Remove an ep ace " oncrete Driveway TP 5 7.S 1Raised Marker TY IC —TPW— EA 5 0: TPW $95,501.16 Sub Total Additions 5 Change Order Additions Page 1 of 1 FoR_ iH City of Fort Worth Change Order Deletions Project Name I CONCRETE RESTORATION 2017-2 AT VARIOUS LOCATIONS CitySec# 48870 ClientProject# F 100631 Co Westhill ConsWcbon,Inc. PM1 Tadquel Islam Inspector Ronnie Davis Change Order Submittal# 0 Date 11172017 DELETIONS —ITEM DESCRIPTION U1,1`1 clr UnitCost xai Miscellaneous Adjustment(utilities TW- 5 nclassified Excavation TPW _1 11 9999.0000 Removeand Replace "sidewalk TP 00CCGCJCO SF [ .0 1T_3217.5001 Curb Address Painting TPW A 13 Remove ADA Ramp TPW EA 14 32135 Install Barrier Free RampTPW3 TPW EA 5 3346,0108 Pipe Underdram,Type 8 TPW 90.00000000 LF $10.00 $90U.UU 7,2101 REFL Raised Marker TY I-A TPW EA 5. 3441.1301 Loop Detector Cable Sawcut TPW 1W.0-09W LF 3441,1302 14 AWG Loop Detector Cable TPW 1 LF 5. 25 o White Thermoplastic( A Crosswalk Lines 15 . 0 Lff 9999.0096 Paving Construction Allowance TPW EA 5, 7 3213.0208 Concrete HE (extra depth) TPW 9. Y 8 3292.0100 Block Sod Placement TPW 1,029,00000000 SY $5.00 9 3213.0700 Joint Sealant TPW 1,531.00000000 LF 3217.0305 Stop Bars Pavement Markings TPW 3 . LF TPW $48,736.00 Sub Total Deletions ,7 Change Order Deletions Page 1 of 1 M/SBE Breakdown for this Change Order M/SBE Sub Type of Service Amount forth is CO Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 CFW Change Order Approval St-COApp01 Page 1 of 3 Routing Assigned To: Due Date: Assigned By: Due Time: Links 1 fortworthgov/Infrastructure Proiects/100631 - Concrete Restoration 2017-2/Contractor/Change Orders/CHANGE ORDER #1 REV. #3 WESTHILL(1).xlsm Attachments(0) No Attachments have been added to this form. https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?Siteld=51500&ProcessId... 1/3/2018 CFW Change Order Approval St-COApp01 Page 2 of 3 FORTWORTH. City of Fort Worth Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: St-COSub04 Change Order No.: St-COApp01 Date Started: 2017-11-20 City Sec. No.: 48870 Date Due: 2017-12-08 Project Name: 100631 - Concrete Restoration 2017-2 100631 DOE Numbers: Project Numbers: Project Remove and replace failed panels on concrete pavement Description: Project Manager: Tariqul Islam City Inspector: Ronnie Davis Contractor: Westhill Construction, Inc. COUNCIL ACTION (If Required): M&C Log Name: M&C Number: M&C Date: COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: $ 46,765.16 30100 0200431 5740010 40 100631 00380 Total Cost: $ 46,765.16 Total Requested Days: 40 Approval Status: https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 1/3/2018 CFW Change Order Approval St-COApp01 Page 3 of 3 Approved: Yes Comments: User: Katie Newby Date: 2017-11-27 1:01 PM Approved: Yes Comments: User: Tariqul Islam Date: 2017-11 27 3:34 PM Approved: Yes Comments: User: Riad Nusrallah Date: 2017-12-06 12:28 PM Approved: Yes Comments: User: Richard Martinez Date: 2017-12-13 2:25 PM Approved: Yes Comments: User: Doug Wiersig Date: 2017-12-18 5:54 PM Approved: Yes Comments: User: Doug Black Date: 2018-01-03 12:21 PM Approved: Yes Comments: User: Jay Chapa Date: 2018-01-03 12:30 PM Action Required: https://projectpoint.buzzsaw.com/ bz__web/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 1/3/2018 Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. 11 10 A AM Tariqul Islam Title This form is N/A as No City Funds are associated with this Contract Printed Name Signature