THE CITY OF FORT WORTH, TEXAS
Construction Manager-at-Risk
Cattle Barn 1 and the Poultry Barn Renovations
Project
PMD2017-09
..
FORTWORTH,
BETSY PRICE DAVID COOKE
MAYOR CITY MANAGER
Susan Alanis
Assistant City Manager
Kirk Slaughter 6
Director, Public Events Department N'`
�• Steve Cooke REEVED
Director, Property Management Department JAN
OFFICIAL RECORD
CITY�:e"EC'RETARY January 2018
Cattle Barn'I and the Poultry Barn Renovations Page 1 of 58
"" CM R, Pre-Construction Services July 2017
L a
CERTIFICATE OF INTERESTED PARTIES FORM 1295
Complete Nos.1-4 and 6 if there are Interested parties. OFFICE USE ONLY
Complete Nos.1,2,3,5,and 6 if there are no interested parties. CERTIFICATION OF FILING
1 Name of business entity filing form,and the city,state and country of the business entity's place Certificate Number:
of business. 12017-277314
SEDALCO,Inc.
Fort Worth,TX United States Date Filed:
2 Name of governmental entity or state agency that is a party to the contract for which the form is 10/27/2017
being filed,
City of Fort Worth Date Acknowl d d ,�
3 Provide the identification number used by the governmental entity or state agency to track or identify the contract,and11provide a
description of the services,goods,or other property to be provided under the contract.
PMD2017.09
General Services
4 Nature of interest
Name of Interested Party City,State,Country(place of business) (check applicable)
Controlling I intermediary
5 Check only if there is NO Interested Party. ❑
X
6 AFFIDAVIT I swear,or affirm,under penalty of perjury,that the above disclosure is true and correct.
"Py8os11ACQU LYN Y).ALLEN
r , Notary Public
STATE OF TEXAS
'°�9 yy Notary ID 0 7098f337-4
F My COmm.Etip.September 23.2021
Signature of authorized agent of Contracting business entity
AFFIX NOTARY STAMP/SEAL ABOVE J ,,
Sworn to and subscribed before me,by the said / {� Q/L this the of day of & db,,r�,
20 1'7 ,to certify which,witness my hand and seal of office.
--
Jai v
Signatur of c ening oath Printed na66 of otfi er administering oath Title of off ic administering oath
F rens pro ed by Texas Ethics Commission www.ethics,state.tx.us Version V1.0.3337
_ City of Fort Worth, Texas
Mayor and Council Communication
,. COUNCIL ACTION: Approved on 12/5/2017
DATE: Tuesday, December 5, 2017 REFERENCE NO.: C-28498
••- LOG NAME: 21 WRMC CATTLE BARN 1 & POULTRY BARN RENOVATIONS
SUBJECT:
Authorize Execution of a Construction Manager at Risk Contract with Sedalco, Inc., d/b/a Sedalco
Construction Services, with a Construction Services Fee of 4.5 Percent of the Construction and General
Conditions Costs Within a Construction Contract Budget Amount of$14,248,486.00 Inclusive of a
$248,486.00 Owners Allowance for Additional Construction Services for the Will Rogers Memorial Center
•– Cattle Barn No. One and Poultry Barn Renovations (COUNCIL DISTRICT 7)
.. RECOMMENDATION:
It is recommended that the City Council authorize execution of a Construction Manager at Risk Contract
with Sedalco, Inc., d/b/a Sedalco Construction Services, with a Construction Services Fee of 4.5 percent of
the construction and general conditions costs within a Construction Contract budget amount of
$14,248,486.00 inclusive of a $248,486.00 Owners Allowance for additional construction services for the
Will Rogers Memorial Center Cattle Barn No. One and Poultry Barn Renovations.
.._.__ _.-----.-.._.__.___ ------- ___—._.___ __ ___ _ -- ---_---
DISCUSSION:
A notice to Construction Manager-At-Risk (CMAR) Offerors was advertised in the Fort Worth Star-
Telegram on Thursday, July 6, 2017 and July 13, 2017 in the Bids and Proposals section. Proposals were
due August 3, 2017. The City received seven proposals from qualified CMAR Contractors. These
contractors were:
• FPI Builders, LLC
• Imperial Construction, Inc.
• Key Construction TX, LLC
• Muckleroy & Falls
• Ridgemont Commercial Construction
• Sedalco, Inc., d/b/a Sedalco Construction Service
• Thos. S. Byrne, Inc., d/b/a Byrne Construction Services
These proposals were evaluated by members of the selection team. The selection team was comprised of
representatives of Public Events Department, Property Management Department, Office of Business
Diversity and Southwest Exhibition and Livestock Show. After individual review and consideration, the
selection team met to review a detailed comparison of the published criteria, including cost of services,
*� references and CMAR experience, similar project types and MBE commitment and plan. After this
discussion, scores for individual categories were determined and then totaled. Based on these
discussions and scores, the selection team reached a consensus on a recommendation to the Fort Worth
,.. City Council. The following is the rankings resulting from this review process:
Criteria Fees and MBE Goal References and Past Relationship Total
-- Expenses and Plan Experience with the City
Logname: 21 WRMC CATTLE BARN 1 POULTRY BARN RENOVATIONS Page 1 of 3
JSedalco, Inc. 52 6.5 21 8 187.5
FF�idgemont
Commercial 53 6.5 18 8 85.5
Construction_– F
[Thos S. Byrne, Inc. 54 8 16 7 85.0
M uckleroy & Falls 55 6.5 15 7 83.5
F P I B'-'-' 5 [
uil��r�, LLC 55 16 7 83.0
(Imperial Construction, 51 —75 18 8 82.0
Inc.
Key Construction TX, 5575.0
Inc. F 5 10 5 F
The selection team recommends award of the Construction Manager at Risk Contract for the remodel of
WRMC Cattle Barn No. One and Poultry Barn Renovation to Sedalco, Inc.
Estimated Costs:
Sedalco Inc. is in the process of establishing a Guaranteed Maximum Price (GMP) for the construction of
the new WRMC Cattle Barn No. One and Poultry Barn Renovation. Once presented and accepted by
staff, the contract will be amended to incorporate the GMP.. The overall project costs are expected to be
as described in table below:
CATTLE BARN 1 1 an I d POULTRY B I ARN R.ENOVATIONS FTOTALS
Architectural and Design 901,514,00
Design Phase Total $ 901,514.00
iCMAR Preconstruction Services $10.00
!Construction Contract Budget including 4.5 percent CMAR Fee and $248-486.00 Owners Construction
Allowance
�1 4�,24 486.00
_ Material Testing,Administration Cost: Site Utilities, Mif�i g, r curity', Project Management, Contingency,FFE, $ 949,990.00
,Etc.
;Construction Phase Total $15,198,486.00
PROJECT TOTAL $16,1100,000.00
A separate Mayor and Council Communication (M&C) will be routed to seek approval of the design
professional services agreement. A Pre-Construction Services agreement with Sedalco Inc- was
administratively executed for$10.00. M&C G-19020, June 6, 2017, authorized the issuance of Tax-
Exempt Special Tax Revenue Bonds, with $15,600,000.00 allocated to this project. When renovating an
older facility, it is normal to encounter unforeseen conditions despite due diligence in the design
process. Projects of this type are typically awarded with a ten percent contingency, but the available
funding only allows a two percent contingency. To provide additional contingency that is projected to be
needed, Southwest Exhibition and Livestock Show has committed to provide up to $500,000.00 in
additional contingency funding during construction if necessary. The Project Budget of$16,100,000.00
above reflects this commitment. Additional funds may still be required if additional unforeseen conditions
are encountered.
M/WBE OFFICE– Sedalco Inc., is in compliance with the City's BIDE Ordinance by committing to 20
percent MBE participation on this CMAR project, The City's MBE goal on this CMAR project is 20 percent.
Logname: 21WRMC CATTLE BARN 1 POULTRY BARN RENOVATIONS Page 2 of 3
-
In accordance with the City Code, City of Fort Worth Building and Trade Permit fees are waived.
The Will Rogers Memorial Center is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendation, funds are available in
the current capital budget, as appropriated of the Venue Capital Project Fund. (Cattle Barn Project.)
FUND IDENTIFIERS (FIDs):
TO
- FundrDepartment JAccoun -ogram ctivity Budget Reference # Amouni
i ID I ID Year Chartfield 2
-
FROM
----IF—n-7c—.. ccoun Project Program ctivity Budget Reference # �Amouni
i IIID ID 1 Year (Chartfield 2) y�_
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Steve Cooke (5134)
® Additional Information Contact: Brian Glass (8088)
ATTACHMENTS
1. CMAR Sedalco, Inc Compliance Memo.pdf (CFW Internal)
2. SAM Sedalco Inc.pdf (CFW Internal)
3. Sedalco Form 1295.pdf (Public)
-
-
-
-
Logname: 21 WRMC CATTLE BARN 1 POULTRY BARN RENOVATIONS Page 3 of 3
rwr
NOTICE TO
CONSTRUCTION MANAGER-AT-RISK(CMAR)
OFFERORS
.rw
The City of Fort Worth is accepting proposals from Construction Manager-at-Risk(CMAR)Offerors for the
Cattle Barn 1 and the Poultry Barn Renovations project located at the Will Rogers Memorial Campus at
3401 Lancaster Avenue, Fort Worth, Texas will be received at the Purchasing Office, City of Fort Worth,
200 Texas Street, Fort Worth, 76102, until 1:30 P.M on Thursday, August 3, 2017, and will be opened
and the names of the CMAR firms will be publicly read aloud approximately thirty minutes later in the
Council Chambers.
A Pre-Proposal Conference will be held at 10:00 A.M., Wednesday, July 19, 2017 at the Architectural
Services conference room at 401 West 13"'Street, Fort Worth, 76102.
The last day for questions from prospective Offerors is at 5:00 PM on Friday,July 28,2017
The construction period for this project is February 5,2018 to December 1,2018.
The City will select the CMAR Contractor by using a two-step Request for Proposal (RFP) process. After
evaluating the submitted Proposals from the CMAR Offerors, the City will shortlist and interview up to
three Offerors. The City will then select and enter into negotiations with the Best Value Offeror. The City
may discuss with the selected Offeror, options for a scope or time modification and any price change
associated with such modification.
.. The selected CMAR Contractor will provide Pre-construction Services including Constructability
Reviews, Value Engineering Recommendations and Estimating Services Fees to review during the
various phases of the design process. Once the construction documents are completed, the selected
CMAR Contractor will provide a Guaranteed Maximum Price (GMP) and construction performance
period for each of the three major portions of the work and all work combined. This GMP will be inclusive
of Value Engineering and Estimating Services fees, General Conditions, Construction Manager's Fee,
contingency, bonds, insurance, and other agreed upon costs; plus the City's General Contingency
Allowance. Refer to the attached"Project Proposal Form".
The City of Fort Worth will negotiate for Pre-Construction Services Contract,and negotiate for a
Construction Services Contract with the selected CMAR firm determined to have made the Best Value
-- offer. Refer to the"Project Proposal Form".
Refer to the Request for Proposal documents for the Minority Business Enterprise (MBE) Information.
MBE participation will be evaluated in awarding this contract. The MBE participation goal is 20% for the
estimated construction budgets. The goal will be applied to the GMPs (and fees) when the GMP
agreements are reached. Offerors must submit an anticipated MBE Utilization Plan with their CMAR
Proposal submittal. The submitted Plan will be part of the weighted selection criteria. Refer to
Instructions to Construction Manager-at-Risk (CMAR) Offerors for additional information. Contact the
MW/BE Office at(817)212-2674 to obtain a list of certified subcontractors and suppliers.
Also, Refer to Section 3. BUSINESS DIVERSITY ENTERPRISE (BDE) ORDINANCE PROVISION in the
^^ Instructions to Construction Manager-at-Risk(CMAR)Offerors.
Upon completing the negotiations with the selected CMAR firm, the City will recommend to the City
Council to award the CMAR contract to the selected CMAR firm based on the negotiations and the agreed
upon estimated construction budgets for each of the three major tasks. The CMAR contract will be
adjusted based on the agreed upon Guaranteed Maximum Price(GMP)after the design is completed.
Cattle Barn 1 and the Poultry Barn Renovations Page 2 of 58
CMAR,Pre-Construction Services July 2017
"'- The selected CMAR Contractor will be required to provide Payment and Performance Bonds and
provide Contractors General Liability and Statutory Workers Compensation Coverage once the
GMP is agreed upon.
CMAR Offerors may access the Instructions to Offerors, any Addendum, Sample Contract, General
Conditions, Drawings, and any other related documents through the City's Buzzsaw website by cutting and
pasting the following link into a web browser:
https://prolectpoint.buzzsaw.com;fortworthgov/PMD%20Prooects/W RMC%20Cattle%20Barn%201?public
�•rr
Contact the Project Manager, Ronald Clements, at (817) 392-8014 or email
Ronald.Clements@fortworthtexas.gov for assistance.
Advertisement: July 6,2017
July 13,2017
,r.
Cattle Barn 1 and the Poultry Barn Renovations Page 3 of 58
CMAR,Pre-Constriction Services July 2017
TABLE OF CONTENTS
• NOTICE TO CONSTRUCTION MANAGER-AT-RISK(CMAR)OFFERORS
• TABLE OF CONTENTS
• INSTRUCTIONS TO CONSTRUCTION MANAGER-AT-RISK(CMAR) OFFERORS
® • PROPOSAL FORM
• CONFLICT OF INTEREST AFFIDAVIT
• CONFLICT OF INTEREST QUESTIONAIRE (CIQ)
• CONFLICT DISCLOSURE STATEMENT (CIS)
• TEXAS SALES AND USE TAX EXEMPTION CERTIFICATE
.e
• 2013 PREVAILING WAGE RATES
• WEATHER TABLE
• GENERAL CONDITIONS FOR CMAR CONSTRUCTION
• CMAR CONSTRUCTION CONTRACT
• PAYMENT BOND
• PERFORMANCE BOND
• CERTIFICATE OF INSURANCE
• CONTRACTOR COMPLIANCE WITH WORKERS' COMPENSATION LAW
• PROJECT SIGN
.■r
® Cattle Barn 1 and the Poultry Barn Renovations Page 4 of 58
CMAR,Pre-Construction Services July 2017
INSTRUCTIONS TO
CONSTRUCTION MANAGER-AT-RISK
._. (CMAR)OFFERORS
1. PROPOSAL REQUIREMENTS: The following requirements shall be used in the preparation of
the response to this Request for Proposals(RFP):
• Use the Proposal Form provided in this RFP document.
• Entries on the Proposal Form may be handwritten or typed.
• Acknowledge all addenda on the Proposal Form.
• Have a Principal sign the Proposal. If the Offeror is a corporation, the president or a vice-
president must sign the Proposal. If the Offeror is a partnership,then the person/entity who is
the managing/general partner must sign the proposal.
• Complete and submit the Conflict of Interest Affidavit form. (Also submit associated Form CIQ
-- and Form CIS if required.)
• Cashier's check or an acceptable bidder's bond IS NOT REQUIRED for this Request for
Proposals.
2. SELECTION OF CMAR CONTRACTOR:
The City shall select the Offeror that offers the best value based upon the below criteria and
ranking evaluation.
In determining the Best Value Offeror,the City will consider:
A. Proposed Fees and Expenses(55%) (Refer to Proposal form).
r, B. Proposed MBE Goal and Utilization Plan(10%).
C. Reputation and Experience in Executing CMAR Projects and Similar Type Projects(25%)
- Reputation and experience of the Offeror, Project Manager, and Superintendent as
demonstrated by listing recently completed and current, "vertical" facilities, CMAR
projects, including references with names, positions, company names, and current
telephone numbers;and list of subcontractors.
w
D. Past relationship with the City (10%) — Offeror's past relationship with the City of Fort
Worth for"vertical"facilities projects shall receive up to 10 points for this rating criteria. If
the Offeror does not have a past relationship with the City of Fort Worth, the Offeror will
-- receive 5 points for this rating criteria.
After ranking the responses to the RFP,the City shall first attempt to negotiate a contract with the
selected Offeror. The City and its architect may discuss with the selected Offeror options for a
scope modification and any price change associated with the modification.
If the City is unable to negotiate a contract with the selected Offeror,the City shall,formally and in
writing, end negotiations with that Offeror and proceed to the next Offeror in the order of the
selection ranking until a contract is reached or all proposals are rejected.
Cattle Bam 1 and the Poultry Sam Renovations Page 5 of 58
CMAR,Pre-Construction Services July 2017
3. BUSINESS DIVERSITY ENTERPRISE(BDE)ORDINANCE PROVISION
A. The City of Fort Worth implemented the Business Diversity Enterprise Ordinance to reflect the
City s availability and disparity study findings. All proposers shall note that it is the policy of the
City to ensure the full and equitable participation of Minority Business Enterprises (MBEs) in the
procurement of goods and services. If the total dollar value of the contract is greater than
$50,000,then an MBE subcontracting goal may be applicable.
There is no MBE diverse goal for Pre-Construction Phase Services on this solicitation.
The MBE diverse goal is 20%for Construction Phase Services(subcontractors, suppliers,etc.)
B. If the Proposer self-performs Construction Phase Services as the general contractor, the MBE
goal must be met. No exceptions.
C. Proposers must obtain MBE listings from the City of Fort Worth's M/WBE Office at (817) 212-
2674 or email mwbeoffice(a)fortworthtexas.Qov. This will ensure that CMAR firms are
acknowledging MBEs (which include DBE firms that are minority owned, controlled and daily
managed) currently certified by the North Central Texas Regional Certification Agency(NCTRCA)
or other certifying agencies that the City may deem appropriate and accepted by the City of Fort
Worth at the time proposals/bids are submitted, in order for the participation to be counted
towards the established diverse goals. The firms must be located in the City's six (6) county
geographic marketplace that includes the counties of: Tarrant, Dallas, Denton, Johnson, Parker
and Wise.
D. At the time the Guaranteed Maximum Price (GMP) is due and submitted to the City, it shall be
accompanied by the MBE Utilization Plan to address the diverse MBE goals for use when
proposals/bids are sought from trade contractors or subcontractors for performance of all major
elements of the Work. At a minimum,the Pian must provide:
■ the company name, address, point of contact, email address, office and fax telephone
numbers of the MBE subcontractors and suppliers;
• a detailed description of the work to be performed by each MBE;
• the tier level, i.e., 13t, 2nd, 31d, etc. (if other than 1st tier, the plan must clearly identify the
firm name and tier from whom the MBE firm will be receiving payment);
■ the sub-contract value or percentage of the GMP construction cost for each phase of
work identified for each MBE participant;
■ state the MBE percentage level of commitment achieved;
■ the timing of the major elements of the work including approximate advertising dates and
�. ■ provide the same identification information for all non-MBE participants
The Plan must also include an element detailing how the Proposer will communicate with, and
report Plan compliance to, the Citys Project Manager and the City's MWBE Office during the
Project including providing to the MWBE Office Letter(s) of intent, purchase orders and or
executed sub-contract agreements after award by the CMAR and prior to the issuance of the
notice to proceed of each relevant phase of the Work.
E. MBE firms must be certified at the time each of the Work's major elements are bid or proposals
submitted, in order for the participation to be counted towards the established goal.
.. F. If a Proposer is certified as a DBE, MBE, SBE or WBE firm,the City's Ordinance does not allow a
Proposer to count itself or its subsidiary-owned companies towards the established goals; the
goals represent subcontracting opportunities.
G. The participation commitment of the MBE Construction Phase Services will be part of the
final weighted selection criteria.
Cattle Barn 1 and the Poultry Bann Renovations Page 6 of 58
CMAR,Pre-Construction Services July 2017
H. Failure to address the diverse goals and state the MBE commitments shall render the Proposer
non-responsive.
,,- For additional information contact the MWBE Office at(817)212-2674.
4. PROPOSAL SECURITY:This is NOT REQUIRED for this Request for Proposals.
,. 5. PAYMENT BOND AND PERFORMANCE BOND: For projects in excess of$25,000 and when
the Guaranteed Maximum Prices (GMPs) are agreed upon,the successful Offeror entering into a
contract for the work will be required to give the City surety in a sum equal to the amount of the
contract attributable to each phase. The form of the bond shall be as herein provided and the
surety shall be acceptable to the City. All bonds furnished hereunder shall meet the requirements
of Texas Government Code Section 2253, as amended.
In order for a surety to be acceptable to the City,the surety must(1)hold a certificate of authority
from the United States Secretary of the Treasury to qualify as a surety on obligations permitted or
required under federal law; or(2)have obtained reinsurance for any liability in excess of$100,000
from a reinsurer that is authorized and admitted as a reinsurer in the State of Texas and is the
holder of a certificate of authority from the United States Secretary of the Treasury to qualify as a
surety on obligations permitted or required under federal law. Satisfactory proof of any such
reinsurance shall be provided to the City upon request. The City, in its sole discretion, will
determine the adequacy of the proof required herein.
No sureties will be accepted by the City that are at the time in default or delinquent on any bonds
or which are interested in any litigation against the City. Should any surety on the contract be
.w determined unsatisfactory at any time by the City,notice will be given to the contractor to that
effect and the contractor shall immediately provide a new surety satisfactory to the City.
If the total contract price is $25,000 or less, payment to the contractor shall be made in one lump
sum. Payment shall not be made for a period of 45 calendar days from the date the work has
been completed and accepted by the City.
aa� If the contract is in excess of$25,000, a Payment Bond shall be executed, in the amount of the
contract, solely for the protection of all claimants supplying labor and materials in the prosecution
of the work.
*�* If the contract amount is in excess of$100,000,a Performance Bond shall also be provided, in the
amount of the contract,conditioned on the faithful performance of the work in accordance with the
plans, specification, and contract documents. Said bond shall be solely for the protection of the
.�r City of Fort Worth.
6. PRE-PROPOSAL SITE INVESTIGATION: Prior to filing a response,the Offeror shall examine the
site(s) of the work and the details of the requirements set out in these specifications to satisfy
�• itself as to the conditions which will be encountered relating to the character, quality, and quantity
of the work to be performed and materials and equipment required.The filing of a response by the
Offeror shall be considered evidence that it has complied with these requirements.
7 WAGE RATES: Not less than the prevailing wage rates set forth in Contract Documents must
be paid on this project.
8. CMAR OFFERORS SUBMITTALS: With their Request for Proposal submittal, Offerors are
required to submit the following additional information to the Purchasing Office, 200 Texas Street,
Fort Worth, Texas 76102 in order to assist City staff in determining the Contractor's capability of
performing the work and in meeting City contract requirements:
• Contractor's CMAR Qualification Statement (AIA Form A305 or equivalent form),
including client references
Cattle Barn 1 and the Poultry Barn Renovations Page 7 of 58
CMAR,Pre-Constriction Services July 2017
• List of any Proposed Specialist or Subcontractors required for Pre-Construction
Services
• Proof of insurability for Statutory Workers Compensation Insurance
.,, • Conflict of Interest Affidavit
The Offerors Minority Business Enterprise (MBE) Utilization Plan Documentation will be required
prior to and evaluated as part of the Interview Phase. Refer to Paragraph 2 (Selection of CMAR
Contractor) and Paragraph 3 (Business Diversity Enterprise) for additional information on these
submittals.
