HomeMy WebLinkAboutContract 26988 CONI HACT No. 9 SJ
AMENDMENT NO. 2
STATE OF TEXAS § CITY SECRETARY CONTRACT
(No M&C Needed)
COUNTY OF TARRANT §
WHEREAS, the City of Fort Worth (City) and Baird, Hampton & Brown,
Inc . Consulting Engineers, Inc. (the "Engineer" ) made and entered into
City Secretary Contract No. 24247, (the Contract) which was authorized by
the City Council by M&C C-16961 on the 1't day of September, 1998 ; and
WHEREAS, the Contract involves engineering services for the
following project :
Water, Sewer, Paving & Drainage Improvements to E. Fogg Street (West of
Berke to Dead End) DOE 2198, Glen Garden Avenue (Old Mansfield to
Stephen Lee) DOE 2199, Kingsdale Drive (Rolling Hills to Ellis Ranch)
DOE 2200, Timberline Drive S. (S . Riverside to S. Dead End) DOE 2201
WHEREAS, it has became necessary to execute Amendment No. 2 to said
Contract to include an increased scope of work and revised maximum fee
to;
(1) modify the original plans to separate Fogg Street into a separate
stand-alone project, (2) add traffic control plans for each of the
streets, (3) modify the details and bid proposals to provide for an
alternate (concrete) pavement section, and (4) additional
printing/reproduction for advertising two separate projects.
NOW THEREFORE, City and Engineer, acting herein by and through their
duly authorized representatives, enter into the following agreement which
amends the Contract :
1.
Article I of the Contract is amended to include the additional
engineering services specified in a proposal letter dated July 31, 2001,
a copy of which is attached hereto and incorporated herein. The cost to
City for the additional services to be performed by Engineer total
$14, 597 . 00
� f����8 °�d G? �1�GP�',Do
IrI llr(4C� 6NI ,R
� �-li DHy M
2 .
Article II of the Contract is amended to provide for an increase in
the maximum fee to be paid to Engineer for all work and services
performed under the Contract, as amended, so that the total fee paid by
the City for all work and services shall not exceed the sum of
$178, 509. 00
3 .
All other provisions of the Contract which are not expressly amended
herein shall remain in full force1 and effect .
EXECUTED on this the f ! day of
2001, in Fort Worth, Tarrant County, Texas.,
APPROVAL RECOMMENDED: APPROVED:
A. Douglas Rademaker, P.E. Mike Groomer
Director, Department of Assistant City Manager
Engineering
ENGINEER: ATT ST:
Baird ampton Brown, Inc.
Konstantin Bakintas, PE Gloria Pearson, City Secretary
Vice President � I f
309 West 7th Street, Suite 500
Fort Worth, Tx. 76102
APPROVED AS TO FORM AND LEGALITY: Contract Aut orization
/ Date
Gary Steinberger
Assistant City Attorney
�u°:D
r"E::�MEly
� Q �
Baird, Hampton & Brown, Inc. c' D e Engineering & Surveying
July 31, 2001
Mr. Fred Ehia, PE, Project Manager
Department of Engineering
City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102
Tel(817)871-8424, Fax 871-7854
RE: REQUEST FOR CONTRACT MODIFICATION
1998 CAPITAL IMPROVEMENT PROGRAM PROJECTS; CONTRACT 25
RECONSTRUCTION WITH NEW ASPHALTIC PAVEMENT, BHB No 9847
E. Fogg Street (West of Berke to Dead End), DOE 2198
Glen Garden Avenue (Old Mansfield to Stephen Lee), DOE 2199
Kingsdale Drive (Rolling Hills to Ellis Ranch), DOE 2200
Timberline Drive S. (S. Riverside to S. Dead End), DOE 2201
Mr. Ehia:
We understand that obtaining the required right-of-way for the reconstruction of E. Fogg Street
has proven to be more'diffcult than originally anticipated. To allow for the reconstruction of the
remaining streets to proceed now, we have been requested to revise our final plans and.break
up the project into two separate sets of bid documents.
We are writing to, request a contract modification to provide additional compensation, for (1)
modifying the original plans to delete Fogg Street from the project, (2) adding traffic control
plans for each of the streets, (3) modifying the details and bid proposals to provide for an
alternate (concrete) pavement section, and (4)the additional printing/reproduction.
