HomeMy WebLinkAboutContract 45746-CO1 CITY SECRETARY CONTRACT NO. City of Fort Worth Change Order Request 50 Naftwl Village Creek Water Reclamation Facility Peak Flow Management Facilities City Sec No.: 45746 roject 56006-0O2009 DOE No. NSA City Proj.No.: 02009 Project Description: Construction of VCWRF Peak Flow Management Facilities(CMAR) Contractor. McCarthy Building Companies,Inc. Change Order# Date: 1 12/21017 City Project Mgr. Dena Johnson City Inspector. COM Smith Inc. Phone Number, 817-392-7866 Phone Number: 817-332.8727 Dept Water Sewer TotalsContract Time Calender days) Original Contract Amount $26,459,406.00 $26,45% (See Note 2) Extras to Date(See Note 1) =747-7 r Credits to Date(See Note 1) Pending Change Orders(in M&C Process) Contract Cost to Date $26,459,406.00 $4.459,406.00 JAmount of Proposed Change Order .$1,0K431.00 410&431.00. Revised Contract Amount $25,364,975.00 $25,364,975.00 Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding(W necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT - 4,W1, MAXALLOINABLE CONTRACTAMOUNT(ORIGWAL CONTRACT COST+25%) 1$264*_*W 4 The project was completed with unspent budget.All unspent cost and contingency budg with CMAR per contract.This change order is to credit the City for the savings related SO- budget savings. Final Contract Cost Ci Estimated Cost at Completion $23,568,056 CMAR Fee(3.596) $824,882 Unspent Cost Budget(50%Split) $362,776 $36 6 Unspent Contingency Budget $309,261 $309, TEX Unspent Owner's Allowance Budget $383,335 CMAR Shared Savings of Contingency from CO,21 $300,000 Unspent CMAR Fee X39,059 Total Final Contract Amount $25,364,975 $1,094,431 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and re en-9 payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. McCarthy Building Companles, Inc. ol, 1 1 12/5/2017 112 AR 6X_ at, D" S M&C Number NIA M&C Date Approved Tlq-or,P,7 FORTTC?RTH City of Fort Worth Change Order Additions Project Name Village Creek Water Reclamation Facility Peak Flow Management Facilities City Sec No.: 45746 Project No.(s): 56006-CO2009 I DOE No. N/A City Proj.No.: 02009 Project Construction of VCWRF Peak Flow Management Facilities(CMAR) Description Contractor McCarthy Building Companies,Inc. Change Order:0 Date: 1215/2017 City Project Mgr. Dena Johnson City Inspector FCDM Smith Inc. ADDITIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total Water Sewer Page 2 of 4 Additions Sub Total M/WBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 Page 4 of 4 FORT t>RTH City of Fort Worth Change Order Deletions Project Name Village Creek Water Reclamation Facility Peak Flow Management Facilities City Sec No.: 45746 Project No.(s): 56006-CO2009 DOE No. N/A City Proj. No.: 1 02009 Project Description Construction of VCWRF Peak Flow Management Facilities(CMAR) Contractor McCarthy Building Companies, Inc. Change Order: M Date 12/5/2017 City Project Mgr. Dena Johnson City Inspector: CDM Smith Inc. DELETIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total Water Sewer Page 3 of 4 Deletions Sub Total Attachment 1 to Change Order#1 Village Creek Water Reclamation Facility Peak Flow Management Facilities City Proiect Number 02009: City Secretary Contract Number 45746 The project was completed yvith unspent budget. Per the executed CMAR contract, all unspent cost and contingency budget is split 50%with CMAR per contract.This change order is to credit the City for the savings related to the unspent budget savings. Additional information and explanation are provided. Final Contract Cost City Savings Cost of Work at Completion $23,568,056 $0 CMAR Fee(3.5%)(see Note 3A) $824,882 $0 Unspent Cost Budget(50%Split)(see Note 39) $362,776 $362,776 Unspent Contingency Budget(see Note 3c) $309,261 $309,261 Shared Savings of Contingency from CO#21(see Note 3D) $300,000 $0 Unspent Owner's Allowance Budget(see Note 4) $0 $383,335 Unspent CMAR Fee(see Note s) $0 $39,059 ------------ ------------ ------------ ------------ Total Final Contract Amount $25,364,975 $1,094,431 (Note 6) NOTES: General Note: Project was completed by CMAR(Construction Manager at Risk) Note 1: Customer Change Orders 1-29 were used to transfer funds from project internal allowances and contingencies to work activities with no change in Total Cost of Work/Total Cost of Contract. Customer Change Order 30 is the basis for this formal Change Order#1. Note 2: Contract did not have designated length of Contract or Contract Time.The adopted GMP 2 (Amendment #2) provided a schedule with projected completion date of approximately 19 months after Notice to Proceed. Change Order #21 added three months to the projected completion date. Note 3:All the Notes Refer to specific sections of the executed CMAR agreement(City Secretary Contract#45746)approved by City Council on March 4, 2014 (M&C C-26693) Note 3A: Section 2 of Article 2 (Compensation) of the this contract states that "The City shall compensate the CMAR for providing Construction Phase Services for the construction fee of 3.5%of the contract work. Note 3B. Section 5 of Article 2 (Compensation)of this contract states that"50%of the Savings will be paid the CMAR." Note 3C. Section 4 of Article 2 (Compensation) of this contract states that "Any unspent Contingency Funds to be shared a 50/50 basis between CMAR and the City". Note 3D. Per Change Order#21,$600,000 of the Contingency Funds where split by mutual agreement per Section 4 of Article 2 (Compensation) of this contract. The $300,000 for the City was placed in the Owner's Allowance and was allocated for additional work requested by City Plant Staff. Note 4.The contract had an Owner's Allowance for additional work as requested by the City in the amount of$963,114 plus an additional$300,000 from the split of Contingency Funds as listed above.At the end of the project$383,335 remained unspent. Note S. As the Final Cost of Work was $830,257 less than the Cost of Work in GMP1 & GMP 2 (contracted Cost of Work)a credit is provided. Actual fee(Note 3A)was less than the budgeted fee Note 6.Total amount to be earned the CMAR(Contractor)for the Contract. Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. t' Signature Dena Johnson Name of Employee Senior Professional Engineer Title