Loading...
HomeMy WebLinkAboutContract 26756 CITY SECRETARY CONTRACT NO, MARTHA LANE CHANNEL REPAIRS SANDY LANE TO STA.208+00 CITY OF FORT WORTH DEPARTMENT OF ENGINEERING .. KENNETH L.BARR HUGO A.MALANGA,P.E. BOB TERRELL MAYOR DIRECTOR OF TRANSPORTATION CITY MANAGER AND PUBLIC WORKS LEE BRADLEY,JR,P.E. DIRECTOR OF WATER DEPARTMENT A.DOUGLAS RADEMAKER,P.E. DIRECTOR OF ENGINEERING DEPARTMENT a. PREPARED BY: Halff Associates,Inc. Engineers• Scientists• Surveyors 4000 Fossil Creek Boulevard Fort Worth,Texas 76137 1999 q ® � AVO 14725R •' 0 CU1S B. . UNDIII .. ,....• ,A ::.... � i77643�Q �a � GISTS -16, IQ')pC- ',L REC0E,@ CQ�' TABLE OF CONTENTS 1. Part B-Proposal 2. Part C-General Conditions Section C1 - Supplementary Conditions to Section C 3. Part D-Special Conditions(Water Dept.) 4. Part E-Specifications 5. Special Provisions 6. Certificate of Insurance 7. Part F-Bonds Performance Bond(F 1-F2) Payment Bond(F3-F4) Maintenance Bond(F5-F6) 8. Part G-City of Fort Worth Contract(G1-G5) PART B - PROPOSAL TO: CITY MANAGER FORT WORTH, TEXAS FOR: MARTHA LANE CHANNEL REPAIRS SANDY LANE TO STA. 208+00 The undersigned Bidder, having thoroughly examined the Contract Documents, including Plans, Special Contract Documents, the General Contract Documents, the site of the project and understanding the amount of work to be done, and the prevailing conditions, hereby proposes to do all the work, furnish all labor, equipment and material, except as specified to be furnished by the City, which is necessary to fully complete the work as provided in the Plans and Contract Documents, and subject to the inspection and approval of the Director of the Department of Engineering of the City of Fort Worth, Texas; and binds himself upon acceptance of this Proposal to execute a contract and furnish an approved Performance Bond, Payment Bond, Maintenance Bond, and such other bonds, if any, as may be required by the Contract Documents for the performing and completing of the said work. Contractor proposes to do the work within the time stated and for the following sums, to wit: B-1 Martha Lane Channel Repair AVO 14725R Pay Spec Approx. Description of Items with Unit Amount Item Item Quantity (Furnish and install,including all appurtenant work,complete in place,the following items) 1 SP 1 LS Mobilization $ 15,420.0 0 $ 15,420.0 0 Complete in Place for Fiftem TholsErd Fbls Hatted TdantV Dollars& ZED Cents per Lump Sum 2 SP 648 LF Sawcut concrete $ 4. 00 $ 2, 592.00 Complete in Place for `ItnD Zhasard Fiw axrbBd Nir>EAv TWD Dollars& ZEM Cents per Linear Foot 3 104 1,171 SY Remove existing concrete riprap channel $ 5.80 $ 6, 791 .80 520 Complete in Place for Six Th3marl ssm HmJred Ninety Ole Dollars& ELghty Cents per Square Yard 4 104 1,171 SY Dispose existing concrete riprap channel $ 4. 60 $ 5, 386.60 520 Complete in Place for FiNe Thoizwd Thme HaiJred E ighL i SiX Dollars& SiXLY Cents per Square Yard 5 SP 1 LS Plug existing 21"RCP storm drain outfall"A" $ 24'0. 00 $ 240.00 Complete in Place for `ItnD Hx dl ed Ftrty Dollars& ZEM Cents per Lump Sum 6 SP 93 CY Low pressure grout channel floor along south bank $ 161 .40 . $ 15, 010,20 B-2 11/19199 Martha Lane Channel Repair AVO 14725R Pay .. Approx. Description of Items with Unit Amount Item Item Quantity Unit Bid Prices Written in Words , (Furnish and install,including all appurtenant work,complete in place,the following items) Complete in Place for Fifbam Thousand 91131 Dollars& 'lirJPnty Cents per Cubic Yard 7 SP 567 CY Select material for fill $ 25.00 $ 14, 175. 00 Complete in Place for Fburtem gh sard Che Haldred Seventy FbMars& ZEsy Cents per Cubic Yard 8 SP 201 CY Impervious clay cut-off wall $ 25.00 $ 5, 025. 00 Complete in Place for Fi%e Thou sand Wa1ty FYI Dollars& Ze Cents per Cubic Yard 9 SP 105 CY Impervious clay for fill $ 25.00 $ 2, 625. 00 Complete in Place for `IAD Tiol1sxd Six Haxk+ed Duel Fi4E Dollars& ZED Cents per Cubic Yard 10 SP 150 LF Underdrain system for half conc.trapezoidal channel $ 34.00 $ 5, 100. 00 (Sta.201+53 to Sta.203+00) Complete in Place for Fiw Thgx d Che IiI]ked Dollars& Zem) Cents per Linear Foot 11 SP 365 LF Underdrain system for half conc.trapezoidal channel $ :,34.00 $ 12, 410. 00 (Sta.203+00 to Sta.206+65) Complete in Place for B-3 11/19/99 Martha Lane Channel Repair AVO 14725R Pay Spec Approx. Description of Items with Unit Amount Item Item Quantity Unit Bid Prices Written in Words Price Bid (Furnish and install,including all appurtenant work,complete in place,the following items) s-e1Ve`117amai d Flan azrteaTm Dollars& 7EED Cents per Linear Foot 12 SP 1 LS Underdrain system at sta.207+95 $ 1 ,450. 00 $ 1 ,450.00 Complete in Place for Om Thm-sar]d Fcur HXdtBd Fifty Dollars& 7�D Cents per Lump Sum 13 410 320 SY 8"reinf.conc.trapezodial channel floor $ 75. 30. $ 24, 096. 00 400 Complete in Place for `IABIty Ftas Zhomand Ninety Six Dollars& 7em Cents per Square Yard 14 410 851 SY 6"reinf.conc.trapezodial channel sloped banks $ 50.4 0 $ 42, 890.40 400 Complete in Place for Futy No Thmsand Eight Hridred WityDollars& Futy Cents per Square Yard 15 SP 1 LS Remove 42"RCP $ 230.00 $ 230.00 Complete in Place for 5D Hx d[ed Zh71"tY Dollars& 79e[o Cents per Lump Sum 16 SP 1 LS Construct 6x5 box culvert $ 91000. 00 $ 91 000!0 0 Complete in Place for Nine 9hoLISEnd Dollars& 7em Cents B-4 11119/99 Martha Lane Channel Repair AVO 14725R Approx.Pay Spec Item Item Quantity s (Furnish and install,including all appurtenant work,complete in place,the following items) per Lump Sum 17 SP 1 LS Construct headwall for 6x5 box culvert $ 12,400 0 0 $ 12, 400.0 0 Complete in Place for TAph.E Thcusarld FCW Ii rated Dollars& ZSM Cents per Lump Sum 18 SP 45 CY Install 18"grouted rock dprap $ 170.00 $ 7, 650.00 Complete in Place for Seven The sEnd Six HmIt ad Fifty Dollars& YAEM Cents per Cubic Yard 19 SP 650 LF Install membrane and 18"clay layer $ 18.80 $ 12,220.00 Complete in Place for 'IWehe gn3sar d`IW Hxdred Twa ty Dollars& 7A.% Cents per Linear Foot 20 SP 0.7 AC Grade tracts south of channel $ 7,480.00 $ 5,236.00 Complete in Place for FiN a'I7'i0tmod`k),Hatted`I itty"SiX Dollars& BEM Cents per Acre 21 SP 1 LS SS L-5481 aerial crossing repair $ 1 , 950.00 $ 1 ,950. 00 Complete in Place for Cne Tholsm-d Nine Hundred Fifty Dollars& Aey Cents per Lump Sum 22 SP 597 LF Remove,salvage,and replace existing V chain link $ 10. 10 $ 6,029. 