"ENGINEER"), for a PROJECT generally described as: M-199C-R Parallel Interceptors for
West Fork Basin.
Article I
Scope of Services
The Scope of Services is set forth in Attachment A.
Article II
Compensation
The ENGINEER's compensation shall be in the amount of $525,000.00 as
set forth in Attachment B.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
(1) The Engineer shall provide the City sufficient documentation, including but
not limited to meeting the requirements set forth in Attachment D to this
AGREEMENT, to reasonably substantiate the invoices.
(2) The ENGINEER will issue monthly invoices for all work performed under this
AGREEMENT. Invoices are due and payable within 30 days of receipt.
(3) Upon completion of services enumerated in Article I, the final payment of
any balance will be due within 30 days of receipt of the final invoice.
(4) In the event of a disputed or contested billing, only that portion so contested
City of Fort Worth,Texas OFFICIAL RECORD
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016 CITY SECRETARY
Page 1 of 16
FT.WORTH,TX
will be withheld from payment, and the undisputed portion will be paid. The
CITY will exercise reasonableness in contesting any bill or portion thereof.
No interest will accrue on any contested portion of the billing until mutually
resolved.
(5) If the CITY fails to make payment in full to ENGINEER for billings contested
in good faith within 60 days of the amount due, the ENGINEER may, after
giving 7 days' written notice to CITY, suspend services under this
AGREEMENT until paid in full. In the event of suspension of services, the
ENGINEER shall have no liability to CITY for delays or damages caused the
CITY because of such suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental
thereto.
B. Standard of Care
The ENGINEER shall perform its services:
(1) with the professional skill and care ordinarily provided by competent
engineers practicing in the same or similar locality and under the same or
similar circumstances and professional license; and
(2) as expeditiously as is prudent considering the ordinary professional
skill and care of a competent engineer.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
work to be performed hereunder. The ENGINEER shall also advise
the CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 2 of 16
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that
could affect the total PROJECT cost and/or execution. These
conditions and cost/execution effects are not the responsibility of the
ENGINEER.
D. Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in .pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires; provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on-site representatives or otherwise, do not make the
ENGINEER or its personnel in any way responsible for those duties that
belong to the CITY and/or the CITY's construction contractors or other
entities, and do not relieve the construction contractors or any other entity of
their obligations, duties, and responsibilities, including, but not limited to, all
construction methods, means, techniques, sequences, and procedures
necessary for coordinating and completing all portions of the construction
work in accordance with the Contract Documents and any health or safety
precautions required by such construction work. The ENGINEER and its
personnel have no authority to exercise any control over any construction
contractor or other entity or their employees in connection with their work or
any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the
progress or quality of the completed work on the PROJECT or to determine,
in general, if the work on the PROJECT is being performed in a manner
indicating that the PROJECT, when completed, will be in accordance with
the Contract Documents, nor shall anything in the Contract Documents or
the agreement between CITY and ENGINEER be construed as requiring
ENGINEER to make exhaustive or continuous on-site inspections to
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 3 of 16
discover latent defects in the work or otherwise check the quality or quantity
of the work on the PROJECT. If the ENGINEER makes on-site
observation(s) of a deviation from the Contract Documents, the ENGINEER
shall inform the CITY.
(3) When professional certification of performance or characteristics of
materials, systems or equipment is reasonably required to perform the
services set forth in the Scope of Services, the ENGINEER shall be entitled
to rely upon such certification to establish materials, systems or equipment
and performance criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs; competitive bidding procedures and market
conditions; time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate
PROJECT cost or schedule. Therefore, the ENGINEER makes no
warranty that the CITY's actual PROJECT costs, financial aspects,
economic feasibility, or schedules will not vary from the ENGINEER's
opinions, analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling
and observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects; that the
ENGINEER has made an examination to ascertain how or for what purpose
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are not other
matters at issue between the CITY and the construction contractor that
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 4 of 16
affect the amount that should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed. The ENGINEER is not responsible for
any errors or omissions in the information from others that is incorporated
into the record drawings.
I. Minority Business and Small Business Enterprise (MBE)(SBE)
Participation
In accord with the City of Fort Worth Business Diversity Ordinance No.
20020-12-2011, as amended, the City has goals for the participation of
minority business enterprises and/or small business enterprises in City
contracts. Engineer acknowledges the MBE and SBE goals established for
this contract and its accepted written commitment to MBE and SBE
participation. Any misrepresentation of facts (other than a negligent
misrepresentation) and/or the commission of fraud by the Engineer may
result in the termination of this Agreement and debarment from participating
in City contracts for a period of time of not less than three (3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers
and records of the ENGINEER involving transactions relating to this
contract. ENGINEER agrees that the CITY shall have access during normal
working hours to all necessary ENGINEER facilities and shall be provided
adequate and appropriate work space in order to conduct audits in
compliance with the provisions of this section. The CITY shall give
ENGINEER reasonable advance notice of intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the
CITY shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
facilities, and shall be provided adequate and appropriate work space, in
order to conduct audits in compliance with the provisions of this article
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 5 of 16
together with subsection (3) hereof. CITY shall give subconsultant
reasonable advance notice of intended audits.
(3) ENGINEER and subconsultant agree to photocopy such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for
the cost of copies at the rate published in the Texas Administrative Code in
effect as of the time copying is performed.
K. INSURANCE
(1) ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain
commercial general liability (CGL) and, if necessary, commercial
umbrella insurance with a limit of not less than $1,000,000.00 per each
occurrence with a $2,000,000.00 aggregate. If such Commercial General
Liability insurance contains a general aggregate limit, it shall apply
separately to this PROJECT or location.
i. The CITY shall be included as an insured with all rights of defense
under the CGL, using ISO additional insured endorsement or a
substitute providing equivalent coverage, and under the
commercial umbrella, if any. This insurance shall apply as
primary insurance with respect to any other insurance or self-
insurance programs afforded to the CITY. The Commercial
General Liability insurance policy shall have no exclusions or
endorsements that would alter or nullify: premises/operations,
products/completed operations, contractual, personal injury, or
advertising injury, which are normally contained within the policy,
unless the CITY specifically approves such exclusions in writing.
ii. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b. Business Auto — the ENGINEER shall maintain business auto liability
and, if necessary, commercial umbrella liability insurance with a limit of
not less than $1,000,000 each accident. Such insurance shall cover
liability arising out of "any auto", including owned, hired, and non-owned
autos, when said vehicle is used in the course of the PROJECT. If the
engineer owns no vehicles, coverage for hired or non-owned is
acceptable.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 6 of 16
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation —ENGINEER shall maintain workers
compensation and employers liability insurance and, if necessary,
commercial umbrella liability insurance with a limit of not less than
$100,000.00 each accident for bodily injury by accident or $100,000.00
each employee for bodily injury by disease, with $500,000.00 policy limit.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability — the ENGINEER shall maintain professional
liability, a claims-made policy, with a minimum of $1,000,000.00 per
claim and aggregate. The policy shall contain a retroactive date prior to
the date of the contract or the first date of services to be performed,
whichever is earlier. Coverage shall be maintained for a period of 5 years
following the completion of the contract. An annual certificate of
insurance specifically referencing this project shall be submitted to the
CITY for each year following completion of the contract.
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be attached to this AGREEMENT prior to its
execution.
b. Applicable policies shall be endorsed to name the CITY an Additional
Insured thereon, subject to any defense provided by the policy, as its
interests may appear. The term CITY shall include its employees,
officers, officials, agents, and volunteers as respects the contracted
services.
c. Certificate(s) of insurance shall document that insurance coverage
specified in this agreement are provided under applicable policies
documented thereon.
d. Any failure on part of the CITY to attach the required insurance
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 7 of 16
documentation hereto shall not constitute a waiver of the insurance
requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent
to the respective Department Director (by name), City of Fort Worth,
1000 Throckmorton, Fort Worth, Texas 76102.
f. Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of A:V or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management.
g. Any deductible or self insured retention in excess of $25,000.00 that
would change or alter the requirements herein is subject to approval by
the CITY in writing, if coverage is not provided on a first-dollar basis. The
CITY, at it sole discretion, may consent to alternative coverage
maintained through insurance pools or risk retention groups. Dedicated
financial resources or letters of credit may also be acceptable to the
CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation
in favor of the CITY as respects the PROJECT.
i. The CITY shall be entitled, upon its request and without incurring
expense, to review the ENGINEER's insurance policies including
endorsements thereto and, at the CITY's discretion; the ENGINEER may
be required to provide proof of insurance premium payments.
j. Lines of coverage, other than Professional Liability, underwritten on a
claims-made basis, shall contain a retroactive date coincident with or
prior to the date of the contractual agreement. The certificate of
insurance shall state both the retroactive date and that the coverage is
claims-made.
k. Coverages, whether written on an occurrence or claims-made basis,
shall be maintained without interruption nor restrictive modification or
changes from date of commencement of the PROJECT until final
payment and termination of any coverage required to be maintained after
final payments.
I. The CITY shall not be responsible for the direct payment of any
insurance premiums required by this agreement.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 8 of 16
m. Sub consultants and subcontractors to/of the ENGINEER shall be
required by the ENGINEER to maintain the same or reasonably
equivalent insurance coverage as required for the ENGINEER. When
sub consultants/subcontractors maintain insurance coverage,
ENGINEER shall provide CITY with documentation thereof on a
certificate of insurance.
L. Independent Consultant
The ENGINEER agrees to perform all services as an independent
consultant and not as a subcontractor, agent, or employee of the CITY.
The doctrine of respondeat superior shall not apply.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure
in writing of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing
of any conflicts of interest that develop subsequent to the signing of this
contract and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
k1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities - Design Changes
If permitting authorities require design changes so as to comply with
published design criteria and/or current engineering practice standards
which the ENGINEER should have been aware of at the time this
Agreement was executed, the ENGINEER shall revise plans and
specifications, as required, at its own cost and expense. However, if design
changes are required due to the changes in the permitting authorities'
published design criteria and/or practice standards criteria which are
published after the date of this Agreement which the ENGINEER could not
have been reasonably aware of, the ENGINEER shall notify the CITY of
such changes and an adjustment in compensation will be made through an
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 9 of 16
amendment to this AGREEMENT.
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City-Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of
the information provided by the CITY.
B. Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services. The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of
the CITY's personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses
required by local, state, or federal authorities; and land, easements, rights-
of-way, and access necessary for the ENGINEER's services or PROJECT
construction.
