HomeMy WebLinkAboutOrdinance 23062-01-2018 Ordinance No. 23062-01-2018
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN
THE AMOUNT OF $275,000.00 IN THE WATER/SEWER CP FUND, FROM AVAILABLE
FUNDS, FOR CONSTRUCTION OF THE IMPROVEMENTS OF PRIMARY AREA
MISCELLANEOUS SWITCHGEAR AT THE VILLAGE CREEK WATER RECLAMATION
FACILITY AND INTERNAL PROJECT COSTS; PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN
EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2017-2018 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the amount
of$275,000.00 in the Water/Sewer CP Fund, from available funds, for construction of the improvements of
primary area miscellaneous switchgear at the Village Creek Water Reclamation Facility and internal project
costs.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 22928-09-2017 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
rNA
r�9t4/
Douglas W Black Mary J. Kay r
Sr.Assistant City Attorney
ADOPTED AND EFFECTIVE: January 9, 2018
N
N
s
2
3
Village Creek Water Reclamation Facility
(VCWRF)
N
N
A
NIT
ALP
nt
61000!0
„F•� IST -�.� �I.� p�_^�_�: "" :' � � _
a r
Ile .
RON
p ` -
��r' Primary Area
.:d
.Irma I.-T ':C
E1,11-0-We
0
F�JQ
switchgear Improvement Locations
0
- :;IIF'• __.._y �N - .y
Feet a •��� ,� Switchgear Improvement Location
0 300 600
FORT WORTH COPVRIGUCTION IS A VIO FORT WORTH
Village Creek Water Reclamation Facility (VCWRF) JHAUTHORIZED REPRODUCTION ISA VIOLATION OF APPLICABLE LAWS
THIS DATA IS TO BE USED FOR A GRAPHICAL REPRESENTATION ONLY,
THE ACCURACY IS NOT TO BETAKEN I USEDAS DATA PRODUCED FOR
Switchgear Improvements-Ph.1 Primary Area ENGINEERINGPURPOSES OR BVA REGISTERED PROFESSIONAL LAND
CITY OFWATM SURVEYOR THE FOR THE F CORT CURACY OF H ASAID DATA RESPONSIBILITY
W
City of Fort Worth, Texas
Mayor and Council Communication
OWM ACTION: Approved on_11912018 Ordinance No. 23062-01-2014.$.Resol0onf o.
4892-01-2018 .
DATE: Tuesday, January 9, 2018 REFERENCE NO.: **C-28531
LOG NAME: 60VCWRF PH1 PRIMARY AREA SWITCHGEAR -GUPTA AMENDMENT NO2
SUBJECT:
Authorize Execution of Amendment No. 2 to the City Secretary Contract No. 47875, an Engineering
Agreement with Gupta and Associates, Inc., in the Amount of$195,000.00 for Engineering Services During
Construction for the Improvements of the Primary Area Miscellaneous Switchgear at the Village Creek
Water Reclamation Facility, Increasing the Total Contract Cost to $795,725.00, Adopt Resolution
Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt and Adopt
Appropriation Ordinance (COUNCIL DISTRICT 5)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached resolution expressing official intent to reimburse expenditures with proceeds of
future debt for the Improvements of Primary Area Miscellaneous Switchgear at Village Creek Water
Reclamation Facility;
2. Adopt the attached appropriation ordinance increasing estimated appropriations in the Water/Sewer
CP Fund in the amount of$275,000.00 and reducing the overall CP authority; and
3. Authorize execution of Amendment No. 2 to City Secretary Contract No 47875, an Engineering
Agreement with Gupta and Associates, Inc., in the amount of$195,000.00, for Engineering Services
during Construction for the Improvements of Primary Area Miscellaneous Switchgear at the Village Creek
Water Reclamation Facility;
DISCUSSION:
On May 17, 2016, (M&C C-27720) the City Council awarded the execution of an Engineering Agreement
with Gupta and Associates, Inc., in the amount of$517,782.00 (City Secretary Contract No. 47875), for
the Design of the Replacement, Removal and/or Modification of the Primary Area Switchgear at the
Village Creek Water Reclamation Facility (VCWRF). Subsequently, an administrative Amendment No. 1
(City Secretary Contract No. 47875-A1)was executed, for the amount of$82,943.00.