70 B-5 11/19/99 Martha Lane Channel Repair AVO 14725R Pay Spec Approx. Description Item Item Quantity Unit Bid Prices Written in Words Price Bid (Furnish and install,including all appurtenant work,complete in place,the following items) fence and fence gates Complete in Place for six Thol3sand`Ite ity MM Dollars& semity Cents per Linear Foot 23 SP 120 CY 6^topsoil $ 19.50 $ 2,340.00 Complete in Place for TAD Thapand'I!ree HjxkedFcrLV Dollars& Ile m Cents per Cubic Yard 24 SP 722 SY Bermuda grass solid block sodding $ 3.30 $ 2,382.60 Complete in Place for `I 9=53d Uxee E4tY tkD Dollars& Sixty Cents per Square Yard TOTAL BID $ 212,650.30- B-6 12,650.30-B'6 11/19/99 Contractor shall, if applicable, identify below the pre-qualified sub-contractor who shall install the water and/or sanitary sewer facilities. Pre-qualified sub-contractor for water and/or sanitary sewer installation. Failure to list a sub-contractor who is pre-qualified by the Water Department shall result in the rejection of the bid as non-responsive. B-7 PART B - PROPOSAL (Cont.) Within ten (10) days after acceptance of this Proposal, the undersigned will execute the formal contract and will deliver an approved Surety Bond and such other bonds as required by the Contract Documents, for the faithful performance of the Contract. The attached bid security in the amount of 5% is to become the property of the City of Fort Worth, Texas, in the event the contract and bond or bonds are not executed and delivered within the time above set forth, as liquidated damages for the delay and additional work caused thereby. The undersigned bidder certifies that he has at least one set of the General Contract Documents and General Specifications for Water Department Projects dated January 1, 1978, and that he has read and thoroughly understands all the requirements and conditions of those General Documents and the specific Contract Documents and appurtenant plans. The undersigned assures that its employees and applicants for employment and those of any labor organization, subcontractors, or employment agency in either furnishing or referring employee applicants to the undersigned are not discriminated against as prohibited by the terms of City Ordinance No. 7278 as amended by City Ordinance No. 7400. Work will not be performed on Sundays or on legal holidays as prescribed by the City Council of the City of Fort Worth for observance by City employees. (Complete A or B below, as applicable:) [] A. The principal place of business of our company is in the State of Nonresident bidders in the State of our principal place of business, are required to be percent lower than resident bidders by state law. A copy of the statute is attached. Nonresident bidders in the State of our principal place of business, are not required to underbid resident bidders. B. The principal place of business of our company or our parent company or majority owner is in the State of Texas. B-8 I (we) acknowledge receipt of the following addenda to the plans and specifications, all of the provisions and requirements of which have been taken into consideration in preparation of the foregoing bid: Addendum No. 1 (initials) Addendum No. 3 (initials) Addendum No. 2 (initials) Addendum No. 4 (initials) Respectfully submitted, Company(Name (ple a print) By: r e ( leas p nt) Sig tur . Title: }� es i Q e vL' (ple se print) .6156 Vesfo, Far �� ' "WStreet Address F" SEAL if Bidder is a Corporation , O� -T4 • 26119 City p State Zip g Date: 1 �' ®o g Y - Phone Number B-9 PART C - GENERAL CONDITIONS TABLE OF CONTENTS NOVEMBER, 1, 1987 TABLE OF CONTENTS C1-1 DEFINITIONS C1-1.1 Definition of Terms C1-1 (1) C1-1. 2 Contract Documents Cl-1 (1) C1-1. 3 Notice to Bidders C1-1 (2) C1-1.4 Proposal C1-1 (2) C1-1.5 Bidder C1-1 (2) C1-1.6 General Conditions C1-1 (2) C1-1. 7 Special Conditions Cl-1 (2) �. C1-1.8 Specifications C1-1 (2) C1-1.9 Bond Cl-1 (2) C1-1.10 Contract C1-1 (3 ) C1-1.11 Plans Cl-1 (3 ) C1-1.12 City Cl-1 (3 ) C1-1.13 City Council Cl-1 (3 ) C1-1.14 Mayor Cl-1 (3) C1-1.15 City Manager C1-1 (3) C1-1.16 City Attorney C1-1 (3) C1-1.17 Director of Public Works Cl-1 (4 ) C1-1. 18 Director, City Water Department C1-1 (4 ) C1-1.19 Engineer C1-1 (4 ) C1-1. 20 Contractor C1-1 (4) C1-1. 21 Sureties i C1-1 (4 ) - C1-1. 22 The Work or Project C1-1 (4) C1-1.23 Working Day Cl-1 (4 ) C1-1.24 Calendar Day C1-1 (4 ) C1-1.25 Legal Holiday C1-1 (4 ) C1-1.26 Abbreviations C1-1 (5) C1-1. 27 Change Order Cl-1 (6 ) .� C1-1. 28 Paved Streets and Alleys C1-1 (6) C1-1. 29 Unpaved Streets and Alleys Cl-1 (6) C1-1. 30 City Streets C1-1 (6) C1-1.31 Roadway Cl-1 (6) C1-1.32 Gravel Street C1-1 (6 ) C2-2 INTERPRETATION AND PREPARATION OF PROPOSAL C2-2.1 Proposal Form C2-2 (1) C2-2. 2 Interpretation of Quantities C2-2 (1) C2-2.3 Examination of Contract Documents and Site C2-2 (2) C2-2. 4 Submitting of Proposal C2-2 (3) C2-2.5 Rejection of Proposals . C2-2 (3) C2-2.6 Bid Security C2-2 (3) �_ (1) C2-2.7 rDelivery of Proposal C2-2 (4 ) C2-2. 8 Withdrawing Proposals C2-2 (4 ) C2-2. 9 Telegraphic Modification of Proposals C2-2 (4 ) C2-2.10 Public Opening of Proposal C2-2 (4 ) C2-2.11 Irregular Proposals C2-2 (4 ) C2-2.12 Disqualification of Bidders C2-2 (5) C3-3 AWARD AND EXECUTION OF DOCUMENTS C3-3.1 Consideration of Proposals. C3-3 (1) C3-3.2 Minority Business Enterpise Women-Owned Business- Enterprise compliance C3-3 (1 ) C3-3.3 Equal Employment Provisions C3-3 (1) C3-3.4 Withdrawal of Proposals C3-3 (2) C3-3.5 Award of Contract C3-3 (2) C3-3.6 Return of Proposal Securities C3-3 (2) C3-3.7 Bonds C3-3 (2) C3-3.8 Execution of Contract C3-3 (4 ) C3-3.9 Failure to Execute Contract C3-3 (4) C3-3.10 Beginning Work C3 C6-6 LEGAL RELATIONS AND PUBLIC RESPONSIBILITY C6-6.1 Laws to be Observed C6-6 (1) C6-6. 2 Permits and Licenses C6-6 (1) C6-6. 3 Patented Devices, Materials and Processes C6-6 (1) C6-6. 4 Sanitary Provisions C6-6 (2) C6-6. 5 Public Safety and Convenience C6-6 (2) C6-6. 6 Privileges of Contractor in Streets, Alleys, and Right-of-Way C6-6 (3 ) C6-6.7 Railway Crossings C6-6 (4) C6-6. 8 Barricades, Warnings and Watchmen C6-6 (4 ) C6-6. 9 Use of Explosives, Drop Weight, etc. C6-6 (5 ) C6-6.10 Work Within Easements C6-6 (6) C6-6.11 Independent Contractor C6-6 (8 ) C6-6.12 Contractor's Responsibility for Damage Claims C6-6 (8 ) C6-6.13 Contractor's Claim for Damages C6-6 (10) C6-6.14 Adjustment of Relocation of Public Utilities, etc. C6-6 (10 ) C6-6.15 Temporary Sewer Drain Connections C6-6 (10) C6-6.16 Arrangement and Charges of Water Furnished by City C6-6 (11) C6-6.17 Use of a Section of Portion of the Work C6-6 (11) C6-6.18 Contractor's Responsibility for Work C6-6 (11) C6-6.19 No Waiver of Legal Rights C6-6 (12) C6-6. 20 Personal Liability of Public Officials C6-6 (12) C6-6. 21 State Sales .Tax C6-6 (12 ) C7-7 PROSECUTION AND PROGRESS C7-7.1 Subletting ' C7-7 (1) C7-7. 2 Assignment -of Contract C7-7 (1) C7-7. 3 Prosecution of the Work C7-7 (1) C7-7.4 Limitations of Operations C7-7 (2) C7-7.5 Character of Workman and Equipment C7-7 (2) C7-7. 