9. PROPOSED SUBCONTRACTORS: Acceptance of the Proposal in no way requires the City to
accept the qualifications of the subcontractors. The Subcontractor lists are for use by the City in
preparing recommendations for award of the contract. The Contractor must provide and use
subcontractors listed unless the City agrees to allow a substitute.
10. DISCREPANCIES AND ADDENDA:
Should an Offeror find any discrepancies in the Request for Proposals Documents, or should it be
in doubt as to their meaning, it shall notify the City at once. If required,the City will then prepare a
written addendum that will be available to all Offerors at the place designated for distribution of the
Request for Proposal Documents by the Notice to Offerors. The Contractor is responsible for
determining if addenda are available and for securing copies prior to submitting a response to this
request for sealed Proposals. Oral instructions or decisions unless confirmed by written addenda
will not be considered valid, legal or binding. No extras will be authorized because of failure of the
contractor to include work called for in the addenda.
Offeror must acknowledge addenda in the Proposal. Failure to acknowledge addenda may cause
the Proposal to be ruled non-responsive. It is the Contractor's responsibility to obtain Addenda
and include its information in the Proposal.
11. WORKERS COMPENSATION INSURANCE: Offerors will be required to demonstrate that
coverage is in effect at time of the agreed upon Final Guaranteed Maximum Prices (FGMPs)for
"• Phases I and II. Sample Certificate of Insurance, or other proof that Workers Compensation
Insurance will be obtained, must be submitted within five working days of agreed upon FGMP.
12. TAXES: Equipment and materials not consumed by or incorporated into the work are subject to
State sales taxes under House Bill 11,enacted August 15, 1991,
13. PERMITS: Contractor shall apply for all City of Fort Worth Permits and for any other permits
— required by this project. City of Fort Worth Building and Trade Permit fees are waived. Separate
permits may be required for each work location.
14. UTILITIES AND IMPACT FEES: The City will pay water and sewer utilities tap fees and impact
fees. Unless shown otherwise, the City will coordinate and pay for water and sewer taps and
meters to the property line. The Contractor will include all remaining fees from the electrical and
gas companies in the Base Proposal. The Contractor will be responsible for coordinating with City
and utility companies for installation of utilities. The Contractor will be responsible for all fees for
electrical,gas, and other utilities within the property line of the project. Unless indicated otherwise
on the plans, the contractor will be responsible for costs and installations from the building side of
the water meter and sewer tap.
15. INSTRUCTIONS TO OFFERORS: Offerors may access the Instructions to Offerors, any
Addendum, Sample Contract, General Conditions, Drawings, and any other related documents
through the City's Buzzsaw website at the following link:
https:Hpro*ectr)oint.buzzsaw.com/fortworthgov/PMD%20Proiects/Como%20CMAR?public
Cattle Bam 1 and the Poultry Bam Renovations Page 8 of 58
CMAR,Pre-Constriction services July 2017
16. TESTING SERVICES: The City shall provide for, independently of the contractor, the inspection
services, the testing of construction materials engineering, and the verification testing services
necessary for the acceptance of the construction work.
17. PROJECT SCHEDULE: The Project Schedule will be submitted with the Guaranteed Maximum
Price (GMP) and at the minimum, include the following: quality control submittals and approvals
mobilization, site preparation, under slab utilities, foundation work, structural erection, interior
finish,commissioning,and closeout.
18. STATE FORM 1295 "CERTIFICATE OF INTERESTED PARTIES": Texas Ethics Commission
.� regulations require that the business entity must fill out the Form 1295 on an electronic filing
application on the Texas Ethics Commission website (www.ethics.state.tx.us). The business
entity that wishes to enter into the contract must supply the completed, signed and notarized Form
*w 1295 to the City.
ar~
.w
e�
w
Cattle Barn 1 and the Poultry Barn Renovations Page 9 of 58
CMAR,Pre-Construction Services July 2017
r�
rre
od
CATTLE BARN 1 AND THE POULTRY BARN RENOVATIONS PROJECT
.. PROPOSAL FORM
T0: MR. DAVID COOKE
CITY MANAGER
ATTN: PURCHASING OFFICE
200 TEXAS STREET
CITY OF FORT WORTH,TEXAS
memo I
FOR: Construction Manager-at-Risk Agreement for the Cattle Barn 1 and the Poultry Barn Renovations
04
Located at Will Rogers Memorial Complex
no 3401 Lancaster Ave `
ON Fort Worth,Texas
Project PMD 2017-09
d04
o
Pursuant to the foregoing "INSTRUCTIONS TO CONSTRUCTION MANAGER-AT-RISK (CMAR)
04 OFFERORS", the undersigned understands the amount of work to be done for the Preconstruction
Services and Construction Services, and hereby proposes to do all the work and furnish all labor,
.. equipment and materials necessary to fully complete all the work as provided in the plans and
specifications and subsequent agreed upon Guaranteed Maximum Prices (GMPs) and subject to the
inspection and approval of the Director of Property Management Department of the City of Fort Worth.
Upon acceptance of this Proposal by the City Council and upon subsequent agreement to the GMPs the
Offeror, if the agreement amount exceeds $25,000.00, shall furnish acceptable Performance and
Payment Bonds approved by the City of Fort Worth for performing and completing the Work within the
time agreed to for the following sum,to wit:
DESCRIPTIONS AND COSTS OF ITEMS IN CMAR AGREEMENT
PRE-CONSTRUCTION SERVICES:including Constructability Reviews,Value Engineering
Recommendations and Estimating Services Fees for:
"Cattle Barn 1 and the Poultry Barn Renovations"—Including all associated
Site Utilities,Civil Site Work:
$ -u-
.r
CONSTRUCTION SERVICES: Based on an estimated total budget of $14,000,000.00, your standard
practice regarding project cost structure and your understanding of this project, complete the line items
below. These items are included in the total not-to-exceed estimated construction budget for:
"Defined Fees"—Estimated Budget of$14,000,000.00 for all associated work.
A) $11,550.630.00 82 5 (%of Total Budget)Subcontractors Material Labor and
Equipment(Lump Sum)
B) $ 629,334.00 , % 4.5 (%of Total Budget)General Condition Expenses(Attach
description of items included)
Cattle Bans 1 and the Poultry Barn Renovations Page 10 of 53
CMAR,Pre-Construction Services Jul} 2017
�w
C) $ % 4 (%of Items A+8)Construction Management Fee(Attach
description of items included)
D) $ 965.C111_;.'!__: % 7.5 (7.5%of Items A+B+C) 7.5% Owners Construction Contingency
Allowance(Remaining Contingency allowance will be retained by the City)
E) $ 16$ 180 30 % 12 (%of Items A+B+C+D) Anticipated Cost of insurance and Bonds
�. F) $ -0- % D-tJ (%of Items A+B+C+D) Any other anticipated Costs(Attach
description of items included)
A Project Schedule will be mutually agreed at the time the Guaranteed Maximum Price is developed.
The City reserves the right to accept or reject any and all bids or any combination thereof proposed for the
above work.
The undersigned assures that its employees and applicants for employment and those of any labor
organization, subcontractors or employment agency in either furnishing or referring employee applicants to
the undersigned are not discriminated against as prohibited by the terms of City Ordinance 7278 as
amended by City Ordinance 7400(Fort Worth City Code Section 13A-21 through 13A-29).
Residency of Offerors: The 1985 Session of the Texas Legislature passed House Bill 620 relative to the
award of contracts to non-resident bidders. The law provides that, in order to be awarded a contract as
� low bidder, non-resident bidders (out of state contractors whose corporate offices or principal place of
business are outside of the State of Texas)that bid projects for construction, improvements, supplies or
services in Texas at an amount lower than the lowest Texas resident bidder by the same amount that
Texas resident bidder would be required to underbid a non-resident bidder in order to obtain a comparable
contract in the state in which the non-resident's principal place of business is located. The appropriate
blanks in Section A must be filled out by all non-resident bidders in order for your bid to meet
specifications.
The failure of out of state or non-resident bidders to complete the forms may disqualify that bidder.
"" Resident bidders must check the box in Section B.
d
A. 1J Non-resident vendors in (give state), our principal place of
business,are required to be percent lower than resident bidders by state
law.
1_1 Non-resident vendors in (give state),are not required to
underbid resident bidders.
M" B. Our principal place of business or corporate offices are in the State of
Texas.
•• Apprgved Perfprmance and Payment Bonds for the faithful performance of this contract will be required
upon agreement of the Guaranteed Maximum Prices(GMPs)for Phases I and 11. An acceptable bidder's
bond or cashier's check is NOT REQUIRED with this Request for Proposal.
Cattle Ram t arxi the Poultry Sam Renovations Page 11 of 53
CMAR,Pre-Constmation Services .July 2017
MINORITY BUSINESS ENTERPRISE(MBE):
.� (For Proposals in excess of$50,000)
I am aware that I must submit information concerning the Minority Business Enterprise (MBE) Utilization
Plan with the submittal of this Proposal in order to be considered RESPONSIVE. I will commit to the City's
MBE goals for this project.
Respectfully submitted,
.1r
SEDALCQ NC.
any Na
r1 By:
Signature
Russ Garnsor., President CEO
w Printed Name of Principal Title
Address: 4100 Fossil Creek Blvd.
Street
Fort Worth, Texas 76137-2723
City Zip
Phone: 817.831.2245
Fax: 817.831,2248
Email: RGARRISONASEDALCO.CONI
Receipt is acknowledged of the following addenda:
Addendum No. Addendum No.2:
Addendum No.3. Addendum No.4:
.1111
Addendum No. 5: Addendum No. 13:
r1r
.111
Cattle Barn 1 and the Poultry Barn Renovations Pam 12 of 53
CMAR,Pre-Construction Services Jul} 2017
CONFLICT OF INTEREST AFFIDAVIT
Each bidder, offeror, or respondent (hereinafter also referred to as "you") to a City of Fort Worth
(also referred to as "City') procurement are required to complete Conflict of Interest Questionnaire
(the attached CIO Form) and. Local Government Officer Conflicts [disclosure Statement(the attached
CIS Form) below pursuant to state law. This affidavit will certify that the Bidder has on file with the
City Secretary the required documentation and is eligible to bid on City Work. The referenced forms
may be downloaded from the website links provided below,
httoa/www ethics,state.tx.us,forms/C10.odf
htto://www.eth�cs.state.tx.as:formsZ1S-Qdf
CIO Form is on file with City Secretary
® CICS Form is being provided to the City Secretary
® CIS Form is on File with City Secretary
0 CIS Form is being provided to the City Secretary
BIDDER:
SEDALCC INC. By:
Company (Please Print) Russ Garrison,President!CE
too fog Address: 4100 Fossil Creek Blvd.
Fort Worth,Texas 76137-2723
.r Cattle Sam 1 and the Poultry Elam Renovations Page 13 of 53
CMAR,Pre-Construction Services July 2017
CONFLICT OF INTEREST QUESTIONNAIRE FORM ClQ
For vendor or other person doing business with local governmental entity
OFFICE USE ONLY
This questionnaire is being filed in accordance with chapter 176 of the Local Date Received
Government Code by a person doing business with the governmental entity.
By law this questionnaire must be filed with the records administrator of the local
government not later than the 7th business day after the date the person becomes
aware of facts that require the statement to be filed_ See Section 176.006, Local
Government Code.
A person commits an offense if the person violates Section 176.006, Local
Government Code.
An offense under this section is a Class C misdemeanor.
1. Name of person doing business with local governmental entity.
Russ Garrison President/CEO of SEDALCO INC.
z.
Check this box if you are filing an update to a previously filed questionnaire.
(The law requires that you file an updated completed questionnaire with the appropriate filing authority not later than
September I of the year for which an activity described in Section 176.006(a),Local Government Code,is pending
and not later than the 7th business day after the date the originally filed questionnaire becomes incomplete or
inaccurate.)
3. Describe each affiliation or business relationship with an employee or contractor of the local
governmental entity who makes recommendations to a local government officer of the local governmental
entity with respect to expenditure of money.
None
4. Describe each affiliation or business relationship with a person who is a local government officer and who
**a appoints or employs a local government officer of the local governmental entity that is the subject of this
questionnaire.
..� None
•r
�+ Cattle Bam 1 and the Poultry Barn Renovations Page 14 of 53
CMAR,Pre-Construction Services July 2017"
+w
w
CONFLICT OF INTEREST QUESTIONNAIRE FORM CIQ
For vendor or other person doing business with local governmental entity Page 2
i 5. Name of local government officer with whom filer has affiliation or business relationship. (Complete this
section only if the answer to A,B,or C is YES.)
This section,item 5 including subparts A. B,C&D. must be completed for each officer with whom the filer has
affiliation or business relationship. Attach additional Rages to this Form CIQ as necessary.
A. Is the local government officer named in this section receiving or likely to receive taxable income from the
woo filer of the questionnaire?
❑ Yes ❑ No Not Applicable
B. Is the filer of the questionnaire receiving or likely to receive taxable income from or at the direction of the
local government officer named in this section AND the taxable income is not from the local governmental
e.a� entity'
❑ Yes ❑ No Not Applicable
..i
C. Is the filer of this questionnaire affiliated with a corporation or other business entity that the local government
officer serves as an officer or director,or holds an ownership of 10 percent or more?
❑ Yes
❑ No Not Applicable
D. Describe each affiliation or business relationship.
None
moo
6. Describe any other affiliation or business relationship that might cause a conflict of interest.
None
7.
Augug 3,2017
r� Signature of person doing b 'n s with the governmental entity Date
now
Cattle Barn t and the Poultry Barn Renovations Page 15 of 53-- -
CM1AR,Pre-Construction Services Judy 2017
.�e
CONFLICT OF INTEREST QUESTIONNAIRE
For vendor doing business with local governmental entity
A complete copy of Chapter 176 of the Local Government Code maybe found athftp://www.statutes.legis.state.tx.us/
Docs/LG/htm/LG.176.htm.For easy reference,below are some of the sections cited on this form.
Local Government Code§176.001(1-a):'Business relationship"means a connection between two or more parties
based on commercial activity of one of the parties. The term does not include a connection based on:
(A) a transaction that is subject to rate or fee regulation by a federal,state,or local governmental entity or an
agency of a federal,state,or local governmental entity;
(B) a transaction conducted at a price and subject to terms available to the public;or
(C) a purchase or lease of goods or services from a person that is chartered by a state or federal agency and
that is subject to regular examination by,and reporting to,that agency.
Local Government Code 4 176.003(a)(2)(A)and(B):
(a) A local government officer shall file a conflicts disclosure statement with respect to a vendor if:
(2) the vendor:
(A) has an employment or other business relationship with the local government officer or a
family member of the officer that results in the officer or family member receiving taxable
income, other than investment income, that exceeds $2,500 during the 12-month period
preceding the date that the officer becomes aware that
(i) a contract between the local governmental entity and vendor has been executed;
or
(ii) the local governmental entity is considering entering into a contract with the
vendor,
(B) has given to the local government officer or a family member of the officer one or more gifts
that have an aggregate value of more than$100 in the 12-month period preceding the date the
officer becomes aware that:
(i) a contract between the local governmental entity and vendor has been executed;or
(ii) the local governmental entity is considering entering into a contract with thevendor.
Local Government Code 4176.006(a)and (a-1)
(a) A vendor shall file a completed conflict of interest questionnaire if the vendor has a business relationship
with a local governmental entity and:
(1) has an employment or other business relationship with a local government officer of that local
governmental entity,or a family member of the officer,described by Section 176.003(ax2)(A);
(2) has given a local government officer of that local governmental entity,or a family member of the
officer,one or more gifts with the aggregate value specified by Section 176.003(a)(2)(B),excluding any
gift described by Section 176.003(a-1);or
(3) has a family relationship with a local government officer of that local govemmentalentity.
(a-1)The completed conflict of interest questionnaire must be filed with the appropriate records administrator
not later than the seventh business day after the later of:
(1) the date that the vendor:
(A) begins discussions or negotiations to enter into a contract with the local governmental
entity; or
(B) submits to the local governmental entity an application,response to a request for proposals
or bids, correspondence, or another writing related to a potential contract with the local
governmental entity;or
(2) the date the vendor becomes aware:
(A) of an employment or other business relationship with a local government officer„ or a
family member of the officer,described by Subsection(a);
(B) that the vendor has given one or more gifts described by Subsection(a);or
(C) of a family relationship with a local government officer.
Form provided by Texas Ethics Commission www.ethics.state.tx.us Revised 11/30/2015
TEXAS SALES AND USE TAX EXEMPTION CERTIFICATE
Name of Purchaser, Firm or Agency: City of Fort Worth,Texas
Address(Street&Number,P.O.Box or Route Number): 1000 Throckmorton
City,State,Zip Code: Fort Worth,Texas 76102
Telephone: (817)392-8360
1,the purchaser named above,claim an exemption from payment of sales and use
taxes for the purchase of taxable items described below or on the attached order or
invoice from:
All vendors
Description of the items to be purchased,or on the attached order or invoice:
••r
All items except motor vehicles as listed below
Purchaser claims this exemption for the following reason*
Governmental Entity
I understand that I will be liable for payment of sales or use taxes which may become
,.. due for failure to comply with the provisions of the state,city,and/or metropolitan transit
authority sales and use tax laws and comptroller rules regarding exempt purchases.
Liability for the tax will be determined by the price paid for the taxable items purchased
or the fair market rental value for the period of time used.
I understand that it is a misdemeanor to give an exemption certificate to the seller for
taxable items which I know,at the time of purchase,will be used in a manner other than
expressed in this certificate and that upon conviction I may be fined not more than$600
per offense.
Purchaser: ldoDk-
Title:
Purchasing Mananer Date: February 1.2007
Note:This certificate cannot be issued for the purchase, lease or rental of a motor
vehicle.
THIS CERTIFICATE DOES NOT REQUIRE A NUMBER TO BE VALID
Sales and Use Tax"Exemption Numbers"or"Tax Exempt"Numbers do not exist.
... This certificate should be fumished to the supplier Do not send the completed
certificate to the Comptroller of Public Accounts.
2013 PREVAILING WAGE RATES
Commercial Construction Projects
CLASSIFICATION •
AC Mechanic 25.24
.r AC Mechanic Helper $
13.67
.�. Acoustical Ceiling Installer $
16.83
Acoustical Ceiling Installer Helper 12.70
Bricklayer/Stone Mason 14 5
Bricklayer/Stone Masan Trainee $
13.31
Bricklayer/Stone Mason Helper $
10.91
Carpenter $
� 17.75
Carpenter Helper $
14.32
Concrete Cutter/Sawer $
17000
Concrete Cutter/Sawer Helper $
1
Concrete Finisher $
15.77
Concrete Finisher Helper $
11.00
�. Concrete Form Builder $
15.27
Concrete Form Builder Helper 1 00
[Drywall Mechanic $
15.36
••• Drywall Helper $
12.54
Drywall Taper $
15.00
Drywall Taper Helper $
11.50
Electrician(Journeyman) 1&3
Electrician Apprentice(Helper) $
15.64
Electronic Technician 20 0
Floor Layer $
18.00
" Floor Layer Helper $
10.00
Glazier $
21.03
Glazier Helper $
12.81
Insulator $
16.59
Insulator Helper $
11.21
Laborer Common $
10.89
Laborer Skilled $
14.15
Lather $
12.99
Metal Building Assembler 16.00
Metal Building Assembler Helper $
12.00
Metal Installer(Miscellaneous) 13.00
Metal Installer Helper(Miscellaneous) $
11.00
Metal Stud Framer $
16.12
Metal Stud Framer Helper $
12.54
Painter $
16.44
Painter Helper $
9.98
Pipefitter $
21.22
.. Pipefitter Helper1 39
Plasterer $
16.17
Plasterer Helper $
12.85
Plumber $
21.98
Plumber Helper $
15.85
Reinforcing Steel Setter 1 87
..
Reinforcing Steel Setter Helper 11.08
.,, Roofer $
16.90
Roofer Helper $
11.15
Sheet Metal Worker $
16.35
Sheet Metal Worker Helper $
13.11..r Sprinkler System Installer $
19.17
® Sprinkler System Installer Helper $
14.15
Steel Worker Structural $
17.00
Steel Worker Structural Helper $
13.74w,
Waterproofer $
15.00
Equipment Operators
Concrete Pump
18.50
Crane,Clamshell,Backhoe,Derrick,D'Line Shovel $
wa 19.31
Forklift $
16.45
Foundation Drill Operator 22.50
Front End Loader $
16.97
Truck Driver $
16.77
Welder $
19.96
Welder Helper $
13.00
The prevailing wage rates shown for Commercial construction projects were based on a salary survey
conducted and published by the North Texas Construction Industry(Fall 2012)Independently compiled
by the Lane Gorman Trubitt,PLLC Construction Group. The descriptions for the classifications listed are
provided on the TEXCI's(The Construction Association)website.
www.texoassodation.org/Chapter/wagerateLasp
CITY OF FORT WORTH
WEATHER TABLE
Average Days
Month of Inches of Rainfall
Rain/Snow/Ice
January 6 2.51
February 7 2.23
w March 9 3.49
April 7
May 10 4.56
w June 8 3.31
July 4 1.83
August 5 1.88
September 5 2.34
October 7 3.65
... November 7 2.70
December 6 2.34
Annually 81 33.81
(1) Mean number of days precipitation of 0.01" or more or 1/2" snow/ice
(2)Average normal precipitation, in inches
This table is based on information reported from Dallas-Fort Worth International Airport,
Texas. Latitude 32 deg 54 min north, longitude 97 deg 02 min west, elevation (ground) 551 ft.
-- Average number of days of rain, snow, and ice days are based on records covering 21 years.
Precipitation is based on recorded information from 1996 through 2016 period.
This table is to be used as a baisis for calculation of excess rain or weather days for projects
with duration in calendar days. If the site records indicate that the Contractor was unable to
carry out operations due to weather, it is counted as a weather day. If the number of weather
days exceeds the number of average rain days plus the snow/ice days for the contract
duration, the contract will be adjusted by Change Order,
Fort Worth Weather Table 24 April 2017
City of Fort Worth, Texas
Transportation Public Works Department
Facilities Management Group/Architectural Services Division
GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
CONSTRUCTION MANAGER-AT-RISK CONTRACT
SECTION A
DEFINITIONS,PROCEDURES AND INTERPRETATIONS
X1 CONTRACT DOCUMENTS: By the term Contract Documents is meant all of the written and drawn documents setting
forth or affecting the rights of the parties,including but not necessarily limited to,the Contract,Notice to Bidders,Proposal,General
Conditions,Special Conditions,Specifications,Plans,Bonds and all Addenda,Amendments signed by all parties,Change Orders,
written Interpretations and any written Field Order for a minor change in the Work.
