WHEREAS, the City of Fort Worth (City) and Wade & Associates,
(Engineer) made and entered into City Secretary Contract No. 22266,
(the Contract) which was authorized by the City Council by M&C
15708 on the 15th day of October 1996; and subsequently revised by
three previous amendments; and
WHEREAS, the Contract involves engineering services for the
following project:
Engineering contract for the design of Sanitary Sewer Main
C1C4B Drainage Area Sanitary Sewer Evaluation Study and
Improvements (Group 6, Contract 2) .
WHEREAS, it has become necessary to execute Amendment No. 4 to
said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly authorized representatives, enter into the following
agreement which amends the Contract:
1.
Article I of the Contract is amended to include the additional
engineering services specified in a proposal letter dated March 13,
2001 , a copy of which is attached hereto and incorporated herein.
The cost to City for the additional design services to be performed
by Engineer total $10,163.27 .
2.
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $1,228,237.77.
Y�.
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the /VM day of 2001, in Fort
Worth, Tarrant County, Texas.
AT � 0 M J'G J&t�-U I K
Z�V" Contract Authorization
Gloria Pe son, City Secret ry
�'-lh -� ` Date
APPROVAL RECOMMENDED: APPROVED:
A. Douglas Rademaker, P.E. Mike Groomer
Director, Department of Assistant City Manager
Engineering
WADE & ASSOCIATES, INC.
ENGINEER
By: 4-/-�"vl
Name: Mark Wade, P.E .
President
213 South Jenninas Avenue
Fort Worth, TX 76104
APPROVE AS TO FORM AND LEGALITY:
Get
CT
Assistant City Attorney
22266-4
D U C1)1 IR,l 1{id fAI U
WHO [
QCI 1<ESLI ,
13 March, 2001
Mr. John Boyer, Project Manager
Fort Worth Department of Engineering
Integrated Wet Weather Program
811 Lamar Street, Suite 310
Fort Worth,Texas 76102
RE: Submission of Contract Amendment No. 4, Main C1C413 Drainage Area,
Sanitary Sewer System Rehabilitation and Improvements Project, Group 6,
Contract 2, Project No. PS46-07046041230, WADE File No. 9627
Dear Mr. Boyer:
We are submitting this contract amendment for your immediate consideration and
approval. This amendment reflects a number of extra services provided on the above-
referenced design projects.
More specifically, we are seeking to recover costs for the removal of M-CIC413, Part 8,
Unit 3, from the original set of Part 8 bid documents, so that Units 1 and 2 could be bid
separately. The information below also includes costs incurred in the initial production of
a Part 14, set of contract documents. Part 14 was comprised of Part 8, Unit 3, and Part 12,
Unit 3 as a set of bid documents. Due to easement acquisition delays, we were asked to
split up Part 14 so that Part 12, Unit 3 could be advertised separately which was done late
last year. Please see the cost-related information in the table below:
Staff/Item Hours Labor Direct Total
Expenses Expenses Expenses
Senior Engineer 24 S2,418.96 S3,023.70
(S 100.79/hr)
Senior Office 74 S4,509.56 S3,412.64
Technician ($60.94/hr)
Printing/Plotting/Costs S 270.00 S 270.00
(In-house)
Labor Subtotal: $ 6,928.52
Direct Expenses Subtotal: S 270.00
TOTALS: $7,198.52
In addition, we have incorporated an amendment request to recover costs associated with
resolving the 8`h Ave. sanitary sewer problem in late January. As a reminder, this situation
arose during the construction of M-32 in 8`h Ave. on the section that we designed located
south of Arlington and 8h Ave. This design segment was incorporated into the Halff &
Associates project because Halff s project replaced M-32 upstream of our project area.
Consulting Engineers
6 70 1 Brent++ood Stair Road _�_._. ..._......__.
S u i t e 1 0 0 W
Fort Worth. Texas 76112
8 1 7 . 4 5 1 . 2 8 2 0 �Hl t+ � nl/
FAX 817.451 •2208 �Un OS(ISS++ L d L
Page 2 of 2
Mr. John Boyer
March 13,.2001
Mr. Domenech requested us to get involved in solving this construction problem in late
January. Essentially the problem was defined by excess subsurface water entering the
trench and preventing trench compaction from meeting specifications. We developed a
viable solution to this problem after reviewing other options presented by a geotechnical
engineer, CMJ Engineering, Inc., who was retained by either the City or by Halff. On
January 25, 2001, we delivered a letter report and plan sheet addressing the sub-surface
drainage problem to Mr. Domenech. This solution has been implemented by the
contractor. We were asked by Mr. Domenech to incorporate CiV1J's costs into our contract
invoice. Therefore, their time-sensitive costs are incorporated in this amendment request
described in the following table:
M-C1C4B X1-32 Draina e Problem - Cost Recovety Items
Staff/Item Hours Labor Direct Total
Expenses Expenses Ex eases
Senior Engineer 20 $ 2,040.00 S2,040.00
(S 102.00/hr)
Senior Office 8 $ 496.00 S '496.00
Technician (562.00/hr)
Printing/Plotting/Costs S 20.00 S 20.00
(In-house)
Mileage expenses S 23.85 S 23.85
Subcontractor Expenses S 350.00 S 350.00
(CMJ Engineering)
Labor Subtotal: S 2.536.00
Direct Expenses Subtotal: S 43.85
Subcontractor expenses, including 10%Administrative Fee: $ 385.00
TOTALS: $2,964.85
In summary, WADE is seeking to only reco6er actual expenses that have been incurred for
this project. Therefore, we are requesting Contract Amendment No. 4 for the M-C1C4B
Agreement in the amount of $ 10,14337. This amendment would increase the total
contract less than one percent from an amount of $1,218,074.40 to 1,228,237.77. Please
advise us immediately if there is a problem with this request. Thank you for your time and
consideration.
4WAD�� ASSOC ES, INC.
Chris Bro ks E.,
CEB/ceb Project Manager
CC: Peter Fu, P.E.,FWWD, City of Fort Worth
Tony Sholola, P.E., DOE, City of Fort Worth
Mark Wade, P.E.,President, WADE —--
Nade & Associates, Inc
;onsulting Engineers