WHEREAS, the City of Fort Worth (CITY) and Gresham,
Smith & Partners, (ENGINEER) made and entered into City
Secretary Contract No. 46599, (the CONTRACT) which was
authorized by M&C C-27231 on the 17th day of March, 2015 in
the amount of $206,325.00; and
WHEREAS, the CONTRACT involves engineering services for
the following project:
Sanitary Sewer Rehabilitation, Contract 89; and
WHEREAS, it has become necessary to execute Amendment
No.l to the CONTRACT to include an increased scope of work and
revised fee.
NOWTHEREFORE, CITY and ENGINEER, acting herein by and
through their duly authorized representatives, enter into the
following agreement, which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the
additional engineering services specified in a proposal dated
January 9, 2018, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional
design services to be performed by Engineer totals $8,640 .00.
2 .
Article II of the CONTRACT is amended to provide for an
increase in the fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall be
an amount of $214,965 .00
3 .
All other provisions of the Contract, which are not
expressly amended herein, shall remain in full force and
effect.
_. st
taw A�ClAL RECORD
�p
" t�Y SECRETARY
41-4 ?'1'.WORTH,TX
9� `� Page -1-
0� 1 Wd W�ti
EXECUTED and EFFECTIVE as of the date last written by a
signatory, below.
APPROVED: ENGINEER r,
City of Fort Worth Gresham, Smith Partners
Jesus J. Chapa Chris Kaakaty, P.E.
Assistant City Manager Senior Vice-President
DATE: �'1 DATE: / /Z
APPROVAL RECOMMENDED:
Christopher Harder, P.E.
Assistant Director, Water Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring
all performance and reporting requirements.
Name of Employee
A ;ky
Title: Project Manager
APPROVED AS TO FORM AND LEGALITY: M&C: N/A
%!� Date N/A
Douglas W. Black
Senior Assistant City Attorney
ATTEST: 0� FORS.
ary J Eys
City Se 4 etary
'CAS
t#FFICIAL RECORD
CITY SECRETARY
Frr WORTH,TX
Page -2-
12
G R E S H A h
S M ITH AN E
P A R T N F R 5
January 9, 2018
Walter Norwood, P.E.
Senior Professional Engineer
City of Fort Worth—Water Department
200 Texas Street
Fort Worth,TX 76102
Subject: City of Fort Worth Project No. 02381,Sanitary Sewer Rehabilitation, Design
Contract 89,Amendment No.1
Walter
Herewith is our request for Amendment No.1 for the subject project. The Amendment includes
additional scope and fee to prepare drawings for an additional line, Segment L-2421. The line is
located.between Park Ridge Boulevard and Mission Street. The line will be rehabilitated or
replaced from the manhole (Station 4+30)just west of Lubbock Avenue to the upstream end of
the line, approximately 700 lineal feet.The additional scope and fee is as follows:
Task No.1 Project Management
• Manage the design team, provide quality assurance,coordinate internal meetings, and
prepare timely invoicing.
Task No.2 Concept Design
• Visit the site, collect available data, and prepare base sheets using available aerial base
mapping and layout line on plan.
Task No.3 Preliminary Design
• Prepare preliminary plan and profile sheets and submit to the City for review.
Task No.4 Preliminary Final Design
• Incorporate City review comments on Preliminary Plans and prepare 90%complete plan
and profile sheets and submit for City review.
• Finalize 100% plan and profile sheets and submit to City to issue to contractor.
Fee
Attached, please find the Level of Effort Spreadsheet showing our fee breakdown.We propose to
perform this work for a lump sum fee of$8,640.00.
Summary:
Original Contract$206,325.00
Amendment 8,640.00
Total Contract $214,965:00
Design Services For The Built Environment
2811 McKinney Avenue,Suite 300 / Dallas,Texas 75204 / Phone 214.350.1500 / www.gspnet_com
January 9, 2018
Page 2
Assumptions
Segment L-2421 will be added to Ark Construction's current construction contract that includes
the other segments of Contract 89 and no bidding or construction phase service will be required
as part of this Amendment.