® A-2 ENTIRE AGREEMENT: The Contract Documents represent the entire agreement between the Parties,and no prior or
contemporaneous, oral or written agreements, instruments or negotiations shall be construed as altering the terms and effects of
the Contract Documents. After being executed,the Contract Documents can be changed only by a written Amendment signed by
the Contractor and the Owner.or Change Order,or by a written Field Order for a minor change.
_+ A-3 WORK: By the term Work is meant all labor supervision,materials and equipment necessary to be used or incorporated
in order to produce the construction required by Contract Documents.
A-4 EXECUTION OF THE CONTRACT DOCUMENTS: The Contract Documents shall be executed in six originals,with all
required attachments,including required bonds and insurance certificates,by the Contractor and the Owner in such form as may be
prescribed by law and returned to the Owner within ten business days of notification to Contractor. Failure to execute contracts and
provide required enclosures will be grounds for revocation of award and taking of Bid Bond.
/M5 FAMILIARITY WITH PROPOSED WORK: Before filing a Proposal, the bidder shall examine carefully the, plans,
specifications,special provisions,and the form of contract to be entered into for the work contemplated. He shall examine the site
of work and satisfy himself as to the conditions that will be encountered relating to the character,quality and quantity of work to be
performed and materials to be furnished. The filing of a bid by the bidder shall be considered evidence that he has complied with
these requirements and has accepted the site as suitable for the work.
Claims for additional compensation due to variations between conditions actually encountered in construction and as indicated by
the plans will not be allowed.
A-6 ONE UNIFIED CONTRACT: Insofar as possible, the Contract Documents will be bound together and executed as a
single unified Contract. The intention of the Contract Documents being to provide for all labor, supervision, materials,equipment
and other items necessary for the proper execution and completion of the Work. Words that have well-recognized technical or
trade meanings are used herein in accordance with such recognized meanings.
A-7 DIVISION OF WORK: The arrangement of Drawings and/or Specifications into Divisions, Sections, Articles, or other
*� Subdivisions shall not be binding upon the Contractor in dividing the work among Subcontractors or Trades.
A18 INTERPRETATIONS: The Architect will furnish such Interpretations of the Plans and Specifications as may be
necessary for the proper execution or progress of the work. Such Interpretations shall be furnished at the instance of the Architect
or at the request of the Contractor,or Owner,and will be issued with reasonable promptness and at such times and in accordance
with such schedule as may be agreed upon. Such Interpretations shall be consistent with the purposes and intent of the Plans and
Specifications and may be effected by Field Order In the event of any dispute between any of the parties to the Contract and the
Architect or each other involving the interpretation of the Contract Documents, the evaluation of work or materials performed or
fumished by the Architect Contractor, or any subcontractor or materialsman, or involving any question of fault or liability of any
party,the decision of the Owner shall be final and binding.
In the event of inconsistency in the contract documents, the following sequence for interpretation shall be used in order of
precedence: Change Orders and/or Field Orders (by date of issuance); Addenda (by date of issuance); Drawings; Notes and
dimensions on Drawings; Technical Specifications; Special Provisions; Supplementary General Conditions; General Conditions;
and,Construction Contract.
A-9 COPIES OF WORKING DRAWINGS AND SPECIFICATIONS: The Architect will furnish to Contractor free of charge 15
sets of working Drawings and 15 sets of Specifications. Contractor shall pay the cost of reproduction for all other copies of
Drawings and Specifications fumished to him.
All Drawings, Specifications and copies thereof furnished by the Owner or the Architect are and shall remain the property of the
Owner. They are not to be used on any other project and,with the exception of one Contract set for each Party to the Contract,are
to be returned to the Owner on request at the completion of the work.
Cattle Barn 1 and the Poultry Barn Renovations Page 27 of 58
CMAR,Pre-Construction Services July 2017
A-10 MINORITY BUSINESS ENTERPRISE(MBE)POLICY: As of June 1,2012,The City of Fort Worth has implemented the
new Business Diversity Ordinance(BDO)to reflect the City's availability and disparity study findings and recommendations. During
this transition period interested Offerors must obtain an MBE listing of African American firms from the M/WBE Office at 817-212-
2674. This will ensure that MBE listings reflect only those currently certified by the North Central Texas Regional Certification
Agency (NCTRCA) located in the six (6)-county geographic marketplace that have been accepted by the City. The City's
geographic marketplace includes the counties of: Tarrant, Dallas, Denton, Johnson, Parker and Wise. Offerors are strongly
encouraged to confirm that each MBE that it intends to use is located in the geographic marketplace that will be counted towards
the established goal.
The City of Fort Worth has goals for the participation of Minority Business Enterprises(MBE)in City contracts. Compliance with the
policies designed to meet these goals is mandatory in order to be considered a responsive bidder, The City policy and procedures
to be followed in submitting proposals are included.
... The City of Fort Worth MBE Program will take precedence over other subcontractor utilization programs
on Block Grant and other federally funded Projects.
A-11 CORRELATION AND INTENT: In general,the drawings indicate dimension,locations,positions,quantities,and kinds of
construction;the specifications indicate the quality and construction procedures required. Work indicated on the drawings and not
specified of vice-versa,shall be furnished as though set forth in both. Work not detailed,marked or specified shall be the same as
similar parts that are detailed,marked or specified. If the drawings are in conflict or conflict with the specifications the better quality
or greater quantity or work or materials shall be estimated and shall be furnished or included. Dimensions on drawings shall take
precedence over small-scale drawings. Drawings showing locations of equipment,piping,ductwork,electrical apparatus,etc.,are
^� diagrammatic and job conditions may not allow installation in the exact location shown. Relocation shall not occur without the
Architects approval.
A-12 Ate: In accordance with the policy("Policy")of the Executive Branch of the federal government,Contractor covenants
that neither it nor any of its officers, members, agents, employees, program participants or subcontractors, while engaged in
performing this contract,shall, in connection with the employment,advancement or discharge of employees or in connection with
the terms,conditions or privileges of their employment,discriminate against persons because of their age except on the basis of a
bona fide occupational qualification,retirement plan or statutory requirement.
Contractor further covenants that neither it nor its officers,members,agents,employees,subcontractors,program participants,or
persons acting on their behalf, shall specify,in solicitations or advertisements for employees to work on this contract,a maximum
age limit for such employment unless the specified maximum age limit is based upon a bona fide occupational qualification,
retirement plan or statutory equipment.
Contractor warrants it will fully comply with the Policy and will defend, indemnify and hold City harmless against any claims or
allegations asserted by third parties or subcontractor against City arising out of Contractor's and/or its subcontractors' alleged
failure to comply with the above referenced Policy concerning age discrimination in the performance of this agreement.
A-13 DISABILITY: In accordance with the provisions of the Americans With Disabilities Act of 1990 ("ADA"), Contractor
warrants that it and any and all of its subcontractors will not unlawfully discriminate on the basis of disability in the provision of
services to the general public,nor in the availability,terms and/or conditions of employment for applicants for employment with,or
employees of Contractor or any of its subcontractors. Contractor warrants it will fully comply with ADA provisions and any other
applicable federal,state and local laws concerning disability and will defend,indemnify and hold City harmless against any claims
.�. or allegations asserted by third parties or subcontractors against City arising out of Contractor's and/or its subcontractors'alleged
failure to comply with the above-referenced laws concerning disability discrimination in the performance of this agreement.
SECTION B
IDENTITY OF ARCHITECT
B-1 CONTRACT ADMINISTRATION: Where the term "Architect" is used in the "General Conditions of the Contract for
Construction",it shall refer to the Director,Transportation and Public Works or his designated Building Construction Manager, The
Director,Transportation will designate a Project Manager and Building Construction Manager(BCM)to administer this contract and
perform the functions of the "Architect"as indicated in the General Conditions. The design architect or engineer may also be
designated to perform the duties of"Architect". The term"City"and"Owner"are used interchangeably and refer to the City of Fort
Worth as represented by the Director of Transportation and Public Works or his designated representative.
^^' B-2 TERMINATION AND SUSPENSION OF WORK: The Owner has the right to terminate the Project for any reason. If the
project is terminated,the Contractor shall:
a) Stop work under the Contract on the date and to the extent specked on the notice of termination.
... b) Place no further orders or subcontracts except as may be necessary for the completion of the work not terminated.
C) Terminate all orders and subcontracts to the extent that they relate to the performance of the work terminated by the
notice of termination.
After termination as above,the City will pay the Contractor a proportionate part of the contract price based on the work completed;
provided, however,that the amount of payment on termination shall not exceed the total contract price as reduced by the portion
thereof allocatable to the work not completed and further reduced by the amount of payments,if,any otherwise made. Contractor
shall submit its claim for amounts due after termination as provided in this paragraph within 30 days after receipt of such claim. In
�" the event of any dispute or controversy as to the propriety or allowability of all or any portion of such claim under this paragraph,
such dispute or controversy shall be resolved and be decided by the City Council of the City of Fort Worth,and the decision by the
City Council of the City of Fort Worth shall be final and binding upon all parties to this contract.
B-3 DUTIES OF THE ARCHITECT: As used herein,the term Architect means the Architect or his authorized representative.
... Nothing contained in these Contract Documents shall create any privity of Contract between the Architect and the Contractor.
B-4 ARCHITECT AS REPRESENTATIVE OF THE OWNER: The Building Construction Manager will provide general
administration of the Contract on behalf of the Owner and will have authority to act as the representative of the Owner to the extent
provided in the Contract Documents unless changed in writing by the Owner. The Architect will be available for conferences and
consultations with the Owner or the Contractor at all reasonable times.
B-5 ACCESS TO JOB SITES: The Architect shall at all times have access to the Work whenever it is in preparation and
progress. The Contractor shall provide facilities for such access so the Architect may perform its assigned functions under the
Contract Documents.
The Architect will make periodic visits to the Site to familiarize himself with the progress and quality of the work and to determine if
the work is proceeding in accordance with the Contract documents. On the basis of on-site observations,the Architect will keep the
Owner informed of the progress of the Work and will endeavor to guard the Owner against defects and deficiencies in the Work of
the Contractor. Based upon such observations and the Contractor's applications for payments,the Building Construction Manager
will make determinations and recommendations concerning the amounts owing to the Contractor and will issue certificates for
payment amounts.
B-6 INTERPRETATIONS: The Architect will be, in the first instance, the interpreter of the requirements of the Plans and
Specifications and the judge of the performance thereunder by the Contractor subject to the final decision of the Owner.
The Architect's decisions in matters relating to artistic effect will be final if consistent with the intent of the Contract Documents.
B-7 AUTHORITY TO STOP WORK: The BCM will have authority to reject work that does not conform to the Plans and
Specifications. In addition,whenever,in its reasonable opinion,the BCM considers it necessary or advisable in order to insure the
proper realization of the intent of the Plans and Specifications, the BCM will have authority to require the Contractor to stop the
Work or any portion thereof,or to require special inspection or testing of the Work whether or not such Work be then fabricated,
installed or completed.
B-8 MISCELLANEOUS DUTIES OF ARCHITECT
Shop Drawings. The Architect will review Shop Drawings and Samples. Two copies of each approved Shop Drawing and submittal
.r will be provided to the Owner by the Architect. Three copies will be returned to the Contractor.
Change Orders. Change Orders and Field Orders for Minor Changes in the Work will be issued by the Owner
Guarantees. The Owner will receive all written guarantees and related documents required of the Contractor. Upon completion of
.� the project the Contractor shall provide the Owner five copies of each guarantee.
Inspections The Owner will conduct inspections for the purpose of determining and making his recommendations concerning the
dates of substantial completion and final completion. The Architect will conduct the final acceptance inspection and issue the
Certificate of Completion.
Operation and Maintenance Manuals The Owner will receive six copies of all applicable equipment installation, operation, and
maintenance brochures and manuals required of the Contractor.
,.. B-9 TERMINATION OF THE ARCHITECT: In case of the termination of the employment of the Architect by the Owner,the
Owner shall either assume the duties of the Architect through the Director of the Department of Transportation and Public Works,
or shall appoint a successor Architect against whom the Contractor makes no reasonable objection.
SECTION C
OWNER
C-1 IDENTIFICATION: By the term Owner is meant the City of Fort Worth acting herein by its duly authorized
representatives in the manner provided by law. Authorized representatives include the City Manager,Assistant City Manager,the
Director and of Transportation and Public Works Department and members of the Facilities Management Division. Generally
speaking a designated representative will be a Building Construction Manager identified from within the Facilities Management
Group to act as a point of contact for day-to-day contract administration.
�. C-2 DUTIES OF THE OWNER: The Owner shall furnish surveys describing the physical characteristics, legal limits and
utility locations for the site of the Work; provided, however, that the Contractor hereby covenants that he has inspected the
premises and familiarized himself therewith and that the locations of utilities and other obstacles to the prosecution of the Work as
shown on the Owner's survey are for information only,are not binding upon the Owner,and the Owner shall not incur any liability
for loss or damage by virtue of any inaccuracies or deficiencies in such surveys. The Owner shall secure and pay for title to the site
and all necessary permanent or construction easements. The Owner will cooperate with the Contractor in the prosecution of the
Work in such manner and to such extent as may be reasonable and shall furnish information under its control with reasonable
promptness at the request of the Contractor.
C-3 INSTRUCTIONS: The Owner shall issue all instructions to the Contractor through the BCM.
C-4 ACCESS TO JOB SITE: The Owner shall at all times have access to the Work whenever it is in preparation and
progress. The Contractor shall provide facilities for such access so the Owner may perform its assigned functions under the
Contract Documents.
C-5 PROGRESS INSPECTIONS: The Owner will make visits to the Site to familiarize themselves with the progress and
quality of the Work and to determine if the work is proceeding in accordance with the Contract documents. On the basis of on-site
observations and reports concerning the progress and quality of the work,the Owner will approve and authorize the Contractor's
applications for payments.
C-6 AUTHORITY TO STOP WORK: The Owner will have authority to reflect work that does not conform to the Plans and
Specifications. Whenever, in its reasonable opinion,the Owner considers it necessary or advisable in order to insure the proper
realization of the intent of the Plans and Specifications,the Owner will have authority to require the Contractor to stop the work or
any portion thereof,or to require the Contractor to stop the Work or any portion thereof,or to require special inspection or testing of
the Work whether or not such Work be then fabricated,installed or completed.
C-7 SUBSTANTIAL COMPLETION INSPECTION: Upon agreement of the Contractor and Architect that the Work is
substantially complete,the Owner will schedule a Substantial Completion Inspection to be conducted by the Architect and attended
by representatives of the Architect,Owner and Contractor. Items identified during this inspection as being incomplete,defective or
deficient shall be incorporated into a punch list and attached to the AIA document G704,which is to be prepared and signed by the
Contractor and accepted,approved and signed by the Owner.
C-8 RIGHT TO AUDIT: Contractor agrees that the City shall,until the expiration of three years after final payment under this
contract, have access to and the right to examine any directly pertinent books,documents,papers and records of the Contractor
involving transactions relating to this contract.
Contractor further agrees to include in all his subcontracts hereunder a provision to the effect that the subcontractor agrees that the
.• City shall,until the expiration of three years after final payment under the subcontract,have access to and the right to examine any
directly pertinent books,documents,papers and records of such subcontractor,involving transactions to the subcontract.The term
"subcontract"as used herein includes purchase orders.
Contractor agrees to photocopy such documents as may be requested by the city. The city agrees to reimburse Contractor for the
costs of copies at the rate published in the Texas Administrative Code.
SECTION D
CONTRACTOR
D-1 IDENTIFICATION: The Contractor is the person or organization identified as such in the Contract.The term Contractor
means the Contractor or his authorized representative.
D-2 INDEPENDENT CONTRACTOR: Contractor shall perform all work and services hereunder as an independent
contractor, not as agent,or employee of the City. Contractor shall have exclusive control of and the exclusive right to control the
details of the Work and services performed hereunder,and all persons performing same,and Contractor shall be solely responsible
for the acts of its officers,agents,and employees. Nothing herein shall be construed as creating a partnership or joint enterprise
between City and the Contractor,its officers,agents and employees,and the doctrine of respondeat superior shall not apply.
D-3 SUBLETTING: It is further agreed that the performance of this Contract,either in whole or in part,shall not be sublet or
assigned to anyone else by said Contractor without the written consent of the Director of Transportation and Public Works of the
City of Fort Worth.
D-4 REVIEW OF CONTRACT DOCUMENTS: The Contractor shall carefully study and compare the Agreement,Conditions
of the Contract,Drawings,Specifications,Addenda and modifications and shall at once report to the Owner and to the Architect any
error inconsistency or omission he may discover. The Contractor shall do no work without Drawings, Specifications and
Interpretations.
D-5 SUPERVISION: The Contractor shall supervise and direct the Work,using his best skill and attention.He shall be solely
responsible for all construction means,methods,safety,techniques,sequences and procedures and for coordinating all portions of
the Work under the Contract Documents.
«. D-6 LABOR AND MATERIALS: Unless otherwise specifically noted, the Contractor shall provide and pay for all labor
materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation and other facilities and
services necessary for the proper execution and completion of the Work.
The successful low bidder will use its reasonable best efforts to hire local laborers, workmen and materialmen. The general
condition is not to be constructed as limiting the right of any bidder to employee laborers, workmen or materialmen from outside
local area.
�.. The Contractor shall at all times enforce strict discipline and good order among his employees,and shall not employ on the Work
any unfit person or anyone not skilled in the task assigned to him.
D-7 COMPLIANCE WITH AND ENFORCEMENT OF PREVAILING WAGE RATE
... Duty to nay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258,Texas Government Code
(Chapter 2258),including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the
prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these contract documents.
Penalty for Violation. A contractor or any subcontractor who does not pay the prevailing wage shall,upon demand made by the
City,pay to the City$60 for each worker employed for each calendar day or part of the day that the worker is paid less than the
prevailing wage rates stipulated in these contract documents.This penalty shall be retained by the City to offset its administrative
costs,pursuant to Texas Government Code 2258.023.
Complaints of Violations and City Determination of Good Cause. On receipt of information,including a complaint by a worker
concerning an alleged violation of 2258.023,Texas Government Code,by a contractor or subcontractor,the City shall make an
initial determination,before the 318t day after the date the City receives the information,as to whether good cause exists to believe
that the violation occurred. The City shall notify in writing the contractor or subcontractor and any affected worker of its initial
determination. Upon the City's determination that there is good cause to believe the contractor or subcontractor has violated
Chapter 2258,the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and
wages due under the prevailing wage rates,such amounts being subtracted from successive progress payments pending a final
determination of the violation.
Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023,Texas Government
Code,including a penalty owed to the City or an affected worker,shall be submitted to binding arbitration in accordance with the
Texas General Arbitration Act(Article 224 et seq.,Revised Statutes)if the contractor or subcontractor and any affected worker do
not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to paragraph
(c)above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required,a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the
arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of
competent jurisdiction.
.. Records to be Maintained. The Contractor and each subcontractor shall,for a period of three(3)years following the date of
acceptance of the Work,maintain records that show(i)the name and occupation of each worker employed by the Contractor in the
construction of the Work provided for in this contract;and(ii)the actual per diem wages paid to each worker The records shall be
open at all reasonable hours for inspection by the City. The provisions of the Audit section of these contract documents shall
pertain to this inspection.
Pay Estimates. With each partial payment estimate or payroll period,whichever is less,the Contractor shall submit an affidavit
stating that the Contractor has complied with the requirements of Chapter 2258,Texas Government Code.
Posting of Wage Rates. The Contractor shall post the prevailing wage rates in a conspicuous place at the site of the project at all
times.
Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its subcontractors
to comply with paragraphs(a)through(g)above.
On projects where special wage rates apply(e.g.Davis-Bacon)the Contractor agrees to meet all requirements of such programs.
D-8 WARRANTY: The Contractor warrants to the Owner and the Architect that all materials and equipment furnished under
this Contract will be new unless otherwise specked,and that all work will be of good quality,free from faults and defects,and in
•" conformance with the Contract Documents. All work not so conforming to these standards may be considered defective. If
required by the Architect or the Owner,the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and
equipment.
The warranty provided in this Section shall be in addition to and not in limitation of any other warranty or remedy provided by law or
the Contract Documents.
D-9 TAXES: The Contractor is exempt from State Sales Tax on material incorporated into the finished construction,Excise
and Use Tax.
D-10 LICENSES, NOTICES AND FEES: The Contractor shall obtain all Permits, Licenses, Certificates, and Inspections,
whether permanent or temporary,required by law or these Contract Documents. The City of Fort Worth Building and Trade Permit
fees are waived. Separate permits may be required for each work location.
... The Contractor shall give all Notices and comply with all Laws,Ordinances,Rules,Regulations and Orders of any public authority
bearing on the performance of the Work. If the Contractor observes or becomes aware that any of the Contract Documents are at
variance therewith in any respect,he shall promptly notify the Architect Owner in writing and any necessary changes will be made.
If the Contractor performs any Work knowing that it is in violation of, or contrary to, any of such Laws, Statutes, Charter
.. Ordinances, Orders or Directives, or Regulations without furnishing Notice to the Owner the Contractor will assume full
responsibility therefore and bear all costs attributable thereto.
D-11 CASH ALLOWANCES: The Contractor shall include in the Contract Sum all allowances stated in the Contract
Documents.These allowances shall cover the net cost of the materials and equipment delivered and unloaded at the site,and all
applicable taxes. The Contractor's handling costs on the site, labor, installation costs, overhead, profit and other expenses
contemplated for the original allowance shall be included in the Contractor Sum and not in the allowance. The Contractor shall
cause the Work covered by these allowances to be performed for such amounts and by such persons as the Owner may direct,but
he will not be required to employ persons against whom he makes a reasonable objection. If the cost,when determined, is more
® than or less than the allowance, the Contract Sum shall be adjusted accordingly by Change Order which will include additional
handling costs on the site,labor,installation costs,field overhead,profit and other direct expenses resulting to the Contractor from
any increase over the original allowance.
D-12 SUPERINTENDENT: The Contractor shall employ a competent superintendent and necessary assistants who shall be in
�* attendance at the Project site during the progress of the Work.The superintendent shall be satisfactory to the Contractor and the
Owner The superintendent shall represent the Contractor and all communications given to the superintendent shall be binding as if
given to the Contractor. Important communications will be confirmed in writing. Other communications will be so confirmed on
written request in each case.
D-13 RESPONSIBILITIES FOR EMPLOYEES AND SUB-CONTRACTORS: The Contractor shall be responsible to the Owner
for the acts and omissions of all his employees and all Sub-contractors, their agents and employees, and all other persons
performing any of the Work under a contract with the Contractor.