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches,
drawings, specifications, proposals, and other documents; obtain advice of
an attorney, insurance counselor, accountant, auditor, bond and financial
advisors, and other consultants as the CITY deems appropriate; and render
in writing decisions required by the CITY in a timely manner in accordance
with the project schedule prepared in accordance with Attachment D.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 10 of 16
E. Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of
such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos
is a result of ENGINEER's negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto the project.
G. Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of
Article IV.E. regarding the ENGINEER's Personnel at Construction Site, and
provisions providing for contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
H. Contractor Claims and Third-Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering
services performed. Only the CITY will be the beneficiary
of any undertaking by the ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third-party beneficiaries.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 11 of 16
(3) The CITY will include in each agreement it enters into with any other entity
or person regarding the PROJECT a provision that such entity or person
shall have no third-party beneficiary rights under this Agreement.
(4) Nothing contained in this section H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER.
I. CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY will ensure that Builders Risk/Installation insurance is maintained
at the replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3) The CITY will specify that the Builders Risk/Installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of the ENGINEER, this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
K. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for performance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
City of Fort Worth,Texas
Standard Agreement for Engineering Related Desigr So-,,,,es
Revised Date:12.22.2016
Page 12 of 16
receipt of a written Notice to Proceed from the CITY.
B. Reuse of Project Documents
All designs, drawings, specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the final designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God, strikes, lockouts, accidents, or other events beyond
the control of the ENGINEER that prevent ENGINEER's performance of its
obligations hereunder.
D. Termination
(1) a.) This AGREEMENT may be terminated for convenience only by the
City on 30 days' written notice.
b.) This AGREEMENT may be terminated by either the CITY or the
ENGINEER for cause if either party fails substantially to perform
through no fault of the other and the nonperforming party does not
commence correction of such nonperformance within 5 days of
written notice or thereafter fails to diligently complete the correction.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans,
specifications or other forms of ENGINEER'S work product;
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
C.) The time requirements for the ENGINEER'S personnel to document
the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all termination expenses. The
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 13 of 16
CITY'S approval will be obtained in writing prior to proceeding with
termination services.
E. Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER
for the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors,
and ENGINEER's compensation will be made.
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify or hold harmless the CITY against liability
for any damage committed by the ENGINEER or ENGINEER's agent,
consultant under contract, or another entity over which the ENGINEER
exercises control, other than liability for damage to the extent caused
by or resulting from an act of negligence, intentional tort, intellectual
property infringement, or failure to pay a subcontractor or supplier.
CITY is entitled to recover its reasonable attorney's fees in proportion
to the ENGINEER's liability.
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the
prior written consent of the other party.
H. Interpretation
Limitations on liability and indemnities in this AGREEMENT are business
understandings between the parties and shall apply to all the different
theories of recovery, including breach of contract or warranty, tort including
negligence, strict or statutory liability, or any other cause of action, except for
willful misconduct or gross negligence for limitations of liability and sole
negligence for indemnification. Parties mean the CITY and the ENGINEER,
and their officers, employees, agents, and subcontractors.
I. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and performance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
Texas.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 14 of 16
J. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any
reason to be invalid, illegal, or unenforceable in any respect, such invalidity,
illegality, or unenforceability will not affect any other provision, and this
AGREEMENT shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained herein. Articles V.F., VI.B., VI.D., VI.F.,
VI.H., and VI.1. shall survive termination of this AGREEMENT for any cause.
K. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in
any way affect this AGREEMENT and the work hereunder, and shall
observe and comply with all orders, laws ordinances and regulations which
may exist or may be enacted later by governing bodies having jurisdiction or
authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. ENGINEER agrees to defend, indemnify and
hold harmless CITY and all of its officers, agents and employees from and
against all claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
Article VII
Attachments, Schedules and Counterparts
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, which supersedes all prior written or oral understandings, and may only be
changed by a written amendment executed by both parties. This Agreement may be
executed in one or more counterparts and each counterpart shall, for all purposes, be
deemed an original, but all such counterparts shall together constitute but one and the
same instrument. The following attachments and schedules are hereby made a part of
this AGREEMENT:
Attachment A- Scope of Services
Attachment B — Compensation
Attachment C -Amendments to Standard Agreement for Engineering Services
Attachment D - Project Schedule
Attachment E - Location Map
Duly executed by each party's designated representative to be effective on the date
subscribed by the City's designated Assistant City Manager.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:12.22.2016
Page 15 of 16
BY: BY:
CITY OF FORT WORTHENGINEER
L4 RJN Group, 11n ,
Jesus J. Chapa Daniel J ckson, P.E.
Assistant City Manager Vice Pr sident
Date: //, oZ 3-112 Date: Vt 5 -
APPROVAL RECOMMENDED:
By: 1% gr L
Chris Harder. P. E.
Assistant Director, Water Department
Contract Compliance Manager:
By signing I acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including
ensuring all performance and reporting
requirements.
Name of Employee
/Vaial ��o
Walter Norwood
Title: Project Manager
APPROVED AS TO FORM AND LEGALITY
By:
_UVIOL(40"P�
Douglas W. Black
Senior Assistant City Attorney
ATTEST: Form 1295 No. 2017-254624
QRT M&C No. C -28461
M ryJ. K ,y
City Secre aM&C Date: 11/07/2017
U �-
r
City of Fort Worth,Texas ] }SAS OFFICIAL RECORD
Standard Agreement for Engineering Related Desi
Revised Date:12.22.2016 "" CITY SECRETARY
Page 16 of 16
FT.WORTH,TX
ATTACHMENT A
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
ATTACHMENT A
Scope for Engineering Design Related Services for Water and/or Sanitary Sewer
Improvements
DESIGN SERVICES FOR
M-199C-R PARALLEL INTERCEPTORS FOR WEST FORK BASIN
CITY PROJECT NO.: 100836
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
Sanitary sewer main M-199C-R serves portions of west Fort Worth, the Town of White
Settlement and Westworth Village located in the West Fork Basin. M-199C-R is located
along Farmers Brach Creek and the West Fork of the Trinity. The City's Wastewater Master
Plan identified the need for a 30-inch parallel relief line to M-199C-R and M-1998 to address
a system capacity issue in the West Fork Basin. The project limits begin near Waterfalls
Trail and Farmers Brach Creek and ends near the intersection of Oak Forest Drive and
Dennis Avenue in Westworth Village, connecting to the existing 60-inch M-199BR*sewer
main.
WORK TO BE PERFORMED
Task 1. Design Management
Task 2. Conceptual Design
Task 3. Preliminary Design
Task 4. Final Design
Task 5. Bid Phase Services
Task 6. Construction Phase Services
Task 7. ROW/Easement Services
Task 8. Survey and Subsurface Utility Engineering Services
Task 9. Permitting
Task 10. Additional Services
Task 11. Plan Submittal Checklists for Tasks 2, 3, and 4
TASK 1. DESIGN MANAGEMENT.
ENGINEER shall ensure efficient and effective use of ENGINEER's and CITY's time and
resources.
ENGINEER shall manage change,
• Communicate effectively,
■ Coordinate internally and externally as needed, and
■ Proactively address issues with the CITY's Project Manager and others as
necessary to make progress on the work.
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012,Modified August 22,2017
Page 1 of 21
ATTACHMENT
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
ENGINEER shall manage the Team,
■ Lead, manage and direct design team activities
■ Ensure quality control is practiced in performance of the work
■ Communicate internally among team members
■ Task and allocate team resources
1.2. Communications and Reporting
• Attend a pre-design project kickoff/chartering meeting with CITY staff to confirm and
clarify scope, understand CITY objectives, and ensure economical and functional
designs that meet CITY requirements.
• Conduct project review meetings with the City and provide meeting notes during all
design phases (see design task sections for additional information).
• Prepare invoices and submit monthly in the format requested by the CITY.
• Prepare and submit monthly progress reports in the format provided by the Water
Department.
• Prepare and submit baseline Project Schedule initially. Submit monthly Project
Schedule updates with a schedule narrative, as required in Attachment D to this
Standard Agreement and according to the City of Fort Worth's Schedule Guidance
Document.
• Include updated LOE's with percent complete and balance remaining on tasks with
monthly invoicing.
• Complete Monthly M/WBE Report Form and Final Summary Payment Report Form at
the end of the project
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare the
design. A summary transmittal letter shall be submitted to TCEQ for this project.
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs, and make changes necessary to meet
their requirements, as part of the design scope. Engineer shall provide notes from
meetings.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub-consultants shall carry readily visible
information identifying the name of the company and the company representative.
ASSUMPTIONS
• 15 MWBE reports will be prepared
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 2 of 21
ATTACHMENT A
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• 1 meetings with city staff(Pre-design Coordination Meeting)
• 15 monthly water department progress reports will be prepared
• 15 monthly project schedule updates will be prepared
DELIVERABLES
A. Pre-design Coordination Meeting summary with action items
B. Monthly invoices
C. Monthly progress reports
D. Baseline design schedule
E. Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
F. Monthly M/WBE Report Form and Final Summary Payment Report Form
TASK 2. CONCEPTUAL DESIGN (30 PERCENT).
The Conceptual Design shall be submitted to CITY per the approved Project Schedule.
The purpose of the conceptual design is for the ENGINEER to
■ Study the project,
■ Identify and develop alternatives (a minimum of three alternatives required)that
enhance the system,
■ Conduct a Route Study of identified project alternatives,
■ Present(through the defined deliverables) these analyzed alternatives to the CITY
■ Production of a Route Study Technical Memorandum which recommends the
alternatives that successfully addresses the design problem, and
■ Obtain the CITY's endorsement of this concept.
■ Develop Conceptual Design Plan and Profiles of City selected pipeline.
ENGINEER will develop the conceptual design of the infrastructure as follows.
2.1. Data Collection
• In addition to data obtained from the CITY, ENGINEER will research proposed
improvements in conjunction with any other planned future improvements that
may influence the project. ENGINEER shall coordinate with other agencies and
entities as necessary for the design of the proposed infrastructure, and provide
and obtain information needed to prepare the design.
• The ENGINEER will also identify and seek to obtain data for existing conditions
that may impact the project including but not limited to; utilities, agencies (TxDOT
and railroads), City Master Plans, and property ownership as available from the
Tax Assessor's office.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.12014,Modified August 22,2017
Page 3 of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• The data collection efforts will also include conducting special coordination
meetings with affected property owners and businesses as necessary to develop
sewer re-routing plans.
• The ENGINEER shall visit the project site and obtain the meter numbers and sizes
on all existing meters to be replaced on the project and shall identify existing
sample stations and fire line locations.