6 Work Schedule C7-7 (3 ) C7-7.7 Time of Commencement, and Completion C7-7 (4 ) C7-7. 8 Extension of time of Completion C7-7 (4) C7-7. 9 Delays C7-7 (4) C7-7.10 Time of Completion C7-7 (5) C7-7.11 Suspension .by Court Order C7-7 (6) C7-7.12 Temporary Suspension C7-7 (6) C7-7.13 Termination of Contract due to National Emergency C7-7 (7) C7-7.14 Suspension of Abandonment of the Work and Annulment of Contract C7-7 (7) C7-7.15 Fulfillment of Contract C7-7 (9) C7-7.16 Termination for Convenience of the Onwer C7-7 (10 ) C7-7.17 Safety Methods and Practices C7-7 (13 ) C8-8 MEASUREMENT AND PAYMENT C8-8 .1 Measurement of Quantities C8-8 (1) C8-8. 2 Unit Prices C8-8 (1) (3 ) C8-8. 3 Lump Sum C8-8 (1) C8-8. 4 Scope of Payment C8-8 (1) C8-8.5 Partial Estimates and Retainage C8-8 (2) C8-8 .5 Withholding Payment C8-8 (3 ) C8-8 .7 Final Acceptance C8-8 (3) C8-8. 8 Final Payment C8-8 (3 ) C8-8. 9 Adquacy of Design C8-8 (4) C8-8 .10 General Guaranty C8-8 (4 ) C8-8 .11 Subsidiary Work C8-8 (5) C8-8 .12 Miscellaneous Placement of Material C8-8 (5) C8-8 .13 Record Documents C8-8 (5) (4) ^� PART C - GENERAL CONDITIONS C1-1 DEFINITIONS SECTION C1-1 DEFINITIONS C1-1 . 1 DEFINITIONS OF TERMS : Whenever in these Contract Documents the following terms or pronouns in place of them are used , the intent and meaning shall be understood and interpreted as follows: C1-1 . 2 CONTRACT DOCUMENTS: The Contract Documents are all of the written and drawn documents , such as specifications , bonds , addenda , plans , etc . , which govern the terms and performance of the contract . These are contained in the .. General Contract Documents and the, Special Contract Documents. a. GENERAL CONTRACT DOCUMENTS : The General Contract Documents govern all Water Department. Projects and include the .following items: PART A - NOTICE TO BIDDERS (Sample) White PART B - PROPOSAL (Sample) White PART C - GENERAL CONDITIONS (CITY) Canary Yellow (Developer) Brown PART D - SPECIAL CONDITIONS Green 4 PART E - SPECIFICATIONS E1-White E2-Golden Rod E2A-White PERMITS/EASEMENTS Blue PART F - BONDS (Sample) White PART G - CONTRACT (Sample) White b. SPECIAL CONTRACT DOCUMENTS : The Special Contract Documents are prepared for each specific project as a supplement to the General Contract Documents and include the following items: PART A - NOTICE TO BIDDERS (Advertisement) Same as above PART B'- PROPOSAL (Bid) PART C - GENERAL CONDITIONS -� PART D - SPECIAL CONDITIONS PART E - SPECIFICATIONS PERMITS/EASEMENTS PART F - BONDS PART G - CONTRACT PART H - PLANS (Usually bound separately) -` C1-1 (1) C1-1 . 3 NOTICE TO BIDDERS : All of the legal publications either actually published in public advertising mediums or furnished direct to interested parties pertaining to the work contemplated under the Contract Documents constitutes the �- notice to bidders. C1-1. 4 PROPOSAL: The completed written and signed offer or tender of a bidder to perform the work which the Owner desires to have done, together with the bid security, constitutes the Proposal , which becomes binding upon the Bidder when it is officially received by the Owner, has been publicly opened and read and not rejected by the Owner. C1-1 . 5 BIDDER: Any person , persons , firm, partnership, - company, association, corporation, acting directly or through a duly authorized representative, submitting a proposal for performing the work contemplated under the Contract Documents, - constitutes a bidder. C1-1 . 6 GENERAL CONDITIONS: The General Conditions are the usual construction and contract requirements which govern the performance of the , work so that it will be carried on in accordance with the customary procedure, the local statutes , and requirements of the City of Fort Worth' s charter and •r promulgated ordinances. Wherever there may be a conflict between the General Conditions and Special Conditions , the latter shall take precedence and shall govern. C1-1 . 7 SPECIAL CONDITIONS : Special conditions are the specific requirements which are necessary for the particular project covered by the Contract Documents and not specifically covered in the General Conditions. When. considered with the General Conditions and other elements of the Contract Documents they provide the information which the Contractor and Owner should have in -order to gain a thorough knowledge of _ the project. C1-1. 8 SPECIFICATIONS: The Specifications is that section or part of the Contract Documents which sets forth in detail the requirements which must be met by all materials, construction, workmanship, equipment and services in order to render a completed and useful project. Whenever reference is made to - standard specifications, regulations, requirements , statutes, etc . ,, 'such referred to documents shall become a part of the Contract Documents just as though they were embodied therein. C1-1. 9 BOND: The bond or bonds are the written guarantee or security furnished by the Contractor for the prompt and _ C1-1 (2 ) faithful performance of the contract and include the f ollowing: a. Performance Bond (see paragraph C3-3.7) b. Payment Bond (see paragraph C3-3.7 ) C, Maintenance Bond (see paragraph C3-3.7) d. Proposal or Bid Security (see Special Instructions to Bidders, Part A and C2-2.6 ) C1-1 .10 CONTRACT: The Contract is the formal signed agreement between the Owner and the Contractor covering the mutual understanding of the two contracting parties about the project to be completed under the Contract Documents. C1-1 . 11 PLANS: The plans are the drawings or reproductions - -- therefrom made by the Owner's representative showing - in detail the location, dimension and position of the various, elements of the project , including such profiles , typical cross-sections, layout diagrams, working drawings, preliminary drawings and such supplemental drawings as the Owner may issue to clarify other drawings or for the purpose of showing changes in the work hereinafter authorized by the Owner. The -plans are usually bound separately from other parts of the Contract Documents, but they are a part of the Contract Documents just. as though they were bound therein. C1-1 . 12 CITY: The City of Fort Worth, Texas , a municipal. corporation , authorized and chartered under the Texas State Statutes , acting by and through its governing body or its City Manger , each of which is required by charter 'to perform specific duties . Responsibility for final enforcement of Contracts involving the City of Fort Worth is by Charter vested in the City Manager. The terms City and Owner are synonymous. C1 -1 . 13 CITY COUNCIL: The duly elected and qualified governing body of the City of Fort Worth, Texas. . C1-1 . 