D-14 FAILURE TO COMMENCE WORK: Should the Contractor fail to begin the Work herein provided for within the time
herein fixed or to carry on and complete the same according to the true meaning of the intent and terms of said Plans,
Specifications and Contract Documents,then the Owner shall have the right to either demand the surety to take over the Work and
complete same in accordance with the Contract Documents or to take charge of and complete the Work in such a manner as it
may deem proper,and if,in the completion thereof,the cost to the said City shall exceed the contract price or prices set forth in the
said plans and specifications made a part hereof,the Contractor and/or its Surety shall pay said City on demand in writing,setting
forth and specifying an itemized statement of the total cost thereof,said excess cost.
D-15 PROGRESS SCHEDULE: The Contractor, immediately after being awarded the contract,shall prepare and submit for
the Architect's approval, an estimated progress schedule for the Work. The progress schedule shall be related to the entire
Project. This schedule shall indicate the dates for the starting and completion of the various states of construction and shall be
revised as required by the conditions of the Work,subject to the Architect's approval. It shall also indicate the dates for submission
and approval of shop drawings and submittals as well as the delivery schedule for major pieces of equipment and/or materials.
�. The Contractor shall submit an updated progress schedule the BCM at least monthly for approval along with the Contractor's
monthly progress payment requests.
D-16 DRAWINGS AND SPECIFICATIONS AT THE SITE: The Contractor shall maintain at the site for the Owner one copy of
all Drawings, Specifications, Addenda, approved Shop Drawings, Change Orders, and other Changes and Amendments in good
order and marked to record all changes made during construction. These shall also be available to the Architect. The Drawings,
marked to record all changes made during construction, shall be delivered to the Owner upon completion of the Work. The
Architect will prepare,and provide to the Owner,one complete set of reproducible record drawings of the Work.
D-17 SHOP DRAWINGS AND SAMPLES: Shop Drawings are drawings, diagrams, illustrations, schedules, performance
charts, brochures and other data which are prepared by the Contractor or any Subcontractor,manufacturer,supplier or distributor,
and which illustrate some portion of the Work.
Samples are physical examples fumished by the Contractor to illustrate materials, equipment or workmanship, and to establish
standards by which the Work will be judged.
The Contractor shall review, stamp with his approval and submit,with reasonable promptness and in orderly sequence so as to
cause no delay in the Work or in the work of any other contractor,normally within the first 90 days of the work,six copies of all shop
Drawings and Samples required by the Contract Documents or subsequently by the Architect as covered by changes or
amendments.Shop Drawings and Samples shall be properly identified as specked,or as the Architect may require.At the time of
submission the Contractor shall inform the Architect in writing of any deviation in the Shop Drawings or Samples from the
requirements of the Contract Documents.
... By approving and submitting Shop Drawings and Samples,the Contractor thereby represents that he has determined and verified
all field measurements, field construction criteria, materials, catalog numbers and similar data, and that he has checked and
coordinated each shop drawing given in the Contract Documents.The Architect's approval of a separate item shall not indicate
approval of an assembly in which the item functions.
The Architect will review and approve Shop Drawings and Samples with reasonable promptness so as to cause no delay,but only
for conformance with the design concept of the Project and with the information given in the Contract Documents.The Architect's
approval of a separate item shall not indicate approval of an assembly in which the item functions.
r� The Contractor shall make any corrections required by the Architect and shall resubmit the required number of corrected copies of
Shop Drawings or new Samples until approved. The Contractor shall direct specific attention in writing or on resubmitted Shop
Drawings to revisions other than the corrections requested by the Architect on previous submissions.
The Architect's approval of Shop Drawings or Samples shall not relieve the Contractor of responsibility for any deviation from the
,.. requirements of the Contract Documents unless the Contractor has informed the Architect in writing of such deviation at the time of
submission and the Architect has given written approval to the specific deviation. Architect's approval shall not relieve the
Contractor from responsibility for errors or omissions in the Shop Drawings or Samples.
No portion of the Work requiring a Shop Drawing or Sample submission shall be commenced until the Architect has approved the
r�MF submittal.All such portions of the Work shall be in accordance with approved Shop Drawings and Samples.
D-18 SITE USE: The Contractor shall confine operations at the site to areas permitted by law,ordinances, permits and the
Contract Documents and shall not unreasonably encumber the site with any materials or equipment.Until acceptance of the Work
by the City Council of the City of Fort Worth,the entire site of the Work shall be under the exclusive control,care and responsibility
ON
of the Contractor, Contractor shall take every precaution against injury or damage to persons or property by the action of the
elements or from any other cause whatsoever.The Contractor shall rebuild,repair,restore and make good at his own expenses all
injuries or damages to any portions of the Work occasioned by any of the above,caused before acceptance.
.`. D-19 CUTTING AND PATCHING OF WORK: The Contractor shall do all cutting,fitting or patching of his Work that may be
required to make its several parts fit together properly,and shall not endanger any Work by cutting,excavating or otherwise altering
the Work or any part of it.
D-20 CLEAN UP: The Contractor at all times shall keep the premises free from accumulation of waste materials or rubbish.At
" the completion of the Work he shall remove all his waste materials and rubbish from and about the Project as well as all his tools,
construction equipment,machinery and surplus materials,and shall clean all glass surfaces and leave the Work"Broom-clean"or
its equivalent,except at otherwise specked. In addition to removal of rubbish and leaving the buildings"broom-clean",Contractor
shall clean all glass,replace any broken glass,remove stains,spots,marks and dirt from decorated work,clean hardware,remove
paint spots and smears from all surfaces,clean fixtures and wash all concrete,tile and terrazzo floors.
If the Contractor fails to clean up,the Owner may do so,and the cost thereof shall be charged to the Contractor,
D-21 COMMUNICATIONS: As a general rule,the Contractor shall forward all communications to the Owner through the BCM.
D-22 CONTRACTOR REQUIREMENTS ON FEDERALLY FUNDED PROJECTS: Contractor shall observe and comply with
the requirements of the City of Fort Worth Fiscal Department, Intergovernmental Affairs and Grants Management as outlined in the
Supplemental Conditions contained in the Project Manual
SECTION E
SUBCONTRACTORS
® E-1 DEFINITION: A Subcontractor is a person or organization that has a direct contract with the Contractor to perform any of
the Work at the site. The term Subcontractor is referred to throughout the Contract Documents as if singular in number and
masculine in gender and means a Subcontractor or his authorized representative.
Nothing contained in the Contract, Documents shall create any contractual relation between the Owner and the Architect and any
subcontractor or any of his sub-subcontractors or materialmen.
E-2 AWARD OF SUBCONTRACTS: The bidder shall furnish a list of the names of the subcontractors or other persons or
organizations(including those who are to furnish materials or equipment fabricated to a special design)proposed for such portions
of the Work as may be designated in the bidding requirements,or if none is so designated in the bidding requirements,the names
of the Subcontractors proposed for the principal portions of the Work.Prior to the award of the Contract,the Architect shall notify
the successful bidder in writing if either the Owner or Architect,after due investigation,has reasonable objection to any person or
organization on such list.Failure of the Owner and Architect to make an objection to any person or organization on the list prior to
the award of this Contract shall not constitute acceptance of such person or organization.
If,prior to the award of the Contract,the Owner or Architect has an objective to any person or organization on such list,and refuses
to accept such person or organization,the apparent low bidder may, prior to the award,withdraw his bid without forfeiture of bid
security. If such bidder submits an acceptable substitute,the Owner may,at its discretion,accept the bid or he may disqualify the
bid. If, after the award, the Owner or Architect objects in writing to any person or organization on such list,the Contractor shall
provide an acceptable substitute.
The Contractor shall not make any substitution for any Subcontractor or person or organization that has been accepted by the
Owner and the Architect,unless the substitution is also acceptable to the Owner and the Architect.
®. E-3 TERMS OF SUBCONTRACTS: All work performed for the Contractor by a Subcontractor shall be pursuant to an
appropriate agreement between the Contractor and the Subcontractor(and where appropriate between Subcontractors and Sub-
subcontractors)which shall contain provisions that:
1 Preserve and protect the rights of the Owner and the Architect under the Contract with respect to the Work to be performed
under the subcontract so that the subcontracting thereof will not prejudice such rights;
2. Require that such Work be performed in accordance with the requirements of the Contract Documents;
..0 3. Require submission to the Contractor of applications for payment under each subcontract to which the Contractor is a party,in
reasonable time to enable the Contractor to apply for payment;
4. Require that all claims for additional costs,extensions of time,damages for delays or otherwise with respect to subcontracted
portions of the Work shall be submitted to the Contractor(via any Subcontractor or Sub-subcontractor where appropriate)in
.. the manner provided in the Contract Documents for like claims by the Contractor upon the Owner,
5. Waive all rights the contracting parties may have against one another for damages caused by fire or other perils covered by
the property insurance,except such rights,N any,as they may have to proceeds of such insurance held by the Owner,and,
6. Obligate each Subcontractor specifically to consent to the provisions of this Section
All of the provisions set out in this section shall be deemed to have been included in every subcontract,and every subcontract shall
be so construed and applied as to the Owner and the Architect,whether or not such provisions are physically included in the sub-
contract.
E-4 MINORITY BUSINESS ENTERPRISE (MBE): Should the base proposal be$50,000 or less,the requirements of this
section do not apply.
General: As of June 1,2012,The City of Fort Worth has implemented the new Business Diversity Ordinance(BDO)to reflect the
Citys availability and disparity study findings and recommendations. During this transition period interested Offerors must obtain a
MBE listing of African Americans fines from the M/WBE Office at 817-212-2674. This will ensure that MBE listings reflect only
those currently certified by the North Central Texas Regional Certification Agency (NCTRCA) located in the six (6) county
geographic marketplace that have been accepted by the City. The City's geographic marketplace includes the counties of:Tarrant,
Dallas, Denton, Johnson, Parker and Wise. Offerors are stronaly encouraged to confirm that each MBE that it intends to use is
located in the geographic marketplace that will be counted towards the established goal.
In accordance with City of Fort Worth Diversity Business Ordinance(6130)No 20020-12-2011 (the"Ordinance"),the City of Fort
Worth sets goals for the participation of Minority Business Enterprises(MBE)in City contracts. Ordinance No 20020-12-2011 is
incorporated in these General Conditions by reference. A copy of the Ordinance may be obtained from the Office of the City
Secretary. Failure to comply with the Ordinance shall be a material breach of contract.
Prior to Award: The MBE documentation required by the procurement solicitation must be submitted within five city business days
after the proposals are opened. Failure to comply with the City's Business Diversity Ordinance, or to demonstrate a "good faith
..� effort",shall result in a bid being considered non-responsive.
During Construction: Contractor shall provide copies of subcontracts or cosigned letters of intent with approved MBE
subcontractors and or suppliers prior to issuance of the Notice to Proceed. Contractor shall also provide monthly reports on
utilization of the subcontractors to the M/WBE Office and the Construction Manager. Contractor must provide the City with
complete and accurate information regarding actual work performed by an MBE on the contract and proof of payment thereof.
Contractor further agrees to permit an audit and/or examination of any books,records or files in it's possession that will substantiate
the actual work performed by an MBE. The misrepresentation of facts and/or the commission of fraud by the Contractor will be
grounds for termination of the contract and/or initiating action under appropriate federal,state,or local laws or ordinances relating to
.. false statement. An Offeror who intentionally and/or knowingly misrepresents material facts shall be determined to be an
irresponsible offeror and barred from participating in City work for a period of time of not less than three(3)years. The failure of an
offeror to comply with this ordinance where such non-compliance constitutes a material breach of contract as stated herein, may
result in the offeror being determined to be an irresponsible offeror and barred from participating in City work for a period of time of
not less than one(1)year.
The Contractor may count toward the goal any tier of MBE subcontractors and/or suppliers. The Contractor may count toward its
goal a portion of the total dollar amount of the contract with a joint venture equal to the percentage of the MBE participation in the
joint venture for a clearly defined portion of the work to be performed. All subcontractors used in meeting the goals must be
certified prior to the award of the Contract.
Change Orders: Whenever a change order affects the work of an MBE subcontractor or supplier the MBE shall be given an
opportunity to perform the work. Whenever a change order is$50,000 or more,the M/WBE Office Coordinator shall determine the
goals applicable to the work to be performed under the change order.
During the term of the contract the Contractor shall:
1 Make no unjustified changes or deletions in its MBE participation commitments submitted with the bid/proposal or during
negotiation,without prior submission of the proper documentation for review and approval by the M/WBE Office.
2. If substantial subcontracting and/or supplier opportunities arise during the tens of any contract when the Contractor
represented in its bid/proposal to the City that it alone would perform the subcontracting/supplier opportunity work, the
Contractor shall notify the City before subcontracts for work and/or supplies are awarded and shall be required to comply with
subsections of the 00rdinance,exclusive of the time requirements stated in such subsections.
3. The Contractor shall submit to the M/WBE Office for approval an MBE REQUEST FOR APPROVAL OF CHANGE FORM,if,
during the term of any contract,the Contractor wishes to change or delete one or more MBE subcontractors or suppliers.
Justification for change of subcontractors may be granted for the following:
1. An MBE's failure to provide Workers'Compensation Insurance evidence as required by state law;or
2. An MBE's-failure to provide evidence of general liability or other insurance-
under the same or similar teens as contained in the Contract Documents with limits of coverage no greater than the lower of
1)the limits required of the Contractor by the City;or 2)the limits contained in the Contractor's standard subcontract or supply
agreements used on other projects of similar size and scope and within the Contractor's normal business practice with non-
M/WBE subcontractor's/subconsultant's or suppliers;or
... 3. An MBE's failure to execute the Contractor's standard subcontract forth,if entering a subcontract is required by the Contractor
in its normal course of business,unless such failure is due to:
a) A change in the amount of the previously agreed to bid or scope of work;or
b) The contract presented provides for payment once a month or longer and the Contractor is receiving
payment from the City twice a month;or
C) Any limitation being placed on the ability of the MBE to report violations of the Ordinance or any other
ordinance or violations of any state or federal law or other improprieties to the City or to provide notice
of any claim to the Contractor's surety company or insurance company.
.. d) Mediation shall be a consideration before the request for change is approved.
4. An MBE defaults in the performance of the executed subcontract. In this event,the Contractor shall:
a) Request bids from all MBE subcontractors previously submitting bids for the work,
b) If reasonably practicable,request bids from previously non-bidding M/WBEs,and
C) Provide to the M/WBE Office documentation of compliance with(a)and(b)above.
5. Any reason found to be acceptable by the M/WBE Office in its sole discretion.
Within ten days after final payment from the City the Contractor shall provide the M/WBE Office with documentation to reflect final
participation of each subcontractor and supplier,including non-MBEs,used on the project.
E-5 PAYMENTS TO SUBCONTRACTORS: The Contractor shall pay each Subcontractor upon receipt of payment from the
Owner,an amount equal to the percentage of completion allowed to the Contractor on account of such Subcontractor's Work.The
Contractor shall also require each Subcontractor to make similar payments to his subcontractors.
If the Owner refuses to issue a Certificate for Payment for any cause which is the fault of the Contractor and not the fault of a
particular subcontractor the Contractor shall pay that Subcontractor on demand,made at any time after the Certificate for Payment
would otherwise have been issued,for his Work to the extent completed,less the retained percentage.
The Contractor shall pay each Subcontractor a just share of any insurance monies received by the Contractor,and he shall require
each Subcontractor to make similar payments to his Subcontractors.
The Owner may,on request and at its discretion,furnish to any Subcontractor,if practicable,information regarding percentages of
completion certified to the Contractor on account of Work done by such Subcontractors.
�r
Neither the Owner nor the Architect shall have any obligation to pay or to see to the payment of any monies to any Subcontractor.
E-6 SUBCONTRACTOR REQUIREMENTS FOR EDA FUNDED PROJECTS: The Contractor will cause appropriate
provisions to be inserted in all subcontracts to bind subcontractors to FDA contract requirements as contained herein and to 15
CFR 24 or OMB Circular A-110,as appropriate.
Each subcontractor must agree to comply with all applicable Federal,State,and local requirements in addition to those set forth in
this section.
No subcontractor will be employed on this Project,except as specifically approved by the City,who is contained in the listing of
contractors debarred, ineligible, suspended or indebted to the United States from contractual dealings with Federal government
departments. The work performed by any such contractor or subcontractor will be ineligible for reimbursement wholly or partially
from EDA grant fluids.
All subcontracts in excess of$10,000 shall include, or incorporate by reference,the equal opportunity clause of Executive Order
11246.
All subcontracts must contain a nondiscrimination clause.
Each subcontract must contain a requirement for compliance with the Davis-Bacon and related acts.
Each subcontractor must submit weekly each weekly payroll record and a weekly statement of compliance. These documents will
a be submitted to the prime contractor who will compile them and submit to the City.The subcontractor can satisfy this requirement
by submitting a properly executed Department of labor Form WH-347.
Each subcontract with every subcontractor must contain a clause committing the subcontractor to employment of local labor to the
maximum extent possible.
All subcontractors who employ more than 50 employees, and is a prime or first tier subcontractor, and has a subcontract or
purchase order of$50,000 or more must submit a completed Standard Form 100(Compliance Report)by March 30 of each year
Subcontractors performing work in areas covered by published goals for minorities will be required to report monthly on Form CC-
257.
SECTION F
SEPARATE CONTRACTS
F-1 OWNER'S RIGHT: The Owner reserves the right to award separate contracts in connection with other portions of the
Work. When separate contracts are awarded for other portions of the Work, "the Contractor"in the Contract Documents in each
®, case shall be the contractor who signs each separate contract.
F-2 MUTUAL RESPONSIBILITY OF CONTRACTORS: The Contractor shall afford other contractors reasonable opportunity
for the introduction and storage of their materials and equipment and the execution of their work, and shall properly connect and
coordinate his work with theirs.
If any part of the Contractor's Work depends for proper execution or results upon the work of any other separate contractor, the
Contractor shall inspect and promptly report to the Owner any apparent discrepancies or defects in such work that render it
unsuitable for such proper execution and results. Failure of the Contractor to inspect and report shall constitute an acceptance of
the other contractor's work as fit and proper to receive his Work, except as to defects which may develop in the other separate
contractor's work after the execution of the Contractor's Work.
Should the Contractor cause damage to the work or property of any separate contractor on the site,the Contractor shall,upon due
notice,settle with such other contractor by agreement,if he will so settle. If such separate contractor sues the Owner on account of
any damage alleged to have been so sustained, the Owner shall notify the Contractor who shall defend against such suit at the
Contractor's expense, and if any judgment against the Owner arises therefrom,the Contractor shall pay or satisfy such judgment
and shall reimburse the Owner for all attorney's fees,court costs and expenses which the Owner has incurred in connection with
such suit.
r` F-3 CUTTING AND PATCHING UNDER SEPARATE CONTRACTS: The Contractor shall do all cutting,fitting or patching of
his Work that may be required to fit it to receive or be received by the work of other contractors shown in the Contract Documents.
The Contractor shall not endanger any work or any other contractors by cutting,excavating or otherwise altering any work and shall
not cut or alter the work of any other contractor except with the written consent of the Architect.
.. Any costs caused by defective or ill-timed work shall be bome by the party responsible therefor.
F-4 OWNER'S RIGHT TO CLEAN UP: If a dispute arises between the separate contractors as to their responsibility for
cleaning up,the Owner may clean up and charge the cost thereof to the several contractors as the Director of the Department of
.r. Transportation and Public Works shall determine to be just.
SECTION G
MISCELLANEOUS PROVISIONS
�r
G-1 CONFLICT OF LAWS: The law of the place where the site is located shall govern the Contract.The Contractor must
familiarize himself and strictly comply with all Federal, State, and County and City Laws, Statutes, Charter Ordinances,
Regulations,or Directives controlling the action or operation of those engaged upon the work affecting the materials used.He shall
® indemnify and save harmless the City and all of its officers and agents against any claim or liability arising from or based on the
violation of any such Laws,Statutes,Charter,Ordinances,Regulations,or Directives,whether by himself,his employees,agents or
subcontractors.
G-2 GOVERNING LAWS: It is mutually agreed and understood that this agreement is made and entered into by the parties
"• hereto with reference to the existing Charter and Ordinances of the City of Fort Worth and the laws of the State of Texas with
reference to and governing all matters affecting this Contract,and the Contractor agrees to fully comply with all the provisions of the
same.
G-3 PERSONAL LIABILITY OF PUBLIC OFFICIALS: In performing their duties under the Statutes of the State of Texas and
the Charter and Ordinances of the City of Fort Worth in connection with this Contract,or in exercising any of the powers granted the
Owner herein,the officers, agents and employees of the City of Fort Worth are engaged in the performance of a governmental
function and shall not incur any personal liability by virtue of such performance hereunder,except for gross negligence or willful
wrong.
G-4 COMPLIANCE WITH LAWS. Contractor agrees to comply with all laws, Federal, state and local, including all
ordinances,rules and regulations of the City of Fort Worth,Texas. Materials incorporated into the finished Project are not subject
to State Sales Tax.
The Owner is responsible for obtaining the Building Permit. The Contractor and the appropriate subcontractor are responsible for
obtaining all other construction permits from the governing agencies. Contractor shall schedule all code inspections with the Code
Inspection Division in accordance with the permit requirements and submit a copy of updated schedule to the Construction
Manager weekly. Building,plumbing,electrical and mechanical building permits are issued without charge. Water and sewer tap,
,. impact&access fees will be paid by the City. Any other permit fees are the responsibility of the Contractor.
G-5 INDEMNIFICATION: Contractor covenants and agrees to indemnify City's engineer and architect, and their
personnel at the project site for Contractor's sole negligence. In addition,Contractor covenants and agrees to indemnify,
' hold harmless and defend,at its own expense,the Owner,Its officers,servants and employees,from and against any and
all claims or suits for property loss,property damage,personal Injury,including death,arising out of,or alleged to arise
out of,the work and services to be performed hereunder by Contractor, Its officers,agents,employees,subcontractors,
licensees or invitees,whether or not any such injury.damage or death is caused,in whole or in part.by the negligence or
...
811009d negligence of Owner,its officers.servants.or employees. Contractor likewise covenants and agrees to Indemnify
and hold harmless the Owner from and against any and all Injuries to Owner's officers,servants and employees and any
damage,loss or destruction to property of the Owner arising from the performance of any of the terms and conditions of
this Contract, whether or not any such Injury or damage is caused in whole or in part by the negligence or alleged
negllgence of Owner.Its officers.servants or emplovees.
In the event Owner receives a written claim for damages against the Contractor or its subcontractors prior to final
payment,final payment shall not be made until Contractor either(a)submits to Owner satisfactory evidence that the claim
has been settled and/or a release from the claimant involved,or(b)provides Owner with a letter from Contractor's liability
Insurance carrier that the claim has been referred to the Insurance carrier.
