CITY OF FORT WORTH, TEXAS
STANDARD AGREEMENT FOR ENGINEERING RELATED PROFESSIONAL
SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home-rule
municipality ("CITY"), and Teal Engineering Services, Inc., authorized to do business in
Texas, ("ENGINEER"), for a PROJECT generally described as: 2014 Bond Signals Year 4
Improvements.
Article I
Scope of Services
The Scope of Services is set forth in Attachment A.
Article II
Compensation and Term of Agreement
A. The ENGINEER's compensation shall be in the hourly, not-to-exceed amount of
$55,347.00 as set forth in Attachment B.
B. Unless otherwise terminated pursuant to Article VI. D. herein, this Agreement
shall be for a term beginning upon the effective date, as described below, and
shall continue until the expiration of the funds or completion of the subject
matter contemplated herein, whichever occurs first.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
Vii) The Engineer shall provide the City sufficient documentation, including but
not limited to meeting the requirements set forth in Attachment D to this
AGREEMENT, to reasonably substantiate the invoices.
#g92pF� (2) The AGREEMENT.Ilnvwill
oices are duemonthly
and payable within 30 days of receipt.under this
'ityar 2019
C/IS C9
4111'Uy of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services OFFICIAL RECORD
Revised Date:11.17.17
Page 1 of 17 CITY SEECR1l TARRY
FT.WORTH,TX
(3) Upon completion of services enumerated in Article I, the final payment of
any balance will be due within 30 days of receipt of the final invoice.
(4) In the event of a disputed or contested billing, only that portion so contested
will be withheld from payment, and the undisputed portion will be paid. The
CITY will exercise reasonableness in contesting any bill or portion thereof.
No interest will accrue on any contested portion of the billing until mutually
resolved.
(5) If the CITY fails to make payment in full to ENGINEER for billings contested
in good faith within 60 days of the amount due, the ENGINEER may, after
giving 7 days' written notice to CITY, suspend services under this
AGREEMENT until paid in full. In the event of suspension of services, the
ENGINEER shall have no liability to CITY for delays or damages caused the
CITY because of such suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental
thereto.
B. Standard of Care
The ENGINEER shall perform its services:
(1) with the professional skill and care ordinarily provided by competent
engineers practicing in the same or similar locality and under the same or
similar circumstances and professional license; and
(2) as expeditiously as is prudent considering the ordinary professional
skill and care of a competent engineer.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 2 of 17
work to be performed hereunder. The ENGINEER shall also advise
the CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that
could affect the total PROJECT cost and/or execution. These
conditions and costlexecution effects are not the responsibility of the
ENGINEER.
D. Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in .pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires; provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on-site representatives or otherwise, do not make the
ENGINEER or its personnel in any way responsible for those duties that
belong to the CITY and/or the CITY's construction contractors or other
entities, and do not relieve the construction contractors or any other entity of
their obligations, duties, and responsibilities, including, but not limited to, all
construction methods, means, techniques, sequences, and procedures
necessary for coordinating and completing all portions of the construction
work in accordance with the Contract Documents and any health or safety
precautions required by such construction work. The ENGINEER and its
personnel have no authority to exercise any control over any construction
contractor or other entity or their employees in connection with their work or
any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the
progress or quality of the completed work on the PROJECT or to determine,
in general, if the work on the PROJECT is being performed in a manner
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 3 of 17
indicating that the PROJECT, when completed, will be in accordance with
the Contract Documents, nor shall anything in the Contract Documents or
this AGREEMENT between CITY and ENGINEER be construed as requiring
ENGINEER to make exhaustive or continuous on-site inspections to
discover latent defects in the work or otherwise check the quality or quantity
of the work on the PROJECT. If the ENGINEER makes on-site
observation(s) of a deviation from the Contract Documents, the ENGINEER
shall inform the CITY.
(3) When professional certification of performance or characteristics of
materials, systems or equipment is reasonably required to perform the
services set forth in the Scope of Services, the ENGINEER shall be entitled
to rely upon such certification to establish materials, systems or equipment
and performance criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs; competitive bidding procedures and market
conditions; time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate
PROJECT cost or schedule. Therefore, the ENGINEER makes no
warranty that the CITY's actual PROJECT costs, financial aspects,
economic feasibility, or schedules will not vary from the ENGINEER's
opinions, analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling
and observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects; that the
ENGINEER has made an examination to ascertain how or for what purpose
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 4 of 17
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are not other
matters at issue between the CITY and the construction contractor that
affect the amount that should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed. The ENGINEER is not responsible for
any errors or omissions in the information from others that is incorporated
into the record drawings.
I. Minority Business and Small Business Enterprise (MBE)(SBE)
Participation
In accord with the City of Fort Worth Business Diversity goals (Chapter 20,
Article X of the City's Code of Ordinances a/k/a Ordinance No. 20020-12-
2011, as amended), the City has goals for the participation of minority
business enterprises and/or small business enterprises in City contracts.
Engineer acknowledges the MBE and SBE goals established for this
contract and its accepted written commitment to MBE and SBE
participation. Any misrepresentation of facts (other than a negligent
misrepresentation) and/or the commission of fraud by the Engineer may
result in the termination of this Agreement and debarment from participating
in City contracts for a period of time of not less than three (3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers
and records of the ENGINEER involving transactions relating to this
contract. ENGINEER agrees that the CITY shall have access during normal
working hours to all necessary ENGINEER facilities and shall be provided
adequate and appropriate work space in order to conduct audits in
compliance with the provisions of this section. The CITY shall give
ENGINEER reasonable advance notice of intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the
CITY shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 5of17
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
facilities, and shall be provided adequate and appropriate work space, in
order to conduct audits in compliance with the provisions of this article
together with subsection (3) hereof. CITY shall give subconsultant
reasonable advance notice of intended audits.
(3) ENGINEER and subconsultant agree to photocopy such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for
the cost of copies at the rate published in the Texas Administrative Code in
effect as of the time copying is performed.
