HomeMy WebLinkAboutContract 26748 AMENDMENT NO. 1 CITY SECRETARY
CONTRACT NO.
STATE OF TEXAS $ CITY SECRETARY CONTRACT NO.26471
(No M&C Needed)
COUNTY OF TARRANT g
WHEREAS, the City of Fort Worth (City) and Halff Associates,
Inc. (Engineer) made and entered into City Secretary Contract No.
26471, (the Contract) which was authorized by the City Council by
M&C 18404 on the 19th day of December 2000; and
WHEREAS, the Contract involves engineering services for the
following project:
Sanitary Sewer Main 452 Extension
WHEREAS, it has become necessary to execute Amendment No. 1
to said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and
through their duly authorized representatives, enter into the
following agreement which amends the Contract:
1.
Article I of the Contract is amended to include the
additional engineering services specified in a proposal letter
dated April 24, 2001, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer total $6, 040 . 00.
j 2.
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work
and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $291, 485 . 00 .
vgcookD
��l01 G�a yu,
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the I7± day of ,
2001, in Fort Worth, Tarrant County, Texas.
A ST: '0 06a�t� TO
Contract Authorization
Gloria Pe son, City Secretary
Date
APPROVAL RECOMMENDED: APPROVED:
A. Douglas Rademaker, P.E. Mike Groomer
Director, Department of Assistant City Manager
Engineering
Halff Associates, Inc.
ENGINEER
By:
Name: Lynn Lovell, P.E.
Vice President
4000 Fossil Creek Blvd.
Fort Worth, TX 76137
APPROVED AS TO FORM AND LEGALITY:
'7-4�
Gary ' berger
Assistant City Attorney
ZYAco)
-2 11 pl7G'NN
% -- ® 4000 FOSSIL
FORT WORTH,TEXAS 761377
momHalff' Associafes (817)847-1422 METAX(817)232-9784
ENGINEERS • ARCHITECTS • SCIENTISTS
PLANNERS • SURVEYORS
April 24,2001
AVO 19384
Bryan Beck,P.E.
City of Fort Worth
Department of Engineering
1000 Throckmorton
Fort Worth,Texas 76102
Re: Amendment No. 1
Sanitary Sewer Main 452 Extension,DOE No. 3237
Dear Mr.Beck:
In response to your request for additional services, Halff Associates is pleased to present this
Amendment for the following additional services: -
Main 452 Additional Services:
• Four(4)additional permanent and four(4)additional temporary construction easements for
properties west of I-35W.
• Easement Acquisition Services for ten(10)parcels.The contract assumed nine(9)parcels.
• Easement revisions for parcels 2PE and 2TCE.
Easement revisions(twice)for parcels IPE and 1TCE.
• Easement modifications(combine)parcels 4,5;and 6 PE's and TCE's.
• Alignment Revisions following completion of the final plans per the approved alignment
utilizing the existing dry crossing at Basswood. Note, it was determined that alterative
alignments at Basswood would conflict with existing storm drainage facilities.
Attached is an updated Project Fee Summary. Note, some tasks were not required or were not
completed through properties that were inaccessible;therefore,the aforementioned additional services
could be funded by reallocating funds of the current budget. Please review the enclosed information
�"i and do not hesitate to call me if you have any questions or require additional information regarding this
fA - proposal for additional services.
,y
Sincerely,
HAUT ASSOCIATES,INC.
A4
Michael
Michael A.Moya,P.E.
FORT WORTH • DALLAS • HOUSTON • McALLEN
TRANSPORTATION WATER RESOURCES • LAND DEVELOPMENT • MUNICIPAL • ENVIRONMENTAL • STRUCTURAL
MECHANICAL • ELECTRICAL • SURVEYING • GEOGRAPHIC INFORMATION SYSTEMS
ARCHITECTURE • LANDSCAPE ARCHITECTURE • PLANNING
FEE SUMMARY 4/25/01
SANITARY SEWER M-452 EXTENSION AVO 19384
Contract Amendment Total
BASIC ENGINEERING DESIGN FEE .
OPINION OF PROBABLE CONSTRUCTION COST. $ '1,506,000
TSPE Curve A 7.25%
Subtotal $ 109,200
-15%Construction Inspection $ (16,380)
TOTAL BASIC FEE(Design) $ 92,820
s
SPECIAL SERVICES(HALFF ASSOCIATES)
Alignment/Flow Study $ 13,300
Alignment Revisions per City Request $ 2,400
Wetland Delineation $ 5,000
Corps Section.404 Nationwide 12 Permit $ 4,000
TxDOT Permit and Coordination $ 1,000
Easement Acquisition Services(9 properties) $ 20,250
Easement Acquisition Services(1 property) $ 2,250
4 Temp Construction Easements $ 400
4 Perm Easements $ 3,200
Subtotal $ 43,550 $- 51050 $ 48,600
t _
SPECIAL SERVICES(SUBCONSULTANT)
9 Property Appraisal Services(James Daniels) $ 13,500
Archeological Study.(AR Consultants) $ 4,000
Aerial Topography(Metropolitan Aerial) $ 4,700
Property and 1-35W ROW-Surveys(Gorrondona) $ 1.0,900
Control&Supplemental,Design Surveys(Gorrondona) $ 19,000
9 Temp Construction Easements(Gorrondona) $ 900
9 Perm Easements(Gorrondona) $ 7,200
Revise 2PE&2TCE $ -
Revise 1 PE,ITCE twice-&Modify 4,5,6 PE/TCE $ 900
Geotechnical Investigation(Tena Mar) $ 9,450
y; Reproduction(Trevino) $ 4,415
Subtotal $ 74,065 $ 900 $ 74,965
10%Fee for Subconsultants $ 7,410 $ 90 $ 7,500
r: Subtotal $. 81,475 $ 990 $ 82,465
TOTAL BASIC AND SPECIAL SERVICES $ 217,845 $ 6,040 $ 223,885
CONSTRUCTION SERVICES
Construction Administration $ _16,380
Construction Staking (Gorrondona) $ 19,000
-. 10%Fee for Subconsultant $ 1,900
Construction Inspection(Paragon) $ 27,560
10% Fee for Subconsultant $ 2,760 --
TOTAL CONSTRUCTION SERVICES FEE $ 67,600
GRAND TOTAL FEE $ 285,445 $ �f� d
P. .EN m.
1