CONTRACT N0.�1�. L.
AMENDMENT No.1
N
MaR �
TO CITY SECRETARY CONTRACT No. 49506
WHEREAS, the City of Fort Worth (CITY) and Fort Worth South, Inc. ,
(a/k/a Near Southside, Inc. ) , ("COMMUNITY PARTNER") made and entered into
City Secretary Contract No. 49506, (the CONTRACT) which was
administratively authorized on the 17th day of August, 2017 in the amount
not to exceed $20, 500.00 plus expenses, up to a maximum of $23, 000.00
and
WHEREAS, the CONTRACT involves design services for the following
project:
Fire Station Park Master Plan; and
WHEREAS, it has become necessary to execute Amendment No. 1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and COMMUNITY PARTNER, acting herein by and
through their duly authorized representatives, enter into the following
agreement, which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional design
services specified in a proposal dated January 10, 2018, a copy of which
is attached hereto and incorporated herein. The cost to City for the
additional design services to be performed by COMMUNITY PARTNER totals
$10, 552.82. (See Attached Funding Breakdown Sheet, Page -4-)
2 .
Article I of the CONTRACT is amended to provide for an increase in
the fee to be paid to COMMUNITY PARTNER for all work and services performed
under the Contract, as amended, so that the total fee paid by the City for
all work and services shall be an amount of not to exceed $33,552.82 .
OFFICIAL RECORD
City of Fort Worth Cf SECRETARY
Services Agreement Amendment Template
CFW Official Release 9/19/2017 FT.WORTH
Page 1 of 4 PTX
3.
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED:
City of Fort Worth Community Partner
Fort Worth South, Inc.
Susan Alanis Paul F. Paine
Assistant City Manager President
DATE: 3 2011B DATE: zlz( to
APPROVAL REC ENDE
Ric rd Zavala
Director, Park & Recreation Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
(�U* VAtt��
Naoto Kumazawa
Landscape Architect
City of Fort Worth 0"10"RECORD
Professional Services Agreement Amendment Template �° • $EiP►R��
CFW Official Release 9/19/2017
Page 2 of 4 FT.WORTH9 TX
APPROVED AS TO FORM AND LEGALITY: M&C:
Date:
Douglas W. Black
Assistant City Attorney
ATTEST:
Mally J. Ka s ;�
City Secre ry
CAS
OFFICIAL RECORD
City of Fort Worth CITY SECRETARY
Professional Services Agreement Amendment Template
CFW Official Release 9/19/2017 FTa WORTHS TX
Page 3 of 4
FUNDING BREAKDOWN SHEET
City Secretary No. 49506
Amendment No. 1
Department Fund-Account-Center Amount
80 30100-0800450-5330500-CO2638-C04930 $10, 552 . 82
Total: $10, 552 . 82
City of Fort Worth
Professional Services Agreement Amendment Template
CFW Official Release 9/19/2017
Page 4 of 4
BOARD OF DIREfiORS
LodBaldock' Near Southside, Inc.
Paul Ballard
Benjamin Barkley'
Eric Behn
Marlene Beckman
Hayden Blackburn
January 10,2018
Chuck Bouligny
Kristen Camareno Joel McElhaney,Capital Program Manager
Jack Clark City of Fort Worth Parks &Recreation Department
John Corbeil 4200 South Fwy#2200
Kathleen Culebro Fort Worth,TX 76115
Nehme Elbitar
Eric Garrison Dear Joel:
Councilmember Kelly Allen Gray
Bobby Grigsby Our collaborative effort working with you and the Parks &Recreation
Jennifer Henderson Department to produce a Fire Station Park master plan is entering its
Ginger Johnson final phase. We are very excited that planning and conceptual design
Robert Kelly work to date by Project for Public Spaces (PPS) has allowed us to
Chad Kerr' thoroughly analyze all issues and produce a preliminary concept plan
Casey Kha that's achieved consensus among all of the project partners,following
Lisa Lankes an extensive and inclusive public planning process.
Mike Lozano
Wilson Martin The final PPS master plan deliverables will include a rendered master
Bobby Mays plan that incorporates all P&R comments,3-D renderings,phasing
Mark McClendon recommendations,cost estimates,and a full summary of the analysis
Lili Meisamy,D.O. and public input that served as the basis for the plan.As you're aware,
Melissa Mitchell our planning study not only addressed the future of the expanded park,
Noe Neaves but also incorporated the community center's future expansion.This
Matt opitz resulted in additional but necessary work by PPS,which has led to an
Ashley Paz proposed amendment to our contract with PPS to complete all work.
Mark Presswood'
I am writing to request approval of the attached amendment to our
Erin Rahr'
agreement,which would increase the budget for this planning and
Gaye Reed design work and allow PPS to complete all of the deliverables listed
Mike Sanborn' above. With your approval we will instruct PPS to complete the work
Ken Schaefer as quickly as possible. We look forward to then working with P&R on
Ted settle final design,fundraising,and first phase implementation.
Shawn Snell
Jesse Stamper` Please let me know of any questions or additional information needed.
Robert Sturns
Andy Taft Sincerely,
Weston Voss__
Corrie Watson
Natalie Wilkins Mike Brennan
Kelly Williams Near Southside,Inc.