The Director may, if he deems it appropriate, refuse to whom a claim for damages is outstanding as a result of work
performed under a City Contract.
G-6 SUCCESSORS AND ASSIGNS: Except as provided in Paragraph E-2,this contract shall be binding upon and insure to
the benefit of the parties hereto,their Successors or Assigns.Contractor shall not assign or sublet all or any part of this Contract or
his rights or duties hereunder without the prior written consent of the Owner. Any such purported assignment or subletting without
the prior written consent of Owner shall be void.
G-7 WRITTEN NOTICE: Written Notice shall be deemed to have been duly served if delivered in person to the individual or
member of the firm or to an officer of the corporation for whom it was intended,or if delivered at or sent by registered or certified
mail to the last business address known to him who gives the notice.
G-8 SURETY BONDS: Surety Bonds are required on all City contracts in excess of$25,000. The Contractor agrees,on the
submittal of his Proposal to make, execute and deliver to said City of Fort Worth good and sufficient surety bonds for the faithful
performance of the terms and stipulations of the Contract and for the payment to all claimants for labor and/or materials fumished
in the prosecution of the Work,such bonds being as provided and required in Article 5160 of the Revised Civil Statutes of Texas,as
amended,in the form included in the Contract Documents,and such bonds shall be 100 percent of the total contract price,and the
-� said surety shall be a surety company duly and legally authorized to do business in the State of Texas,and acceptable to the City
Council of the City of Fort Worth.
Bonds shall be made on the forms furnished by or otherwise acceptable to the City. Each bond shall be properly executed by both
the Contractor and the Surety Company. Bonds required by the City shall be in compliance with all relevant local,state and federal
statutes.
To be an acceptable surety on the bond the name of the surety should be included on the current U.S.Treasury List of Acceptable
Securities [Circular 570], and must be authorized to do business in Texas. Sureties not listed in Circular 570 may write
performance and payment bonds on a project without reinsurance to the limit of 10 percent of its capital and surplus. Such a surety
must reinsure any obligation over 10 percent.The amount in excess of 10 percent must be reinsured by reinsurers who are duly
authorized,accredited,or trusteed to do business in the State of Texas.
Should any surety for the contracted project be determined unsatisfactory at any time during same, the Contractor shall
immediately provide a new surety bond satisfactory to the City.
If the contract amount is less than $25,000, payment shall be made in one lump sum 30 calendar days after completion and
acceptance of the Work.
G-9 OWNER'S RIGHT TO CARRY OUT THE WORK: If the Contractor defaults or neglects to carry out the Work in
accordance with the Contract Documents or fails to perform any provision of the Contract,the Owner may,without prejudice to any
other remedy he may have,enter the site and make good such deficiencies. In such case an appropriate Change Order shall be
issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies, including the
.�. cost of the Architect's additional services made necessary by such default,neglect or failure.If the payments then or thereafter due
the Contractor are not sufficient to cover such amount,the Contract shall pay the difference to the Owner.
G-10 ROYALTIES AND PATENTS: The Contractor shall pay all royalties and license fees.He shall defend all suits or claims
for infringement of any patent rights and shall save the Owner harmless from loss on account thereof and shall be responsible for
all such loss when a particular design,process or the product of a particular manufacturer or manufacturers is specked;however if
the Contractor has reason to believe that the design, process or product specified is an infringement of a patent, he shall be
responsible for such loss unless he promptly gives such information to Owner
®. G-11 TESTS: If the Contract Documents, Laws, Ordinances, Rules, Regulations or Orders of any public authority having
jurisdiction require any Work to be inspected,tested or approved,the Contractor shall give the Owner timely notice of its readiness
and the date arranged so the Architect may observe such inspection,testing or approval.The Owner shall bear all costs of such
inspection,tests and approvals unless otherwise provided.
If after the commencement of the Work,the Owner determines that any work requires special inspection,testing or approval not
included above,the Owner upon written authorization from the Owner will instruct the Contractor to order such special inspection,
testing or approval,and the Contractor shall give notice as required in the preceding paragraph.If such special inspection or testing
reveals a failure of the Work to comply(1)with the requirements of the Contract Documents or(2)with respect to the performance
of the Work, with Laws, Statutes, Charter, Ordinances, Regulations or Orders of any public authority having jurisdiction, the
Contractor shall bear all costs thereof, including the Architect's additional services made necessary by such costs; otherwise the
Owner shall bear such costs,and an appropriate Change Order shall be issued.
The Contractor shall secure certificate of inspection,testing or approval,and three copies will be promptly delivered by him to the
w Owner.The Architect will review the certificates and forward one copy of each with his recommendation(s)to the Owner.
If the Owner wishes to observe the inspections, tests or approvals required by this Section,they will do so promptly and,where
practicable,at the source of supply.
Neither the observations of the Architect or the Owner in their administration of the Construction Contract,nor inspections,tests or
approvals by persons other than the Contractor shall relieve the Contractor from his obligations to perform the Work in accordance
with the Contract Documents.
^^'^ G-12 INTERRUPTION OF EXISTING UTILITIES SERVICES: The Contractor shall perform the Work under this Contract with
a minimum of outage time for all utilities. Interruption shall be by approved sections of the utility. In some cases,the Contractor
may be required to perform the Work while the existing utility is in service.The existing utility service may be interrupted only when
approved by the Owner When it is necessary to interrupt the existing utilities,the Contractor shall notify the Owner in writing at
least ten days in advance of the time that he desires the existing service to be interrupted.The interruption time shall be kept to a
minimum. Depending upon the activities at an existing facility that requires continuous service from the existing utility, an
interruption may not be subject to schedule at the time desired by the Contractor In such cases,the interruption may have to be
scheduled at a time of minimum requirements of demand for the utility.The amount of time requested by the Contractor of existing
utility services shall be as approved by the Owner.
G-13 LAYING OUT WORK: The Contractor shall verify dimensions and elevations indicated in layout of existing work.
Discrepancies between Drawings, Specifications, and existing conditions shall be referred to Architect for adjustment before work
affected is performed. Failure to make such notification shall place responsibility upon Contractor to carry out work in satisfactory
workmanlike manner at the Contractor's sole expense.
The Contractor shall be held responsible for the location and elevation of all the construction contemplated by the Construction
Documents.
r� Prior to commencing work,the Contractor shall carefully compare and check all Architectural,Structural, Mechanical an Electrical
drawings; each with the other that in any affects the locations or elevation of the work to be executed by him, and should any
discrepancy be found,he shall immediately report the same to the Architect for verification and adjustment.Any duplication of work
made necessary by failure or neglect on his part to comply with this function shall be done at the Contractor's sole expense.
... G-14 MEASUREMENTS: Before ordering any material or doing any work,the Contractor shall verify all measurements at the
site or at the building and shall be wholly responsible for the correctness of same. No extra charge or compensation will be allowed
on account of any difference between actual dimensions and dimensions indicated on the drawings. Any difference that may be
found shall be submitted to the Architect for consideration and adjustment before proceeding with the project.
G-15 EXISTING OVERHEAD OR UNDERGROUND WORK: The Contractor shall carefully check the site where the project is
to be erected and observe any existing overhead wires and equipment.Any such work shall be moved, replaced or protected,as
required,whether or not shown or specked at the Contractor's sole expense.
Attention is directed to the possible existence of pipe and other underground improvements that may or may not be shown on the
Drawings.All reasonable precautions shall be taken to preserve and protect any such improvements whether or not shown on the
Drawings.
Location of existing underground lines, shown the Drawings are based on the best available sources, but are to be regarded as
approximate only.Exercise extreme care in locating and identifying these lines before excavation in adjacent areas.
G-16 ALIGNMENT OF JOINTS IN FINISH MATERIALS: It shall be the responsibility of the Contractor to make certain in the
installation of jointed floor,wall and ceiling materials that:
1. Preserve and protect the rights of the Owner and the Architect under the Contract with respect to the Work to be performed
under the subcontract so that the subcontracting thereof will not prejudice such rights;
2. Place joints to relate to all opening and breaks in the structure and be symmetrically placed wherever possible.This includes
heating registers,light fixtures,equipment,etc.
If because of the non-related sizes of the various materials and locations of openings, etc., it is not possible to accomplish the
above, the Contractor shall request the Architect to determine the most satisfactory arrangement. The Contractor shall establish
centerlines for all trades.
G-17 INTEGRATING EXISTING WORK: The Contractor shall protect all existing street and other improvements from
damages.
Contractor's operations shall be confined to the immediate vicinity of the new work and shall not in any interfere with or obstruct the
ingress or egress to and from existing adjacent facilities.
Where new site work is to be connected to existing work,special care shall be exercised by the Contractor not to disturb or damage
the existing work more than necessary.All damaged work shall be replaced, repaired and restored to its original condition at no
.� cost to the Owner
G-18 HAZARDOUS MATERIAL CERTIFICATION: It is the intent of the contract documents,whether expressly stated or not,
that nothing containing hazardous materials, such as asbestos, shall be incorporated in to the project. The Contractor shall
exercise every reasonable precaution to ensure that asbestos-containing materials are not incorporated into any portion of the
.� project, including advising all materials suppliers and subcontractors of this requirement. The Contractor shall verify that
components containing lead do not contact the potable water supply.
G-19 LOCATION OF EQUIPMENT AND PIPING: Drawing showing location of equipment, piping, ductwork, etc. are
diagrammatic and job conditions may not always permit their installation in the location shown.When this situation occurs,it shall
""' be brought to the Architect's attention immediately and the relocation determined in a joint conference.The Contractor will be held
.� responsible for the relocating of any items without first obtaining the Architect's approval.He shall remove and relocate such items
at his own expense if so directed by the Architect. Where possible, uniform margins are to be maintained between parallel lines
and/or adjacent wall,floor or ceiling surfaces.
® G-20 OVERLOADING: The Contractor shall be responsible for loading of any part or parts of structures beyond their safe
carrying capacities by placing of materials, equipment,tools, machinery or any other item thereon. No loads shall be placed on
floors or roofs before they have attained their permanent and safe strength.
G-21 MANUFACTURER'S INSTRUCTIONS: Where it is required in the Specifications that materials, products, processes,
equipment,or the like be installed or applied in accordance with manufacturer's instructions,direction or specifications,or words to
this effect it shall be construed to mean that said application or installation shall be in strict accordance with printed instructions
furnished by the manufacturer of the material concerned for use under conditions similar or those at the job site.Six copies of such
instructions shall be furnished to the Architect and his approval thereof obtained before work is begun.
G-22 CLEANING UP: The Contractor shall keep the premises free from accumulation of waste material or rubbish caused by
employees or as a result of the Work.
w At completion of work,the General Contractor shall,immediately prior to final inspection of complete building,execute the following
final cleaning work with trained janitorial personnel and with material methods recommended by the manufactures of installed
materials.
1. Sweep and buff resilient floors and base,and vacuum carpeting.
aaa
2. Dust all metal and wood trim and similar finished materials.
3. Clean all cabinets and casework.
4. Dust all ceilings and walls.
5. Dust,and if necessary wash,all plumbing and electrical fixtures.
.., 6. Wash all glass and similar non-resilient materials.
7 All hardware and other unpainted metals shall be cleaned and polished and all equipment and paint or decorated work shall be
cleaned and touched-up if necessary,and all temporary labels,tags,and paper coverings removed throughout the buildings.
Surfaces that are waxed shall be polished.
8. The exterior of the building,the grounds,approaches,equipment,sidewalks,streets,etc.shall be cleaned similar to interior of
buildings and left in good order at the time of final acceptance. All paint surfaces shall be clean and unbroken,hardware shall
be clean and polished,all required repair work shall be completed and dirt areas shall be scraped and cleared of weed growth.
9. Clean all glass surfaces and mirrors of putty,paint materials,etc.,without scratching or injuring the glass and leave the work
bright,clean and polished.Cost of this cleaning work shall be bome by Contractor.
10. Cleaning,polishing,scaling,waxing and all other finish operations indicated on the Drawings or required in the Specifications
shall be taken to indicate the required condition at the time of acceptance of all work under the Contract.
11. Burning:Burning of rubbish on the premises will not be permitted.
G-23 DUST CONTROL: Precaution shall be exercised at all times to control dust created as a result of any operations during
the construction period.If serious problems or complaints arise due to air-borne dust,or when directed by the Architect,operations
causing such problems shall be temporarily discontinued and necessary steps taken to control the dust.
G-24 FIRE PROTECTION: The Contractor shall at all times maintain good housekeeping practices to reduce the risk of fire
damage or injury to workmen.All scrap materials,rubbish and trash shall be removed daily from in and about the building and shall
not be permitted to be scattered on adjacent property.
Suitable storage space shall be provided outside the immediate building area for storing flammable materials and paints; no
storage will be permitted in the building. Excess flammable liquids being used inside the building shall be kept in closed metal
.® container and removed from the building during unused periods.
A fire extinguisher shall be available at each location where cutting or welding is being performed.Where electric or gas welding or
cutting work is done, interposed shields of incombustible material shall be used to protect against fire damage due to sparks and
hot metal.When temporary heating devices are used,a watchman shall be present to cover periods when other workmen are not
on the premises.
The Contractor shall provide fire extinguishers in accordance with the recommendations and NFPA Bulletins Nos. 10 and 241
However in all cases a minimum of two fire extinguishers shall be available for each floor of construction.
G-25 CUTTING AND PATCHING: Wherever cutting and removal of portions of the existing work is indicated,such work shall
be neatly sawed or cut by Contractor in a manner that will produce a neat straight line, parallel to adjacent surfaces or plumb for
vertical surfaces.Care should be exercised not to damage any work that is to remain.
At no time shall any structural members be cut without written consent from the Architect.
G-26 PROJECT CLOSEOUT
Final Inspection. Record Drawings: Attention is called to General Conditions Section entitled, "Substantial Completion and Final
Payment".
Maintenance Manual: Sheets shall be 8'r4"x 11" except pull out sheets may be neatly folded to 8'h"x 11". Manuals shall be
bound in plastic covered,3 ring,loose leaf binder with title of project lettered on front and shall contain:
1) Name,address and trade of all sub-contractors.
2) Complete maintenance instructions; name, address, and telephone number of installing Contractor manufacturer's local
representative,for each piece of operative equipment.
3) Catalog data on plumbing fixtures,valves,water heaters, heating and cooling equipment,temperature control,fan,electrical
panels,service entrance equipment and light fixtures.
4) Manufacturer's name, type, color designation for resilient floors, windows, doors, concrete block, paint, roofing, and other
materials.
Submit six copies of Maintenance Manual,prior to request for final payment.
Operational Inspection and Maintenance Instruction: The Contractor shall provide at his expense, competent manufacturer's
representatives to completely check out all mechanical and electrical systems and items covered by the Drawings and
Specifications. This requirement shall be scheduled just prior to and during the initial start up. After all systems are functioning
property the representatives shall instruct maintenance personnel of the Owner in the proper operation and maintenance of each
item.
POP
G-27 GUARANTEE AND EXTENDED GUARANTEE: Upon completion of the Project, prior to final payment, guarantees
required by technical divisions of Specifications shall be properly executed in quadruplicate by subcontractors and submitted
through the Contractor to Architect. Delivery of guarantees shall not relieve Contractor from any obligation assumed under
Contract.
ow
The Contractor shall guarantee the entire Project for one year. In addition,where separate guarantees,for certain portions of work,
are for longer periods, General Contractor's guarantee shall be extended to cover such longer periods. Manufacturer's extended
warrantees shall be included in this contract.
no Guarantees shall become valid and operative and commence upon issuance of Certificate of Inspection and Acceptance by Owner.
Guarantees shall not apply to work where damage is result of abuse,neglect by Owner or his successor(s)in interest.
The Contractor agrees to warrant his work and materials provided in accordance with this contract and the terms of the Technical
Specifications contained herein. Unless supplemented by the Technical Specifications or the manufacturer's normal extended
warrantees,the Contractor shall warrant all work materials,and equipment against defects for a period of one year from the date of
final acceptance. The Contractor further agrees to bear all costs of making good all work that is found to be defective or not
provided in accordance with the Contract Documents. Additionally if the facility or contents are damaged due to defective materials
or workmanship of the Contractor,the Contractor further agrees to bear all cost of repairing and/or replacing damaged items and
components to bring such items back to at least their original condition.
G-28 RECORD DRAWINGS: Upon completion of the Work and prior to application for final payment,one print of each of the
drawings accompanying this specification shall be neatly and clearly marked in red by the Contractor to show variations between
the construction actually provided and that indicated or specified in the Contract Documents. The annotated documents shall be
delivered to Architect. Where a choice of materials and/or methods is permitted herein and where variations in the scope or
character of the work from the entire work indicated or specified are permitted either by award of bidding items specified for that
purpose, or by subsequent change to the drawings, the record drawings shall define the construction actually provided. The
representation of such variations shall conform to standard drafting practice and shall include supplementary notes, legends and
details which may be necessary for legibility and clear portraval of the actual construction.The record drawings shall indicate, in
addition,the actual location of all sub-surface utility lines,average depth below the surface and other appurtenances.
G-29 CONSTRUCTION FENCE: At the Contractor's option,he may provide a substantial chain-link construction fence around
... all or a part of the site. The fences and gates must be maintained throughout the construction period. Remove the fences and
gates upon completion of the Project and restore the site to the required original or contract condition.
G-30 PRODUCT DELIVERY.STORAGE.HANDLING: The Contractor shall handle,store and protect materials and products,
including fabricated components, by methods and means which will prevent damage,deterioration and loss, including theft(and
resulting delays), thereby ensuring highest quality results as the work progresses. Control delivery schedules so as to minimize
unnecessary long-term storage at project site prior to installation.
G31 REMOVAL OF SALVAGED MATERIAL: The Contractor shall remove salvaged material and equipment from the Project
site and dispose of it in accordance with the law. Equipment or material identified in the Specifications or Plans for Owner salvage
shall be carefully removed and delivered to the Owner at any location in within the City limits as directed by the City.
G-32 MANUFACTURER'S REFERENCE: Catalog, brand names, and manufacturer's references are descriptive, not
restrictive. Bids on brands of like nature and quality will be considered. Contractor shall inform the City of any substitutions
intended for the project within 5 business days of bid opening. Failure to inform the City of substitute projects will obligate the
Contractor to provide the specked material if awarded the contract. Within 14 days after bid opening and upon request of the
Contractor the Contractor will submit a full sized sample and/or detailed information as required to allow the architect to determine
the acceptability of proposed substitutions. Where equipment has been listed as"no substitute accepted",the City will accept no
alternates to the specified equipment.
�. SECTION H
CONTRACT TIME
H-1 DEFINITIONS
The Contract Time is the period of time allotted in the Contract Documents for completion of the Work and is the number of
calendar days elapsing between the date of commencement and the date of substantial Completion plus additional days assessed
for failure to complete punch list items from the Final Inspection in a timely manner
The Date of Commencement of the Work is the date established in the Notice to Proceed. If there is no notice to proceed,it shall
be the date of the Agreement or such other date as may be established therein.
The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Architect with the approval
of the Owner that construction is sufficiently complete,in accordance with the Contract Documents,so the Owner may occupy the
.," Work or designated portion thereof for the use for which it is intended. Final acceptance of the completed work or any portion
thereof can be made only by the Assistant City Manager and no other form of acceptance will be binding upon the Owner.
A Calendar Day constitutes 24 hours of time and is any one of the seven days of a week,including Sunday,regardless of whether a
"Working Day" or not, and regardless of weather conditions or any situation which might delay construction. An extension of
*� contract time shall be in accordance with this Section. Extensions of time will be as recommended by the BCM with final approval
by City of Fort Worth.
A Working Da v is defined as a calendar day, not including Saturdays, Sundays, and legal holidays, in which weather or other
conditions not under the control of the Contractor permit the performance of work for a continuous period of not less than seven
hours between 7:00 a.m. and 6:00 p.m. However, nothing in these Contract Documents shall be construed as prohibiting the
Contractor from working on Saturdays if he so desires. Legal holidays are defined as being New Year's Day, Independence Day,
Labor Day,Thanksgiving Day,Christmas Day,Memorial Day,and Veteran's Day.
... H-2 PROGRESS AND COMPLETION: All the time limits stated in the Contract Documents are of essence to the Contract.
The Contractor shall begin the Work on the date of commencement as defined in this Section. He shall carry the Work forward
expeditiously with adequate forces and shall complete it within the Contract Time.
H-3 DELAYS AND EXTENSIONS OF TIME: If the Contractor is delayed at any time in the progress of the Work by any act
or neglect of the Owner or the Architect,or by any employee of the Owner,or by any separate contractor employed by the Owner,
or by changes ordered in the Work, or by labor disputes, fire, unusual delay in transportation, unavoidable casualties or any
causes beyond the Contractor's control,or by any cause which the Architect determines may justify the delay,then the contract
„r time may be extended by Change Order for such reasonable time as recommended by the Architect and approved by the Owner.
When the Contractor is delayed due to abnormal weather conditions, the weather table provided as WT-1 in these Contract
Documents shall be used as the basis for providing a fair and equitable adjustment of the contract time.
All claims for extension of time shall be made in writing to the Architect no more than fifteen days after the occurrence of the delay;
otherwise they shall be waived.
If no schedule or agreement is made stating the dates upon which written interpretations shall be furnished,then no claim for delay
shall be allowed on account of failure to furnish such interpretation until fifteen days after demand is made for them,and not then
s
unless such a claim is reasonable.
H-4 NO DAMAGE FOR DELAY: No payment, compensation or adjustment or any kind (other than the extensions of time
provided for)shall be made to the Contractor for damages because of hindrances or delays from an cause in the progress of the
work,whether such hindrances or delays be avoidable or unavoidable,and the Contractor agrees that he will make no claim for
compensation,damages or mitigation of liquidated damages for any such delays,and will accept in full satisfaction for such delays
said extension of time.
SECTION I
PAYMENTS AND COMPLETION
1-1 CONTRACT SUM: The Contract Sum is stated in the contract and is the total amount payable by the Owner to the
Contractor for the performance of the Work under the Contract Documents.
1-2 SCHEDULE OF VALUES: Before the first Applicable for Payment, the Contractor shall submit to the Architect a
Schedule of Values of the various portions of the Work, including quantities if required by the Architect, aggregating the total
Contract Sum,divided so as to facilitate payments to Sub-contractors,prepared in such form as specked or as the Architect and
the Contractor may agree upon,and supported by such data to substantiate its correctness as the Architect may require.Each item
... in the Schedule of Values shall include its proper share of overhead and profit.This Schedule,when approved by the Architect and
the Owner,shall be used as a basis for the Contractor's Applications for Payment.