14 MAYOR: The officially elected Mayor, or in his absence, the Mayor Pro tem of the City of Fort Worth, Texas. C1-1.15 CITY MANAGER: The officially appointed and authorized City Manager of the City of Fort Worth, Texas , or his duly authorized representative. C1-1:'16 CITY ATTORNEY: The officially appointed City Attorney of the City of Fort Worth, Texas , or his duly authorized representative. Cl-1 (3 ) CI-1 . 17 DIRECTOR OF PUBLIC WORKS: The duly appointed official - of the City of Fort Worth , referred to in the Charter as the City Engineer, or his duly authorized representative. C1-1 . 18 DIRECTOR, CITY WATER -DEPARTMENT: The duly appointed Director of the City Water Department of the City of Fort Worth , Texas , or his duly authorized representative , - assistant, or agents. C1-1 . 19 ENGINEER: The Director of Public Works, the Director of the Fort Worth City Water Department , or their duly authorized assistants , agents , engineers , inspectors, or superintendents , acting within the scope of the particular duties entrusted to them. C1-1 . 20 CONTRACTOR : The person , persons , partnership, company, firm, association , or corporation., entering into a -� contract with the Owner for the execution of the work, acting directly or through a duly authorized representative. A sub-contractor is a person, firm, corporation, or others under _ contract with the principal contractor , supplying •labor and materials or only labor, for work at the site of the pr `-ct. C1-1 . 21 SURETIES: The Corporate bodies which are by such bonds are required with and for the Contract The sureties engaged are to be fully responsible for tae entire and satisfactory fulfillment of the Contract and for any and all requirements as set forth in the Contract Documents and approved changes therein. C1-1. 22 THE WORK OR PROJECT: The completed work contemplated in and covered by the Contract Documents , including but not limited to the furnishing of all labor, materials, tools , equipment, and incidentals necessary to produce a completed and serviceable project. C1-1. 23 WORKING DAY: A working day is defined as a calendar - ay, not including Saturdays, Sundays , and legal holidays , 'in. which the weather or other conditions not under the control of the Contractor permit the performance of the principal unit of Y work for a period of not less than seven (7 ) hours between 7: 00 a.m. and 6 : 00 p.m. , with exceptions as permitted in paragraph C7-7.6. C1-1 . 24 CALENDAR DAYS: A calendar day is any day of the week or month, no days being excepted. C1-1 . 25 LEGAL HOLIDAYS : Legal holidays shall be observed as prescribed by the City Council of the City of Fort Worth for observance by City employees as follows : C1-1 (4) 1. New Year' s Day January 1 2. M. L. Ring, Jr. Birthday Third Monday in January 3. Memorial Day Last Monday in May 4. Independence Day July 4 5. Labor Day First Monday in September 6. Thanksgiving Day Fourth Thursday in November F 7. Thanksgiving Friday Fourth Friday in November 8 . Christmas Day December 25 9. Such other days in lieu of holidays as the City Council may determine _ When one of the above named holidays or a special holiday is declared by the City Council , falls on Saturday, the holiday shall be observed on the preceding Friday or if it falls on Sunday, it shall be observed on the following Monday, by those employees working on working day operations. Employees working calendar day operations will consider the calendar holiday as the holiday. C1-1 . 26 ABBREVIATIONS: Wherever the abbreviations defined herein appear in Contract Documents , the intent and meaning shall be as follows: •AASHTO - American Association of MGD - Million Gallons Per State Highway Transportation Day Officials ASCE - American Society of Civil CFS - Cubic Foot per: Engineers Second LAW - In Accordance With ASTM - American Society of Min. - Minimum Testing Materials Mono. Monolithic AWWA - American Water Works % - Percentum Association R - Radius ASA - American Standards Association I.D. - Inside Diameter HI - Hydraulic Institute O. D. - Outside -' Diameter Asph. - Asphalt Elev.- Elevation Ave. - Avenue F - Fahrenheit Blvd. - Boulevard C - Centigrade CI• - Cast Iron In. Inch CL - Center Line Ft. Foot GI - Galvanized Iron St. - Street Lin. - Linear or Lineal CY - Cubic Yard lb. Pound Yd. - Yard MH - Manhole SY - Square Yard Max. - Maximum L.F. - Linear Foot D.I. - Ductile Iron Cl-1 (5 ) C1 - 1 . 27 CHANGE ORDER : A " Change Order " is a written supplemental agreement between the Owner and the Contractor covering some added or deducted item or feature which may be found necessary and which was not specifically included in the scope of the project on which bids were submitted. Increase in unit quantities stated in the proposal are not the subject matter of a Change Order unless the increase or decrease is more than 25% of the amount of the particular item or items in the original proposal. All "Change Orders " shall be prepared by the City from information as necessary furnished by-the Contractor. C1-1. 28 PAVED STREETS AND ALLEYS : A paved street or alley shall be defined as a street or alley having one of the following types of wearing surfaces applied over the natural unimproved surface: 1. Any type of asphaltic concrete with or without separate base material. 2. Any type of asphalt surface treatment , not including an oiled surface , with or without separate base material. 3 . Brick, with or without separate base material. 4. Concrete, with or without separate base material. 5. Any combination of the above. C1-1 . 29 UNPAVED STREETS OR ALLEYS: An unpaved street, alley, roadway or other surface is any area except those defined above for "Paved Streets and Alleys. " C1-1 . 30 CITY STREETS: A city street is defined as that area between the right-of-way 'lines as the street is dedicated. C1-1 . 31 ROADWAY: The roadway is defined as the area between parallel lines two '( 21 ) feet back of the curb lines or four ( 4 ' ) feet back of the average edge of pavement where no curb - exists . C1-1 . 32 GRAVEL STREET: A gravel street is any unpaved street to which as been--a-d-d-e-a one or more applications of gravel. or similar material other than the natural material found on the .street surface before any improvement was made. C1-1 (6 ) ,. SECTION C - GENERAL CONDITIONS C2-2 INTERPRETATION AND PREPARATION OF PROPOSAL SECTION C2-2 INTERPRETATION AND PREPARATION OF PROPOSAL ~ C2-2 . 1 PROPOSAL FORM: The Owner will. furnish bidders with proposal form, which will contain an itemized list of the items of work to be done or materials to be furnished and upon which bid prices are requested. The Proposal form will state the Bidder ' s general understanding of the project to. be completed, provide a space for furnishing the amount of bid .