HomeMy WebLinkAboutOrdinance 23106-02-2018 Ordinance No. 23106-02-2018
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
DEVELOPER CONTRIBUTION FUND IN THE AMOUNT OF $334,863.00, FROM
AVAILABLE FUNDS, FOR THE MARINE CREEK PARKWAY AND OLD DECATUR ROAD
PROJECT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE
CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2017-2018 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the
Developer Contribution Fund in the amount of $334,863.00, from available funds, for the Marine Creek
Parkway and Old Decatur road project.
Department Project Amount
CO2506 — Marine Creek Parkway/Old Decatur $334,862.61
Transportation/Public Works Road Project
Total $334,862.61
$334,862.61
Funding Source Developer Contribution Fund
Total $334,862.61
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 22928-09-2017 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
R V AS TO FORM AND LEGALITY: CITY ECR A
Douglas r BIac-k Mafry J. e
Sr. Assistant City Attorney
ADOPTED AND EFFECTIVE: February 6. 2018
EMS ISD Middle School No. 6 Location
Council District 2
Lake
reek U�k e
C* 1_T_
107
White yak
PALUXY
.k
l•
.y
�5
t4
SANDS
C(?"ANCHE PEAK
GRAYSON RIDGE
8
Map References
Legend Hepato 47F
-Location Area
Fort Worth City Limit
Fort Worth ETJ
a
Adjacent Cities 1:10,000
MAYOR AND COUNCIL COMMUNICATION MAP
Old Decatur Road and Marine Creek Parkway
Project Management and Construction Phase Services
guy 411,
0 300 600 900
Feet
N
4.Lf •N
�1 rn
199
W
IV
0 500 1,000 1,500
Feet
Copyright 2016 City of Fort Worth.Unauthorized reproduction is a violation of applicable laws.
This product is for information purposes and may not have been prepared for or be suitable for legal,engineering,or surverying
purposes.It does not represent an on-the-ground survey and represents only the approximate relative location of property boundaries_ CITY PROJECT# 02506
The City of Fort Worth assumes no responsibility for the accuracy of said data.
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 2/6/201$ Ordinance No. 23706-02-2(118
DATE: Tuesday, February 6, 2018 REFERENCE NO.: **C-28572
LOG NAME: 20MARINE CREEK PARKWAY EMS ISD SCHOOL FIA
SUBJECT:
Authorize Execution of Change Order No. 1 to City Secretary Contract No. 48125 with Jackson
Construction Ltd. in the Amount of$321,470.42 for the Marine Creek Parkway and Old Decatur Road
Project and Adopt Appropriation Ordinance (COUNCIL DISTRICT 2)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached appropriation ordinance increasing the estimated receipts and appropriations in the
Developer Contribution Fund in the amount of$334,863.00 for payment from Eagle Mountain-Saginaw
Independent School District; and
2. Authorize execution of Change Order No. 1 to City Secretary Contract No. 48125 with Jackson
Construction, Ltd. in the amount of$321,470.42 for the Marine Creek Parkway and Old Decatur Road
Project, thereby increasing the contract to an amount up to $11,747,769.42 (CO2506).
DISCUSSION:
Eagle Mountain-Saginaw Independent School District is developing and constructing Middle School No. 6
North of Grayson Ridge Drive and South of Longhorn Road which is within the Marine Creek project limits.
To accommodate the new school development the City's contractor, Jackson Construction, Ltd, will
construct water connections and sanitary sewer to serve the new middle school as Change Order No. 2.
By including this additional work with the Marine Creek construction project, additional or future
construction needs are significantly minimized along or within the roadway.
The funds for Change Order No. 1 were collected from Eagle Mountain-Saginaw Independent School
District in the amount of$334,862.61. The funding was collected with the execution of the Future
Improvements Agreement in October, 2017. The amount includes materials testing and inspection fees in
addition to the change order work by the Contractor.
On June 28, 2016, (M&C C-27816) the City Council authorized award of a construction contract with
Jackson Construction, Ltd., in the amount up to $11,531,299.00, inclusive of$105,000.00 in potential
incentives, for the construction of improvements to Marine Creek Parkway/Old Decatur Road from South
of McLeroy Boulevard to North of Grayson Ridge Drive.
M/WBE OFFICE: No MBE goal was applied to this Change Order No. 1, effectively waiving a goal. The
prime contractor's self-performance and non-MBE subcontractors account for the significant portion of this
additional work.
The project is located in COUNCIL DISTRICT 2.
Logname: 20MARINE CREEK PARKWAY EMS ISD SCHOOL FIA Page 1 of 2
FISCAL INFORMATION /CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendation and adoption of the
attached appropriation ordinance funds will be available in the current capital budget as appropriated.
FUND IDENTIFIERS (FIDs):
TO
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID Year Chartfield 2
FROM
Fund Department ccoun Project JProgram ctivity Budget Reference # moun
ID ID Year Chartfield 2
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Douglas Wiersig (7801)
Additional Information Contact: Lissette Acevedo (2722)
Logname: 20MARINE CREEK PARKWAY EMS ISD SCHOOL FIA Page 2 of 2