K. INSURANCE
(1) ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain
commercial general liability (CGL) and, if necessary, commercial
umbrella insurance with a limit of not less than $1,000,000.00 per each
occurrence with a $2,000,000.00 aggregate. If such Commercial General
Liability insurance contains a general aggregate limit, it shall apply
separately to this PROJECT or location.
i. The CITY shall be included as an additional insured with all rights
of defense under the CGL, using ISO additional insured
endorsement or a substitute providing equivalent coverage, and
under the commercial umbrella, if any. This insurance shall apply
as primary insurance with respect to any other insurance or self-
insurance programs afforded to the CITY. The Commercial
General Liability insurance policy shall have no exclusions or
endorsements that would alter or nullify: premises/operations,
products/completed operations, contractual, personal injury, or
advertising injury, which are normally contained within the policy,
unless the CITY specifically approves such exclusions in writing.
ii. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b. Business Auto — the ENGINEER shall maintain business auto liability
and, if necessary, commercial umbrella liability insurance with a limit of
not less than $1,000,000 each accident. Such insurance shall cover
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 6 of 17
liability arising out of "any auto", including owned, hired, and non-owned
autos, when said vehicle is used in the course of the PROJECT. If the
engineer owns no vehicles, coverage for hired or non-owned is
acceptable.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation — ENGINEER shall maintain workers
compensation and employers liability insurance and, if necessary,
commercial umbrella liability insurance with a limit of not less than
$100,000.00 each accident for bodily injury by accident or $100,000.00
each employee for bodily injury by disease, with $500,000.00 policy limit.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability — ENGINEER shall maintain professional liability, a
claims-made policy, with a minimum of $1,000,000.00 per claim and
aggregate. The policy shall contain a retroactive date prior to the date of
the contract or the first date of services to be performed, whichever is
earlier. Coverage shall be maintained for a period of 5 years following the
completion of the contract. An annual certificate of insurance specifically
referencing this project shall be submitted to the CITY for each year
following completion of the contract.
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be attached to this AGREEMENT prior to its
execution.
b. Applicable policies shall be endorsed to name the CITY an Additional
insured thereon, subject to any defense provided by the policy, as its
interests may appear. The term CITY shall include its employees,
officers, officials, agents, and volunteers as respects the contracted
services.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 7 of 17
c. Certificate(s) of insurance shall document that insurance coverage
specified in this agreement are provided under applicable policies
documented thereon.
d. Any failure on part of the CITY to attach the required insurance
documentation hereto shall not constitute a waiver of the insurance
requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent
to the respective Department Director (by name), City of Fort Worth, 200
Texas Street, Fort Worth, Texas 76102.
f. Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of A:V or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management.
g. Any deductible or self insured retention in excess of $25,000.00 that
would change or alter the requirements herein is subject to approval by
the CITY in writing, if coverage is not provided on a first-dollar basis. The
CITY, at it sole discretion, may consent to alternative coverage
maintained through insurance pools or risk retention groups. Dedicated
financial resources or letters of credit may also be acceptable to the
CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation
in favor of the CITY as respects the PROJECT.
i. The CITY shall be entitled, upon its request and without incurring
expense, to review the ENGINEER's insurance policies including
endorsements thereto and, at the CITY's discretion; the ENGINEER may
be required to provide proof of insurance premium payments.
j. Lines of coverage, other than Professional Liability, underwritten on a
claims-made basis, shall contain a retroactive date coincident with or
prior to the date of the contractual agreement. The certificate of
insurance shall state both the retroactive date and that the coverage is
claims-made.
k. Coverages, whether written on an occurrence or claims-made basis,
shall be maintained without interruption nor restrictive modification or
changes from date of commencement of the PROJECT until final
payment and termination of any coverage required to be maintained after
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 8 of 17
final payments.
I. The CITY shall not be responsible for the direct payment of any
insurance premiums required by this agreement.
m. Sub consultants and subcontractors to/of the ENGINEER shall be
required by the ENGINEER to maintain the same or reasonably
equivalent insurance coverage as required for the ENGINEER. When
sub consultants/subcontractors maintain insurance coverage,
ENGINEER shall provide CITY with documentation thereof on a
certificate of insurance.
L. Independent Consultant
The ENGINEER agrees to perform all services as an independent
consultant and not as a subcontractor, agent, or employee of the CITY.
The doctrine of respondeat superior shall not apply.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure
in writing of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing
of any conflicts of interest that develop subsequent to the signing of this
contract and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities -Design Changes
If permitting authorities require design changes so as to comply with
published design criteria and/or current engineering practice standards
which the ENGINEER should have been aware of at the time this
Agreement was executed, the ENGINEER shall revise plans and
specifications, as required, at its own cost and expense. However, if design
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page9of17
changes are required due to the changes in the permitting authorities'
published design criteria and/or practice standards criteria which are
published after the date of this Agreement which the ENGINEER could not
have been reasonably aware of, the ENGINEER shall notify the CITY of
such changes and an adjustment in compensation will be made through an
amendment to this AGREEMENT.
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City-Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of
the information provided by the CITY.
B. Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services. The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of
the CITY's personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses
required by local, state, or federal authorities; and land, easements, rights-
of-way, and access necessary for the ENGINEER's services or PROJECT
construction.
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches,
drawings, specifications, proposals, and other documents; obtain advice of
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
RevisedDate:11.17.17
Page 10 of 17
an attorney, insurance counselor, accountant, auditor, bond and financial
advisors, and other consultants as the CITY deems appropriate; and render
in writing decisions required by the CITY in a timely manner in accordance
with the project schedule prepared in accordance with Attachment D.
E. Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of
such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos
is a result of ENGINEER's negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto the project.
G. Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of
Article IV.E. regarding the ENGINEER's Personnel at Construction Site, and
provisions providing for contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
H. Contractor Claims and Third-Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering
services performed. Only the CITY will be the beneficiary
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 11 of 17
of any undertaking by the ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third-party beneficiaries.
(3) The CITY will include in each agreement it enters into with any other entity
or person regarding the PROJECT a provision that such entity or person
shall have no third-party beneficiary rights under this Agreement.
(4) Nothing contained in this Section H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER.
I. CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY may secure Builders Risk/Installation insurance at the
replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3) The CITY will specify that the Builders Risk/Installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of the ENGINEER, this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
K. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for performance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 12 of 17
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed from the CITY.
B. Reuse of Project Documents
All designs, drawings, specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the final designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God, strikes, lockouts, accidents, or other events beyond
the control of the ENGINEER that prevent ENGINEER's performance of its
obligations hereunder.
D. Termination
(1) This AGREEMENT may be terminated
a.) by the City for its convenience upon 30 days' written notice to
ENGINEER.
b.) by either the CITY or the ENGINEER for cause if either party fails
substantially to perform through no fault of the other and the
nonperforming party does not commence correction of such
nonperformance within 5 days' written notice or thereafter fails to
diligently complete the correction.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans,
specifications or other forms of ENGINEER'S work product;
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 13 of 17
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
C.) The time requirements for the ENGINEER'S personnel to document
the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all termination expenses. The
CITY'S approval will be obtained in writing prior to proceeding with
termination services.
E. Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER
for the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors,
and ENGINEER's compensation will be made.
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify or hold harmless the CITY against liability
for any damage committed by the ENGINEER or ENGINEER's agent,
consultant under contract, or another entity over which the ENGINEER
exercises control to the extent that the damage is caused by or
resulting from an act of negligence, intentional tort, intellectual
property infringement, or failure to pay a subcontractor or supplier.
CITY is entitled to recover its reasonable attorney's fees in proportion
to the ENGINEER's liability.
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the
prior written consent of the other party.
H. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and performance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 14 of 17
Texas.
I. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any
reason to be invalid, illegal, or unenforceable in any respect, such invalidity,
illegality, or unenforceability will not affect any other provision, and this
AGREEMENT shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained herein. Articles V.F., VI.B., VI.D., VI.F.,
VI.H., and VI.I. shall survive termination of this AGREEMENT for any cause.
J. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in
any way affect this AGREEMENT and the work hereunder, and shall
observe and comply with all orders, laws ordinances and regulations which
may exist or may be enacted later by governing bodies having jurisdiction or
authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. ENGINEER agrees to defend, indemnify and
hold harmless CITY and all of its officers, agents and employees from and
against all claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
K. Immigration Nationality Act
ENGINEER shall verify the identity and employment eligibility of its
employees who perform work under this Agreement, including completing
the Employment Eligibility Verification Form (1-9). Upon request by CITY,
ENGINEER shall provide CITY with copies of all 1-9 forms and supporting
eligibility documentation for each employee who performs work under this
Agreement. ENGINEER shall adhere to all Federal and State laws as well
as establish appropriate procedures and controls so that no services will
be performed by any ENGINEER employee who is not legally eligible to
perform such services. ENGINEER SHALL INDEMNIFY CITY AND
HOLD CITY HARMLESS FROM ANY PENALTIES, LIABILITIES, OR
LOSSES DUE TO VIOLATIONS OF THIS PARAGRAPH BY ENGINEER,
ENGINEER'S EMPLOYEES, SUBCONTRACTORS, AGENTS, OR
LICENSEES. CITY, upon written notice to ENGINEER, shall have the
right to immediately terminate this Agreement for violations of this
provision by ENGINEER.
L. Prohibition On Contracts With Companies Boycotting Israel
ENGINEER acknowledges that in accordance with Chapter 2270 of the
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 15 of 17
Texas Government Code, CITY is prohibited from entering into a contract
with a company for goods or services unless the contract contains a
written verification from the company that it: (1) does not boycott Israel;
and (2) will not boycott Israel during the term of the contract. The terms
"boycott Israel" and "company" shall have the meanings ascribed to those
terms in Section 808.001 of the Texas Government Code. By signing
this contract, ENGINEER certifies that ENGINEER'S signature
provides written verification to the CITY that ENGINEER: (1) does not
boycott Israel; and (2) will not boycott Israel during the term of the
contract.
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, which supersedes all prior written or oral understandings, and may only be
changed by a written amendment executed by both parties. This AGREEMENT may be
executed in one or more counterparts and each counterpart shall, for all purposes, be
deemed an original, but all such counterparts shall together constitute but one and the
same instrument. The following attachments and schedules are hereby made a part of
this AGREEMENT:
Attachment A - Scope of Services
Attachment B - Compensation
Attachment C -Amendments to Standard Agreement for Engineering Services
Attachment D - Project Schedule
Attachment E - Location Map
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 16 of 17
Duly executed by each party's designated representative to be effective on the date
subscribed by the City's designated Assistant City Manager.
BY: BY:
CITY OF FORT WORTH ENGINEER
Teal Engineering Servi Inc.
"an IAn iS Gary . Jost,15-1-1
Assistant City Manaycr Vice President
Dater Date. OZ20)Zo1g
APPRO AL RECOMMENDED:
By: l6j, 1,J r
DouglA W. Wiersig, P.E.
Director, Department of Transportation
and Public Works
Contract Compliance Manager:
By signing, 1 acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including
ensuring all performance and reporting
,r/eqements.
Lissette Acevedo, P.E., PTOL, PMP
Engineering Manager
APPROVED AS TO FORM AND LEGALITY
B r
Y�
Douglas W. Black A`
Assistant City Attorn
ATT T: rm 1295 No. N/A
i �
Mary J. s M&C No.: N/A
City Secre
M&C Date: N/A
City of Fort Worth,Texas !►�a!AL�AOpw
Standard Agreement for Engineering Related Design Services OFFICIAL RECORD
11.17.17
Page 17 of 17 CITY!N/►R11117my
ATTACHMENT "A"
Scope for Engineering Design Related Services for
CPN 101369—2014 Bond Signals Year 4 (Teal Engineering Services)
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
OBJECTIVE
The project includes the development of Plans, Specifications and Estimate for roadway
improvements at the intersection of North Main Street and East Long Avenue in Fort Worth,
Texas. The objectives of the project include the following:
• Replace the existing traffic signal with a new traffic signal meeting current Fort
Worth City Standards.
• Improve corner turning radii to improve vehicle operations and reduce pedestrian
crossing distances.
• Provide ADA compliant accessibility.
WORK TO BE PERFORMED
Task 1. Design Management
Task 2. Preliminary Design
Task 3. Final Design
Task 4. ROW/Easement Services
Task 5. Survey and Subsurface Utility Engineering Services
Task 6. Permitting
TASK 1. DESIGN MANAGEMENT.
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use
of ENGINEER's and CITY's time and resources. ENGINEER will manage change,
communicate effectively, coordinate internally and externally as needed, and proactively
address issues with the CITY's Project Manager and others as necessary,to make progress
on the work.
1.1. Managing the Team
• Lead, manage and direct design team activities
• Ensure quality control is practiced in performance of the work
• Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting
• Attend a pre-design project kickoff/chartering meeting with CITY staff to confirm
and clarify scope, understand CITY objectives, and ensure economical and
functional designs that meet CITY requirements.
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 1 of 11
• Conduct and document monthly project update meetings with CITY Project
Manager.
• Conduct review meetings with the CITY at the end of each design phase—60%,
and 90%. The 60% review meeting shall be held in the field, all others to be held
at Traffic Management.
• Prepare invoices, in accordance with Attachment B to this Standard Agreement
and submit monthly in the format requested by the CITY.