� security , and state the basis for entering into a formal contract. The Owner will furnish forms for the Bidder ' s "Experience Record, " "Equipment Schedule," and "Financial Statement, " all of which must . be properly executed and filed with the Director of the City Water Department one week prior to the hour for opening of bids. The financial statement required shall have been prepared by an independent certified public accountant or an independent public accountant holding a valid permit issued by an appropriate state licensing agency, and shall have been so prepared as to reflect the current financial status. This statement must be current and not more than one (1) year old. In the case that a bidding date falls within the time a new statement is being prepared, the previous statement shall be updated by proper verification . Liquid assets in the amount of ten (10% ) percent of the estimated project cost will be required. For an experience record to be considered to be acceptable for a given project, it must reflect the experience of the firm seeking qualification in work of both the same nature and magnitude as that of the project for which bids are to be received , and such experience must have been on projects completed not more than five ( 5 ) years prior to the date on which are to be received . The Director of the Water department shall be sole judge as to the acceptability of experience for qualification to bid on any Fort Worth Water Department project. The prospective bidder shall schedule the equipment he has available for the project and state that he will rent such additional equipment as may be required to complete the .� project on which he submits a bid. C2-2. 2 INTERPRETATION OF QUANTITIES : The quantities of work and materials to be furnished as may be listed in the proposal C2-2 (l) forms or other parts of the Contract Documents will be considered as approximate only and will be used for the purpose of comparing bids on a uniform basis. Payment will be made to the Contractor for only the actual quantities of work performed or materials furnished in strict accordance with the Contract Documents and Plans . The quantities of work to be performed and materials to be furnished may be increased or decreased as hereinafter provided , without in any way invalidating the unit prices bid or any other requirements of the Contract Documents. C2-2 . 3 EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF PROJECT: Bidders are advised that the Contract Documents on file with the Owner shall constitute all of the information which the Owner will furnish. All additional information and data which the owner will supply after promulgation of the formal contract documents shall be issued in the form of written - addenda and shall become part of the Contract Documents just as though such addenda were actually written into the original Contract Documents. Bidders are required, prior to the filing of proposal, to read and become familiar with the Contract Documents , * to vis4t the site of the project and examine carefully all local conditions , to inform themselves by their own independent research and investigations, tests, boring, and by such other means as may be necessary to gain a complete knowledge of the conditions which will be encountered during the construction of the project . They must judge for themselves the difficulties of the work and all attending circumstances affecting the cost of doing the work or the time required for its completion, and obtain all information required to make an intelligent proposal. No information given by the Owner or any representative of the Owner other than that contained in the Contract Documents and officially promulgated addenda thereto, shall be binding upon the Owner. Bidders shall rely exclusively and solely upon their own estimates , investigation, research, tests , explorations, and other data which are necessary for full and complete information upon which the proposal is to be based. It is mutually agreed that the submission of a proposal is prima-facie evidence that the bidder' has made the investigations , examinations and tests herein required. Claims for additional compensation due to variations between conditions actually encountered in construction and as indicated in the Contract Documents will not be allowed. The logs of Soil Borings, if any, showing on the plans are for general information only and may not be correct. Neither the C2-2(2 ) Owner nor the Engineer guarantee that the data shown is representative of conditions which actually exist. C2-2 . 4 SUBMITTING OF PROPOSAL: The Bidder shall submit his. Proposal on the form furnished by the Owner. Allblank spaces, applicable to the project contained in the •form shall be correctly filled in and the Bidder shall state the prices , written in ink in both words and numerals , for which he proposes to do the work contemplated or furnishe the materials required. All such prices shall be written legibly. In case of discrepancy between the price written in words and the price written in numerals, the price most advantageous to the City shall govern. If a proposal is submitted by an individual, his or her name must be signed by him (her) or his (her) duly authorized agent. _ If a proposal is submitted by a firm, association , or partnership, the name and address of each member must be given , and the proposal must be signed by a member of the firm, association, or partnership , or by a person duly authorized . If a proposal is submitted by a company or corporation , the company or corporate name and business address must be given, and the proposal signed by an official or duly authorized agent. The corporate seal must be affixed . Power of Attorney authorizing agents or others to sign proposal must be properly certified and must be in writing and submitted with the proposal. C2-2 . 5 REJECTION OF PROPOSALS : Proposals may be rejected if they show any alteration of words or figures , additions not called for , conditional or uncalled for alternate bids , incomplete bids, erasures , or irregularities of any kind, or contain unbalance value of .any items . Proposal tendered or delivered after the official time designated for receipt of proposal shall be returned to the Bidder unopened. C2-2. 6 BID SECURITY: No proposal will be considered unless it is accompanied by a "Proposal Security" of the character and in the amount -indicated in the "Notice to Bidders" and the "Proposal. " The Bid Security is required by the Owner as evidence of good faith on the part of the Bidder, and by way of a guarantyethat if awarded thecontract, the Bidder will within the required time execute a formal contract and furnish the required performance and other bonds. The bid security of- the three lowest bidders will be retained until the contract is awarded or other disposition is made thereof . The bid security of all other bidders may be returned promptly after the canvass of bids. C2-2(3 ) C2-2 . 