1-3 ADJUSTMENT OF QUANTITIES(NOT USED)
1-4 PROGRESS PAYMENTS: On the first day of each month after the first month's work has been completed, the
Contractor will make current estimates in writing for review by the Architect of materials in place complete and the amount of work
performed during the preceding month or period and the value thereof at the prices contracted for as shown on the approved
.� Schedule of Values and Progress Schedule.
If payments are to be made on account of materials or equipment not incorporated in the Work but delivered and suitably stored at
the site or in an independent,bonded warehouse such payments shall be conditioned upon submission by the Contractor of bills of
sale or such other procedures satisfactory to the Owner to establish the Owner's title to such materials or equipment or otherwise
i protect the Owner's interest including applicable insurance and transportation to the site.
The Contractor warrants and guarantees that title to all Work, materials and equipment covered by an Application for Payment,
whether incorporated in the Project or not, will pass to the Owner upon the receipt of such payment by the Contractor, free and
clear of all liens, claims, security interests or encumbrances hereinafter referred to as "liens"; and that no Work, materials or
equipment covered by an Application for Payment will have been acquired by the Contractor,or by any other persons performing
the Work at the site or furnishing materials and equipment for the Work,subject to an agreement under which an interest therein or
an encumbrance thereon is retained by the seller or otherwise imposed by the Contractor or such other person.
The Contractor shall prepare each application for payment on AIA Document G702,"Application and Certificate for Payment",and
attached thereto AIA Document G703, "Continuation Sheet", to indicate the progress made to date and the period or month for
which payment is requested for each Item listed in the Schedule of Values. A copy of the revised monthly work progress schedule
must be attached before the pay request can be accepted.
"�- 1-5 CERTIFICATES FOR PAYMENT: If the Contractor has made Application for Payment as above, the above, the
Architect will,with reasonable promptness but not more than seven days after the receipt of the Application,prepare a Certificate of
Payment,with a copy to the Contractor,for such amount determined to be properly due,or state in writing reasons for withholding a
Certificate.
The issuance of a Certificate for Payment will constitute a representation by the Owner, based on the BCM's observations at the
site and the data comprising the Application for Payment,that the Work has progressed to the point indicated;that the quality of the
Work is in accordance with the Contract Documents(subject to an evaluation of the Work as a functioning whole upon Substantial
Completion, to the results of any subsequent tests required by the Contract Documents, to minor deviations from the Contract
Documents correctable prior to completion,and to any speck qualifications stated in the Certificate);and recommendations to the
Owner that the Contractor be paid in the amount certified.In addition,the Architect's approval of final payment assures the Owner
that the conditions precedent to the Contractor's being entitled to final payment as set forth in this Section have been fulfilled.
After the Architect has issued a Certificate for Payment,the Owner shall approve or disapprove same within ten days after it has
-� been delivered to the Director of the Department of Transportation and Public Works. For contracts less than$400,000, Owner
shall pay 90%of the approved estimate to the Contractor within seven days after its approval,and the remaining 10%of each such
estimate will be retained by the Owner until the final estimate is approved and the Work is accepted by the City Council of the City
of Fort Worth. For contracts in excess of$400,000, the Owner will retain only 5% of each estimate until the final estimate is
approved and work accepted by the City Council of the City of Fort Worth.
No Certificate for a progress payment,nor any progress payment,nor any partial or entire use or occupancy of the Project by the
Owner, shall constitute an acceptance of any Work not in accordance with the Contract Documents,or relieve the Contractor of
liability in respect to any warranties or responsibility for faulty materials or workmanship.The Contractor shall promptly remedy any
.. defects in the Work and pay for any damage to other work resulting therefrom that shall appear within a period of one year from the
date of final acceptance of the Work unless a longer period is specified.
1-6 PAYMENTS WITHHELD: The BCM may decline to approve an Application for Payment and may withhold his Certificate
in whole or in part if in his opinion he is unable to make the representations to the Owner as provided in this Section.The Architect
may also decline to approve any Applications for Payment or, because of subsequently discovered evidence or subsequent
inspections,may nullify the whole or any part of any Certificate for Payment previously issued to such extent as may be necessary
in his opinion to protect the Owner from loss because of:
1) Defective work not remedied;
■w
2) Claims filed or reasonable evidence indicating probable filing of claims;
3) Failure of the Contractor to make payments properly to Subcontractors,or for labor,materials or equipment;
r®
4) Reasonable doubt that the Work can be completed for the unpaid balance of the Contract Sum;
5) Damage to another contractor;
6) Reasonable indication that the Work will not be completed within the Contract Time;or
r 7) Unsatisfactory prosecution of the Work by the Contractor.
When such grounds for the refusal of payment are removed,payment shall be made for amounts withheld because of them.The
Owner reserves the right to withhold the payment of any monthly estimate,without payment of interest, if the Contractor fails to
perform the Work in accordance with the specifications.
1-7 NOT USED
1-8 LIQUIDATED DAMAGES: The deduction for liquidated damages shall be as follows:
°-^ 1-8 LIQUIDATED DAMAGES: The deduction for liquidated damages shall be as follows:
Amount of Contract Liquidated Damages Per Day
.,. $15,000 or less $45
$15,001 to $25,000 $63
$25,001 to $50,000 $105
$50,001 to $100,000 $154
$100,000 to $500,000 $210
,., $500,001 to$1,000,000 $315
$1,000,001 to$2,000,000 $420
$2,000,001 to$5,000,000 $630
$5,000,001 to$10,000,000 $840
over$10,000,000 $980
1-9 FAILURE OF PAYMENT: If,without fault on the part of the Contractor,the BCM should fail to issue any Certificate for
Payment within seven days after receipt of the Contractor's Application for Payment,if the Contractor's Application for Payment,or
if,without fault on the part of the Contractor the Owner should fail to approve such estimate or to pay to the Contractor 90%or
95% (as applicable) of the amount thereof within the period of time specified, then the Contractor may, upon seven (7) days
additional written notice to the Owner and to the Architect,stop the Work until payment of the amount owing has been received.
1-10 SUBSTANTIAL COMPLETION AND FINAL PAYMENT Prior to the request for final payment,the CMAR must meet all
provisions for Project Closeout.When the CMAR determines that the Work or a designated portion thereof acceptable to the Owner
is substantially complete,the CMAR shall prepare the submission to the Architect a list of items to be completed or corrected.The
failure to include any items on such list does not relieve the CMAR of its responsibility to complete all Work in accordance with the
Contract Documents. When the Architect, on the basis of an inspection, determines that the Work is substantially complete, he
then will prepare a Certificate of Substantial Completion(G704)which,when approved by the Owner, shall establish the Date of
' Substantial Completion,shall state the responsibilities of the Owner and the CMAR for maintenance,heat,utilities,and insurance,
and shall fix the time within which the CMAR shall complete the items listed therein,said time to be within the Contract time unless
extended.
Upon receipt of written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for
Payment and upon receipt of a final application for payment,providing the record drawings have been received by the Architect,the
Architect will conduct such tests and/or inspections as he deems necessary,and if in his opinion the Work has been completed in
accordance with the Contract Documents,the Architect will promptly issue a final Certificate of Substantial Completion stating that
to the best of his knowledge, information and belief, and on the basis of his observations and inspections, the Work has been
completed in accordance with the terms and conditions of the Contract Documents and that the entire balance found to be due the
CMAR is due and payable. Final acceptance can be made by the City's or its designated representative, and no other form of
acceptance will be binding upon the Owner. Final payment and release of the retainage amount will become due within thirty(30)
days following the date of such acceptance.
Neither the final payment nor the remaining retained percentage shall become due until the CMAR submits the following
documentation to the Architect:
1) CMAR's Affidavit of Payment of Debts and Claims(G706)stating that all payrolls,bills for materials and equipment,and other
indebtedness connected with the Work for which the Owner or his property might in any way be responsible,have been paid
or otherwise satisfied,
2) Consent of Surety to Final Payment(G707),If any,to final payment,
3) CMAR's Affidavit of Release of Liens(G706A),and,
4) Other data establishing payment or satisfaction of all such obligations,such as receipts,releases and waivers of liens arising
out of the Contract,to the extent and in such form as may be designated by the Owner,
If any Subcontractor,materialman or laborer refuses to furnish a release or waiver required by the Owner,the CMAR may,at the
election of the Owner,furnish a bond satisfactory to the Owner to indemnify the Owner against any right,claim or lien which might
be asserted by such Subcontractor materialman or laborer If any such right,claim or lien remains unsatisfied after all payments
are made.CMAR shall refund to the Owner all monies that the Owner may be compelled to pay to discharging such right,claim or
lien,including all costs and reasonable attorney's fees.
The acceptance of final payment shall constitute a waiver of all claims by the CMAR except those previously made in writing and
,.. still unsettled.
1-11 FINAL PAYMENT FOR UN-BONDED PROJECTS: Final payment will not be made for a period of 30 calendar days and
until all requirements have been met,with the exception of Consent of Surety for Final Payment.
SECTION J
PROTECTION OF PERSONS AND PROPERTY
J-1 SAFETY PRECAUTIONS AND PROGRAMS: The Contractor shall be responsible for initiating, maintaining and
supervising all safety precautions and programs in connection with the Work.The Contractor shall designate a responsible member
of his organization at the site whose duty shall be the prevention of accidents.This person shall be the Contractor's superintendent
unless otherwise designated in writing by the Contractor to the Architect.
J-2 SAFETY OF PERSONS AND PROPERTY: The Contractor shall take all reasonable precautions for the safety of,and
shall provide all reasonable protection to prevent damage,injury or loss to:
(1) All employees on the Work and all other persons who may be affected thereby;
.. (2) All the Work and all materials and equipment to be incorporated therein,whether in storage on or-off the site,under the care,
custody or control of the Contractor or any of his Subcontractors or Sub-contractors;and
(3) Other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures and
utilities not designated for removal,relocation or replacement in the course of construction.
Until acceptance of the Work,it shall be under the charge and care of the Contractor,and he shall take every precaution against
injury or damage to the Work by the action of the elements or from any other cause whatsoever,whether arising from the execution
or from the non-execution of the Work.The Contractor shall rebuild,repair restore and make good,at his own expense,all injuries
,. or damages to any portion of the Work occasioned by any of the above,caused before its completion and acceptance.
The Contractor shall comply with all applicable Laws, Ordinances, Rules, Regulations and Orders of any public authority having
jurisdiction for the safety of persons or property or to protect them from damage, injury or loss. He shall erect and maintain, as
required by existing conditions and progress of the Work, all reasonable safeguards for safety and protection, including posting
danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent
utilities.
When the use or storage of explosives or other hazardous materials or equipment is necessary for the execution of the Work,the
Contractor shall exercise the utmost care and shall carry on such activities under the supervision of property qualified personnel.
All damage or loss to any property referred to in the preceding paragraphs caused in whole or in part by the Contractor, any
Subcontractor,or anyone directly or indirectly employed by any of them,or by anyone for whose acts any of them may be liable,
shall be remedied by the Contractor, including damage or loss attributable to faulty Drawings or Specifications and acts or
omissions of the Architect or anyone employed by him or for whose acts he may be liable, and not attributable to the fault or
.. negligence of the Contractor or anyone claiming through the Contractor for such damage or loss.
The Contractor shall not load or permit any part of the Work to be loaded so as to endanger its safety.
J-3 HARD HATS: Hard Hats will be required at all construction sites included in this Contract from start to completion of
work. Each Contractor,employee and visitor at any construction site included in the Contract will be required to wear a hard hat.
The Contractor shall enforce the wearing of hard hats by Contractor employees and visitors.Contractor shall provide ten hard hats
for use by the consulting Architects and Engineers and visitors.
J-4 EMERGENCIES: In any emergency affecting the safety of persons or property,the Contractor shall act at his discretion
to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on
account of emergency work shall be determined as provided in Changes in the Work.
J-5 SAFE WORK PRACTICES: The Contractor shall employ safe practices in handling materials and equipment used in
*� performing required work so as to insure the safety of his workmen,City employees and the public. The Contractor shall keep the
premise free at all times from accumulation of waste materials or rubbish. At the completion of the work, the Contractor shall
remove all his wastes and rubbish from and about the work area,as well as his tools,equipment and surplus materials and shall
leave the area as clean and free of spot,stains,etc.,as before the work was undertaken.
J-6 TRENCH SAFETY: The Contractor shall be responsible for all design and implementation of trench shoring and
stabilization to meet regulatory requirements. If the Proposal requires,the Contractor shall include a per-unit cost for trench safety
measures in his bid. If not included in the Proposal,the Contractor shall include a cost for trench safety measures for all trenches
over 5 feet in depth in his Schedule of Values.
SECTION K-INSURANCE
K-1 INSURANCE REQUIRED: The Contractor shall not commence work under this Contract until he has obtained all
insurance required under this Section and such insurance has been approved by the City of Fort Worth, nor shall the Contractor
allow any Subcontractor to commence work to be performed under this Contract until all similar insurance of the Subcontractor has
been so obtained and approved. The City of Fort Worth will be listed as an "additional insured"on all policies except Worker's
Compensation.
K-2 WORKERS'COMPENSATION INSURANCE
11 General
.� a) Contractor's Workers Compensation Insurance. Contractor agrees to provide to the Owner(City)a certificate showing
that it has obtained a policy of workers compensation insurance covering each of its employees employed on the project
in compliance with state law. No Notice to Proceed will be issued until the Contractor has complied with this section.
b) Subcontractors Workers Compensation Insurance. Contractor agrees to require each and every subcontractor who will
perform work on the project to provide to it a certificate from such subcontractor stating that the subcontractor has a
policy of workers compensation insurance covering each employee employed on the project. Contractor will not permit
any subcontractor to perform work on the project until such certificate has been acquired. Contractor shall provide a copy
of all such certificates to the Owner(City).
c) By signing this Contract or providing or causing to be provided a certificate of coverage,the Contractor is representing to
the City that all employees of the Contractor who will provide services on the project will be covered by workers
compensation coverage for the duration of the project, that the coverage will be based on proper reporting of
classification codes and payroll amounts, and that all coverage agreements will be filed with the appropriate insurance
carrier or, in the case of a self-insured,with the Texas Workers Compensation Commission's Division of Self-Insurance
Regulation. Providing false or misleading information may subject the Contractor to administrative penalties, criminal
penalties,civil penalties or other civil actions.
d) The Contractors failure to comply with any of these provisions is a breach of contract by the Contractor which entitles the
w.r City to declare the contract void if the Contractor does not remedy the breach within ten days after receipt of notice of
breach from the City.
2) Definitions:
a) Certificate of Coverage("certificate"). A copy of a certificate of insurance,a certificate of authority to self-insure issued
by the Texas Workers' Compensation Commission, or a coverage agreement (TWCC-81, TWCC-82, TWCC-83, or
TWCC-84),showing statutory workers'compensation insurance coverage for the person's or entity s employees providing
services on a project,for the duration of the project.
b) Duration of the Project. Includes the time from the beginning of the work on the project until the Contractor'slperson's
work on the project has been completed and accepted by the City.
c) Persons providing services on the project("subcontractor"in section 406.096)-includes all persons or entities performing
all or part of the services the Contractor has undertaken to perform on the project, regardless of whether that Derson
contracted directly with the Contractor and regardless of whether that person has employees. This includes, without
limitation, independent contractors, subcontractors, leasing companies, motor carriers, owner-operators, employees of
any such entity, or employees of any entity which furnishes persons to provide services on the project. "Services"
include, without limitation, providing, hauling,or delivering equipment or materials,or providing labor,transportation,or
other services related to a project. "Services"does not include activities unrelated to the project,such as food/beverage
vendors,office supply deliveries,and delivery of portable toilets.
3) Requirements
a) The Contractor shall provide coverage,based on proper reporting of classification codes and payroll amounts and filing of
any coverage agreements, which meets the statutory requirements of Texas Labor Code, Section 401.011(44)for all
employees of the Contractor providing services of the project,for the duration of the project.
b) The Contractor must provide a certificate of coverage to the governmental entity prior to being awarded the contract.
c) If the coverage period shown on the Contractors current certificate of coverage ends during the duration of the project,
the Contractor must,prior to the end of the coverage period,file a new certificate of coverage with the City showing that
coverage has been extended.
d) The Contractor shall obtain from each person providing services on a project,and provide to the City:
i) a certificate of coverage,prior to that person beginning work on the project,so the governmental entity will have on
file certificates of coverage showing coverage for all persons providing services on the project;and
ii) no later than seven days after receipt by the Contractor, a new certificate of coverage showing extension of
coverage,if the coverage period shown on the current certificate of coverage ends during the duration of the project.
e) The Contractor shall retain all required certificates of coverage for the duration of the project and for one year thereafter.
Q The Contractor shall notify the City in writing by certified mail or personal delivery, within ten (10) days after the
Contractor knew or should have known, of any change that materially affects the provision of coverage of any person
®, providing services on the project.
g) The Contractor shall post on each project site a notice, in the text,form and manner prescribed by the Texas Workers
Compensation Commission,informing all persons providing services on the project that they are required to be covered,
and stating how a person may verify coverage and report lack of coverage.
h) The Contractor shall contractually require each person with whom it contracts to provide services on a project,to:
i) provide coverage, based on proper reporting on the classification codes and payroll amounts and filing of any
coverage agreements,which meets the statutory requirements of Texas labor Code,Section 401.011(44)for all of
its employees providing services on the project,for the duration of the project;
ii) provide to the Contractor,prior to that person beginning work on the project,a certificate of coverage showing that
coverage is being provided for all employees of the person providing services on the project,for the duration of the
project;
0"
iii) provide the Contractor, prior to the end of the coverage period,a new certificate of coverage showing extension of
coverage,if the coverage period shown on the current certificate of coverage ends during the duration of the project;
iv) obtain from each other person with whom it contracts,and provide to the Contractor:
(1) a certificate of coverage,prior to the other person beginning work on the project;and
(2) a new certificate of coverage showing extension of coverage, prior to the end of the coverage period, if the
coverage period shown on the current certificate of coverage ends during the duration of the project;
v) retain all required certificates of coverage on file for the duration of the project and for one year thereafter.
vi) notify the City in writing by certified mail or personal delivery,within ten(10)days after the person knew or should
have known,of any change that materially affects the provision of coverage of any person providing services on the
project;and
vii contractually require each person with whom it contracts,to perform as required by paragraphs h-i)-vii),with the
certificates of coverage to be provided to the person for whom they are providing services.
4) Posting of Required Worker's Compensation Coverage
aw a) The Contractor shall post a notice on each project site informing all persons providing services on the project that they
are required to be covered,and stating how a person may verify current coverage and report failure to provide coverage.
This notice does not satisfy other posting requirements imposed by the Texas Workers Compensation Act or other
Texas Workers Compensation Commission rules. This notice must be printed with a title in at least 30 Doint bold type
and text in at least 19-point normal type,and shall be in both English and Spanish and any other language common to
the worker population. The text for the notices shall be the following text,without any additional words or changes:
"REQUIRED WORKER'S COMPENSATION COVERAGE
The law requires that each person working on this site or providing services related to this construction project
must be covered by workers compensation insurance. This includes persons providing,hauling,or delivering
equipment or materials,or providing labor or transportation or other service related to the project,regardless of
the identity of their employer or status as an employee".
Call the Texas Workers Compensation Commission at 512-440-3789 to receive information on the legal
requirement for coverage,to verify whether your employer has provided the required coverage,or to report an
employers failure to provide coverage."
K-3 LIABILITY INSURANCE: The Contractor shall procure and maintain during the term of this Contract such Liability
Insurance as shall protect him,the City of Fort Worth and any Subcontractor performing work covered by this Contract,from claims
of damage which may arise from operations under this Contract,including blasting,when blasting is done on,or in connection with
the Work of the Project, whether such operations be by himself or by any Subcontractor or by anyone directly or indirectly
employed by either of them and the limits of such insurance shall be not less than the following:
1) Automobile Liability: $1,000,000 each accident or reasonably equivalent split limits for bodily injury and property damage.
Coverage shall be on"any auto"including leased, hired,owned,non-owned and borrowed vehicles used in connection with
this Contract.
2) Commercial General Liability: $1,000,000 each occurrence. Coverage under the policy shall be as comprehensive as that
provided in a current Insurance Services Office (ISO) policy form approved for use in Texas and the policy shall have no
exclusions by endorsement unless such are approved by the City.
3) Asbestos Abatement Liability Insurance:When the Project specifically requires the removal of Asbestos Containing Materials,
the Contractor or subcontractor performing the removal,shall be required to maintain Asbestos Abatement Liability Insurance
as follows: $1,000,000 per occurrence; $2,000,000 aggregate limit. The coverage shall include any pollution exposure,
including environmental impairment liability, associated with the services and operations performed under this contract in
addition to sudden and accidental contamination or pollution liability for gradual emissions and clean-up costs.
�.. K-4 BUILDER'S RISK INSURANCE: Unless stated otherwise in the Proposal or Invitation,the Contractor shall procure,pay
for and maintain at all times during the term of this Contract,Builders Risk Insurance against the perils of fire,lightning,windstorm,
hurricane,hail,riot,explosion,civic commotion,smoke,aircraft,land vehicles,vandalism,and malicious mischief,at a limit equal to
100%of the Contract Sum.
The policy shall include coverage for materials and supplies while in transit and while being stored on or off site. If specifically
required in the Instructions to Bidders, the policy shall include coverage for flood and earthquake. Different sub-limits for these
coverages must be approved by the City.
Consequential damage due to faulty workmanship and/or design performed by the Contractor or his agents shall be covered.
Upon completion of the Work,the Contractor shall notify the City of Fort Worth in writing before terminating this insurance.
K-5 PROOF OF CARRIAGE OF INSURANCE: The Contractor shall provide a certificate of insurance documenting the
Transportation and Public Works Department,City of Fort Worth as a"Certificate Holder",and noting the specific project(s)covered
by the Contractors insurance as documented on the certificate of insurance. More than one certificate may be required of the
Contractor depending upon the agents and/or insurers for the Contractors insurance coverages specified for the project(s).
K-6 OTHER INSURANCE RELATED REQUIREMENTS
R 1) The City of Fort Worth shall be an additional insured,by endorsement,on all applicable insurance policies.
2) Applicable insurance policies shall each be endorsed with a waiver of subrogation in favor of the City of Fort Worth.
3) Insurers of policies maintained by Contractor and its subcontractor(s),if applicable,shall be authorized to do business in the
State of Texas,or otherwise approved by the City of Fort Worth,and such shall be acceptable to the City of Fort Worth insofar
as their financial strength and solvency are concerned. Any company through which the insurance is placed must have a
rating of at least A:VII, as stated in current edition of A. M. Best's Key Rating Guide. At the City's sole discretion, a less
favorable rate may be accepted by the City.
4) Deductible limits on insurance policies and/or self-insured retentions exceeding$10,000 require approval of the City of Fort
Worth as respects this Contract.