• Prepare and submit monthly progress reports in the format provided by the
respective CITY Department.
• Prepare and submit baseline Project Schedule initially, and Project Schedule
updates with a schedule narrative monthly, as required in Attachment D to this
Standard Agreement and according to the City of Fort Worth's Schedule
Guidance Document.
• Prepare and submit a preliminary Project Risk Register, preliminary Stakeholder
Register, and preliminary Project Communications Plan. CITY to modify and
finalize.
• Prepare monthly updates to the Total Project Budget Estimate (TPBE)
spreadsheet and the Project Risk Register.
• Complete Monthly M/WBE Report Form and Final Summary Payment Report
Form at the end of the project.
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare
the design.
• Prepare for and attend one (1) PEER review meeting. The ENGINEER will
participate via video conference and answer questions from the PEER review
participates.
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with the Texas Department of Transportation (TxDOT) such that
their regulatory requirements are appropriately reflected in the designs.
ENGINEER shall work with TxDOT to obtain approval of the designs, and make
changes necessary to meet their requirements, as part of the design scope.
ASSUMPTIONS
• One (1) pre-design project kickoff/chartering meeting.
• Five (5) monthly project update meetings with CITY Project Manager.
• Two (2) plan review meetings.
• Project design phase is anticipated to take five (5) months.
• Prepare five (5) monthly updates of project status reports, MWBE forms, TPBE,
risk register, and project schedule.
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 2 of 11
• Prepare for and participate in one (1) PEER review meeting.
DELIVERABLES
A. Meeting summaries with action items
B. Monthly invoices
C. Monthly progress reports
D. Baseline design schedule
E. Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
F. Monthly M/WBE Report Form and Final Summary Payment Report Form
G. Monthly TPBE spreadsheet updates
H. Monthly Project Risk Register updates
1. Preliminary Project Risk Register, Stakeholder Register, and Project
Communications Plan.
TASK 2. DATA COLLECTION
The purpose of this task is for the ENGINEER to assemble the necessary information that
may impact the project design and/or operations of the intersection.
ENGINEER will assemble and/or collect the following information
3.1. Data Collection
• In addition to data obtained from the CITY, ENGINEER will research and make
efforts to obtain pertinent information to aid in coordination of the proposed
improvements with any planned future improvements that may influence the
project. ENGINEER will also identify and seek to obtain data for existing
conditions that may impact the project including; utilities, agencies (TxDOT and
railroads), City Master Plans, and property ownership as available from the Tax
Assessor's office.
• Collect new 24-hour bi-directional traffic volume counts one(1) project intersection.
• Collect AM,PM and Off-peak turning movement counts (TMCs) at one (1) project
intersection.
• Traffic Count Data: Microsoft Excel spreadsheet of Raw 24-hour Turning
Movement Count data gathered at 15 minute intervals at a minimum on all
raw data collected. Provide Daily Summaries by Approach and Peak-Period
Summaries by Approach. Spreadsheet shall be uploaded to the Buzzsaw
folder`TPW Traffic Count Data'.
DELIVERABLES
A. Log of assembled pertinent data
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 3 of 11
B. Traffic Count Data
TASK 2. PRELIMINARY DESIGN (60 PERCENT).
Preliminary plans and specifications shall be submitted to CITY per the approved Project
Schedule.
ENGINEER will develop the preliminary design of the infrastructure as follows.
2.1 Development of Preliminary Design Drawings and Specifications shall include, but
not be limited to, the following:
• Cover Sheet
• Sheet Index
• Quantity Summary
• General Notes
• Traffic Signal Existing Conditions and Removals Sheet
• Traffic signal proposed conditions layout sheet showing the location of proposed
signal poles and mast arms, ground boxes, controller cabinet, and electrical
service meter.
• Traffic Signal Equipment Detail Sheets(1 sheet per comer,1"= 10' scale)
• Traffic Signal Summary Charts
• Paving Removal Sheet
• Paving Layout Sheet
• Paving Detail Sheets (1 sheet per comer, 1" = 10' scale)
• Pavement Markings Removal Sheet
• Pavement Markings Installation Sheet
• Signing Removal Sheet
• Signing Installation Sheet
• Traffic Control Plan for paving work including all construction signage and
pavement markings which will be in accordance with the latest edition of the Texas
Manual on Uniform Traffic Control Devices. Traffic control for signal equipment
installation will be covered by the CITY's standard details D660 and D661.
• Applicable CITY and/or TxDOT standard details, 1 per sheet.
• All design sheets shall include project control data. The following information
shall be indicated for each Control Point: Identified (existing City Monument
#8901, PK Nail, 5/8" Iron Rod); X, Y and Z Coordinates, in an identified coordinate
system, and a referred bearing base. Z coordinate on City Datum only; descriptive
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 4 of 11
location (i.e. set in the centerline of the inlet in the South curb line of North Side
Drive at the East end of radius at the Southeast comer of North Side Drive and
North Main Street).
• Documentation of key design decisions_
• Opinion of probable construction cost (OPCC).
2.2 Constructability Review
Prior to the 60 percent review meeting with the CITY, the ENGINEER shall
schedule and attend a project site visit with the CITY Project Manager and
Construction personnel to walk the project. The ENGINEER shall summarize the
CITY's comments from the field visit and submit this information to the CITY in
writing.
2.3 Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities and government agencies to determine the approximate location
of above and underground utilities, and other facilities (current and future) that
have an impact or influence on the project. ENGINEER will design CITY facilities
to avoid or minimize conflicts with existing utilities, and where known and
possible consider potential future utilities in designs.
• The ENGINEER shall upload individual DWF files for each plan sheet of the
approved preliminary plan set to the designated project folder in Buzzsaw for
forwarding to all utility companies which have facilities within the limits of the
project. The DWF files should be created directly from the CAD files as opposed
to PDF files.
2.4 Data Collection
• In addition to data obtained from the CITY, ENGINEER will research and make
efforts to obtain pertinent information to aid in coordination of the proposed
improvements with any planned future improvements that may influence the
project. ENGINEER will also identify and seek to obtain data for existing
conditions that may impact the project including; utilities, agencies (TxDOT and
railroads), City Master Plans, and property ownership as available from the Tax
Assessor's office.
• Collect new 24-hour bi-directional traffic volume counts one(1) project intersection.
• Collect AM,PM and Off-peak turning movement counts (TMCs) at one (1) project
intersection.