Tabulation of Additional Services and Fees by Consultant
BHB Engineering & Surveying $ 3,500 -modify plans & specs to delete Fogg Street
BHB Engineering & Surveying $ 4,800 -addition of traffic control plans
BHB Engineering & Surveying $ 2,000 -addition of alternate pavement option
Trevino &Associates $ 3,906 -total additional printing/reproduction
Consultants Admin. Cost 391 -contract allowance of 10% for admin. costs
Amendment No 2 Total = $14,597 - REQUESTING $14,597 TOTAL
CNN
309 W. 7th Street Suite 500 Fort Worth, Texas 76102 'Tel: 817-338-1277 Fax: 817-338-9245 E-Mail: mail@bhbinc.com
Mr. Fred Ehia, PE
REQUEST FOR CONTRACT MODIFICATION
1998 CAPITAL IMPROVEMENT PROGRAM PROJECTS; CONTRACT 25
July 31, 2001
Page 2
Summary of Overall Contract Fees &Amendments
Original Contract $152,505 Authorized 09/01/98, City Secretary No 24247
Amendment No 1 $ 11,407 Approved 02/16/99, City Secretary No 24656
Amendment No 2 14,597 Requested Herein
Revised Amount $178,509
Summary of M/WBE Participation
ANA Consultants 30,000 -original contract of$30,000 already paid
Jim's Reproduction 3,070 -original contract plus $570 already overspent
Trevino & Associates 3,906 -total additional printing/reproduction
M/WBE Subs Total 36,979 - m/wbe participation = 20.71% = 21% Goal
We appreciate the opportunity to submit this request for contract modification and look forward
to working with you on this project.
Sincerely,
BAIRD, HAMPTON & BROWN, tNC.
Konstantine Bakintas, PE
Vice President
Enclosure:
Printing/Reproduction Cost Estimate
G:\CIVIL\98471SCOPE\SCOPE MOD.DOC
CURCCIAL GECN`ML
U Uu ��IIj��8t19 �liWa
REQUEST FOR CONTRACT MODIFICATION
1998 CAPITAL IMPROVEMENT PROGRAM PROJECTS; CONTRACT 25
RECONSTRUCTION WITH NEW ASPHALTIC PAVEMENT, BHB No 9847
E. Fogg Street (West of Berke to Dead End), DOE 2198
Glen Garden Avenue (Old Mansfield to Stephen Lee), DOE 2199
Kingsdale Drive (Rolling Hills to Ellis Ranch), DOE 2200
Timberline Drive S. (S. Riverside to S. Dead End), DOE 2201
Summary of Additional Printing/Reproduction Costs
FOGG STREET
Final Plans
2 Sets of Constr. Plans $2.00/Sht X 6 Sht/Plan X 2 - $ 24
2 Sets of Specifications $0.20/Sht X 250 Pg/Spec X 2 = $ 100
Bid Documents
44 Sets of Constr. Plans $2.00/Sht X 6 Sht/Plan X 44 = $ 528
40 Sets of Specifications $0.20/ShtX 250Pg/Spec X 40 = $2,000
Mylars for Record Purposes $5.00/Sht X 6 Sht/Plan X 1 = 30
Subtotal for additional reproduction costs (by Trevino&Associates) =$2,682
98 C1P PROJECT
December 1998 Concept Submittal -In Original Scope of Work
June 1999 Preliminary Plans -In Original Scope of Work
September 1999 Utility Clearance - In Original Scope of Work
October 1999 Final Plans -In Original Scope of Work
January 2000 Corrected Final -Additional Printing
January 2000 For Real Properties -Additional Printing
Sept. 2000 Revised/Corrected Final -Additional Printing
Fall 2001 Bid Documents (Proof Set) -Additional Printing
Additional Printing
7 Sets of Constr. Plans $2.00/Sht X 66 Sht/Plan X 7 =$ 924
6 Sets of Specifications $0.20/Sht X 250 Pg/Spec X 6 = 300
Subtotal for additional reproduction costs (by Trevino &Associates) =$1,224
TOTAL FOR ADDITIONAL REPRODUCTION = $ 3,906