5) The City of Fort Worth shall be notified in writing a minimum of thirty days prior to an insurer's action in the event of
cancellation or non-renewal in coverage regarding any policy providing insurance coverage required in this Contract.
6) Full limits of insurance shall be available for claims arising out of this Contract with the City of Fort Worth.
7) The Contractor shall provide certificates of insurance to the City prior to commencement of operations pursuant to this
Contract. Any failure on part of the City of Fort Worth to request such documentation shall not be construed as a waiver of
insurance requirements specified herein.
8) The City of Fort Worth shall be entitled,upon request and without incurring expense,to review the insurance policies including
endorsements thereto and,at its discretion,to require proof of payment for policy premiums.
9) The City of Fort Worth shall not be responsible for paying the cost of insurance coverages required herein.
10) Notice of any actual or potential claim and/or litigation that would affect insurance coverages required herein shall be provided
to the City in a timely manner
11) "Other insurance" as referenced in any policy of insurance providing coverages required herein shall not apply to any
insurance policy or program maintained by the City of Fort Worth.
12) Contractor shall agree to either require its subcontractors to maintain the same insurance coverages and limits thereof as
specified herein or the Contractor shall provide such coverage on the Contractor's subcontractors.
SECTION L
CHANGES IN THE WORK
... L-1 CHANGE ORDER: The Owner without invalidating the Contract, may order Changes in the Work within the general
scope of the Contract consisting of additions,deletions or other revisions,the Contract Sum and the Contract Time being adjusted
accordingly. All Such Changes in the Work shall be authorized by Change Order and shall be executed under the applicable
conditions of the Contract Documents.
rse
A Change Order is a written order to the Contractor signed by the Contractor,Owner and the Architect,issued after the execution of
the Contract,authorizing a Change in the Work or adjustment in the Contract Sum or the Contract Time. The Contract Sum and
the Contract Time may be changed only by Change Order
Any changes in work required due to changed or unforeseen conditions,or by request of either the Contractor or the City,shall be
coordinated with the Director Department of Transportation and Public Works. A change order must be written and duly negotiated
and executed prior to performing changed work.
... The cost or credit to the Owner resulting from a Change in the work shall be determined in one or more of the following ways:
1) by mutual acceptance of a lump sum property itemized, including the allowance to Contractor for overhead and profit
stipulated in the original contract proposal;
2) by unit prices stated in the Contract Documents or subsequently agreed upon;or
3) by cost and a mutually acceptable fixed or percentage fee.
If none of the methods set forth herein above is agreed upon,the Contractor,provided he receives a Change Order,shall promptly
proceed with the Work involved. The cost of such work shall then be determined on the basis of the Contractor's reasonable
expenditures and savings,including a reasonable allowance for overhead and profit as indicted in the original contract proposal.In
such cases,the Contractor shall keep and present,in such form as the Architect shall prescribe,an itemized accounting together
with appropriate supporting data. Pending final determination of cost to the Owner, payments on account shall be made on the
Architect's Certificate of Payment as approved by the Owner.
If after the Contract has been executed, the Architect, requests a price proposal from the Contractor for a proposed change in
scope of the work,Contractor shall process such proposal within seven days of receipt and return the price quote to the Architect in
writing.The Architect shall review the once quotation and if approval is recommended,forward the proposed change order request
and price proposal to the Owner for approval. If approval is not recommended, the Architect will attemat to negotiate with
�w
Contractor to revise the proposal to a figure which is fair and reasonable and forward it on to the Owner for approval. If the
negotiations do not result in an equitable solution, the Architect shall prepare a cost-plus type Change Order with a price-not-to-
exceed figure for approval by the City and require specific documentation to be provided by Contractor in accordance with the
paragraph above.
r. Contractor is advised that according to City of Fort Worth Charter,that,the City Council must approve all Change Orders and Work
Orders which results in an increase in cost of the contract amount by over$25,000. Normal processing time for the City Staff to
obtain City Council approval, once the recommended change order has been received at the City, is approximately thirty days.
Owner and Contractor shall endeavor to identify Change Order items as early in the Construction process as possible to minimize
their impact on the construction schedule.
If unit prices are stated in the Contract Documents or subsequently agreed upon,and if the quantities originally contemplated are
so changed in a proposed Change Order that application of the agreed unit prices to the quantities of Work proposed will create a
hardship on the Owner or the Contractor,the applicable unit prices shall be equitably adjusted to prevent such hardship.
If the Contractor claims that additional cost or time is involved because of(1)any written interpretation issued pursuant to Section
A,(2)any order by the Architect or Owner to stop the Work pursuant to Section B,where the Contract was not at fault,or(3)any
written order for a minor change in the Work,the Contractor shall make such claim.
L-2 CLAIMS FOR ADDITIONAL COST OR TIME: If the Contractor wishes to make a claim for an increase in the Contract
Sum or an extension in the Contract Time, he shall give the Architect written notice thereof within a reasonable time after the
occurrence of the event that gave rise to such claim.This notice shall be given by the Contractor before proceeding to execute the
Work,except in an emergency endangering life or property in which case the Contractor shall proceed in accordance with Section
J. No such claim shall be valid unless so made. Any change in the Contract Sum or Contract Time resulting from such claim,if
approved by the Owner,shall be authorized by Change Order.
L-3 OVERHEAD ALLOWANCES FOR CHANGES: Should any change in the work or extra work be ordered,the following
,,. applicable percentage shall be added to Material and Labor costs to cover overhead and profit:
1. Allowance to the Contractor for overhead and profit for extra work performed by the Contractor's own forces shall not exceed
fifteen percent Llff2l.
2. Allowance to the Contractor for overhead and profit for extra work performed by a Subcontractor and supervised by the
Contractor shall not exceed ten percent 11M.
L-4 MINOR CHANGES IN THE WORK: The Architect shall have authority to order minor changes in the Work not involving
.rw an adjustment in the Contract Sum or an extension of the Contract Time and not inconsistent with the intent of the Contract
Documents. Such changes may be effected by Field Order or by other written order. Such changes shall be confirmed in writing
by the Architect and shall be binding on the Owner and the Contractor.
L-5 FIELD ORDERS: The Architect may issue written Field Orders which interpret the Contract Documents,or which order
�* minor changes in the Work without change in Contract Sum or Contract Time. The Contractor shall carry out such Field Orders
promptly.
SECTION M
�. UNCOVERING AND CORRECTION OF WORK
M-1 UNCOVERING OF WORK: If any Work should be covered contrary to the request of the Owner it must be uncovered
for observation and replaced,at the Contractor's expense.
If any other work has been covered which the Owner has not specifically requested to observe prior to being covered,the Architect
or the Owner may request to see such work and it shall be uncovered by the Contractor.If such Work be found in accordance with
the Plans and Specifications, the cost of uncovering and replacement shall, by appropriate Change Order, be charged to the
Owner. If such work be found not in accordance with the Plans and Specifications,the Contractor shall pay such costs unless it is
found that this condition was caused by a separate contractor employed by the Owner.
M-2 CORRECTION OF WORK: The Contractor shall promptly correct all work rejected by the Owner as defective or as
failing to conform to the Plans and Specifications whether observed before or after Substantial Completion and whether or not
fabricated, installed or completed.The Contractor shall bear all costs of correcting such rejected Work, including the cost of the
Architect's additional service thereby made necessary.
If,within one year after the Date of Substantial Completion or within such longer period of time as may be prescribed by law or by
the terms of any applicable special guarantee required by the Contract Documents,any of the work is found to be defective or not
in accordance with the Contract Documents,the Contractor shall correct it promptly after receipt of a written notice from the Owner
to do so,unless the Owner has previously given the Contractor a written acceptance of such condition,describing same specifically
and not generally.The Owner shall give such notice promptly after discovery of the condition.
All such defective or non-conforming work under the preceding paragraphs shall be removed from the site where necessary and the
work shall be corrected to comply with the Contract Documents without cost to the Owner
The Contractor shall bear the cost of making good all work of separate contractors destroyed or damaged by such removal or
correction.
If the Contractor does not remove such defective or non-conforming work within a reasonable time fixed by written notice from the
Owner,the Owner may remove it and may store the materials or equipment at the expense of the Contractor.If the Contractor does
not pay the cost of such removal and storage within ten days thereafter,the Owner may upon ten additional days'written notice sell
such work at auction or at private sale and shall account for the net proceeds thereof,after deducting all the costs that should have
been bome by the Contractor including compensation for additional architectural services.If such proceeds of sale do not cover all
costs that the Contractor should have bome,the difference shall be charged to the Contractor and an appropriate Change Order
shall be issued. If the payments then or thereafter due the Contractor are not sufficient to cover such amount,the Contractor shall
pay the difference to the Owner.
If the Contractor fails to correct such defective or non-conforming work,the Owner may correct it in accordance with Section G.
The obligation of the Contractor under this Section shall be in addition to and not in limitation of any obligations imposed upon him
by special guarantees required by the Contract Documents or otherwise prescribed by law.
.. M-3 ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK: If the Owner prefers to accept defective or non-
conforming work, he may do so instead of requiring its removal and correction, in which case a Change Order will be issued to
reflect an appropriate reduction in the Contract Sum, or, if the amount is determined after final payment, it shall be paid by the
Contractor.
SECTION N
TERMINATION OF THE CONTRACT
N-1 TERMINATION BY THE CONTRACTOR: If the work is stopped for a period of 30 days under an order or any court or
other public authority having jurisdiction,through no act or fault of the Contractor or a Subcontractor or their agents or employees or
any other persons performing any of the work under a contract with the Contractor or if the work should be stopped for a period of
30 days by the Contractor for the Owner's failure to make payment thereon as provided in Section I then the Contractor may after
-- the end of such period of 30 days and upon seven additional days'written notice to the Owner terminate the Contract.
N-2 TERMINATION BY THE OWNER: If the Contractor is adjudged as bankrupt, or if he makes a general assignment for
the benefit of his creditors,or if a receiver is appointed on account of his insolvency,of if the Contractor refuses,except in cases for
which extension of time is provided,to supply enough properly skilled workmen or proper materials,or if he fails to make prompt
payment to Subcontractors or for materials or labor,or fails to comply with all Laws,Statutes,Charter,Ordinances,Regulations or
Orders of any public authority having jurisdiction, or otherwise is guilty of a substantial violation of a provision of the Contract
Documents, then the Owner,on its own initiative that sufficient cause exists to justify such action, may,without prejudice to any
rights or remedy and after giving the Contractor and his surety,If any,seven(7)days'written notice,terminate the employment of
the Contractor and take possession of the site and of all materials, equipment, tools, construction equipment and machinery
thereon owned by the Contractor and may finish the work by whatever method he may deem expedient. In such case the
Contractor shall not be entitled to receive any further payment until the Work is finished.
If the costs of finishing the Work, including compensation for the Architect's additional services.exceed the unpaid balance of the
Contract,the Contractor shall pay the difference to the Owner.
The City of Fort Worth may terminate this contract in whole,or from time to time,in part,whenever such termination is in the best
interest of the City. Termination will be effected by delivering to the Contractor a notice of termination specifying to what extent
performance of the work of the contract is being terminated and the effective date of termination. After receipt of termination the
Contractor shall:
a) Stop work under the Contract on the date and to the extent specified on the notice of termination.
b) Place no further orders or subcontracts except as may be necessary for the completion of the work not terminated.
c) Terminate all orders and subcontracts to the extent that they relate to the performance of the work terminated by the notice of
termination.
After termination as above,the City will pay the Contractor a proportionate part of the contract price based on the work completed;
provided,however that the amount of payment on termination shall not exceed the total contract price as reduced by the portion
thereof allocatable to the work not completed and further reduced by the amount of payments,if,any otherwise made. Contractor
shall submit its claim for amounts due after termination as provided in this paragraph within 30 days after receipt of such claim. In
the event of any dispute or controversy as to the propriety or allowability of all or any portion of such claim under this paragraph,
such dispute or controversy shall be resolved and be decided by the City Council of the City of Fort Worth,and the decision by the
City Council of the City of Fort Worth shall be final and binding upon all parfies to this contract
err SECTION O
SIGNS
The Contractor shall construct and install the project designation sign as required in the Contract Documents and in strict
accordance with the Specifications for"Project Designation Signs."This sign shall be a part of this Contract and shall be included in
ww the Contractor's Base Bid for the Project.
SECTION P
w TEMPORARY FACILITIES
P-1 SCOPE: The Contractor shall furnish, erect, and maintain facilities and perform temporary work required in the
performance of this Contract,including those shown and specified.
P-2 USE OF TEMPORARY FACILITIES: All temporary facilities shall be made available for use by all workmen and
subcontractors employed on the project, subject to reasonable directions by the Contractor as to their proper and most efficient
utilization.
P-3 MAINTENANCE AND REMOVAL: The Contractor shall maintain temporary facilities in a proper, safe operating and
sanitary condition for the duration of the Contract. Upon completion of the Contract,all such temporary work and facilities shall be
removed from the premises and disposed of unless otherwise directed or specified hereunder.
P-4 FIELD OFFICES AND SHED: The Contractor is not required to provide a temporary field office or telephone for projects
under$1,000,000. Contractor shall equip the Project Superintendent with a pager and provide 24-hour contacts to the City.
The Contractor shall provide a temporary field office building for himself, his subcontractors and use by the Architect. For
construction contracts with a bid price in excess of$1,000,000.00,the Contractor shall provide a separate field office for the City's
field representative (but the separate office may be in the same structure). The buildings shall afford protection against the
weather and each office shall have a lockable door,at least one window,adequate electrical outlets and lighting,and a shelf large
enough to accommodate perusal of the project drawings. Openings shall have suitable locks. Field offices shall be maintained for
the full time during the operation of the work of the Contract. During cold weather months, the field offices shall be suitably
insulated and equipped with a heating device to maintain 70 degree Fahrenheit temperature during the workday. During warm
weather the offices shall be equipped with an air conditioning device to maintain temperature below 75 degrees F. Upon
completion of the work of the Contract,the Contractor shall remove the building from the premises. In addition to the drawing shelf,
provide for the City field representatives office: one deck,four chairs, plan rack and a four drawer filing cabinet(with lock). Each
office shall contain not less than 120 square feet of floor space.
*� The Contractor shall provide and maintain storage sheds other temporary buildings or trailers on the project site as required for his
use.Location of sheds and trailers shall be as approved by the Owner.Remove sheds when work is completed,or as directed.
P-5 TELEPHONE: The Contractor shall provide and pay for telephone installation and service to the field offices described
above. Service shall be maintained for the duration of operations under this contract.The Contractor shall provide for and pay for
an automatic telephone-answering device at the site office for the duration of the project. Contractor will install separate fax lines
and instruments for the City and the Contractor.
P-6 TOILET FACILITIES: The Contractor shall provide proper, sanitary and adequate toilet facilities for the use of all
workmen and subcontractors employed on the project.
P-7 UTILITIES: Contractor shall make all necessary arrangements and provide for temporary water and electricity required
during the construction. Contractor shall provide and install temporary utility meters during the contract construction period. These
meters will be read and the Contractor will be billed on this actual use. The Contractor shall provide all labor and materials required
to tap into the utilities. The Contractor shall make the connections and extend the service lines to the construction area for use of
all trades. Upon completion of the work all utility lines shall be removed and repairs made to the existing lines. Only utilities at
existing voltages,pressures,frequencies,etc.will be available to the Contractor
Water. Provide an ample supply of potable water for all purposes of construction at a point convenient to the project or as shown
on the Drawings. Pipe water from the source of supply to all points where water will be required. Provide sufficient hose to carry
water to every required part of the construction and allow the use of water facilities to subcontractors engaged on the work. Provide
pumps,tanks and compressors as may be required to produce required pressures.
rwrr Electric Service. Provide adequate electric service for power and lighting to all points where required. Temporary,electric service
shall be of sufficient capacity and characteristics to supply proper current for various types of construction tools,motors,welding
machines, lights, heating plant, air conditioning system, pumps, and other work required. Provide sufficient number of electric
outlets so that 50 foot long extension cords will reach all work requiring light or power
Lighting. Supply and maintain temporary lighting so that work of all trades may be properly and safely performed, in such areas
and at such time that day-lighting is inadequate. Provide at least 0.75 watts of incandescent lighting per squgr4e foot and maintain
a socket voltage of at least 110 volts. Use at least 100-watt lamps. In any event,the lighting intensity shall not be less than 5 foot
candles in the vicinity of work and traffic areas.
P-8 HEATING: Heating devices required under this paragraph shall not be electric. The Contractor shall provide heat,
ventilation,fuel and services as required to protect all work and materials and to keep the humidity down to the extent required to
prevent corrosion of any metal and to prevent dampness or mildew which is potentially damaging to materials and finishes. All
such heating, ventilation and services shall be provided and maintained until final acceptance of all work. In addition, the
.ter Contractor shall provide heat ventilation prior and during the following work operations as follows:
a) At all times during the placing, setting and curing of concrete provide sufficient heat to insure the heating of the spaces
involved to not less than 40 F
b) From the beginning of the application of drywall and during the setting and curing period,provide sufficient heat to produce a
temperature in the spaces involved of not less than 55 F.
c) For a period of seven(7)days previous to the placing of interior finish materials and throughout the placing of finish painting,
,. decorating and laying of resilient flooring materials,provide sufficient heat to produce a temperature of not less than 60 F.
CITY OF FORT WORTH,TEXAS
CMAR CONSTRUCTION CONTRACT(LUMP SUM)
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
This agreement made and entered into this the �h day of A.D., 20 �� , by and between the
CITY OF FORT WORTH,a municipal corporation of Tarrant County, Texas, organized and existing under
and by virtue of a special charter adopted by the qualified voters within said City on the 11th day of
December, A.D. 1924, under the authority (vested in said voters by the "Home Rule" provision) of the
Constitution of Texas, and in accordance with a resolution duly passed at a regular meeting of the City
Council of said City, hereinafter called OWNER, and SEDALCO, INC. of the City of Fort Worth, County of
Tarrant,State of Texas, hereinafter called CONTRACTOR.
w
CONTRACT DOCUMENTS: This Contract,General Conditions, Instructions to Offerors,Project Proposal
Form and Plans and Specifications to be added by the Architect at a later date are attached hereto and
incorporated herein, are made a part of this Contract for all purposes. In the event of any conflict
between the terms and conditions of General Conditions, Instructions to Offerors, Proposal Form and
Plans and Specifications and the terms and conditions set forth in the body of this Contract, the terms
and conditions of this Contract shall control.
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned to
be made and performed by the Owner, and under the conditions expressed in the bond bearing even date
herewith, the said Contractor hereby agrees with the said Owner to commence and complete the
construction of certain improvements described as follows:
City of Fort Worth
... Cattle Barn 1 and the Poultry Barn Renovations
Will Rogers Memorial Complex
3401 Lancaster Ave
Fort Worth,Texas
PM D2017-09
That the work herein contemplated shall consist of furnishing as an independent contractor all labor, tools,
appliances and materials necessary for the construction and completion of said project in accordance with
the Plans and Specifications and Contract Documents adopted by the City Council of the City of Fort
Worth, which Plans and Specifications and Contract Documents are hereto attached and made a part of
this contract the same as if written herein.
The Contractor hereby agrees and binds himself to commence the construction of said work within ten
(10)days after being notified in writing to do so by the Owner.
City agrees and binds itself to pay, and the said Contractor agrees to receive,for all of the aforesaid work,
and for stated additions thereto or deductions there from, the price shown on the Proposal submitted by
the successful bidder hereto attached and made a part hereof. Payment will be made in monthly
installments upon actual work completed by contractor and accepted by the Owner and receipt of invoice
from the Contractor.
The agreed upon estimated construction budget amounts shall be a total of not-to-exceed
® $14.248.486.00. This amount include the City's General Contingency Allowance of$248,486.00 (1,77%)
for use by the OWNER only and any Allowance remaining at the end of construction will be retained by the
OWNER.
�. The performance periods in calendars for Phase I and calendar days for Phase II will be determined when
the Guaranteed Maximum Price is agreed upon for each phase.
Cattle Barn 1 and the Poultry Barn Renovations Page 22 of 58
CMAR,Pre-Constriction Services July 2017
Insurance Requirements:
All insurance and bonds will be required once the Guaranteed Maximum Price is agreed upon.
The Contractor shall not commence work under this contract until it has obtained all insurance
required under the Contract Documents, and the Owner has approved such insurance. The
..r Contractor shall be responsible for delivering to the Owner the sub-contractors' certificates of
insurance for approval. The Contractor shall indicate on its certificate of insurance included in the
documents for execution whether or not its insurance covers subcontractors. It is the intention of
the Owner that the insurance coverage required herein shall include the coverage of all
subcontractors.
a. WORKER'S COMPENSATION INSURANCE:
" Statutory limits.
• Employer's liability:
• $100,000 disease each employee.
.s • $500,000 disease policy limit.
• $100,000 each accident.
b. COMMERCIAL GENERAL LIABILITY INSURANCE:
The Contractor shall procure and shall maintain during the life of this contract public
liability insurance coverage in the form of a Commercial General Liability insurance policy
to cover bodily injury, including death, and property damage at the following limits:
�. $1,000,000 each occurrence and$2,000,000 aggregate limit.
• The insurance shall be provided on a project specific basis and shall be endorsed
.. accordingly.
• The insurance shall include, but not be limited to, contingent liability for independent
contractors,XCU coverage,and contractual liability.
C. BUSINESS AUTOMOBILE LIABILITY:
• $1,000,000 each accident.
• The policy shall cover any auto used in the course of the project.
d. BUILDER'S RISK OR INSTALLATION FLOATER:
This insurance shall be applicable according to the property risks associated with the
project and commensurate with the contractual obligations specified in the contract
documents.
e. EXCESS LIABILITY UMBRELLA:
• $1,000,000 each occurrence;$2,000,000 aggregate limit.
• This insurance shall provide excess coverage over each line of liability insurance
required herein. The policy shall follow the form(s)of the underlying policies.
f. SCOPE OF INSURANCE AND SPECIAL HAZARD:
The insurance required under the above paragraphs shall provide adequate protection for
the Contractor and its subcontractors, respectively, against damage claims which may
arise from operations under this contract,whether such operations be by the insured or by
Cattle Sam 1 and the Poultry Bam Renovations Page 23 of 58
CMAR,Pre-Constriction Services July 2017
anyone directly or indirectly employed by it, against any insurable hazards which may be
encountered in the performance of the Contract.
g. PROOF OF CARRIAGE OF INSURANCE:
The Contractor shall furnish the owner with satisfactory proof of coverage by insurance
required in these Contract Documents in the amounts and by insurance carriers
satisfactory to the Owner. The form to be used shall be the current Accord certificate of
insurance form or such other form as the Owner may in its sole discretion deem
acceptable. All insurance requirements made upon the Contractor shall apply to the sub-
contractors, should the Contractor's insurance not cover the subcontractor's work
operations performed in the course of this contracted project.