• Traffic Count Data: Microsoft Excel spreadsheet of Raw 24-hour Turning
Movement Count data gathered at 15 minute intervals at a minimum on all raw
data collected. Provide Daily Summaries by Approach and Peak-Period
Summaries by Approach. Spreadsheet shall be uploaded to the Buzzsaw folder
'TPW Traffic Count Data'.
ASSUMPTIONS
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 5 of 11
• Three (3) sets of 11" x 17"size plans will be delivered for the 60% design.
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in Buzzsaw.
• One(1)set of full size drawings will be delivered for Utility Clearance.
• ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Preliminary Design plans.
• One(1) plan review meeting with the CITY.
DELIVERABLES
A. Preliminary Design drawings and specifications
B. Utility Clearance drawings and Utility Clearance Cover Letter
C. Estimates of probable construction cost
D. Meeting summary from plan review meeting
E. Traffic Count Data
TASK 3. FINAL DESIGN (90 PERCENT)AND FINAL CONSTRUCTION DOCUMENTS
(100 PERCENT).
Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as
follows:
• Final draft construction plans (90%) shall be submitted to CITY per the approved
Project Schedule.
• Following a 90% construction plan review meeting with the CITY, the ENGINEER
shall submit Final Plans (100%)to the CITY per the approved Project Schedule.
Each plan sheet shall be stamped, dated, and signed by a Professional Engineer
registered in State of Texas.
• The ENGINEER shall submit a final design estimate of probable construction
cost with both the 90% and 100% design packages. This estimate shall use
ONLY standard CITY bid items.
• Prior to final design plans (90%) obtain a file number for the project, contact the
Department of Transportation and Public Works Vault at telephone number(817)
392-8426. File numbers will not be issued to a project unless the appropriate
project numbers and fund codes have been assigned and are in the Department of
Transportation and Public Works database, coordinate with CITY Project Manager.
ASSUMPTIONS
• Three (3) sets of 11" x 17" size drawings will be delivered for the 90% Design
package.
• A DWF file for the 90% Design will be created from design CAD drawings and
will be uploaded to the project folder in Buzzsaw.
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 6 of 11
• Three(3) sets of 11" x 17" size drawings will be delivered for the 100% Design
package.
• A DWF file for the 100 % Design will be created from design CAD drawings and
will be uploaded to the project folder in Buzzsaw.
DELIVERABLES
A. 90% construction plans with Utility Clearance Cover Letter.
B. 100% construction plans with Utility Clearance Cover Letter.
C. Detailed estimates of probable construction costs including summaries of bid
items and quantities using the CITY's standard bid items and format.
D. Original cover mylar for the signatures of authorized CITY officials.
TASK 4. ROW/EASEMENT SERVICES.
ENGINEER will support and perform activities related to ROW and land as outlined below,
per scoping direction and guidance from the CITY's Project Manager.
4.1 Right-of-Way Research
• The ENGINEER shall determine rights-of-way and easements needs for
construction of the project. Required temporary and permanent easements will
be identified based on available information and recommendations will be made
for approval by the CITY.
4.2 Temporary Construction Easement Preparation and Submittal
• Prior to construction, the ENGINEER shall prepare and submit Temporary
Construction Easement documents to Real Property.
• The documentation shall be provided in conformance with the checklists and
templates available on the CITY's Buzzsaw site.
• The ENGINEER shall prepare up to four (4) temporary construction easement
documents.
ASSUMPTIONS
• It is assumed that temporary or permanent easements will be required.
• Right-of-Way research includes review of property/right-of-way records based on
current internet based Tarrant Appraisal District (TAD) information available at
the start of the project and available on-ground property information (i.e. iron
rods, fences, stakes, etc.). It does not include effort for chain of title research,
parent track research, additional research for easements not included in the
TAD, right-of-way takings, easement vacations and abandonments, right-of-way
vacations, and street closures.
DELIVERABLES
A. Easement exhibits and meets and bounds provided on CITY forms.
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 7 of 11
TASK 5. SURVEY AND SUBSURFACE UTILITY ENGINEERING SERVICES.
ENGINEER will provide survey support as follows.
5.1 Design Survey
• ENGINEER will perform field surveys to collect horizontal and vertical elevations
and other information needed by ENGINEER in design and preparation of plans
for the project. Information gathered during the survey shall include topographic
data, elevations of all sanitary and adjacent storm sewers, rim/invert elevations,
location of buried utilities, structures, trees (measure caliper, identify overall
canopy, and have qualified arborist identify species of trees), and other features
relevant to the final plan sheets. Existing drainage at intersections will be verified
by field surveys. Spot elevations will be shown on intersection layouts with cross
slope to fit intersecting grade lines.
• The minimum survey information to be provided on the plans shall include, but
not be limited to, the following:
- A Project Control Sheet, showing ALL Control Points, used or set while
gathering data. Generally on a scale of not less than 1:400:
- The following information about each Control Point;
a. Identified (Existing. CITY Monument#8901, PK Nail, 5/8" Iron Rod)
b. X, Y and Z Coordinates, in an identified coordinate system, and a
referred bearing base. Z coordinate on CITY Datum only.
c. Descriptive Location (Ex. Set in the centerline of the inlet in the South
curb line of North Side Drive at the East end of radius at the Southeast
comer of North Side Drive and North Main Street).
- Coordinates on all P.C.'s, P.T.'s, P.I.'s, Manholes, Valves, etc., in the
same coordinate system, as the Control.
- No less than two horizontal bench marks, per line or location.
- Bearings given on all proposed centerlines, or baselines.
- Station equations relating utilities to paving, when appropriate.
5.2 Subsurface Utility Engineering
Provide Subsurface Utility Engineering (SUE) to Quality Level A as described below.
The SUE shall be performed in accordance with CI/ASCE 38-02.
Quality Level D
• Conduct appropriate investigations (e.g., owner records, County/CITY records,
personal interviews, visual inspections, etc.), to help identify utility owners that
may have facilities within the project limits or that may be affected by the project.
• Collect applicable records (e.g., utility owner base maps, "as built" or record
drawings, permit records, field notes, geographic information system data, oral
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06 2015
Page 8 of 11
histories, etc.) on the existence and approximate location of existing involved
utilities.
• Review records for: evidence or indication of additional available records;
duplicate or conflicting information; need for clarification.
• Develop SUE plan sheets and transfer information on all involved utilities to
appropriate design plan sheets, electronic files, and/or other documents as
required. Exercise professional judgment to resolve conflicting information. For
information depicted, indicate: utility type and ownership; date of depiction;
quality level(s); end points of any utility data; line status (e.g., active, abandoned,
out of service); line size and condition; number of jointly buried cables; and
encasement.