7 DELIVERY OF PROPOSAL: No proposal will be considered unless it is delivered, accompanied by its proper Bid Security, to the City Manager or his representative in the official place of business as set forth in the "Notice to Bidders . " It is the Bidder ' s sole responsibility.-to deliver the proposal at the proper time to the proper place. The mere fact that a proposal was dispatched will not be considered. .. The Bidder must have the proposal actually delivered. Each proposal shall be in a sealed envelope plainly marked with the word "PROPOSAL," and the name or description of the project as PW designated in the "Notice to Bidders. " The envelope shall be addressed to the City Manager, City Hall, Fort Worth, Texas. C2-2 . 8 WITHDRAWING PROPOSALS: Proposals actually filed with the City Manager cannot be withdrawn prior to the time set for opening proposals . A request for non-consideration of a proposal must - be made in writing , addressed to the City Manager , and filed with him prior to the time set for the opening of proposals. After all proposals not requested for non-consideration are opened and publicly read aloud, the proposals for which non-consideration requests have been properly filed may, at the option of the Owner , be returned unopened. C2-2. 9 TELEGRAPHIC MODIFICATION OF PROPOSALS: Any bidder may modify his proposal by telegraphic communication at any time prior to the time set for opening proposals, provided such telegraphic communication is received by the City Manager prior to the said proposal opening time, and provided further, that the City Manager is satisfied that a written` and duly authenticated confirmation of such telegraphic communication over' the signature of the bidder was mailed prior to the proposal opening time. If such confirmation is not received . g; within forty-eight (48 ) hours after the proposal opening time, " no further consideration will be given to the proposal. C2-2 . 10 PUBLIC OPENING OF PROPOSAL: Proposals which have been .� properly filed and for which no "Non-consideration Request" I has been received will be publicly opened and read aloud by �. k the City Manager or his authorized representative at the time and place indicated in the "Notice to Bidders. " All proposals which have been opened and read will remain on file with the Owner until the contract has been awarded. Bidders or their authorized representatives are invited to be present for the opening of bids. 4 C2-2. 11 IRREGULAR PROPOSALS: Proposals shall be considered as or being "Irregular" if they show any omissions , alterations of form, additions, or conditions not called for, unauthorized alternate bids, or irregularities of any kind. However, the C2-2(4) Owner reserves the right to waive any and all irregularities and to make the award of the contract to the best interest of the City. Tendering a . proposal after the closing hour is an irregularity which cannot be waived. C2- 2 . 12 DISQUALIFICATION OF BIDDERS : Bidders may be disqualified and their proposals not considered for any of , -� but not limited to, the following reason: a. Reasons for believing that collusion exists among •• bidders. b. Reasonable grounds for believing that any bidder is interested in more than one proposal for work F contemplated. C. The bidder being interested in any litigation against the Owner or where the Owner may have a claim against or be engaged in litigation against the bidder. d. The .bidder being in arrearson any existing contract or having defaulted on a previous contract. e. The bidder having performed a prior contract in an unsatisfactory manner. f. Lack of competency as revealed by the financial statement, experience record, equipment schedule , and such inquiries as the Owner may see fit to make. g. Uncompleted work which , in the judgment 'of the Owner, will prevent or hinder the prompt completion of additional work if awarded. h. The bidder not filing with the Owner, one week in advance of the hour of the opening of proposals the following: 1. Financial Statement showing the financial condition of the bidder as specified in Part "A" - Special Instructions. 2. A current experience record showing especially the projects of a nature similar to the one under consideration , which have been successfully- completed by the Bidder. 3. An equipment schedule showing the equipment the bidder has available for use on the project. t The Bid Proposal of a bidder who, in the judgment of the Engineer, is disqualified under the requirements stated herein, shall be set aside and not opened. C2-2(5 ) '■ PART C - GENERAL CONDITIONS C3-3 AWARD AND EXECUTION OF DOCUMENTS SECTION C3-3 AWARD AND EXECUTION OF DOCUMENTS: C3-3 . 1 CONSIDERATION OF PROPOSALS: After proposals have been opened and read aloud, the proposals will be tabulated on the basis of the quoted prices , the quantities shown in the proposal , and the application of such formulas or other methods of bringing items to a common basis as may be established in the Contract Documents. The total obtained by taking the sum of the products of unit prices quoted and the estimated quantities plus any lump sum items and such other quoted amounts as may enter into the cost of the completed project will be considered as the amount of the bid. Until the award of the contract is made by the Owner, the right will be reserved to reject any or all proposals and waive technicalities, to re-advertise for new proposals, or to proceed with the work in any manner as maybe considered for the best interest of the Owner. C3-3 . 2 MINORITY BUSINESS ENTERPRISE/WOMEN-OWNED BUSINESS ENTERPRISE COMPLIANCE: Contractor agrees to provide to Owner , upon request , complete and accurate information regarding actual work performed by a Minority Business Enterprise (MBE) and or a a Woman-owned Business Enterprise (WBE) on the contract and the payment- therefor. Contractor further agrees , upon request by Owner , to allow and audit and/or an examination of any books, records, or files in the possession of Contractor that will substantiate the actual work performed by the MBE or WBE. Any material misrepresentation of any nature will be grounds for termination of the contract and for initiating any action under appropriate federal , state or local laws and ordinances relating to false statements _ further , any such misrepresentation may be grounds for disqualification of Contractor at Owner ' s discretion for bidding on future Contracts with the Owner for a period of �- time of not less than six (6) months. C3-3 .3 EQUAL EMPLOYMENT PROVISIONS: The Contractor shall �. comply with Current City. Ordinance prohibiting discrimination in employment practices. s .. C3-3 (1) The Contractor shall post the required notice to that effect on the project site, and, at his request, will be provided assistance by the City of Fort Worth ' s Equal Employment Officer who will. refer any qualified applicant he may have on file in his office to the Contractor. Appropriate notices may be acquired from the Equal Employment Officer. C3-3 . 