HomeMy WebLinkAboutOrdinance 23089-01-2018 Ordinance No. 23089-01-2018
AN ORDINANCE REDUCING UNALLOCATED RECEIPTS AND APPROPRIATIONS IN
THE AMOUNT OF $3,591,570.00 IN THE WATER AND SEWER COMMERCIAL PAPER
FUND FOR THE CLEAR FORK LIFT STATION AND FORCE MAIN PROJECT;
PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE
OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2017-2018 in the
Budget of the City Manager, there shall also be reduced unallocated receipts and appropriations in the amount
of$3,591,570.00 in the Water and Sewer Commercial Paper Fund for the Clear Fork Lift Station and Force
Main project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 22928-09-2017 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY LAI
Quop—> /X 45141�� )
Douglas W Black Mary J. Kay e
Sr. Assistant City Attorney
ADOPTED AND EFFECTIVE: January 23, 2018
MAYOR AND COUNCIL COMMUNICATION MAP
60CFLSFM-KHA
N tri +� �#' •- y� •�+� 1ul
FINISH
` LW
`.. X -�
' �AI�I�AST�R,A
4{�—al�
*,�--:. ` .r _ X11 � +I�i,�•„y 'M i ti, .ry, d X' , i
uj
�"����,��,,; �+ `� � FORE .. �•
r � �o� �`� � ��• MAIN � .�
°
-
H - 300 WEST.FREEWAY, � ol
W 0 da
LIFT
•��y�}�+�-. �'. � ��' r fti ' �115 �r� �:,�,.� _.
TATIONp,
STAR r �" ` ,v � � e
FORT WORTH . .
r ,e S
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 1/23/2018 - Ordinance No. 23089-01-2018 & Resolution
No. 4898-01-2018
DATE: Tuesday, January 23, 2018 REFERENCE NO.: C-28545
LOG NAME: 60CFLSFM-KHA
SUBJECT:
Authorize Execution of Engineering Agreement with Kimley-Horn and Associates, in the Amount of
$1,795,070.00 for Clear Fork Lift Station and Force Main, Provide for Staff Costs, Property Acquisition and
Utility Coordination for a Total Project Amount of$3,591,570.00, Adopt Resolution Expressing Official
Intent to Reimburse Expenditures and Proceeds of Future Debt and Adopt Appropriation Ordinance
(COUNCIL DISTRICT 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached resolution expressing Official Intent to Reimburse expenditures with proceeds of
future enterprise fund debt for the Clear Fork Lift Station and Force Main Project;
2. Adopt the attached appropriation ordinance reducing unallocated appropriations and increasing
appropriations for the Clear Fork Lift Station and Force Main Project in the Water and Sewer Commercial
Paper Fund in the amount of$3,591,570.00; and
3. Authorize execution of an Engineering Agreement with Kimley-Horn and Associates, in the amount of
$1,795,070.00 for the Clear Fork Lift Station and Force Main Project (City Project No. 100996).
DISCUSSION:
This Mayor and Council Communication (M&C) is to authorize the preparation of plans and specifications
for the Clear Fork Lift Station and Force Main Project. Additional wastewater conveyance is needed in
order to eliminate repeated sanitary sewer overflows over the years near the intersection of University
Drive and Rosedale Street. Flow projections indicate that the existing collection system is undersized in
the Clear Fork corridor from the University Drive/I.H. 30 intersection to 7th Street. There are two existing
collector mains (M-272 and M-439) conveying sewage flows, that parallel the Clear Fork of the Trinity
River from University Drive, downstream through Trinity Park, and ultimately connecting to the downtown
deep tunnel sewers. These two collector mains vary in size from 48-inch to 54-inch in diameter. The Fort
Worth Wastewater Master Plan recommends two projects (Nos. 6 and 8) to increase the capacity of the
Clear Fork collector sanitary sewer system by replacing M-272 with a gravity sewer main that is 66-inch to
84-inch in diameter.