Quality Level C (includes tasks as described for Quality Level D)
• Identify surface features, from project topographic data and from field
observations, that are surface appurtenances of subsurface utilities.
• Include survey and correlation of aerial or ground-mounted utility facilities in
Quality Level C tasks.
• Survey surface features of subsurface utility facilities or systems, if such features
have not already been surveyed by a professional surveyor. If previously
surveyed, check survey data for accuracy and completeness.
• The survey shall also include (in addition to subsurface utility features visible at
the ground surface): determination of invert elevations of any manholes and
vaults; sketches showing interior dimensions and line connections of such
manholes and vaults; any surface markings denoting subsurface utilities,
furnished by utility owners for design purposes.
• Exercise professional judgment to correlate data from different sources, and to
resolve conflicting information.
• Update (or prepare) plan sheets, electronic files, and/or other documents to
reflect the integration of Quality Level D and Quality Level C information.
• Recommend follow-up investigations (e.g., additional surveys, consultation with
utility owners, etc.) as may be needed to further resolve discrepancies.
• Provide Quality Level C to identify overhead utilities on the project and provide
the overhead utility information on the SUE plan sheets.
Level B (includes tasks as described for Quality Level C)
• Select and apply appropriate surface geophysical method(s)to search for and
detect subsurface utilities within the project limits, and/or to trace a particular
utility line or system.
• Based on an interpretation of data, mark the indications of utilities on the ground
surface for subsequent survey. Utilize paint or other method acceptable for
marking of lines.
• Unless otherwise directed, mark centerline of single-conduit lines, and outside
edges of multi-conduit systems.
• Resolve differences between designated utilities and utility records and surveyed
appurtenances.
• Recommend additional measures to resolve differences if they still exist.
Recommendations may include additional or different surface geophysical
methods, exploratory excavation, or upgrade to Quality Level A data.
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 9 of 11
• As an alternative to the physical marking of lines, the ENGINEER may,with
CITY's approval, utilize other means of data collection, storage, retrieval, and
reduction, that enables the correlation of surface geophysical data to the project's
survey control.
Level A
• Expose and locate utilities at specific locations.
• Tie horizontal and vertical location of utility to survey control.
• Provide utility size and configuration.
• Provide paving thickness and type, where applicable.
• Provide general soil type and site conditions and such other pertinent information
as is reasonably ascertainable from each test hole site.
ASSUMPTIONS
• Level B SUE limits are: fifty (50) feet each direction from the center of the
intersection.
• Up to five (5) Level A test holes are included per intersection.
DELIVERABLES
A. Copies of field survey data and notes signed and sealed by a Registered
Professional Land Surveyor (RPLS) registered in the State of Texas.
B. Drawing of the project layout with dimensions and coordinate list.
C. SUE plan drawings sealed by a Professional Engineer registered in the State of
Texas.
TASK 6. PERMITTING.
ENGINEER will provide permitting support for the CITY to obtain any and all agreements
and/or permits normally required for a project of this size and type, as follows.
6.1 Texas Department of Transportation (TxDOT) Permit
• Meet, negotiate and coordinate to obtain approval of the agency issuing the
agreement and/or permits.
• Completing all forms/applications necessary.
• Submitting forms/applications for CITY and TxDOT review.
• Submitting revised forms for agency review.
• Responding to agency comments and requests.
ASSUMPTIONS
• Permit preparation will begin after approval of the 90% design.
• CITY will pay all costs associated with TxDOT permits.
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 10 of 11
• One(1) meeting is assumed with TxDOT for the TxDOT Permit.
DELIVERABLES
A. None
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services --CITY and
ENGINEER agree that the following services are beyond the Scope of Services
described in the tasks above. However, ENGINEER can provide these services, if
needed, upon the CITY's written request. Any additional amounts paid to the
ENGINEER as a result of any material change to the Scope of the Project shall be
agreed upon in writing by both parties before the services are performed. These
additional services include the following:
• Negotiation of easements or property acquisition.
• Bid phase services.
• Construction Phase Services
• Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre-qualification, bid protests, bid rejection
and re-bidding of the contract for construction.
• Construction management and inspection services
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of
God.
• Services related to warranty claims, enforcement and inspection after final
completion.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Performance of miscellaneous and supplemental services related to the project
as requested by the CITY.
City of Fort Worth,Texas
Attachment A
PMO Release Date 02.06.2015
Page 11 of 11
ATTACHMENT B
COMPENSATION
Design Services for
2014 BOND SUGNALS—YEAR 4, Main and Long
City Project No. 101369
Time and Materials with Rate Schedule Project
I. Compensation
A. The ENGINEER shall be compensated for personnel time, non-labor expenses,
and subcontract expenses in performing services enumerated in Attachment A as
follows:
i. Personnel Time. Personnel time shall be compensated based upon hours
worked directly in performing the PROJECT multiplied by the appropriate Labor
Category Rate for the ENGINEER's team member performing the work.
Labor Category Rate as presented in the rate schedule table below is the rate for
each labor category performing the work and includes all direct salaries, overhead,
and profit.
Labor Category 2018 Rate 2019 Rate
$/hour ($/hour)
Project Director $198.00 $204.00
Project Manager $155.00 $160.00
Project Engineer $120.00 $130.00
E I T $60.00 $75.00
CADD Technician $120.00 $130.00
ii. Non-Labor Expenses. Non-labor expenses shall be reimbursed as Direct
Expenses at invoice or internal office cost.
Direct Expenses (non-labor) include, but are not limited to, mileage, travel and
lodging expenses, mail, supplies, printing and reproduction services, other direct
expenses associated with delivery of the work; plus applicable sales, use, value
added, business transfer, gross receipts, or other similar taxes.
iii. Subcontract Expenses. Subcontract expenses and outside services shall be
reimbursed at cost to ENGINEER plus a markup of ten percent (10%).
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 1 of 4
B-1
ATTACHMENT B
COMPENSATION
iv. Budgets. ENGINEER will make reasonable efforts to complete the work within
the budget and will keep the City informed of progress toward that end so that
the budget or work effort can be adjusted if found necessary.
ENGINEER is not obligated to incur costs beyond the indicated budgets, as may be
adjusted, nor is the City obligated to pay ENGINEER beyond these limits.
If ENGINEER projects, in the course of providing the necessary services, that the
PROJECT cost presented in Article 2 of this Agreement will be exceeded, whether
by change in scope of the project, increased costs or other conditions, the
ENGINEER shall immediately report such fact to the City and, if so instructed by the
City, shall suspend all work hereunder.