• The Engineer shall purchase aerial photography of the project area to use in the
development of project design alternatives evaluated in during the production of
the Route Study Technical Memorandum.
2.2. Field Data Services
• The ENGINEER shall complete up to 15 manhole inspections of existing M-199
interceptors utilizing RJN field crews. RJN shall produce a summary report,
including the site inspection forms for each manhole inspection performed.
• The ENGINEER shall utilize collected flow monitoring and rainfall data from two
CITY owned flow meters and one CITY owned rain gauge applicable to this
project area in order to process and analyze the hydraulic data to assist with
capacity designs. The ENGINEER shall perform independent calibrations at each
flow meter site.
2.3. Route Analysis & Conceptual Design Exhibits
• The CITY shall provide the ENGINEER with record drawings associated with the
project area and CITY GIS files available for water, storm, and sanitary sewers.
• The ENGINEER shall obtain (purchase) NCTCOG topography and aerial image
photography.
• Select Field Surveys shall be completed for the Route Analysis by the
ENGINEER's sub consultants to:
i. Set survey control, confirm NCTCOG topography, tie-down existing
manholes on all M-199 pipelines in the study area, and provide levee
boundaries
ii. Phase 1 EA screening (conduct desktop EA) and initial USACE
project coordination (with field visit(s)as necessary), and
iii. Cultural Resources Study
• The ENGINEER shall investigate property ownership in the project area and
identify with a field visual investigation utilities, including the common carrier
natural gas pipeline managed by Williams Engineering, which may impact the
route analysis and study.
• The ENGINEER shall generate GIS and/or CAD exhibits for each route analyzed
2.4. The Design Technical Memorandum Report package shall include the following:
■ Technical Memorandum Cover Sheet
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 4 of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• Graphic exhibits (Task 2.3) and written summary of alternative design
concepts considered, strengths and weaknesses of each, and the
rationale for selecting the recommended design concept.
■ Proposed phasing of any water and sanitary sewer work that is included
in this project documented in both the project schedule and narrative
form.
■ Documentation of key design decisions.
• Estimates of probable construction cost.
2.5. 30% Design Drawings for Selected Route (.dwg files)
• The ENGINEER shall produce 30% Plans for the selected route from Task 2.4
agreed upon with the CITY. 30% Plan shall be generated in AUTOCAD CIVIL
3D. Plans shall include plan and profile drawings to a 1:20 scale based upon
survey completed under Task 2.3 including overlaid aerial photography.
• The ENGINEER's structural sub consultant will provide conceptual level
advisement and cost estimate for structural components
2.6. QA/QC
• The ENGINEER shall conduct appropriate QA/QC measures for the conceptual
design phase.
2.7. Construction Estimate
• The ENGINEER will provide a conceptual construction estimate for the selected
design pipe route.
2.8. Project Update Meetings
• Up to 2 project update meetings will be held with the CITY. The ENGINEER will
provide notes of the meeting to the CITY.
2.9. Design Submittal Review Meeting
• One design submittal meeting will be conducted with the CITY. The ENGINEER
will provide notes of the meeting to the CITY.
ASSUMPTIONS
• 5 copies of the conceptual design package (30% design)will be delivered. The
Design Technical Memorandum (Conceptual Design) Report shall be letter sized
and comb- bound with a clear plastic cover. Drawings will be 01x17) size
fold outs bound in the report
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in Buzzsaw.
• Up to two (2) project coordination meetings may be held with the CITY. After any
project meetings are conducted, the ENGINEER shall prepare and distribute
meeting minutes.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 5 of 21
ATTACHMENT A
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• ENGINEER shall prepare the meeting minutes of the Concept Review meeting
and revise the report, if needed.
• ENGINEER shall not proceed with Preliminary Design activities without obtaining
written approval by the CITY of the Technical Memorandum Report and
Conceptual Design Package.
DELIVERABLES
A. Design Technical Memorandum Report and Conceptual Design (30%)
AUTOCAD CIVIL 3D plans for the selected route
B. Plan Submittal Checklists (See Task 10)
TASK 3. PRELIMINARY DESIGN (60 PERCENT).
Preliminary plans and specifications shall be submitted to CITY per the approved Project
Schedule.
ENGINEER will develop the preliminary design of the infrastructure as follows.
3.1 Development of Preliminary Design Drawings and Specifications shall include the
following:
• Cover Sheet
• A Project Control Sheet, showing all Control Points, used or set while gathering
data. Generally on a scale of not less than 1:400.The following information shall
be indicated for each Control Point: Identified (existing City Monument#8901, PK
Nail, 5/8" Iron Rod);X, Y and Z Coordinates, in an identified coordinate system,
and a referred bearing base. Z coordinate on City Datum only; descriptive location
(i.e. set in the centerline of the inlet in the South curb line of North Side Drive at the
East end of radius at the Southeast comer of North Side Drive and North Main
Street).
• Overall project easement layout sheet(s)with property owner information and a
number for each easement required.
• Overall proiect water and/or sanitary sewer layout sheets. The water layout sheet
shall identify the proposed water main improvement/existing water mains in the
vicinity and all water appurtenances along with pressure plane boundaries, water
tanks, pump stations, valves, and fire hydrants. The sewer layout sheet shall
identify the proposed sewer main improvement/existing sewer mains and all
sewer appurtenances in the vicinity. The lateral and/or main ID numbers with
pipe sizes shall be shown.
• Overall water and/or sanitary sewer abandonment sheet.
• Coordinates on all P.C.'s, P.T.'s, P.I.'s, manholes, valves, mainline fittings, etc.,
in the same coordinate system as the Control Points.
• Bench marks per 1,000 ft of plan/profile sheet—two or more.
• Bearings given on all proposed centerlines, or baselines.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.12014,Modified August 22,2017
Page 6 of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• Station equations relating utilities to paving, when appropriate.
• Plan and profile sheets which show the following: proposed water and/or sanitary
sewer plan/profile and recommended pipe size, fire hydrants, water service lines
and meter boxes, gate valves, isolation valves, manholes, existing meter
numbers and sizes that are to be replaced, existing sample locations, existing fire
line locations, existing utilities and utility easements, and all pertinent information
needed to construct the project. Legal description (Lot Nos., Block Nos., and
Addition Names) along with property ownership shall be provided on the plan
view. The existing profile number or record drawing location and year of
installation shall be referenced/shown on the plans.
• The ENGINEER shall make provisions for reconnecting all identifiable water and/or
wastewater service lines which connect directly to any main being replaced,
including replacement of existing service lines within City right-of-way or utility
easement. When the existing alignment of a water and sanitary sewer main or
lateral is changed, provisions will be made in the final plans and/or specifications
by the ENGINEER to relocate all service lines which are connected to the existing
main and connect said service lines to the relocated main.
• The following shall be applicable at all locations where it is necessary to relocate or
reroute the existing private sanitary sewer service line due to the abandonment or
realignment of the existing public sanitary sewer lateral or main: The CITY shall
fumish the ENGINEER with a sample format of how the sewer service line
reroute/relocation should be designed and submitted for construction. During
design survey, if a rod can be inserted through the cleanout to the bottom of the
service line, the ENGINEER will obtain the flow line elevation and design the
service line prior to advertising the project for bid. If the service flow line
information cannot be obtained during design survey, the ENGINEER shall delay
the design of the sewer service line until after a Quality Level A Subsurface Utility
Engineering (SUE investigation has been performed). The Level A SUE will be
performed; (1) by the ENGINEER if included in the fee proposal; or(2) by the CITY
prior to bidding if the CITY determines that it is needed for satisfactory completion
of the design; or(3) by the Contractor after the project has been bid, by means of a
bid item to that effect. In all options, the ENGINEER shall propose appropriate de-
hole locations in the project and collect flow line elevation and other applicable
information of the sewer service line. The ENGINEER shall use this information to
provide the design for the sanitary sewer service line to be rerouted or relocated.
• ENGINEER shall coordinate with other agencies and entities as necessary for
the design of the proposed infrastructure, and provide and obtain information
needed to prepare the design.
• Provide map showing location of new manhole construction at the end of existing
sewer segments, 90 degree bends, or tee connections. Site survey or specific
design plans for manhole construction is not included as part of the scope. The
contract documents shall specify that it is the Contractor's responsibility to
coordinate utility location, etc. manhole construction.
• The ENGINEER will prepare standard and special detail sheets for water line
installation and sewer rehabilitation or replacement that are not already included in
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 7 of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
the CITY's Standard Specifications. These may include connection details
between various parts of the project, tunneling details, boring and jacking details,
waterline relocations, details unique to the construction of the project, trenchless
details, and special service lateral reconnections.
• The ENGINEER shall provide a detailed cost estimate showing quantity take offs
designated by each sheet of the plans.
3.2. Geotechnical Investigations
• Soil investigations, including field and laboratory tests, borings, related
engineering analysis and recommendations for determining soil conditions will be
made within the project limits as designated by the ENGINEER. In addition to
the above investigations, twelve (12) borings and appropriate field and laboratory
analysis will be made at reasonable intervals along the project alignment for the
Contractor's use in determining soil conditions for preparing bids and a Trench
Safety Plan. Up to six(6) additional geotechnical bores may be required
depending on the final design alternative selected.
3.3. Constructability Review
• Prior to the 60 percent review meeting with the CITY, the ENGINEER shall
schedule and attend a project site visit with the CITY Project Manager and
Construction personnel to walk the project. The ENGINEER shall summarize the
CITY's comments from the field visit and submit this information to the CITY in
writing.
3.4. Public Meeting
• During the preliminary design phase the ENGINEER shall provide project
exhibits and attend a public meeting to help explain the proposed project to
residents. The CITY shall select a suitable location and mail the invitation letters
to the affected customers.
• A list of affected citizens shall be provided to the CITY in an excel file in the
required format listing the following:
o Property Owner and Address
o Business Owner and Address
o Resident Owner and Address
3.5. Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities, private utilities and impacted government agencies (eg:
Westworth Village, USACE/TRWD, NAS Joint Reserve Base Fort Worth)to
determine the approximate location of above and underground utilities, and other
facilities (current and future)that have an impact or influence on the project.
ENGINEER will design CITY facilities to avoid or minimize conflicts with existing
utilities, and where known and possible consider potential future utilities in
designs.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 8 of 21
ATTACHMENT
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• The ENGINEER shall upload individual DWF and/or files for each plan sheet of the
approved preliminary plan set to the designated project folder in Buzzsaw for
forwarding to all utility companies which have facilities within the limits of the
project. The DWF files should be created directly from the CAD files as opposed
to PDF files.