4 WITHDRAWAL OF PROPOSALS : After a proposal has been read by the Owner it cannot be withdrawn by the Bidder within forty-five ( 45 ) days after the date on which the proposals were opened. C3-3 . 5 AWARD OF CONTRACT: The Owner reserves the right to withholdfinai action on the proposals for a reasonable time, not to exceed forty-five ( 45 ) days after the date of opening proposals, and in no event will an award be made until. after investigations have been made as to the responsibility of the proposed awardee. The award of the contract, if an award is made, will be to the lowest and best responsible bidder. The award of the contract shall not become effective until the Owner has notified the Contractor in writing of such award. C3-3 . 6 RETURN OF PROPOSAL SECURITIES : As soon as proposed price totals have been determined for comparison of bids , the Owner may, at its discretion, return the proposal security which accompanied the proposals which , in its judgment, would not be considered for the award . All other proposal securities, usually those of the three- lowest bidders , will be retained by the Owner until the required contract has been executed and bond furnished or the Owner has otherwise disposed of the bids, after which they will be returned by the City Secretary. C3-3 . 7 BONDS: With the execution and delivery of the Contract Documents, the Contractor shall furnish to, and file with the Owner in the amounts herein required, the following bonds: a. PERFORMANCE BOND : A good and sufficient performance bond in" an amount not less than 100 percent of the amount of the contract, as• evidenced by the proposal tabulation or otherwise , — guaranteeing the full and faithful execution of the work and performance of the contract, and for the protection of the Owner and all other persons - against damage by reason of negligence of the Contractor , or improper execution of the work or the use of inferior materials . This performance C3-3 (2) bond shall guarantee the payment for all labor , materials, equipment, supplies , and services used in the construction of the work, and shall remain in full force and effect until provisions as above stipulated are accomplished and final payment is made on the project by the City. b. MAINTENANCE BOND : A good and sufficient maintenance bond, in the amount of not less than 100 percent of the amount of the contract, as _ evidenced by the proposal tabulation or otherwise , guaranteeing the prompt , full and faithful performance of the general guaranty which is set forth in paragraph C8-8.10. C. PAYMENT BOND: A good and sufficient payment bond, in an amount not less than 100 percent of the amount of the contract , as evidenced by . the proposal tabulation or otherwise, guaranteeing the prompt, full and faithful payment of all claimants as defined in Article 5160 , Revised Civil Statutes of Texas , 1925 , as amended by House Bill 344 Acts 56th Legislature, Regular Session , 1959 , effective April 27 , 1959 , and/or the latest version thereof, supplying labor and materials in the prosecution of the work provided for in the contract being constructed under these specifications . Payment Bond shall remain in force until all payments as above stipulated are made. d. OTHER BONDS : Such other bonds as may be required by these Contract Documents shall be furnished by the Contractor. No sureties will be accepted by the Owner which are at the time in default or delinquent on any bonds or which are interested in any litigation against. the owner. All bonds - shall be made on the forms furnished by 'the Owner and shall be executed by an approved surety company doing business in the City of Fort Worth, Texas , and which is acceptable to the r owner . In order to be acceptable, the name of the surety shall be -included on the- current U. S . Treasury list of acceptable sureties, and the amount of bond written by any one acceptable company shall not exceed the amount shown on the Treasury list for that company. Each bond shall be properly executed by both the Contractor and Surety Company. .. Should any surety on the contract be determined unsatisfactory at any time by the Owner, notice will be given the Contractor to that effect and the Contractor shall immediately provide a C3-3 (3 ) new surety satisfactory to the Owner. No payment will be made under the contract until the new surety or sureties , as required , have qualified and have been accepted by the --Owner. The contract shall not be operative nor will any payments be -. due or paid until approval of the bonds by the Owner. �C3-3 . 8 EXECUTION OF CONTRACT: Within ten (10) days after the Owner has by appropriate resolution, or otherwise, awarded the = contract, the Contractor shall execute and file with the Owner the Contract and such bonds as may be required in the Contract Documents. No contract shall be binding upon the owner until it has been attested by the City Secretary , approved as to rm and legality by the City Attorney, and executed for tri wher by either the Mayor or City Manager. C3-3 . 9 FAILURE TO EXECUTE CONTRACT : The failure of the Awardee to execute the required bond or bonds or to sign the required contract within ten (10 ) days after the dontract is awarded shall be considered by the Owner as an abandonment of his proposal , and the Owner may annul the Award. By reason of the uncertainty of the market prices of material and labor , and it being impracticable and difficult to accurately determine the amount of damages occuring to the Owner by reason of said awardee ' s failure to execute said bonds and contract within ten ( 10 ) days , the proposal security accompanying the proposal shall be the agreed amount of damages which Owner will suffer by reason of such failure on the part of the Awardee and shall thereupon immediately be forfeited to the Owner. — The filing of a proposal will be considered as an acceptance of this provision by the Bidder. C3-3 . 