When any budget has been increased, ENGINEER's excess costs expended prior
to such increase will be allowable to the same extent as if such costs had been
incurred after the approved increase.
B. The ENGINEER shall be paid monthly payments as described in Section Il -
Method of Payment.
II. Method of Payment
A. The ENGINEER shall be paid by the City based upon an invoice created on the
basis of statements prepared from the books and records of account of the
ENGINEER, based on the actual hours and costs expended by the ENGINEER in
performing the work.
B. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
C. ENGINEER shall prepare and submit invoices in the format and including content
as presented in Exhibit B-1.
D. Payment of invoices will be subject to certification by the City that such work has
been performed.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Transportation and Public Works Department monthly progress reports and
schedules in the format required by the City.
City of Fort Worth,Texas
Attachment 4
PMO Official Release Date:8.09.2012
Page 2 of 4
B-2
ATTACHMENT B
COMPENSATION
IV. Summary of Total Project Fees
Firm Primary Responsibility Fee Amount %
Prime Consultant
Teal Engineering Services, Inc. Project Management, Traffic $28,407.00 51.33
signal Design
Proposed MBE/SBE Sub-Consultants
Hayden Consultants, Inc Surveying, Subsurface Utility $25,665.00 46.37
Engineering
CJ Hensch and Associates, Inc Traffic Volume Data $1.275.00 2.30
Collection
Non-MBE/SBE Consultants
TOTAL $55,347.00 100%
Project Number& Name Total Fee MBE/SBE Fee MBE/SBE
CPN # 101369 $55,347.00 $26,940.00 48.67%
2014 Bond Signals- Year 4
City MBE/SBE Goal = 25% Consultant Committed Goal = 48.67 %
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 3 of 4
B-3
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across desired work types and work phases.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 4 of 4
B-4
Professional Services Payment Request Ploj-t Ma"-ler issenelcevedo,PE„PTCE,PMP Summary
Project: 2014 Bond Signals Year 4 Improvements
City Project#: 101369
City Sec Number: causultentinstructlons:
Fill in green cells including Invoice Number,Fran and To Dates and the included worksheets.
Company Name: Teal Engneenng Services,Inc. When your Invoice is complete,save and close,std 13uusaw and Add your Invoice to the
consultant holder within Project's Felder.
Consultant's PM: Gary DJoat,PE email: geryiostatealengmm
Vendor invoice#: Office Address:2000 Dcn'�.son St— Ste 109”,Denton Telae 7620;
Payment Request#: Telephone: (817)832-4004
From Date: Fax: (940)435-0087
To Date:
Invoice Date: Remit Address:2000 Denison Street,Ste 103,Demon,T-ae 76201
FID No.:
Agreement
Agreement Amendment Amount to Amount Percent ($)Invoiced Current Remaining
Sheet FAC and Work Type Description Amount Amount Date Spell s nt Previousl Invoice Balance
Work Tvae 1 ID.. i 555,34i. A sSS34i. a55 s4i.
Work Type 2
Work Type 3
Work Type 4
Work Type 5
Work Type e
Totals This Payment Request s 3a_m s55.34z00 V,5.34i LID
Overall Percentage Spent
Teal Engineering Services,Inc. 617 632-40x4
940 435-0087 Invoice
2000 Denison Street,Ste 103, 2000 Denison Street,Ste 103,
Denton,Texas 76201 Dernon,Tetras 76201
Consultant Project No.
CFW Project Manager Lissette Acevedo,P.E,PTOE,PMP Proj.Invoice No,
Invoice date:
Consultants Project Manager.crew D Jost,PE
Consultants email: aary instatealeno con. Period From Date
To Date
Name of Project: City Secretary Contract A:
2014 Bond Signals Year 4 Improvements P.O.Number:
Labor Category Name Hours Rate Whirl Amount
Propact Director Caly D Jost 198.00 $0.00
Pro ct Man.er Gery D Jost 155.00 $0.00
Project Engineer Kathleen Jost 120.00 $0.00
EIT NA 60.00 $0.00
CADD Techru— Chir.Quick 120.00 $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$000
$000
Total Labor 0.0 $0.00
Subcontract Service
Hayden an .
CJ Hens.h ch and and ssoc,atiates,Inc.
Subcontractor Subtotal $0.00
10 Percent Markup on Subcontract Services $0.00
Nonlabor Ex enses
Reproduction
Nonlabor Expense Subtotal $0.00
Total Expenses(Subcontract Services+Markup+Nonlabor Expenses) $0.00
TOTAL DUE THIS INVOICE $0.00
Professional Services Payment Request F*IManager LisseaeA—du,PE,PTOE,PMP
Project: 2014 Bond Signals Year 4 Improvements
City Project t: 101369
Work Type Desc: Design Consultantinswcnone:
FIAIC:
City Sec Number. FM In green ceAa IneludMg Percent Complete end I—Mced PreviGusty Ouanitln
Purchase Order. Mien your Invoke Is complete,saw and close,seat 15—and Add year Invoke to the
Conaultenl rower wlthln Prolecrs rower.