This Amendment No. 2 will provide for the engineering services during construction. These services will
include project administration and coordination; maintenance of electronic filing systems; pre-construction
conference; monthly progress meetings and site visits; coordination with City, contractor and Inspector as
necessary; review of shop drawings, pay estimates, record data, operational and maintenance manuals
and other submittals; project closeout and completion activities; and preparation of Record Drawings from
Redlines markups.
Gupta and Associates, Inc., are proposing to provide the necessary services for a fee in the amount of
Logname: 60VCWRF PHI PRIMARY AREA SWITCHGEAR- GUPTA AMENDMENT NO2 Page 1 of 3
$195,000.00. The Staff considers this fee to be fair and reasonable for the additional scope of services as
proposed.
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer Fund.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation
authority authorized under the Commercial Paper(CP) program will be used to provide interim financing
for this project until debt is issued. To the extent resources other than the Water and Sewer portfolio are
used to provide interim financing, the Water and Sewer Fund will be charged interest that is equivalent to
the overall rate of return being earned by the City portfolio (currently approximately one-percent annually).
Should the City's portfolio not support the liquidity needed to provide an interim short-term financing
source, another funding source will be required, which could mean issuance of securities under the CP
program or earlier issuance of Water and Sewer revenue bonds than is currently planned. Once debt
associated with this project is sold, bond proceeds will be used to reimburse the Water and Sewer
portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2017-2021 Five-Year Capital Improvement
Plan on January 24, 2017 (M&C G-18927). This City Council adopted plan includes this specific project,
with funding identified through the CP program to be reimbursed with future revenue bonds. In accordance
with the provisions of the Financial Management Policy Statements, Staff anticipates presenting revenue-
supported debt issuances to the City Council for consideration within the next three years. This debt must
be issued within approximately three years to provide reimbursement for these expenses. If that does not
occur, the costs will no longer be reimbursable by issuing tax-exempt debt and the funding source will
have to be made whole through other budgetary methods. Adoption of this Resolution does not obligate
the City to sell bonds, but preserves the ability to reimburse the City from tax-exempt bond proceeds.
These engineering services are anticipated to commence in January 2018, with a contract time of 24
months, it is estimated to be completed by December 2019.
M/WBE OFFICE: Gupta and Associates is in compliance with the City's BDE Ordinance by committing to
25 percent SBE participation on this Amendment No. 2. The City's goal on this Amendment is 18
percent. Additionally, Gupta and Associates is a certified M/WBE firm.
In addition to the contract amount, $50,000.00 is required for project contingency allowance and
$30,000.00 is required for project management and associated Staff time for the Water Department.
This project serves the entire City and is located in COUNCIL DISTRICT 5.
FISCAL INFORMATION I CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in the Water/Sewer CP Fund for the
Improvements of Primary Area Miscellaneous Switchgear at Village Creek Water Reclamation Facility
Project. . The Water and Sewer CP Fund includes authority of$150,000,000.00 for the purpose of
providing interim funding for Water and Sewer Capital Projects. After this transfer, the balance will be
$76,025,529.00.
Logname: 60VCWRF PHI PRIMARY AREA SWITCHGEAR- GUPTA AMENDMENT NO2 Page 2 of 3
Funding for this project is depicted in the table below.
Fund Existing Additional Project
Appropriations Appropriations Total*
2016 Water
and Sewer $612,800.00 $0 $612,800.00
Bond Fund
56005
Water and
Sewer CP $0 $275,000.00 $275,000.00
Fund 56014
Project Total 1 $612,800.00 F $275,000.00 $887,800.00
* Numbers rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO
Fund Department ccoun Project JProgram ctivity Budget Reference # moun
ID ID Year Chartfield 2
FROM
Fund Departmentccoun Project JProgram ctivity Budget Reference # �mounl
ID ID Year Chartfield 2
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Kara Shuror (8819)
Additional Information Contact: Farida Goderya (8214)
Logname: 60V'CWRF PHI PRIMARY AREA SWITCHGEAR- GUPTA AMENDMENT NO2 Page 3 of 3