3.6. Traffic Control Plan
• Develop a traffic control plan utilizing standard traffic reroute configurations
posted as "typical details" on the CITY's Buzzsaw website. The typical details
need not be sealed individually, if included in the sealed contract documents.
• Develop supplemental traffic control drawings as needed for review and approval
by the Traffic Division of the Transportation and Public Works Department.
These drawings shall be sealed by a professional engineer registered in the
State of Texas.
3.7. Construction Estimate
• The ENGINEER will provide a preliminary design construction estimate for the
selected design pipe route.
3.8. QA/QC
• The ENGINEER shall conduct appropriate QA/QC measures for the preliminary
design phase.
3.9. Project Update Meetings
Up to 2 project update meetings will be held with the CITY. The ENGINEER will
provide notes of the meeting to the CITY.
3.10. Design Submittal Review Meeting
• One design submittal meeting will be conducted with the CITY. The ENGINEER
will provide notes of the meeting, including action items, to the CITY.
ASSUMPTIONS
• 1 public meeting(s)will be conducted or attended during the preliminary
design phase.
• 18 Geotechnical borings are expected for this project. The ENGINEER has
included 12 geotechnical bores with an average bore depth of 25 feet each to
be obtained during Preliminary Design Phase and those costs are included in the
preliminary design budget.
• Traffic Control "typical details"will be utilized to the extent possible. It is assumed
an additional 1 project specific traffic control sheets will need to be
developed for any pipeline alignment utilizing public right of way (ROW) in
Westworth Village or Fort Worth.
• 5 sets of 11x17 size plans will be delivered for the Constructability
Review.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 9 of 21
ATTACHMENT A
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• 5 sets of 11x17 I size plans will be delivered for the Preliminary Design
(60% design).
• 2 sets of specifications will be delivered for the Preliminary Design (60%
design).
• DWF and/or PDF files created from design CAD drawings will be uploaded to the
designated project folder in Buzzsaw.
• The CITY's front end and technical specifications will be used. The ENGINEER
shall supplement the technical specifications, 4 as needed.
• Preliminary design (60% plans) DWF and/or PDF drawings will be delivered for
Utility Clearance and posted on Buzzsaw.
• ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Preliminary Design plans.
DELIVERABLES
A. Preliminary Design drawings and specifications
B. Utility Clearance drawings
C. Traffic Control Plan
D. Storm Water Pollution Prevention Plan
E. Estimates of probable construction cost
F. Data Base listing names and addresses of owner/residents and businesses
affected by the project.
G. Plan Submittal Checklists (See Task 10)
TASK 4. FINAL DESIGN (90 PERCENT)AND FINAL CONSTRUCTION DOCUMENTS
(100 PERCENT).
Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as
follows:
• For projects that disturb an area greater than one (1)acre, the Contractor will be
responsible for preparing and submitting the Storm Water Pollution Prevention Plan
(SWPPP)with appropriate regulatory agencies. The Engineer will prepare the iSWM
Construction Plan according to the current CITY iSWM Criteria Manual for Site
Development and Construction which will be incorporated into the SWPPP by the
contractor.
• ENGINEER shall coordinate with other agencies and entities as necessary for the
design of the proposed infrastructure, and provide and obtain information needed to
prepare the design.
• Draft Final plans (90%) and specifications shall be submitted to CITY per the approved
Project Schedule.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.12014,Modified August 22,2017
Page 10 of 21
ATTACHMENT
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• Following a 90% construction plan review meeting with the CITY, the ENGINEER shall
submit Construction Documents (100%)to the CITY per the approved Project Schedule.
Each plan sheet shall be stamped, dated, and signed by the ENGINEER registered in
State of Texas.
• The ENGINEER shall submit a final design estimate of probable construction cost with
both the 90% and 100% design packages.Whenever feasible, this estimate shall use
ONLY standard CITY bid items.
• A project summary letter shall be submitted to TCEQ describing this project and seeking
TCEQ's interest in receiving a formal review submittal of the pre-final design (90%) plans
and specifications.
ASSUMPTIONS
• 2 sets of full size drawings and 2 specifications will be delivered for the
90% Design package.
• A DWF and/or PDF file for the 90% Design will be created from design CAD drawings
and will be uploaded to the project folder in Buzzsaw.
• Up to one Project Update Meeting is included in this Task.
• ENGINEER to provide estimated final sheet list(cover/index, general notes, control point
location, easement layout, SUE plan sheets, no. of plan/profiles, special detail sheets,
etc.)
• 2 sets of full size drawings and 2 specifications will be delivered for
the 100% Design package.
• A DWF and/or PDF file for the 100% Design will be created from design CAD drawings
and will be uploaded to the project folder in Buzzsaw.
DELIVERABLES
A. 90% construction plans and specifications.
B. Submit project summary letter to TCEQ.
C. 100% construction plans and specifications.
D. Detailed estimates of probable construction costs including summaries of bid items and
quantities using the CITY's standard bid items and format.
E. Original cover mylar for the signatures of authorized CITY officials.
F. Plan Submittal Checklists (See Task 10)
TASK 5. BID PHASE SERVICES.
ENGINEER will support the bid phase of the project as follows.
5.1. Bid Support
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 11 of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• The ENGINEER shall upload all plans and contract documents onto Buzzsaw for
access to potential bidders.
• Contract documents shall be uploaded in a .PDF file.
• Unit Price Proposal documents are to be created utilizing CFW Bidtools only
and combined in a specified spreadsheet workbook, Bid Proposal Worksheet
Template, and will be populated and configured so that all pages are
complete and the Summary Worksheet(s) in the workbook detail and
automatically summarize the totals from the inserted Unit Price Proposal
document worksheets.
• Plan Sets are to be uploaded to Buzzsaw in two formats, .pdf and AM files.
The .pdf will consist of one file of the entire plan set. The Awf will consist of
individual files, one for each plan sheet, and will be numbered and named in
a manner similar to that of the plan set index.
• The ENGINEER shall sell contract documents and maintain a plan holders list on
Buzzsaw from documents sold and from Contractor's uploaded Plan Holder
Registrations in Buzzsaw.
• The ENGINEER will develop and implement procedures for receiving and
answering bidders' questions and requests for additional information. The
procedures shall include a log of all significant bidders questions and requests
and the response thereto. The log shall be housed and maintained in the
project's Buzzsaw folder titled Request for Information. The ENGINEER will
provide technical interpretation of the contract bid documents and will prepare
proposed responses to all bidder's questions and requests, in the form of
addenda. The ENGINEER shall upload all approved addenda onto Buzzsaw and
mail addenda to all plan holders.
• Attend the pre-bid conference in support of the CITY.
• Assist the CITY in determining the qualifications and acceptability of prospective
contractors, subcontractors, and suppliers.
• When substitution prior to award of contracts is allowed in the contract
documents, the ENGINEER will advise the CITY as to the acceptability of
alternate materials and equipment proposed by bidders.
• Attend the bid opening in support of the CITY.
• Tabulate and review all bids received for the construction project, assist the CITY
in evaluating bids, and recommend award of the contract. A copy of the Bid
Tabulation and the CFW Data Spreadsheet created utilizing CFW Bidtools only
are to be uploaded into the project's Bid Results folder on Buzzsaw.
• Incorporate all addenda into the contract documents and issue conformed sets.
5.2 Final Design Drawings
1) Final Design Drawings shall be submitted in both Adobe Acrobat PDF format
(version 6.0 or higher)format and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 12 of 21
ATTACHMENT
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
the Water plan set. Each PDF and DWF file shall be created from the original
CAD drawing files and shall contain all associated sheets of the particular plan
set. Singular PDF and DWF files for each sheet of a plan set will not be
accepted. PDF and DWF files shall conform to naming conventions as follows:
I. TPW file name example — "W-1956-0rg47.pdf" where "W-1956" is the
assigned file number obtained from the CITY, "—org" designating the file is
of an original plan set, "47" shall be the total number of sheets in this file.
Example: W-0053_org3.pdf and K-0320 org5.pdf
II. Water and Sewer file name example — "X-35667_org36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_org"
designating the file is of an original plan set, "36"shall be the total number of
sheets in this file.
Example: X-12755—org18.pdf
Both PDF and DWF files shall be uploaded to the project's Final Drawing folder in
Buzzsaw.
2) In addition to the PDF and DWF files, the ENGINEER shall submit each plan sheet
as an individual DWG file with all reference files integrated into the sheet. If the plans
were prepared in DGN format, they shall be converted to DWG prior to uploading.
The naming convention to be used for the DWG files shall be as follows:
I. TPW files shall use the W number as for PDF and DWF files, but shall
include the sheet number in the name — "W-1956—SHT01.dwg", "W-
1956—SHT02.dwg", etc.
II. Water and Sewer file names shall use the X number as for PDF and
DWF files, but shall include the sheet number in the name — "X-
12155_SHT01.dwgn, "X-12755—SHT02.dwg", etc.
For information on the proper manner to submit files and to obtain a file number for
the project, contact the Department of Transportation and Public Works Vault at
telephone number(817) 392-8426. File numbers will not be issued to a project
unless the appropriate project numbers and fund codes have been assigned and
are in the Department of Transportation and Public Works database.
ASSUMPTIONS
• The project will be bid only once and awarded to one contractor.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 13 of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C•R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• 18 sets of construction documents will be sold to and made available on
Buzzsaw for plan holders and/or given to plan viewing rooms.
• 8 sets of full size and 6 sets of 11x17 size drawings plans and
8 specifications (conformed, if applicable)will be delivered to the CITY.
• PDF, DWF and DWG files will be uploaded to Buzzsaw.
DELIVERABLES
A. Addenda
B. Bid tabulations
C. CFW Data Spreadsheet
D. Recommendation of award
E. Construction documents (conformed, if applicable)
TASK 6. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
6.1 Construction Support
• The ENGINEER shall attend the preconstruction conference.
• After the pre-construction conference, the ENGINEER shall provide project
exhibits and attend public meeting to help explain the proposed project to
residents. The CITY shall select a suitable location and mail the invitation letters
to the affected customers.
• The ENGINEER shall visit the project site at requested intervals as construction
proceeds to observe and report on progress.
• As requested by the CITY, the ENGINEER shall provide necessary interpretations
and clarifications of contract documents, review change orders, and make
recommendations as to the acceptability of the work.
The ENGINEER shall attend the "Final' project walk through and assist with preparation of
final punch list
6.2 Record Drawings
• The ENGINEER shall prepare Record Drawings from information provided by
the CITY depicting any changes made to the Final Drawings during construction.
