HomeMy WebLinkAboutContract 46585-CO1 CITY SECRETARY .� FORT WORTH® City of Fort Worth CONTRACT NO.. Change Order Request Breakdown Project Namel HMAC STREET REHAB(2015-1) City Sec# 1 46585 Client Project#(s)i CPN 02423;DOE 7384 Contractorl JLB Contracting PM K.Sughm Inspector G.Deyon Change Order Submittal# 0 Date 1/23/2018 Dept. T/PW Water Sewer Contract Time Totals CD Original Contract Amount $833,545.84 $416,772.92 $416,772.92 $1,667,091.68 210 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $833,545.84 $416,772.92 $416,772.92 $1,667,091.68 210 Go to ADD&DEL Tabs to Enter CO Backup $0.00 $0.00 $0.00 271 Revised Contract Amount $833,545.84 $416,772.92 $416,772.92 $1,667,091,68 481 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 $0.00 $0.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,083,864.60 Additional time is required for the rehabilitation of Meadowbrook Dr.(Beach St.-Haynes Ave.)which was delayed from water and gas conflicts and compounded by a procedural change for Fire Station 14. 0�61 8 9 10 N � a FF9 I VF0 M ciryor 2418 OFFICIAL RECORD moo, Cis cq��A°Rry ti CITY SECRETARY C>'aw FT.WORTH,TX 6 F<�_ H City of Fort worth Change Order Additions Project Name HMAC STREET REHAB(2015-1) CitySec# 46585 Client Project# CPN 02423;DOE 7384 Contractor JLB Contracting PM K.Sugrim Inspector G.Deyon Change Order Submittal# 0 Date 1/23/2018 ADDITIONS -ITEM DESCRIPTION DEPT Qty Unit U I Cost Total T/PW $0.00 Water $0.00 Sewer $0.00 Sub Total Additions Change Order Additions Page 1 of 1 FORTT WWORTH City of Fort worth Change Order Deletions Project Name HMAC STREET REHAB 2015-1) CitySec# 46585 Client Project# CPN 02423;DOE 7384 Contractor JLB Contracting PM K.Sugrim Inspector G Deyon Change Order Submittal# 0 Date 1/2312018 DELETIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total T/PW $0.00 Water $0.00 Sewer $0.00 Sub Total Deletions Change Order Deletions Page 1 of 1 MISBE Breakdown for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 CFW Change Order Approval St-COApp02 Page 1 of 3 Routing Assigned To: Due Date: Assigned By: Due Time: Links 1 fortworthaov/Infrastructure Proiects/02423 - HMAC Street Rehabilitation 2015-1/Contractor/Change Orders/H2O15-1 Change Order Breakdown DOE 7384- additional time.xls Attachments(91 —� No Attachments have been added to this form. https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?Siteld=51500&ProcessI... 2/13/2018 CFW Change Order Approval St-COApp02 Page 2 of 3 FORT WORTS, City of Fort Worth Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.. :.................................................... Change Order No.: St-COApp02 Date Started: 12018-01-31 City Sec. No.: Date Due: ,2018-03-22 Project Name: 102423 - HMAC 2015-1 Street Rehabilitation Project Numbers: 02423 DOE Numbers: -_-- DOE No. ProjectiRemoval and replacement on nonfunctional driveway, curb&gutter Description: land sidewalks; followed by the pulverization and stabilization of the existing pavement and a 2"HMAC overlay. Project Manager: Kristian Sugrim _ � City Inspector: Gary Deyon Contractor: 'JLB Contracting, LLC. COUNCIL ACTION (If Required): M&C Log Name: M&C Number: M&C Date: _ COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: TPw _ $ 0.00 i 271 r F F Total Cost: $ 0.00 Total Requested Days: 271 Approval Status: https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessI... 2/13/2018 CFW Change Order Approval St-C0App02 Page 3 of 3 Approved: Yes Comments: User: Sam Davis Date: 2018-01-31 12:08 PM Approved: Yes Comments: User: Kristian Sugrim Date: 2018-01-31 1:02 PM Approved: Yes Comments: User: Lane Zarate Date: 2018-01-31 9:20 PM Approved: Yes Comments: User: Kim Arnold Date: 2018-02-13 10:05 AM Approved: Yes Comments: User: Doug Wiersig Date: 2018-02-13 4:11 PM Approved: Yes Comments: User: Jay Chapa Date: 2018-02-13 4:28 PM qa��7 Na OA k-C, k d Action Required: � FORT�O Aid t'Y J• see Ci Secre •�L'XAS OFFICIAL RECORD CITY SECRETARY FT.WORTH,TX https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?SiteId=51500&ProcessI... 2/13/2018 Contract Compliance Manager Re: Change Order No. 1 ($0.00) Contractor: JLB Contracting, LLC. Project Name: HMAC 2014-3 Surface Overlay City Secretary No.: 45640 Project No.: CO2258 By signing, I acknowledge that I am the person responsible for the monitoring and administration of this contract including ensuring all performance and reporting requirements. Name of Employee Project Manager Title 67 89r � O j Q Axe B�� c/�'sFc9��9�18 .eCU L99 ,9