ADDITIONAL INSURANCE REQUIREMENTS:
a. The Owner, its officers, employees and servants shall be endorsed as an additional
insured on Contractor's insurance policies excepting employer's liability insurance
coverage under Contractor's workers'compensation insurance policy.
b. Certificates of insurance shall be delivered to the City of Fort Worth, contract
administrator in the respective department as specified in the bid documents, 200 Texas
Street, Fort Worth,TX 76102, prior to commencement of work on the contracted project.
..r
C. Any failure on part of the Owner to request required insurance documentation shall
not constitute a waiver of the insurance requirements specified herein.
*■ d. Each insurance policy shall be endorsed to provide the Owner a minimum thirty days'
notice of cancellation, non-renewal, and/or material change in policy terms or coverage.
A ten days notice shall be acceptable in the event of non-payment of premium.
e. Insurers must be authorized to do business in the State of Texas and have a current
A.M. Best rating of A:VII or equivalent measure of financial strength and solvency.
,® f. Deductible limits, or self-funded retention limits, on each policy must not exceed $10,000
per occurrence unless otherwise approved by the Owner.
g. In lieu of traditional insurance, Owner may consider alternative coverage or risk treatment
-• measures through insurance pools or risk retention groups. The Owner must approve in
writing any alternative coverage.
h. Workers' compensation insurance policy(s) covering employees employed on the
project shall be endorsed with a waiver of subrogation providing rights of recovery in
favor of the Owner,
L Owner shall not be responsible for the direct payment of insurance premium costs for
contractor's insurance.
j. Contractor's insurance policies shall each be endorsed to provide that such
insurance is primary protection and any self-funded or commercial coverage
maintained by Owner shall not be called upon to contribute to loss recovery.
,.� k. In the course of the project, Contractor shall report, in a timely manner, to Owner's
officially designated contract administrator any known loss occurrence which could
give rise to a liability claim or lawsuit or which could result in a property loss.
I. Contractor's liability shall not be limited to the specified amounts of insurance
required herein.
Cattle Dam 1 and the Poultry Bam Renovations Page 24 of 58
CHAR,Pre-Consbuction Services July 2017
.111
am M. Upon the request of Owner, Contractor shall provide complete copies of all insurance
policies required by these contract documents.
If this Contract is in excess of$25,000, the Contractor shall provide a Payment Bond in the full amount of
the contract. If the contract is in excess of $100,000 Contractor shall provide both Payment and
Performance Bonds for the full amount of the contract. When the Guaranteed Maximum Prices (GMPs)
for Phases I and II are agreed upon, the successful Offeror entering into a contract for the work will be
required to give the City surety in a sum equal to the amount of the contract attributable to each phase.
The form of the bond shall be as herein provided and the surety shall be acceptable to the City. All bonds
furnished hereunder shall meet the requirements of Texas Government Code Section 2253,as amended.
Contractor shall apply for all City of Fort Worth Permits and for any other permits required by this project.
,. City of Fort Worth Permit fees are waived. Separate permits will be required for each facility.
If the Contractor should fail to complete the work as set forth in the Plans and Specifications and Contract
Documents within the time so stipulated, plus any additional time allowed as provided in the General
Conditions, there shall be deducted from any monies due or which may thereafter become due him, the
liquidated damages outlined in the General Conditions, not as a penalty but as liquidated damages, the
Contractor and his Surety shall be liable to the Owner for such deficiency.
IMMIGRATION NATIONALITY ACT:
IIMI City actively supports the Immigration & Nationality Act (INA) which includes provisions addressing
employment eligibility, employment verification, and nondiscrimination. Vendor shall verify the identity and
employment eligibility of all employees who perform work under this Agreement. Vendor shall complete
the Employment Eligibility Verification Form (1-9), maintain photocopies of all supporting employment
" eligibility and identity documentation for all employees, and upon request, provide City with copies of all 1-9
forms and supporting eligibility documentation for each employee who performs work under this
Agreement. Vendor shall establish appropriate procedures and controls so that no services will be
performed by any employee who is not legally eligible to perform such services. Vendor shall provide City
with a certification letter that it has complied with the verification requirements required by this Agreement.
Vendor shall indemnify City from any penalties or liabilities due to violations of this provision. City shall
have the right to immediately terminate this Agreement for violations of this provision by Vendor.
HOUSE BILL 89:
Contractor acknowledges that in accordance with Chapter 2270 of the Texas Government Code, the City
is prohibited from entering into a contract with a company for goods or services unless the contract
contains a written verification from the company that it: (1)does not boycott Israel;and (2)will not boycott
Israel during the term of the contract. The terms"boycott Israel"and "company" shall have the meanings
ascribed to those terms in Section 808.001 of the Texas Government Code. By signing this contract,
Contractor certifies that Contractor's signature provides written verification to the City that Contractor: (1)
does not boycott Israel;and(2)will not boycott Israel during the term of the contract.
Cattle Barn 1 and the Poultry Bam Renovations Page 25 of 58
CMAR,Pm-Construction Services July 2017
so
ow IN WITNESS WHEREOF, the City of Fort Worth has caused this instrument to be signed in four
counterparts in its name and on its behalf by the City Manager and attested by its Secretary, with the
corporate seal of the City of Fort Worth attached. The Contractor has executed this instrument through its
MR duly authorized officers in four counterparts with its corporate seal attached.
Done in Fort Worth,Texas,this the � day o i-;20�/
CONTRACTOf APPROVED:
I c CITY FORT WORTHr
By: '""
2w
Russ Garrison Jesus J. Chapa
President/CEO Assistant City Manager
APP E OMMEND RECO
.. By: � By:
�. Steve Cooke, PE Mary J. Ka s �{
... Director. Property Management Dept. City Secretary .1��'" TG lo
U: :O
* :2
APPROVED AS TO FO AND LEGALITY: Alua3 a '
CantractAutinintion
! �
By. ,
J n B. Strong
Assistant City Attorney 1295: .�-= �3
Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and
administration of this contract, including ensuring all performance and reporting requirements.
By: lk•
Brian R.Glass,AIA
Architectural Services Manager OFFICIAL.RECORD
CITY SECRETARY
FT.WORTH,TX
Cattle Bam 1 and the Poultry Ram Renovations Page 26 of 58
CMAR,Pre-Construction Services July 2017
Bond#30009838
PERFORMANCE BOND
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
That we, SEDALCO.Inc. known as"Principal"herein
and Continental Casualty Company_ ,a corporate
surety(sureties, if more than one)duly authorized to do business in the State of Texas,known as
"Surety"herein(whether one or more),are held and firmly bound unto the City of Fort Worth,a
municipal corporation created pursuant to the laws of Texas,known as"City"herein,in the penal sum of,
Fourteen Million Two Hundred Forty Eight Thousand Four Hundred Eighty Six Dollars and no
Cents(514.248.486.00), lawful money of the United States,to be paid in Fort Worth,Tarrant County,
.• Texas for the payment of which sum well and truly to be made,we bind ourselves,our heirs,executors,
administrators,successors and assigns,jointly and severally,firmly by these presents.
WHEREAS,the Principal has entered into a certain written contract with the City awarded the
5t day of!DQZG, 20 11, which Contract is hereby referred to and made a part hereof for all purposes as
if fully set forth herein,to furnish all materials, equipment labor and other accessories defined by law, in
the prosecution of the Work, including any Change Orders, as provided for in said Contract designated as
i
CMAR for Cattle Barn 1 and the Poultry Barn Renovations located at 3401 Lancaster Ave in Fort
Worth.Texas (Project PMD2017-091.
r.r
NOW,THEREFORE,the condition of this obligation is such that if the said Principal shall
faithfully perform it obligations under the Contract and shall in all respects duly and faithfully perform
the Work, including Change Orders,under the Contract, according to the plans,specifications,and
contract documents therein referred to,and as well during any period of extension of the Contract that
may be granted on the part of the City,then this obligation shall be and become null and void,otherwise
to remain in full force and effect.
PROVIDED FURTHER,that if any legal action be filed on this Bond,venue shall lie in Tarrant
+�•M County,Texas or the United States District Court for the Northern District of Texas,Fort Worth
Division.
This bond is made and executed in compliance with the provisions of Chapter 2253 of the Texas
Government Code,as amended, and all liabilities on this bond shall be determined in accordance with the
provisions of said statue.
wer
IN WITNESS WHEREOF,the Principal and the Sure1have SIGNED and SEALED this
instrument by duly authorized agents and officers on this the 1 day of �AA, 20_.��
PRINCIPAL:
SEDALCO, 1 e.
BY:
Signature
�r TT
*� (Pri cipal)Secr C> Name and Title
Address: 4100 Fossil Creek Blvd.
Fort Worth,TX 76137
Witness as to Principal
SURETY:
Continental Casualty Comp
w .
BY:
Signature W
� .
Amber Jones,Attorney-in-Fact
Name and Title
Address: 333 S. Wabash Avenue
Chicago,IL 60604
Witness as to Surety Telephone Number: (312)822-5000
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract from the by-laws
showing that this person has authority to sign such obligation. If Surety's physical address is different from its
mailing address,both must be provided.The date of the bond shall not be prior to the date the Contract is awarded.
no
Bond#30009838
PAYMENT BOND
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
That we, SEDALCO.Inc. known as "Principal" herein, and
Continental Casually Company a corporate
surety(sureties), duly authorized to do business in the State of Texas, known as"Surety"herein(whether
one or more), are held and firmly bound unto the City of Fort Worth, a municipal corporation created
pursuant to the laws of the State of Texas, known as "City" herein, in the penal sum of,
Fourteen Million Two Hundred Forty Eight Thousand Four Hundred Eighty Six Dollars and no
Cents 014.248.486.001, lawful money of the United States, to be paid in Fort Worth, Tarrant County,
"^ Texas, for the payment of which sum well and truly be made, we bind ourselves, our heirs, executors,
administrators, successors and assigns,jointly and severally,firmly by these presents:
WHEREAS, Principal has entered into a certain written Contract with City, awarded the 5 day
ofDt, 20which Contract is hereby referred to and made a part hereof for all purposes as if fully
set forth herein, to furnish all materials, equipment, labor and other accessories as defined by law, in the
prosecution of the Work as provided for in said Contract and designated as CMAR for Cattle Barn 1
and the Poultry Barn Renovations located at 3401 Lancaster Ave in Fort Worth. Texas (Project
PMD2017-09).
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if Principal
., shall pay all monies owing to any(and all)payment bond beneficiary (as defined in Chapter 2253 of the
Texas Government Code, as amended) in the prosecution of the Work under the Contract, then this
obligation shall be and become null and void; otherwise to remain in full force and effect.
This bond is made and executed in compliance with the provisions of Chapter 2253 of the Texas
Government Code, as amended, and all liabilities on this bond shall be determined in accordance with the
provisions of said statute.
.r
■w.
IN WITNESS WHEREOF,the Principal and Surety have each SIGNED and SEALED this
.. instrument by duly authorized agents and officers on this the=Aday of VQ 0,20A
PRINCIPAL:
SEDALC , Wc.
7 T \;
ATTEST: BY:
7 Signature
(Princ' a Se etary Name and Title
Address: 4100 Fossil Creek Blvd.
7 Fort Worth,TX 76137
7 Witness as to Principal
SURETY:
' 1
Continental Casualty Company
ATTEST: BY:
'" Signature
Amber Jones,Attorney-in-Fact
(Surety)Secretary Name and Title
Address: 333 S.Wabash Avenue
Chicago,IL 60604
j
Witness as to Surety
Telephone Number: (312)822-5000
*Note: If signed by an officer of the Surety, there must be on file a certified extract from the bylaws showing that
7 this person has authority to sign such obligation. If Surety's physical address is different from its mailing address,
both must be provided.The date of the bond shall not be prior to the date the Contract is awarded.
w
1 �
i
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY-IN-FACT
Know All Men By These Presents,That Continental Casualty Company,an Illinois insurance company,National Fire Insurance Company of
.. Hartford,an Illinois insurance company,and American Casualty Company of Reading,Pennsylvania,a Pennsylvania insurance company(herein called
"the CNA Companies"),are duly organized and existing insurance companies having their principal offices in the City of Chicago,and State of Illinois,
and that they do by virtue of the signatures and seals herein affixed hereby make,constitute and appoint
Darrin Weber,Amber Jones,Chris Polk,April Penny,Julie Baumberger,Individually
of Dallas,TX,their true and lawful Attomey(s)-in-Fact with full power and authority hereby conferred to sign,seal and execute for and on their behalf
bonds,undertakings and other obligatory instruments of similar nature
-In Unlimited Amounts-
rre
and to bind them thereby as fully and to the same extent as if such instruments were signed by a duly authorized officer of their insurance companies and
all the acts of said Attorney,pursuant to the authority hereby given is hereby ratified and confirmed.
�* This Power of Attorney is made and executed pursuant to and by authority of the By-Law and Resolutions,printed on the reverse hereof,duly
adopted,as indicated,by the Boards of Directors of the insurance companies.
In Witness Whereof,the CNA Companies have caused these presents to be signed by their Vice President and their corporate seals to be hereto
affixed on this 23rd day of July,2015.
,µGASU14 04SUR4 o AHr of Continental Casualty Company
A, National Fire Insurance Company of Hartford
American Cas lty Company of Reading,Pennsylvania
2 JULY 71,
L) SEAL Y i 4k 19a
a
1897 HAN!FaP� J dfi'
Paul T.Bruflat Vice President
State of South Dakota,County of Minnehaha,ss:
On this 23rd day of July,2015,before me personally came Paul T.Bruflat to me known,who,being by me duly sworn,did depose and say: that he
resides in the City of Sioux Falls,State of South Dakota;that he is a Vice President of Continental Casualty Company,an Illinois insurance company,
National Fire Insurance Company of Hartford,an Illinois insurance company,and American Casualty Company of Reading,Pennsylvania,a
Pennsylvania insurance company described in and which executed the above instrument;that he knows the seals of said insurance companies;that the
seals affixed to the said instrument are such corporate seals;that they were so affixed pursuant to authority given by the Boards of Directors of said
insurance companies and that he signed his name thereto pursuant to like authority,and acknowledges same to be the act and deed of said insurance
companies.
4awwwawwaaaaaa.waaaa4aaaw
S.ETCH r
ROTARY PURUC
SOUTH AAwwR"
�'wwa.h.a+.,+,##.4b-e41iS114Swa
My Commission Expires February 12,2021 S.Eich Notary Public
CERTIFICATE
I,D.Bult,Assistant Secretary of Continental Casualty Company,an Illinois insurance company,National Fire Insurance Company of Hartford,an
Illinois insurance company,and American Casualty Company of Reading,Pennsylvania,a Pennsylvania insurance company do hereby certify that the
Power of Attorney herein above set forth is still in force,and further certify that the By-Law and Resolution of the Board of Directors of the insurance
.� companies printed on the reverse h eof is still in forc . In testimony whereof I have hereunto subscribed my name and affixed the seal of the said
insurance companies this 3r� day of s,
�GAS t1q�T �NSURgA Q�noAr+►oo Continental Casualty Company
A-%; National Fire Insurance Company of I a order
c 1PO"°* ` ; � �w�a"�aarFc American Casualty Company of Read tib„P a
4 n JULY 71. y
SEAL t s 1902
a <
1897 � MARIF�� _�____�
D.Bult Assistant Se:_ems v
,,,,, Form F6853-4/2012
Authorizing By-Laws and Resolutions
ADOPTED BY THE BOARD OF DIRECTORS OF CONTINENTAL CASUALTY COMPANY:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the
Company at a meeting held on May 12,1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents,agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents,agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of Continental Casualty Company.
rr
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April,2012:
"Whereas,the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers(the"Authorized Officers")to ■..
execute various policies,bonds,undertakings and other obligatory instruments of like nature;and
Whereas,from time to time,the signature of the Authorized Officers,in addition to being provided in original,hard copy format,may be provided via
facsimile or otherwise in an electronic format(collectively,"Electronic Signatures");Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF NATIONAL FIRE INSURANCE COMPANY OF HARTFORD:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the on
Company by unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents,agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents,agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of National fire Insurance Company of Hartford. w
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25d day of April,2012:
.r
"Whereas,the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers(the"Authorized Officers") to
execute various policies,bonds,undertakings and other obligatory instruments of like nature;and
Whereas,from time to time,the signature of the Authorized Officers,in addition to being provided in original,hard copy format,may be provided via
facsimile or otherwise in an electronic format(collectively,"Electronic Signatures");Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING,PENNSYLVANIA: nr
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the
Company by unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents,agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents,agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of American Casualty Company of Reading,Pennsylvania.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25's day of April,2012:
"Whtreas,the�Dy4ws of the Company or specific resolution of the Board of Directors has authorized various officers(the"Authorized Officers") to
execote various 1�gl`r¢jes,bonds,undertakings and other obligatory instruments of like nature;and
Wherea-,from thne,to time,the signature of the Authorized Officers,in addition to being provided in original,hard copy format,may be provided via
-fa.:T:mile in utherwise in an electronic format(collectively,"Electronic Signatures");Now therefore be it resolved: that the Electronic Signature of any
.wilt rize�-Officer shall be valid and binding on the Company."
Figure: 28 TAC§1.601(a)(3)
1 IMPORTANT NOTICE AVISO IMPORTANTE
To obtain information or make a complaint: Para obtener informacion o para someter una queja:
*- 2 You may contact Continental Casualty Company, Puede comunicarse con Continental Casualty
National Fire Insurance Company of Hartford, Company, National Fire Insurance Company de
American Casualty Company of Reading, PA and Hartford, American Casualty Company de Reading, PA
Continental Insurance Company at 312-822-5000. y Continental Insurance Company al 312-822-5000.
3 You may call Continental Casualty Company, Usted puede Ilamar al numero de telefono gratis de
National Fire Insurance Company of Hartford, Continental Casualty Company, National Fire
American Casualty Company of Reading, PA and Insurance Company de Hartford, American Casualty
Continental Insurance Company's toll-free telephone Company de Reading, PA y Continental Insurance
number for information or to make a complaint at: Company's para informacion o para someter una
.� queja al:
1-877-672-6115 1-877-672-6115
4 You may also write to Continental Casualty Usted tambien puede escribir a Continental Casualty
Company, National Fire Insurance Company of Company, National Fire Insurance Company de
Hartford, American Casualty Company of Reading, Hartford,American Casualty Company de Reading,
PA and Continental Insurance Company at: PA y Continental Insurance Company:
CNA Surety CNA Surety
333 South Wabash 333 South Wabash
Chicago, IL 60604 Chicago, IL 60604
5 You may contact the Texas Department of Puede comunicarse con el Departamento de Seguros
Insurance to obtain information on companies, de Texas para obtener informacion acerca de
coverages, rights or complaints at: companias, coberturas, derechos o quejas al:
1-800-252-3439 1-800-252-3439
.■ 6 You may write the Texas Department of Puede escribir al Departamento de Seguros de
Insurance: Texas:
P.O. Box 149104 P.O. Box 149104
Austin, TX 78714-9104 Austin, TX 78714-9104
Fax: (512)490-1007 Fax: (512)490-1007
Web: www.tdi.texas.gov Web: www.tdi.texas.gov
E-Mail: ConsumerProtection@tdi.texas.gov E-Mail: ConsumerProtection@tdi.texas.gov
7 PREMIUM OR CLAIM DISPUTES: DISPUTAS SOBRE PRIMAS O RECLAMOS:
Should you have a dispute concerning your Si tiene una disputa concerniente a su prima o a
premium or about a claim you should contact un reclamo, debe comunicarse con el Continental
Continental Casualty Company, National Fire Casualty Company, National Fire Insurance
Insurance Company of Hartford, American Casualty Company de Hartford,American Casualty Company
Company of Reading, PA and Continental Insurance de Reading, PA y Continental Insurance Company
Company first. If the dispute is not resolved, you primero. Si no se resuelve la disputa, puede
may contact the Texas Department of Insurance. entonces comunicarse con el departamento (TDI).
8 ATTACH THIS NOTICE TO YOUR POLICY: UNA ESTE AVISO A SU POLIZA: Este aviso es
This notice is for information only and does not solo para proposito de informacion y no se
become a part or condition of the attached convierte en parte o condicion del documento
document. adjunto.
Form F8277-6-2015
wM
State of Texas
Claim Notice Endorsement
To be attached to and form a part of Bond No. 30009838
In accordance with Section 2253.021(f) of the Texas Government Code and Section
53.200(6) of the Texas Property Code any notice of claim to the named surety under
this bond(s) should be sent to:
CNA Surety
333 South Wabash
Chicago, IL 60604
Telephone: (312) 822-5000
*�+ Form F6944
�.
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
WPursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it provides
worker's compensation insurance coverage for all of its employees employed on City Project. CMAR
for Cattle Barn 1 and the Poultry Barn Renovations located at 3401 Lancaster Ave in Fort Worth
1 Texas (Proiect PiNID2017-09). Contractor further certifies that, pursuant to Texas Labor Code, Section
J 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with
worker's compensation coverage.
CONTRACTOR:
SEDALCO, INC. By: Russ Garrison, President/CEO
Company ase P • t)
4100 Fossil Creek Blvd. Signature:
Address
■� Fort Worth,Texas 76137-2723 Title:
City/State/Zip (Please Print)
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
ff COUNTY OF TARRANT §
.�i
I BEFORE ME,the undersigned authority,on this day personally appeared
0 Russ Garrison, President/CEO , known to me
A to be the person whose name is subscribed to the foregoing instrument, and acknowledged to me that
he/she executed the same as the act and deed of SEDALCO. INC.
for the purposes and consideration therein expressed and in the capacity therein stated.
GIVEN UNDER MY HAND AND SEAL OF OFFICE this f Au us#2017.
```````````�a►anWd
na,
a �G�..... Notary u is i and for the State of Texas
JA,A,
' f OF
4._O"
2'-0" 2'-0" 7 01
CENTERLINE OF
SIGN, LOGO &
TEXT INFORMATION
ORT WORTH.,
Project Title
Architect:
Architect's Name
Contractor:
Contractor's Name
FUNDED BY
(Ust Bond Fund,etc.)
SCHEDULED COMPLETION DATE
YEAR
s
�;14
r r
SIGN COLOR & FONT:
BACKGROUND - WHITE
BORDER - 5/16-WIDE, 3"RADIUS CORNERS, PMS 288 (BLUE)
TEXT - HELVETICA or ARIAL, PMS 288 (BLUE)
FORT WORTH LOGO COLORS & FONT:
FORT WORTH - PMS 288 (BLUE), CHELTENHAM BOLD
LONGHORN LOGO - PMS 725 (BROWN)
PROJECT DESIGNATION SIGN