The following information shall be provided by the CITY:
As-Built Survey
Red-Line Markups from Contractor
o Red-Line Markups from City Inspector
o Copies of Approved Change Orders
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 14 of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
o Approved Substitutions
• The ENGINEER shall modify the Final Drawings electronically and shall place a
stamp on the plans indicating that they represent Record Drawings of the project
as constructed. The stamp shall be signed and dated by the ENGINEER and
shall be placed on each plan sheet,whether there are any revisions on the sheet
or not. Each sheet shall clearly indicate all changes which apply to that sheet by
clouding and numbering, or other suitable means.
• The following disclaimer shall be included with the Record Drawing stamp:
o These Record Drawings were prepared using information provided by
others and represent the as constructed conditions to the extent that
documented changes were provided for recording. The ENGINEER
assumes no liability for undocumented changes and certifies only that the
documented changes are accurately depicted on these drawings.
• The ENGINEER shall submit a set of sealed Final Drawings, modified and
stamped as Record Drawings, on mylar for record storage. The ENGINEER may
keep copies of the information provided by the CITY for their files, but all original
red-lined drawings shall be returned to the CITY with the mylars.
2) Record Drawings shall also be submitted in both Adobe Acrobat PDF format
(version 6.0 or higher)format and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for
the Water plan set. Each PDF and DWF file shall contain all associated sheets
of the particular plan set. Singular PDF and DWF files for each sheet of a
plan set will not be accepted. PDF and DWF files shall conform to naming
conventions as follows:
I. TPW file name example — "W-1956_rec47.pdf' where "W-1956" is the
assigned file number obtained from the CITY, "_rec"designating the file is of
a record drawing plan set, "47" shall be the total number of sheets in this file.
Example: W-0053—rec3.pdf and K-0320—org5.pdf
II. Water and Sewer file name example — "X-35667_rec36.pdf' where "X-
35667" is the assigned file number obtained from the CITY, "_rec"
designating the file is of a record drawing plan set, "36" shall be the total
number of sheets in this file.
Example: X-12755_rec18.pdf
Both PDF and DWF files shall be uploaded to the project's Record Drawings folder
in l u:zzsa
ASSUMPTIONS
• 20 RFI's and Submittals are assumed.
cease Date:08.1.2014,Modified August 122 2017
of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CRY PROJECT NO.:100836
• 1 Change Orders are assumed
• One copy of full size (22"x34") mylars will be delivered to the CITY.
DELIVERABLES
A. Public meeting exhibits
B. Response to Contractor's Request for Information
C. Review of Change Orders
D. Review of shop drawings
E. Final Punch List items
F. Record Drawings on Mylar
TASK 7. ROW/EASEMENT SERVICES.
ENGINEER will support and perform activities related to ROW and land as outlined below,
per scoping direction and guidance from the CITY's Project Manager.
7.1. Right-of-Way Research
The ENGINEER shall determine rights-of-way, easements needs for construction of the
project. Required temporary and permanent easements will be identified based on
available information and recommendations will be made for approval by the CITY.
7.2. Right-of-Way/Easement Preparation and Submittal.
• The ENGINEER shall prepare documents to be used to obtain right-of-way and
permanent and/or temporary easements required to construct the improvements.
• The ENGINEER shall submit the right-of-way and/or easement documents to CITY PM
for real property acquisition
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's Buzzsaw site.
ASSUMPTIONS
• 20 Easements or right-of-way documents will be necessary.
• Right-of-Way research and mapping includes review of property/right-of-way records
based on current internet based Tarrant Appraisal District(TAD) information available at
the start of the project and available on-ground property information (i.e. iron rods,
fences, stakes, etc.). It does not include effort for chain of title research, parent track
research, additional research for easements not included in the TAD, right-of-way
takings, easement vacations and abandonments, right-of-way vacations, and street
closures.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 16 of 21
ATTACHMENT A
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
DELIVERABLES
A. Project Parcel/Right of Way Map
B. Easement exhibits and meets and bounds provided on CITY forms.
TASK 8. SURVEY AND SUBSURFACE UTILITY ENGINEERING SERVICES.
ENGINEER will provide survey support as follows.
8.1. Design Survey
• ENGINEER will perform field surveys to collect horizontal and vertical elevations and
other information needed by ENGINEER in design and preparation of plans for the
project. Information gathered during the survey shall include topographic data,
elevations of all sanitary and adjacent storm sewers, rim/invert elevations, location of
buried utilities, structures, trees (measure caliper, identify overall canopy, and have
qualified arborist identify species of trees), and other features relevant to the final plan
sheets. Existing drainage at intersections will be verified by field surveys. Spot
elevations will be shown on intersection layouts with cross slope to fit intersecting grade
lines.
• Due to the complexities of the developing design alternatives and selecting a final
alignment and design plans, the ENGINEER has budgeted funds for limited surveying
support during the project route study and conceptual design phase and then a total of
13,000 LF of topographic survey to be used for design. All survey above and beyond this
amount will require additional funding to be authorized in the form of an amendment.
• The minimum survey information to be provided on the plans shall include the following:
A Project Control Sheet, showing ALL Control Points, used or set while gathering
data. Generally on a scale of not less than 1:400:
— The following information about each Control Point;
a. Identified (Existing. CITY Monument#8901, PK Nail, 5/8" Iron Rod)
b. X,Y and Z Coordinates, in an identified coordinate system, and a referred bearing base.
Z coordinate on CITY Datum only.
c. Descriptive Location (Ex. Set in the centerline of the inlet in the South curb line of North
Side Drive at the East end of radius at the Southeast corner of North Side Drive
and North Main Street).
— Coordinates on all P.C.'s, P.T.'s, P.I.'s, Manholes, Valves, etc., in the same
coordinate system, as the Control.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 17 of 21
ATTACHMENT A
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
No less than two horizontal bench marks, per line or location.
Bearings given on all proposed centerlines, or baselines.
Station equations relating utilities to paving,when appropriate.
8.2. Temporary Right of Entry Preparation and Submittal
• Prior to entering any property, the ENGINEER shall prepare and submit a Temporary
Right of Entry letter to CITY PM for signature for coordinating site access with
landowners. This letter shall be presented to property owners by the ENGINEER and its
Sub-consultants prior to attempting to enter a property.
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's Buzzsaw site.
8.3. Subsurface Utility Engineering (SUE)
• Level A SUE for two (2) potholes; Level B SUE of a single (1) crossing of known utility
corridors or street intersection and associated sub-centimeter accuracy survey are
included in this subtask. The ENGINEER's sub consultant will complete work for this
task as directed by the ENGINEER at locations agreed upon between the ENGINEER
and the CITY. All SUE survey above and beyond this amount will require additional
funding to be authorized in the form of an amendment.
ASSUMPTIONS
Topographic survey at intersection will include no more than 100 ft. in each direction.
DELIVERABLES
A. Copies of field survey data and notes signed and sealed by a licensed surveyor.
B. Drawing of the project layout with dimensions and coordinate list.
C. Temporary Right Of Entry Letter from City authorizing project surveying
TASK 9. PERMITTING ENGINEERING SERVICES.
ENGINEER will provide permitting support as follows.
9.1. SWPPP
• For projects that disturb an area greater than one (1) acre, the Contractor will be
responsible for preparing and submitting the Storm Water Pollution Prevention Plan
(SWPPP)with appropriate regulatory agencies. The Engineer will prepare the iSWM
Construction Plan according to the current CITY iSWM Criteria Manual for Site
Development and Construction which will be incorporated into the SWPPP by the
contractor.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 18 of 21
ATTACHMENT A
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
9.2. Floodplain Services
• The ENGINEER will obtain applicable floodplain boundary geospatial data from FEMA to
implement into conceptual, preliminary, and final plans. The project shall be designed in
accordance with TCEQ regulations on construction in flood plain where applicable.
9.3. TOOT Permitting
The ENGINEER will assist the CITY will required exhibits and project data for TOOT
permitting. The ENGINEER shall fill out up to one (1) draft TOOT permit application
form for the CITY to review and SUBMIT to TOOT.
9.4. Gas Main Crossing Permit
The ENGINEER will coordinate efforts for up to two (2)gas main encroachments or
crossings with the appropriate entities, including submitting deliverables to such entities
and filling out encroachment requests on behalf of the CITY.
9.5. TRWD &City of Fort Worth Parks Conversion
The ENGINEER will assist the CITY with pre-permit park conversion services, if required
by the selected project design alignment. Formal permitting processes for park conversions
will require additional funding to be authorized in the form of an amendment.
TASK 10. PLAN SUBMITTAL CHECKLISTS
Engineer shall complete and submit Plan Submittal Checklists in accordance with the
following table:
PLAN SUBMITTAL CHECKLIST REQUIREMENTS
Traffic Traffic Traffic
Traffic Street Water Traffic Control Control Control
90 60/° /0 /o
Attachment°A° Signal Storm Storm Lights /Sewer Engineering 30
Water Water (Submit (Submit
Type (Submit All 30% 60% All @ All @ (Submit All
@ 30%) 30% 60%) @ 60%} Required for all work in City
ROW
Street X X X X X' X X X X
Storm Water X X X X X
Water/Sewer X X X X
*If included in street project
City of Fort Worth,
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 19 of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
ASSUMPTIONS
N/A
DELIVERABLES
A. N/A
B. N/A
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existinq Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services described in
the tasks above. However, ENGINEER can provide these services, if needed, upon the
CITY's written request. Any additional amounts paid to the ENGINEER as a result of any
material change to the Scope of the Project shall be agreed upon in writing by both parties
before the services are performed. These additional services include the following:
• Negotiation of easements or property acquisition, including temporary right-of-
entries.
• Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre-qualification, bid protests, bid rejection and re-
bidding of the contract for construction.
• Construction management and inspection services
• Periodic site visits during construction phase
Additional project coordination and review meetings or extra public meetings
Additional reproduction/printing costs beyond the budget/quantities specified in this
document.
• Performance of materials testing or specialty testing services.
Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of God.
• Services related to warranty claims, enforcement and inspection after final
completion.
Services related to permit submittals (ie, NWP, USACE (Section 404/408), railroad,
etc...). No environmental permitting services have been included in this contract
and may be needed.
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 20 of 21
ATTACHMENTA
DESIGN SERVICES FOR
M199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN
CITY PROJECT NO.:100836
• Services related to Survey Construction Staking.
• Services related to acquiring real property including but not limited to easements,
right-of-way, and/or temporary right-of-entries.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Construction Shop drawing review, samples and other submittals submitted by the
contractor.