Jason Williamson
Councilmember Ann Zadeh
Executive committee'
Near Southside, Inc., 1606 Mistletoe Boulevard, Fort Worth,Texas 76104
Phone 817.923.4113, mike nearsouthsidefw.org
® PROJECT FON
r PUBLIC
`A SPACES
December 21, 2017
To:Mike Brennan,Megan Henderson
Near Southside Inc.
1606 Mistletoe Blvd
Ft. Worth, TX 76104
Re.: Additional services to complete the Fire Station Park expansion concept plan and final report
Dear Mike and Megan,
This letter proposes an amendment to the agreement based on our conversation with you and Fort Worth
Parks and Recreation during our visit on December 6th and 7`h, 2017.
In 2016 NSI and Fort Worth P&R engaged PPS to develop a program and a concept plan for the newly
designated parkland at 1616 Hemphill Street. Below is a list of additional services performed by PPS
outside the original scope of work:
DESCRIPTION OF ADDITIONAL SERVICES PERFORMED BY PPS DURING THE
SUMMER/FALL 2017
• During the Spring and Summer 2017, in response to the City's analysis of community center
expansion needs,a new programmatic requirement was added to PPS tasks: a 10,000 SF building
expansion to the existing Fire Station Community Center. This new element needed to be included
in the long term Park plan and renderings for city approvals and community outreach and to
properly plan for activities and design.
• In July 2017,as requested by NSI,PPS performed design work to analyze alternate locations for the
building addition to the Community Center.From several alternatives studied in comparative
diagrams,PPS and NSI identified a recommended location along Lipscomb Street,and PPS
prepared draft park concept plan, park program, and two renderings for review.
• After further consultation with community center operations staff,Fort Worth P&R asked PPS to
investigate an additional alternate building location on Hemphill Street. P&R ultimately selected the
alternative with a contiguous expansion east of the historic fire station building as the preferred
location for the future building.
• With the new expansion location approved by all parties,PPS worked with NSI and Fort Worth
P&R to study parking demands,zoning requirements,and various potential parking locations and
scenarios,developing several additional diagrams for this analysis.
These additional tasks performed by PPS also included several conference calls and communications
with Clients, in addition to the necessary drawings to convey the concepts.
DESCRIPTION OF SCOPE OF WORK TO COMPLETE TASK 3.
PPS original contract fee was spent to complete the above described work,including our last trip on 12/6
and 12/7. We are requesting additional services,in order to complete our tasks 3.2 and 3.3.
Listed below is our proposed Scope of work:
PPS will prepare a summary booklettreport.The purpose of this booklet will be for continued community
outreach,proposal to potential fundraising partners,and City uses(the booklet will be in sections that
could be added or removed according to who the audience is)
Contents:
1-Summary of last year's workshop/survey and the results of the Open House(12/6)to be typed and
organized as an appendix
2-Final illustrative plan(removing service road parking and transform that into a path,modifying building
to be 1 story 8,000 SF no atrium,showing uses on the east side toward the lawn area and two renderings.
(add a view from Maddox street looking into the park,and remove the 3D of the lawn)The plan will be
rendered and labeled to be used for future planning board presentations.
3-Phasing plan strategies:
Phase 1:grading and pathway,vacate easement,trees in key places
Phase 2: Skate park,bike and entry plaza with shade, flex lawn,parking along Maddox(remove existing
parking to be on street parking on Maddox)+itemized estimate
Phase 3: Building addition and additional parking as required,playground relocation/change flex plaza
and multi purpose court and shade structures +itemized estimate
4-Estimated probable costs associated to each area and phase (with Parks and Recreation support)
5-Management strategy: recommendation for partnership and different roles that partners could
play
The development of this booklet will include conference calls and feedback from NSI and P&R
on an ongoing basis.
PROPOSED FEES FOR ADDITIONAL SERVICES
The cost for the additional services to complete Task 3 is $ $9,500,expenses are $ 1,000
that will cover the additional renderings presented on 12/6 and the corrections and additional
rendering.
Breakdown of fees
A.Galletti P. Patel
Project Dir. Designer Total hours
Task 3.3 Additional Additional
Final Report and Presentation
Summary of Open House 1 5 6.00
Final illustrative plan 10 5 15.00
Phasing plan strategies 7 7 14.00
Cost estimates 7 7 14.00
Management strategy 5 5 10.00
Report layout/graphics 1 7 8.00
TOTAL HOURS : 31 36 67.00
Billing Rate/hour $169.30 $119.57
Total:Labor $5,248.30 $4,304.52 $9,552.82
Renderings $1,000.00
Pursuant to Texas Local Government Code Section 271.904, PPS indemnifies and hold harmless
the City of Fort Worth against liability for any damage caused by or resulting from an act of
negligence, intentional Mort, intellectual property infringement,or failure to pay a subcontractor or
supplier committed by PPS or PPS's agent, consultant under contract,or another entity over which
PPS exercises control.
THIS AGREEMENT AUTHORIZES THE PARTICIPANTS TO PROCEED WITH
ADDITIONAL SERVICES FOR TASK 3.2 AND 3.3
Participants in the agreement:
tt1
rcoe
Alessanda Galletti, Vice President Mike Brennan, Planning Director
Project for Public Spaces Inc Near Southside, Inc.
Date: 12/21/2017 Date: 1/11207