Due to the cost involved with installing a deep tunnel large diameter gravity main in this congested corridor
which includes Trinity Park, staff is recommending the installation of a 10 —20 million gallon per day lift
station and a 14,000 linear feet, 30-inch diameter, sanitary sewer force main (in lieu of a gravity main) that
would operate under both normal and peak flow conditions. The proposed lift station and force main could
also be utilized to perform bypass pumping operations during rehabilitation work on the existing two sewer
trunk mains, which would save significant rehabilitation costs in the future.
Logname: 60CFLSFM-KHA Page 1 of 3
Kimley-Horn and Associates proposes to provide all the necessary design services for the Lift Station and
Force Main for a fee of$1,795,070.00. Staff considers the proposed fee to be fair and reasonable for the
scope of services proposed.
In addition to the contract amount, $1,796,500.00 is required for project management, utility coordination
and real property acquisition.
Engineering for the Clear Fork Lift Station and Force Main project is one component of the overall project
that includes project management, real property/easement acquisition, utility coordination, material testing,
inspection, construction and contingencies. The overall project budget is $22,591,570.00. Design is
expected to start in February 2018 and be completed by April 2019. Construction is anticipated to
commence in August 2019 and be completed by December 2021. This project is part of the Water
Department's Sanitary Sewer Overflow Initiative Program.
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer Fund.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation
authority authorized under the Callable Commercial Paper Program (CP) will be used to provide interim
financing for this project until debt is issued. To the extent resources other than the Water and Sewer
portfolio are used to provide interim financing, the Water and Sewer Fund will be charged interest that is
equivalent to the overall rate of return being earned by the City portfolio (currently approximately one-
percent annually). Should the City's portfolio not support the liquidity needed to provide an interim short-
term financing source, another funding source will be required, which could mean issuance of securities
under the CP Program or earlier issuance of Water and Sewer revenue bonds than is currently planned.
Once debt associated with this project is sold, bond proceeds will be used to reimburse the Water and
Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2018-2022 Five Year Capital Improvement
Plan on December 12, 2017, Mayor and Council Communication (M&C G-19187). This City Council
adopted plan includes this specific project, with funding identified through the CP program to be
reimbursed with future revenue bonds. In accordance with the provisions of the Financial Management
Policy Statement, Staff anticipates presenting revenue-supported debt issuances to the City Council for
consideration within the next three years. This debt must be issued within approximately three years to
provide reimbursement for these expenses. If that does not occur, the costs will no longer be reimbursable
by issuing tax-exempt debt and the funding source will have to be made whole through budgetary
methods. Adoption of this resolution does not obligate the City to sell bonds, but preserves the ability to
reimburse the City from tax-exempt bond proceeds.
This project will have no impact on the Water Department operating budget.
M/WBE OFFICE: Kimley-Horn and Associates, is in compliance with City's BDE Ordinance by committing
to 24 percent SBE participation. The City's SBE goal on this project is 13 percent.
The project is located in COUNCIL DISTRICT 9.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in the Water and Sewer Commercial Paper Fund
for the Clear Fork Lift Station and Force Main Project. The Water and Sewer Commercial Paper Fund
includes authority of$150,000,000.00 for the purpose of providing interim funding for Water and Sewer
Capital Projects. After this transfer, the balance will be $111,233,959.00. Funding for this project is
depicted in the table below.
Logname: 60CFLSFM-KHA Page 2 of 3
'FUND Existing Additional Project
Appropriations Appropriations Total*
Water and Sewer
Commercial Paper $0.00 $3,951,570.00 $3,951,570.00
56014
Project Total [$0.00 1$3,951,570'.00 $3,951,570.00
*Numbers rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID Year ChartField 2
FROM
Fund Department ccounJ Project Program ctivity Budget Reference # moun
ID ID Year Chartfield 2
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Kenneth Morgan (8246)
Additional Information Contact: John Kasavich (8480)
Logname: 60CFLSFM-KHA Page 3 of 3