Performance of miscellaneous and supplemental undefined services related to the
project as requested by the CITY(City Directed Services).
City of Fort Worth,Texas
Attachment A
PMO Release Date:08.1.2014,Modified August 22,2017
Page 21 of 21
ATTACHMENT B
COMPENSATION
Design Services for
M-199C-R PARALLEL INTERCEPTORS FOR WEST FORK BASIN
City Project No. 100836
Lump Sum Project
I. Compensation
A. The ENGINEER shall be compensated a total lump sum fee of $525,000.00 as
summarized in Exhibit B-1 — Engineer Invoice and Section IV—Summary of Total
Project Fees. The total lump sum fee shall be considered full compensation for
the services described in Attachment A, including all labor materials, supplies,
and equipment necessary to deliver the services.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. Partial payment shall be made to the ENGINEER monthly upon City's approval of
an invoice prepared and submitted by the ENGINEER in the format and including
content as presented in Exhibit B-1, Progress Reports as required in Item III, of
this Attachment B, and Schedule as required in Attachment D to this Agreement.
B. The estimated current physical percent complete as required on the invoice shall
be calculated from the progress schedule as required in Attachment D to this
Standard Agreement and according to the current version of the City of Fort
Worth's Schedule Guidance Document.
C. The cumulative sum of such monthly partial fee payments shall not exceed the
total current project budget including all approved Amendments.
D. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Water Department monthly progress reports and schedules in the format
required by the City.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.092012
Page 1 of 3
B-1
ATTACHMENT B
COMPENSATION
IV. Summary of Total Project Fees
Fee Amount Percent %
Firm rr
m�ari ;
Responsibility
Prime Consultant
RJN Group, Inc. Design $356,606.00 67.92
Proposed MBE/SBE Sub-Consultants
Gorrondona & Survey, Easements and $123,044.00 23.44
Associates, Inc. Geotechnical Services
Symonds Ecology, Ltd. Environmental Services $8,000.00 1.52
— Regulatory Screening
Jakan Engineering, PLLC Structural and Civil $30,000.00 5.71
Design Services
The Rios Group Subsurface Utility $7,350.00 1.40
Engineering (SUE)
Services
Non-MBE/SBE Consultants
TOTAL $525,000.00 100%
`" reject Number& Nam""e Total Fee $ MBEISF' , W$ MBEISBE %
City Project Number 100836:
M-199C-R Parallel Interceptors For $ 525,000.00 $ 168,394.00 32 %
West Fork Basin
City MBE/SBE Goal = 10 %
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 2 of 3
B-2
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert.required invoice format following this page, including negotiated total budget and
allocations of budgets across work types and work phases.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 3 of 3
B-3
Professional Services Payment Request Project Manager: Walter Norwood Summary ttacx
Project: M-199C-R PARALLEL INTERCEPTORS FOR WEST FORK BASIN I uNut-CK
City Project#: 100836
City Sec Number: C-XXXXX Consultant Instructions:
FIN In green cells including involve Number,From and To Dates and the Included worksheets.
Company Name: RJ N GROUP,INC. When your Invoice Is complete,save and close,start Buaaeaw and Add your Invoice to the
Consultant folder within Project's folder.
Consultant's PM: Chris Brooks,P.E. email: cbrook5@rinmail.com
Vendor Invoice 0:
Offce Address:6701 Brentwood Stair Road,Suite 100W,Fart Worth,Texas 76112
Payment Request#: Telephone: (817)4513500,Ext.21
From Date: Fax: (817)451-3506
To Date:
Invoice Date: Remit Address:RJN Group,Inc.,200 W.Front Street,Wheaton,IL 60187 or Send Electronic Payments
First Midwest Bank Routing Number 071901604;Account Number 8100217309
Agreement
Agreement Amendment Amount to Completed Percent ($)Invoiced Current Remaining
Sheet FAC and Work Type Description Amount Amount Date Amount Completed Previously Invoice Balance
Work Type SEWER $525,00000 $525,000.DC $525,000.00
Work Type 2
Work Type 9
Work Type 4
Work Type 5
Work Type 8
Totals This Payment Request s525,000.00 $525.000.00 $525000.00
Overall Percentage Complete:
Professional Services Payment Request Prn)ect Muugar We N—w
Project: M-199C-R PARALLEL INTERCEPTORS FOR N
City Project 0: 100836
Work Type Desc: Sewer Conaueentmet�„adnn+:
F/A/C:
City Sec Number: C-xxxxx FIN In g—mil,InchMlng P—e,,t Complete and lr-o P—wb Iy ownul.s
Purchase Order: When your Irw"Is complete.save end cbse,snn a....and Add rour M—I-Io Iue
Conauemt}elder W.P.J—s Wdar.
Company Name: RJN GROUP,INr:,
Consultants PM: Chas woes,P.e. email: unrooas®rynmel—
VendorInvolce0: Office Address: 8701 ere and SMIr Road,Sues 1m .Fort wad,.Teas let12
Payment Request R: Telephone: (817)451-850x.rBrt.21
From Date: Fax: (817)a 1.1606
To Date:
invoice bate: Remit Address: RJN Group,Im.,zoo W.Front Sumt,Wl—a It.W167 or sena
Pay Items Agreement
Agreement Amendment Amendment Amountto Completed Percent ISj Invoiced Current Remaining
Oescnption Amount Number Amount Date Amount Completed Previously Invoice Balance
30-Design j525,Opg.00 5525.0011.. $525,gW W
Totals This Unit: s52s e0000 ss2s.000.m s'2,—2Q
Overall Percentage Complete:
Level of Effort Spreadsheet
TASK/HOUR BREAKDOWN
Design Services for
M-199C-R Parallel Interceptor For West Fork Basin
City Pro'ect No.100836
Labor hours
Task b-a iption Project Project Project Data Field Fi*d TOUT Labor Se Total Expense
Tesk No. ec- E EIT CARD Atlminlstrative .pager Technician Cast SUDcalsulUM nTraval Reprotluc0an Cast Task SUB Total %CelnploWtl SBemelnln8
r 5245 na32tS ;155 115 40.5 A std F,n 5 rvis8 M MWBE Non-MWBE
IA -j-Management 0 42 0 14 0 o 0 S13,2a8 so W 50 W SO 513,220
1.2.1 Pre-0eslgn Dvortllretlon Mee'Ing o 2 1 2 C 10 0 0 0 5015 $o $815
Prepare B-11-Schedule 0 8 11 0 0 52.955 _ $0 $2,955
125 Prepare Monrhly"mgfess Repvrta wrn o 24 0 01 0 0 0 0
sehadwa ss,10o $D as,lso
13.6 Preparo Mo,tlhly MBE/59E Reports 0 0 '9 0 C $4,295 $0 $4298
a0....Conceptual Design(308erceM) 3 90 79 154 208 3 a 12 9 12 $76,090 Sa.,$00 so $1,000 $2.315 $23,815 $100,713
Data Conec'lon
14 12 15 6 0 0 0 0 Ei,349. 816,500 5]50 5'790 519,040 326,380
22 RG acenad by Ne DOFW)515. 1 - 0 6 12 9 12 $1,09] $11v $250 $7,347
Route Anzysis&Conp.Mual Cba9n E ,bits 0 16 40 60 100 0 0 .427,o40 $a 52],040
Design-.eehnleal Memorandum 0 B 16 6 0 0 0 0 Cj $5,020 $525 5525 $5,645
25 Des.gr Drawinga br Selected RodU D 40 B 32 96 0 0 0 523,]71 $4,000 $400(1 $2]171
2 C -C 20 0 0 0 51,350 $0 __51,350
27 Cm-...U-Fatimale 6 4 4 4 0 0 0 0 0 0 51.940 so $1,940
1-1 ;2 us-d1 C 6 5 4 0 0 0 0 0 32525 EO_ 52525
2& nesi5n 6<b-Ittal Pe.erery Mseting 0 1 2 0 0 0 0 5815 SO 58'16
3.0 Pr.-...y De Ig 160 Percent) 7 105 135 102 350 e o 0 o 0 5101,331 $4a,MI f0 So $5a5 543,018 S145,150
31 Preli'inary Deslgn Orawbl�z 0urcludes 2: 00 343 6 0 0 0 0 $14,881 $17,C00 $525 $17,525 $92.188
s,vc uta eng,necrng sunvr _
Gevtaohniczllnvesllgativns A 65 2 V 0 0 C 0 0 0 E1 970 $26,294 $26294 528,264
33 Cprlslruclabillry Review 0 0 0 0 U 0 $1,225 SII $1,226
anng o a J 6 $2oao $c $;c3D
I Pwn„Ma a o c c v
3.: Uillry Cearance C B 20 40 0 0 0 Il 0 E9,42J $D Bd42o
0
35 TrafficC,-I Pear a 6 5 6 10 _ 0 0 9 0 0 $3,9.1 $o $3,mo
37 �nstrudion estimate 0 3 4 o 0 o 0 0 0 $2035 $a 52,036
3.6 .1- 0 a 0 o 0 0 $1.720 $0 $1,720
Dro'eN L' ate Meetln alt sasumetll D 5 fi 6 0 0 0 J 0 0 x340 EO 83,340
3.10 0 2 2 0 0 p 0 $970 FO $970
40 F nal Design 2 04 et 03 147 20 0 0 D 0 553,983 59,000 EO 30 ;SaS f9,528 183,518
4, E1nal Qrah(90%J ConsVuolivn Plans an0 C' 33 49 10 11 '.6 0 0 $30,212 $6,000 5263 $fi,.a ;36475
Specifi-w.