The City will provide field survey limited to top of rim and invert elevations of the two existing
manholes on Segment L-2421.The city will assist the contractor in obtaining access to the site
and permission to construct the proposed improvements. Our scope and fee excludes permits
and easements.
Please let me know if you have any questions or need any clarifications.Thank you for the
opportunity to assist you.
Sincerely,
GRESHAM, SMITH AND PARTNERS
Alex Martinez, P.E.,
Senior Associate
Attachments: Level of Effort Spreadsheet
t
EXHIBIT B-2
Level of Effort Spreadsheet
TASKIHOUR BREAKDOWN
Design Services for
Sanitary Sewer Replacement Contract,89,Amendment No 1
City Project No.02381
Labor hours Expense
Task Na.. Task Description principal Project Project EIT CADD Administrative Total Labor SuOconsultant Total Expense Task Sub Total
Man er Ert ineer Cost Travel Reproduction Cost
Ra $250 $240 $125 $100 $1001 U01 MWBE Non-MWSE
1.0Pfa'act M—emant 01 41 01 01 01 0 $960 $D $0 $0 $0 $0 $960
1.1 Mana jng the Team
1.1.1 QAlQC 2 $480 1 1 $0 $480
1.2 Communications and Re orOn 21 1 _
2.o Conc.Desi n 30-Percent 0 4 4 0 0 0 $1.460 $0 $0 50 SO $60 $1,610
2.1 Data C011e0o0 & i[o VisR 4 4 $1,460 $50 $50 $1.510
3.0 Prslirhma Desi n 60 Percent 0 1 16 0 8 0 $3,040 $0 $0 $0! $30 $30 $3,070
3.1 Prelimm Deaf P=1`3 a $0 $0
3.1.3 Plan and Plan/Profile Sheets 1 lal e $3,040 $$0 $30 $3 070
4.0 Final D-1 g. 01 1 18 0 8 0 $3040 $0 $0 0 $6D $60 $3100
Final Draft(90%)CunstruclP-Plans and
4.1 S eCIfICa!i°ns 0.5 8 41 $1,520 $30 $30 $1,550
4.2 Final"10OV, Plans and Specifications I 0,5'i, 81 4 $1,520 $30_ $30_$1550
5.0 Bid Phase 0 0 _ of 01 0 0 $0 $0 $0 $0 $0 $0 $0
5.1 Bid Su °r
6.0 Construction Phase Services 01 01 0 01 0 $0 $0 $0 $0 $0 $0 $0
7.0 RpVflF.asemant Servioes 0 — 0 0 0 0 0 so $0 YO 0 $0 $0 0
aiahk-e'-Ent Uoouments $D $o $0
S.0— Suvey n D 0 0 D 0 $0 $0 $0 $o $0 $0 $0
_— ex:!,7 r.Sur✓ey 0 $D $0
Totals
01 101 Sri. 01 16 0 $8,500 $0 $0 $50 Y90 $140 $8,640.00
Water Line Footage 60% Project Summary
Sewer Line Footage 700 40% Total Hours 62
700 100% Tota{Labor $8,500
Total Expense $140
(A) Total F $8,640 MSE/SBE Subconsultant $0
(B) Survey Feee e $D Wn-MBEISB'c Subconsultant $0
(G) Tatat Fsa r-1 surveyFee $8640 101, Sub Markup
$C
Water Fee(60%of C) I Sewer Fee(40%of C) MBE/SBE Paaf tion 0 0°1
$6,18?.00 $3,456.00 Total Project C..tl $6,640.00
Cescri;iorj TIp 'Nater Sewer
Conce tual Desi n'30k 31 $1,535.00 $1,037.00
Prelimira Desi n 60h 32 ! 1 $2,074.00
Final Desi n 10% 38 $518,00 $348.00
Survey 51
Subtotal $5,193,00 1 $3,457.00
Total. $6,640.00