Company Name: TealEngloeenngsery es,me
Consultant's PM: Gary O Jost,PE email: Wypt®tealeng.kom
Vendor Invoice is Office Address:20DO Demsen street,Ste 133,Denw,Teaas 76201
Payment Request 0: Telephone: 1817 832-4004
From Date: Fax: (840)435-0087
To Date:
Invoice Date: Remit Address:2000 Demsen Street Ste 103,Deno,n,Taxa.76201
FID No.:
Pay Items Agreement
Agreement Amendment Amendment Amount to Amount Percent (3)Invoiced Current RemlaWng
Description Amount Number Amount Date Spent SDent Previousiv Invoice Balance
30-Desi n Desgn $55347.00 $5534700 $55,347.00
Totals This Unit: $55347.00 56534701 $55.34700
Overall Percentage Spent
Level of Effort Sprealfaheet
TASKMOUR BREAKDOWN
Dealgn SerAm for
2014 BOND WNAL.S-YEAR 4 Main at Lora(TES)
C Pro No.101369
trber
Tuk NO. TW Ota earl Project PCO)IR PrO1eR F17 CADD AOMWArmffre T 0� aWronptrM T� �uc�T God TatSW TaIY
S 61M M• 6126 L WBE I ssen 18E
1.0 Fr. Men enw8 1 38 16 0 6 6Win to
1.1 Mansaing the Team
1. Intimal Team Moseting, 1 5 5 $1,573 /
t OA10C 0 6 $0 1103o
1.2 Cwn-acabone WO Re
I,, PniDesign COmdNaOOn Meetng 3 3
1. Monthly Proisat U dab Meetings 5 5 61375 f0 11,375
Design SuUnOtel Review McRings(7
tj 1 PEER Review 60% 01 3 3 1825 $501
1. Pr ro BeaeOrc 6ctwduIs I 1 7 Sm SD
repro r6hry Ogroa epabw
1. Schedule 5 S St.375 W $1,
1 Prepam MontInly MBF/SBE Ftspoft 5 Jim S
i. bvo' s
2.0 PmlknWmy Design 100 Pmmtl 42 0 ti 0 1 1160
2.1 PW"Wwy DesignDmsl 2 28 52 x8'70 225 175 11
2.2 C-sbuct.Wi Review 9 4
23 Ufi Clearance 2 2
24 Dab COINRhn 4 SOD 11 175 $1 1
25 Pro Decislonlm(SD%) 1 2
2.8 ICaedrucbcn Elhnete tk]% 1 4
3.0 Tinel 6 0 M 1
iml a0(90%)Carmtruclior�Piens and
3.1 5 em0ons 2 3 8 S1.300 1 $1251 1 1
32 Mml 100%Plans and 3 tdBcRlam 2 2 Lo
33 Proiedt DscesmL end 1009b 1 121 1
34 CMMMI WEaOmatee 9096end 100% 1 2 SO
4.0 ROWMawrrnt Service 0 l 4 0
4.1 Rjght-,My Research 2 137 $1 $1,290
42 i rssq Cominctbn Eeaemenle 2 1 f4 31
6.0 Survey and ubeurface Wily
Engineering Services / 0 4 0 • • 10160
5.1 D.C.S—y 0 2 18 fa
5.2 Subau m tAifity Engtneinft(S Net twice 0 2 40 $12.115 112355
6.0 6 4 • •
8.1 4
7Ob1 1.B 2A ••. 0 m .00
Pi
Tclel Hann 1
TOW Law MASS
Tob Eqanse $27,215
MBE/SBE SuOcawlbM
NOIMBEISBE SubmmuNere SD
10% $W WOW801
MBr'SBF 1a01 I aeon 4 7%
TotR COR 3q
CNVOI rel Nblh. —
ACeCcar4 B-te%*of Ellod Srppbmni
PMO Official Rolesa DMe.8.00.2012
1a1
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
2014 Bond Signals Year 4 Improvements
City Project No. 101369
No changes to the Standard Agreement are proposed.
City of Fort Worth,Texas
Attachment C
PMO Release Date:05.19.2010
Page i of I
Consulting Contract Schedule Specifications FORT WORTH
City of Fort Worth Capital Improvement Program
Attachment D-Project Schedule
This PRO(ECT requires a Tier 3 schedule as defined herein and in the City's Schedule Guidance
Document.
Dl. CONSULTING SERVICES SCHEDULE DEVELOPMENT: The CONSULTANT shall
prepare schedules for consulting services that meet the requirements described in this
specification, showing by Critical Path Method (CPM) the planned sequence and timing of
the Work associated with the Agreement. All submittals shall be submitted in PDF format,
and schedule files shall also be submitted in native file format (i.e. file formats associated
with the scheduling software). The approved scheduling software systems for creating the
schedule files are:
- Primavera(Version 6.1 or later or approved by CITY)
- Primavera Contractor(Version 6.1 or later or approved by CITY)
- Microsoft Project(Version 2003/2007 or later or approved by CITY)(PHASING OUT)
D2. BASELINE CONSULTING SERVICES SCHEDULE: Following notice-to-proceed, the
CONSULTANT shall develop, submit and review the draft detailed baseline consulting
services schedule with the CITY to demonstrate the CONSU L l ANT's understanding of the
Agreement requirements and approach for performing the work. The CONSULTANT will
prepare the final detailed baseline consulting services schedule based on CITY comments, if
any, and submit to the CITY no later than the submittal of the first project invoice.
The following guidelines shall be adhered to in preparing the baseline schedule, and as
described in further detail in the CITY's Schedule Guidance Document.
a. The scope shall be subdivided by work breakdown structure (WBS) representing the
tasks,subtasks,and activities associated with delivering the work.
b. The schedule shall accurately describe the major work activities, key milestones, and
dependencies/relationships as appropriate to the work.
c. The schedule should include appropriate meetings, review periods, critical decision
points,including third party utility dependencies and reviewing agencies.
D3. PROGRESS CONSULTING SERVICES SCHEDULE: The CONSULTANT shall prepare
and submit monthly to the CITY for approval the updated schedule in accordance with D1
and D2 and the CITY's Schedule Guidance Document inclusive. As the Work progresses,
the CONSULTANT shall enter into the schedule and record actual progress as described in
the CITY's Schedule Guidance Document.
The updated schedule submittal shall also include a concise schedule narrative that
highlights the following,if appropriate and applicable:
• Changes in the critical path,
• Expected schedule changes,
• Potential delays,
• Opportunities to expedite the schedule,
• Coordination issues the CITY should be aware of or can assist with,
City of Fort Worth,Texas
Attachment D
PMO Release Date:02.15.2011
Page 1 of 2
• Other schedule-related issues that the CONSULTANT wishes to communicate to the
CITY.
D4. PERFORMANCE AND CONSULTING SERVICES SCHEDULE: If the work
accomplished falls behind that scheduled due to factors within the CONSULTANT's
control, the CONSULTANT shall take such action as necessary to improve the progress of
the Work. In addition, the CITY may require the CONSULTANT to submit a revised
schedule demonstrating the proposed plan to make up the delay in schedule progress and
to ensure completion of the Work within the allotted Agreement time.
D5. SCHEDULE TIERS SPECIAL INSTRUCTIONS:
The requirements for the schedule are determined based on the nature and needs of the
project. The schedule tier for this project is stated at the top of this document.
CONSULTANT shall submit each schedule relying on the CITY's current Schedule
Guidance Document.
D6. SCHEDULE SUBMITTAL AND PAYMENT:
As stated in III.A.(1). of the Agreement, CONSULTANT shall provide the information
required by Attachment D. CONSULTANT's monthly invoices will not be accepted and
processed for payment without monthly schedule updates that are submitted in the time
and manner required by Attachment D and the CITY's current Schedule Guidance
Document.
City of Fort Worth,Texas
Attachment D
PMO Release Date 02.15.2011
Page 2 of 2