42 Final(100%)Plarm and Spevifisallons 2. 1s' 20 35 55 6 0 0 0 0 $1],351 5263 $253 b1T,611
4.3 f=inal!100%1%arm56peci0mtiona!subs) A o o 0 0 b 0 $9,880 53,000 $3.o00 54.690
J< ggrqq 0 8 0 D J 0 0 0 0 $em $0 ;660
4.5 on EsBma!es(v0°F,ard',00'F) o 2 o 0 0 $5,395 51345
nose,co J 0 0 z'0
P-cloct J:Na'a Meatnes j'.assumed! A 9 0 0 0 0 D 0 51,515 $0 $1,515
4.7 Deslgn�ubmiCal Rev'ew MesLng 0 2 2 2 W. $0 f9]0
$o B,d Phase 0 18 1 22 12 0 0 0 0 0 58,018 SO SO 30 5655 565$ S9,BT1
5^1 Contract Dxumen'a an0 ManUin Plan 9 B 4
ioloara L:aI $2160 ED
Ct1y of FCR Wonh,Texas
AttacOmen!a 1awl Ef 66pplemerrt
PMO OXicial ReleaseDale'.8092012.MODIFIED August Yl,2011 1 or'e
Level of Effort Spreadsheet
TASKIHOUR BREAKDOWN
Design Services for
M-199C.R Parallel Interceptor For West Fork Basin
City Pr act No.100896
Labor hoarn Ea
TaaM No. Task Oeacrlp6on Project Pr¢jec[ Protect En ADD AtlmiMatrafEve Date Fieltl Manger Field Field —I Isboi sabcansurteM ae F.� T—Sub T—I %C'anp- S Remainfr0
Director E Mal m Su Technician Co61 Tiaval RaprlducYion teiCoal
$245 Maw$215 n$10 115 C Mwe6 n-MwBF
5 t.3 ACand�reLitl Cor'erence 0 20 0 0 D 0 0 0 0 $430 $0 3430
51 4 A[tend Bid I A20
0 0 5430 f0 5450
51.5 Tabulxe Bqe and ReaommaM AwaM 0 2 o 4 0 0 0 c D saw 30 3350
5.1.9 laaee Cori(Prmed Co[Xrect Oocumenls 0 4 14 B 9 0 C 0 $5399 $6i5 $656 55,?4t
�....
6.0 Cbrasbuc0¢n Phase Services o 37 ]A 5/ 0 o 0 0 0 $2,155 So to t0 3525 5525 $22,5&06.1,1 tend PmcenstrucGen Conlemnce 0 1 2 0 0 0 0 0 $756 9'0 $?5b
6.12 ArtsrM PUWic Mee9n41Preconsiruclion) 0 2 2 0 0 $7aG Sc 5740
8'3 P.o�ecf Slfe Marta 0 10 10 B 0 C 0 C 0 J f4,6:0 50 K.0
6.'.4 B�bmT.al Review 0 12 16 24 0 0 o 0 0 o $7,820 so $7.820
6.1.5 mlmxi¢r 0 4 6 0 0 5R1R1 iC $2,170
6r fi Final Walk Tnro nand nancn Llsl 0 4 0 4 0 G 0 L 0 0 $1,310 SE 51,320
52 ecord Drawings 04 1 20 14130 $525 $F2E 55,255
70 ROWIFacemenf serNcea 0 8 10 26 4 o 0 0 u 0 $6,910 m'.o 30 M 30 32o.o. S26,-
7 Researcn 0 $26,.a I SE 52,620
].! 4 4 B 4 0 1 1
72 R',gh-ol-WaylEasemert Preparat on aro o 6 3 C 54:Jc3 $20.[0[ 524090
8.0 Surve 0 10 5 13 10 0 0 0 01 0 65,4To $75,9o0i 30 534 f0 fT5,834 f6Y,lod
B' Design burve 0 6 4B 9' 1 53,670 EEA260 37",.920
82 Tem1 R19ht cl Entry 8,1m11 o 2 $669 50 5860
8.3 SUMuhace Jtllrty E,,—ring(SI.EI 0 2 12 2 o o D 0 0 31140 57,150 E $7,514 56524
0.0 Perm1[bn9 o 16 2$ 42 24 4 0 o 0 0 115,166 so 30 f0 f0 $0 316,18&
BWPFF 0 4 '6 12 0 D $5,568 $o $5.668
3.2 9—'1ain 5ercices o 4 6 6 2 $2920 $D $2.9211
93 iMOt oortnitting 0 2 4 11
51,430 So 31,920
9.4 Gaa M.M Droasing�ermXS(2 a5sumetl) 0 2 6 l2 4 0 0 0 $9,160 $0 so in
TRW D 6 City of Fort WOM Parka
B.5 Conversion(pre-permit services anly)tt 0 4 2 1 2o o $1,610 SO 31&10
enf needed
10A city Directed 8arvluea o 0 0 o 6 0 0 0 0 0 s0 so soSo fo
$3,066 390,000
101 city Olrected Service 4 0 o I 0 o 0 s0 s0 EO $36,000 s30.wo
T.W. 12 398 $65 ST2 T/6 56 5 12 9 12 $$04,167 3166,8 50 II $4,545 $175,974 $106,161
RoJ«1 Summary
247
,it Labor 5304,9187
Eapenaa 5173.74
491191E 1-1
51 GB 380
or.-Mt3EM1JL Su[tionsrltanl 30
$19,63940
YF-EEFartico 321%
Total Project Budget a u 1
crty or F¢rtwrnn.T«aa
Altacnmarl DwartUa 12 M
PMO Ofnctel Rei¢ax¢❑eM'.A.C9.2913.MODIFIED August 22,2017 2&2
CITY OF FORT WORTH,TEXAS
M-199C-R PARALLEL INTERCEPTOR FOR WEST FORK BASIN-CPN 100836
ENGINEER'S PROBABLE OPINION OF COST
23.4.ug-17
I'I'lAl N0 DESCRUTION NIT QUANTIC' 7 -PE ., 14
1 'fearing and Grubbing(Tree Removal) LS 1 1 0 $1;oQ0
2 !'ipe-Sewer-48 to 54"FRP(picks up M-356B)-Install by Open Cut LF 670 45t.,1 10 $3,,11.4�(i-i
3 'ipe-Sewer-42"FRP-Install by Open Cut LF 7,355 37 5,.
4 'ipe-Sewer-42"FRP in 60"Casing Pipe or TLP-Installed B.O.T.O.C. LF 442 2,000.00 $8R
.-..-...--...
5 Pipe-Sewer-36"PVC-Install by Open Cut LF 601 275.00 $165,275
6 Pipe-Sewer-30"PVC-Install by Open Cut LF 236 250.00 $59,000
7 Connect to Existing Pipe(Ex M-199B) EA 1 10,000.00 $10,000
8 Inspection-Pre-Construction Cleaning&TV-Study LF 11,100 6.25 $69,375
9 Inspection-Post Construction Cleaning&TV-Study LF 9,304 3.50 $32,564
10 Structures-Trench Safety Systems-Install LS 1 10,000.00 $10,000
11 Pipe-Trench Safety System -Install LF 8,862 2.00 $17,724
12 Conshield Manhole-7-11 Dia Large Base Manhole(to 7 Ft Depth)-Install EA 3 12,500.00 $37,500
13 Conshield Manhole-Std 6-ft Dia Manhole(to 6 Ft Depth)-Install EA 8 10,000.00 $80,000
14 Conshield Manhole-Std Type A with 5 Ft Dia.Riser(to 6 Ft Depth)-Install EA 2 9,000.00 $18,000
15 Conshield Manhole-Std 6 Ft Dia MH-Added Depth(>6 Ft depth)-Install VF 72 375.00 $27,000
16 Conshield Manhole-Std 5 Ft Dia MH Riser-Added Depth(>6 Ft depth)-Install VF 42 350.00 $14,700
16 Manhole Coating System-Install on all MH's SF 5,688 15.00 $85,320
17 Concrete Street Replacement(assume 26'width) SY 11,353 135.00 $1,532,700
18 Asphalt Street Replacement(assume 26'width) SY 4,845 95.00 $460,243
19 Concrete Curb and Gutter LF 12,100 40.00 $484,000
20 Concrete Collars EA 13 450.00 $5,850
21 Junction Box/Vault at US Connection(includes internal protective coating) LS 1 55,000.00 $55,000
Iunction BoxNaults at Connections(includes internal protective
22 LS 1 75,000.00 $75,000
cin 1
22 Manhole-Vacuum Test-Services EA 13 250.00 $3,250
23 Storm Water Pollution Prevention Plan>1 Ac SWPPP-Install LS 1 20,000.00 $20,000
24 Seeding,Hydromulch,-Install&Maintenance Period SY 38,933 6.00 $233,600
25 Abandon Existing 24"Sanitary Sewer Pipe(M-199C)in Place CY 725 125.00 $90,625
26 Abandon Existing 36"Sanitary Sewer Pipe(M-199C-R and M-199B)in Place CY 8,445 125.00 $1,055,625
27 Abandon Existing M-199C-R,M-199C&M-199B Sanitary Sewer Manholes in EA 14 2,500.00 $35,000
Place
28 Owner's Allowance(2.5%) LS 1 $215,900.00 $215,900
29 Mobilization(21/o) LS 1 $172,720.00 $172,720
30 15%Contingency LS 1 $1,295,400.00 $1,295,400
Land Rights(very rough estimate)-see below Subtotal: $10,319,996
Temporary Construction Easements -PSSE Length plus 3000 LF for M-199C= SF 192,000 2.50 $480,000
7,400 LF in length x 30 LF wide)
Permanent Sanitary Sewer Easements 3400 LF in length x 40 LF wide) SF 136,000 10.00 $1,360,000
Subtotal: $1,840,000
Total Estimate: $12,159,996
NOTE: EPOC is for Alternative 1A-see attached Exhibit. Bypass pumping is considered as a subsidiary cost to all other
items bid.Average MH depth of 15 ft assumed. Estimate includes approximately$2.48 million in Westworth Village street
reconstruction. See estimate 1A1 if all trenchless is performed in those streets
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
M-199C-R PARALLEL INTERCEPTORS FOR WEST FORK BASIN
City Project No. 100836
NO CHANGES
City of Fort Worth,Texas
Attachment C
PMO Release Date:05.19.2010
Page 1 of 1
Attachment D-M-1"C-R Parallel Intercept"for West Fork Basin-proposed Project Baseline Schedule
M
................ ..............
............
............. ..........
..........
............ ................... .......................
....................... .............................................
12—
...................... .......... ........... ........ ............. ..........
...........
.................................... . ............................... ............................. .................................................... ................
............ ..........—
...... ....... .......... .
............. ..........................................nXm Tr YO.'O ...
Z M ....
•
W.—.W—bmF
..... ..... .lb:Y.6:.647..... ....... . .............. ......... ....
P �w� ...
. . ..... ..b .... .....
77. 7
...................... ............... ................................................................. ...................
ssi
.........................................................................................
..............
...... .................
W.,
............................. .................................................................................................. .................
VV
.....................................................
..........
.......................................... ........
...................... .................. ....................................................
.. ................................................................................................................j
......."..... .... .L.. . . .... .... ... ...................
..........................
41
............................
5.15 NYItlIY1cMMt9lPnlANtdml tar Wes!alt vte ries t9Hw9�
.................................. .................. ...........
Aan te20 1A
P.J.— d— fs., ........... ......... ...............................................................
................. ..... ..... ................
...............................................
..................
4
I
......................................................................
..................
iis�.
...................... ...........
............. ..........—........... ................. ................
............................................. ...................................................................................
ftr�0-1 T. I I ............. ....................... ..................... ........... ............
d3 51ael59ne
..................... ............................... ................................ ..............................I........... ............. .......... ..........
$2910
........... ....................................................................................................................... ..................
...........
............................!t_........................................ ....................................................—...................................................
(2 .............................................................................................................L.......................................................
P.W.Ow w
+
N -
GASOLINEIJET FUEUDIESEL •n
,. 44
I�,•,�•rti, ra.�•
� IIS
P
G
W
L-a
318
r
i
YYILLLIAMS
% CV NATURAL i
PIPELINE
IPELINE
dp L-414
I
�r
- _
3
tr
Y
_ � III L,4314 l`Y(§"eS dMl>E". (�]
- apt (Wrvt 41 -+v Cl)
41
�,ym aw �t 9 c+7
} i99e51 J ef'
� RA�Ilblpil CY � '
p�
westwort i, N L-4282 U)
Cl)
i YA+ a Pcpr..n L� �•
ag n vl
68
-4 L-428
Noun - j �
. N6.Lep 110 Richland � t9
;zO Huis Hurst c9� o -430
'., Lake Wmth Hait—City i r
�
Sansom Park r •,a","'d Fria a �' UJ
RN�` ✓� -2068
M-207 M-'207 M-207 L-4874 L-5053 L-5053 00.
ettietnent ,* 1N .. E+etcwy -
Fort Worth � � 'ra
r
R a^ _L-4138" -4873 L-5052 L-5052
n79
L-4872 I L-5051 L-5 5y
PROJECT
* ATTACHMENT E
LOCATION
M- 199C- R Parallel Interceptor
for West Pork Basin
PROHIBITION ON CONTRACTS WITH COMPANIES BOYCOTTING
ISRAEL
Contractor acknowledges that in accordance with Chapter 2270 of the Texas
Government Code, the City is prohibited from entering into a contract with a
company for goods or services unless the contract contains a written verification
from the company that it: (1) does not boycott Israel; and (2) will not boycott Israel
during the term of the contract. The terms "boycott Israel" and "company" shall
have the meanings ascribed to those terms in Section 808.001 of the Texas
Government Code. By signing this contract, Contractor certifies that
Contractor's signature provides written verification to the City that Contractor:
(1) does not boycott Israel; and (2) will not boycott Israel during the term of the
contract.
M&C Review Page 1 of 3
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA rQ
RTMar
COUNCIL ACTION: Approved on 11/7/2017 - Ordinance No. 22983-11-2017 & Resolution No,
4858-11-2017
DATE: 1117/2011' REFERENCE **C-28461 LOG NAME: 6060M 1 99CRPIWFB - RJN
NO..
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Engineering Agreement with RJN Group, Inc., in the Amount of
$525,000.00 for M-199 C-R Sanitary Sewer Main Parallel Interceptor, Provide for Staff
Costs, Property Acquisition and Utility Coordination for a Total Project Amount of
$600,000.00, Adopt Resolution Expressing Official Intent to Reimburse Expenditures and
Proceeds of Future Debt and Adopt Appropriation Ordinance (COUNCIL DISTRICT 7)
RECOMMENDATION:
1. Adopt the attached resolution expressing official Intent to reimburse expenditures with proceeds of
future debt for the M-199 C-R Sanitary Sewer Main Parallel Interceptor Project;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water and Sewer DPN Fund in the amount of$600,000.00; and
3. Authorize execution an Engineering Agreement with RJN Group, Inc., in the amount of
$525,000.00 for the M-199 C-R Sanitary Sewer Main Parallel Interceptor Project(City Project
No.100836).
DISCUSSION:
This Mayor and Council Communication (M&C) is to authorize the preparation of plans and
specifications for the installation of M-199 C-R Sanitary Sewer Main Parallel Interceptor Project.
Sanitary Sewer Main 199 C-R services the West Fork Basin. As part of the City's Wastewater System
Master Plan, the need for a 30-inch parallel relief line to M-199 C-R was identified.
RJN Group, Inc. proposes to provide the necessary design services for a fee of$525,000.00. Staff
considers the proposed fee to be fair and reasonable for the scope of services proposed.
In addition to the contract amount, $75,000.00 is required for project management, utility
coordination, real property acquisition and material testing.
Engineering for the M-199 C-R Sanitary Sewer Main Parallel Interceptor is one component of the
overall project that includes project management, easement acquisition, utility coordination, material
testing, inspection, construction and contingencies. The overall project budget is $4,600,000.00.
Design is expected to start in December 2017 and be completed by June 2019. Construction is
anticipated to commence in November 2019 and be completed by October 2021 This project is part
of the Water Department's Sanitary Sewer Overflow Initiative Program.
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer
Fund. Available cash within the Water and Sewer portfolio and the City's portfolio along with the
appropriation authority authorized under the Direct Purchase Note (DPN) Program will be used to
provide interim financing for this project until debt is issued. To the extent resources other than the
Water and Sewer portfolio are used to provide interim financing, the Water and Sewer Fund will be
charged interest that is equivalent to the overall rate of return being earned by the City portfolio
http://apps.cfwnet.org/council_packet/mc review.asp?ID=25292&councildate=11/7/2017 11/9/2017
M&C Review Page 2 of 3
(currently approximately one-percent annually). Should the City's portfolio not support the liquidity
needed to provide an interim short-term financing source, another funding source will be required,
which could mean issuance of securities under the DPN Program or earlier issuance of Water and
Sewer revenue bonds than is currently planned. Once debt associated with this project is sold, bond
proceeds will be used to reimburse the Water and Sewer portfolio and the City's portfolio in
accordance with the attached Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2017-2021 Five Year Capital
Improvement Plan on January 24, 2017, Mayor and Council Communication (M&C G-18927). This
City Council adopted plan includes this specific project, with funding identified through the DPN
program to be reimbursed with future revenue bonds. In accordance with the provisions of the
Financial Management Policy Statement, Staff anticipates presenting revenue-supported debt
issuances to the City Council for consideration within the next three years. This debt must be issued
within approximately three years to provide reimbursement for these expenses. If that does not occur,
the costs will no longer be reimbursable by issuing tax-exempt debt and the funding source will have
to be made whole through budgetary methods. Adoption of this resolution does not obligate the City
to sell bonds, but preserves the ability to reimburse the City from tax-exempt bond proceeds.
This project will have no impact on the Water Department operating budget.
M/WBE OFFICE - RJN Group, Inc., is in compliance with City's BIDE Ordinance by committing to 31
percent SBE participation. The City's SBE goal on this project is 16 percent.
The project is located in COUNCIL DISTRICT 7 and Westworth Village.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of
the attached appropriation ordinance, funds will be available in the Water/Sewer DPN Fund for the M-
199 C-R Sanitary Sewer Main Parallel Interceptor Project. The Water& Sewer DPN Fund includes
authority of$100,000,000.00 for the purpose of providing interim funding for Water and Sewer Capital
Projects. After this transfer the balance will be $86,370,529.00. Funding for this project is depicted in
the table below.
Fund Existing Additional Project
Appropriations Appropriations Total*
Water & Sewer DPN $0.00 $600,000.00 $600,000.00
Fund 56014
Project Total $0.00 $600,000.00 $600,000.00
*Numbers rounded for presentation purposes.
TO
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year Chartfield 2
FROM
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year Chartfield 2
http://apps.cfwnet.org/council_packet/mc review.asp?ID=25292&councildate=11/7/2017 11/9/2017
M&C Review Page 3 of 3
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Kara Shuror(8819)
Additional Information Contact: Walter Norwood (5026)
ATTACHMENTS
6060M199CRPIWFB RJN 60 AO 18 REVISED.pdf
60M199CRPIWFB RJN Form 1295.pdf
60M199CRPIWFB RJN Map 1.pdf
60M199CRPIWFB-RJN-REIMB RESOLUTION.doc
http://apps.cfwnet.org/council_packet/mc review.asp?ID=25292&councildate=11/7/2017 11/9/2017
Page + 1
60M199CRPIWFB RJN RD Table:
FIDs (Budget)
Rec Fund Dept Account . Activity CF Aniount
Purpose
1&2 56014 0700430 1C)08362018
S 2 .�si2014 07004301 5330500100936___ 70C-'7-,0 ._ 2016 � _ $660,000.00 i
Rec Fund .- t Account ProjectlD Activity BudgetYear CF Program Amount
}
FIDs (Budget)
Rec Fund
Dept Account ProjectlD Activity OudgetYear CF Program Aniount
3 5601.4 0700,43[7 5330500 1008525,000.66
a -a�Lt 1
CERTIFICATE OF INTERESTED PARTIES
FORM 1295
1 of 1
Complete Nos,1-4 and 6 if there are interested parties, OFFICE USE ONLY
Complete Nos.1,2,3,5,and 6 if there are no interested parties, CERTIFICATION OF FILING
1 Name of business entity filing form,and the city,state and country of the business entity's place Certificate Number:
of business. 2017-254624
RJN Group, Inc.
Dallas,TX United States Date Piled:
2 Name of governmental entity or state agency that is a party to the contract for which the form is 08/28/2017
being filed.
City of Fort Worth Date Acknowle ged:
I L !L)
3 Provide the identification number used by the governmental entity or state agency to track or identify the contract,and provide a
description of the services,goods,or other property to be provided under the contract.
100836
Engineering Services-M-199C-R Parallel Interceptors for West Fork Basin Project-Design
4 Nature of interest
Name of Interested Party City,State,Country(place of business) (check applicable)
Controlling I Intermediary
Jackson, Daniel Dallas,TX United States X
Plymale, Paul Dallas,TX United States X
5 Check only if there is NO Interested Party. ❑
6 AFFIDAVIT I swear,or affirm,under penalty of perjury,that the above disclosure is true and correct.
►cY'�"�;, CHERYL.D.TEAMES
MY COMMISSION EXPIRES
NOVEMBER 30. 201 Signature of author i ed agent of contracting business entity
AFFIX NOTARY STAMP I SEAL ABOVE � ,)
Sworn to and subscribed before me,by the said DAP-J-'6-L J AC1.SorJ this the c214'k day of�,
20 1—+ to certify which,witness my hand and seal of office.
L TE CS ssi5 Ate'
ign re of officer administering oath Printed name of officer administering oath Title of officer administering oath
Forms provided by Texas Ethics Commission www.ethics.state.tx.us Version V1.0.3337