10 .BEGINNING WORK: The Contractor shall not commence work until authorized in writing to do so by the Owner . Should the Contractor fail to commence work at the site of the project within the time stipulated in the written authorization usually termed the "Work Order" or "Proceed Order" , it is agreed that the Surety Company will , within ten ( 10 ) days after the commencement date set forth in such written authorization, commence the physical execution of the contract. .� C3-3 . 11 INSURANCE: The Contractor shall not commence work under this contract until he has obtained all the insurance required under the Contract Documents, and such insurance has been approved by the Owner. The prime Contractor shall be responsible for delivering to the Owner the sub-contractors ' C3-3 (4) - • certificate of insurance for approval. The prime contractor shall indicate on the certificate of insurance included in the documents for execution whether or not his insurance covers sub-contractors. It is the intention of the Owner that the insurance coverage required herein shall include the coverage of all sub-contractors. - a. COMPENSATION INSURANCE : The Contractor shall maintain , during the life of this contract , Workers ' Compensation Insurance on all of his employees to be engaged in work on the project under this contract, and for all sub-contractors. In case any class of employees engaged in hazardous .. work on the project under this contract is not protected under the Workers ' Compensation Statute, the Contractor shall provide adequate employer ' s general liability insurance for the protection of such of his employees not so protected. b. COMPREHENSIVE GENERAL LIABILITY INSURANCE: The Contractor shall procure and shall maintain during the life of this contract Contractor ' s Comprehensive General Liability Insurance (Public Liability and Property Damage Insurance) in an amount not less than $ 500 , 000 covering each occurrence on account of bodily injury, including death , and in an amount not less than $ 500 , 000 covering each occurrence on account of property damage with $2,000,000 umbrella policy coverage. C. ADDITIONAL LIABILITY: The Contractor shall furnish insurance as separate policies or by additional endorsement to one of the above-mentioned policies, and in the amount as set forth for public liability and property damage, the following insurance: 1. Contingent Liability ( covers General Contractor ' s Liability for acts of sub-contractors) . 2. Blasting, prior to any blasting being done. 3. Collapse of buildings or structures adjacent to excavation ( if excavations are to be performed adjacent to same) . 4. Damage to underground utilities for $500, 000. C3-3 (5 ) i 5. Builder's risk (where above-ground structures are involved) . 6. Contractual Liability ( covers all indemnification requirements of Contract) . d. AUTOMOBILE INSURANCE - BODILY INJURY AND PROPERTY DAMAGE: The Contractor shall procure and maintain, during the life of this Contract, Comprehensive Automobile Liability insurance in an amount not less than $ 250 , 000 for injuries including accidental death to any one person and subject to the same limit for each person an amount not less than $ 500 , 000 on account of• one accident , and — automobile property damage insurance in an amount not less than $100,000. e. SCOPE OF INSURANCE AND SPECIAL HAZARD : The insurance required under the above paragraphs shall provide adequate protection for .the Contractor and his sub-contractors , respectively, against damage _ claims which may arise from operations under this contract, whether such operations be by the insured or by anyone directly or indirectly employed by him, and also against any of the following special hazards which may be encountered in the performance of the Contract. f. PROOF OF CARRIAGE OF INSURANCE: The Contractor shall furnish the Owner with satisfactory proof of coverage by insurance required in these Contract _ Documents in amounts and by carriers satisfactory to the Owner . ( Sample attached. ) All insurance requirements made upon the Contractor shall apply to the sub- contractor , should the Prime t Contractor ' s insurance not cover the sub-contractor's work operations. g• LOCAL AGENT FOR INSURANCE AND BONDING: The insurance and bonding companies with whom the Contractor ' s insurance and performance, payment, maintenance and all such other bonds are written shall be represented by an agent or agents having an office located within the city limits of the C3-3 (6) City of Fort Worth, Tarrant County, Texas . Each such agent shall be a duly qualified, one upon whom service of process may be had , and must have authority and power to act on behalf of the insurance and/or bonding company to negotiate and settle with the City of Fort Worth, or any other claimant, any claims that the City of Fort Worth or other claimant or any property owner who has been . damaged , may have against the Contractor , insurance , and/or bonding company. If the local insurance representative is not so empowered by the insurance or bonding companies, then such authority must be vested in a local agent or claims officer residing in the Metroplex, the Fort Worth-Dallas area. The name of the agent or agents shall be set forth on all of such bonds and certificates of insurance. C3-3 .12 CONTRACTOR ' S OBLIGATIONS: Under the Contract, the Contractor shall pay for all materials , labor and services when due. C3-3 . 13 WEEKLY PAYROLL: A certified copy of each payroll covering payment of wages to all person engaged in work on the project at the site of the project shall be furnished to the Owner's representative within seven ( 7 ) days after the close of each payroll period. A copy or copies of the applicable minimum wage rates as set forth in the Contract Documents shall be kept posted in a conspicuous place at the site of the project at all times during the course of the Contract . - Copies of the wage rates will be furnished the Contractor, by the Owner; however, posting and protection of the wage rates shall be the responsibility of the Contractor. C3-3 . 14 CONTRACTOR' S CONTRACT ADMINISTRATION: Any Contractor, whether a person , persons , partnership , company , firm., association , corporation or other who is approved to do business with and enters into a contract with the City for construction of water and/or sanitary sewer facilities, will have or shall establish a fully operational business office within the Fort Worth-Dallas metropolitan area . The Contractor shall charge, delegate, or assign this office ( or he may delegate his Project Superintendent ) with full authority to transact all business actions required in the performance of the Contract. This local authority shall be made -responsible to act for the Contractor in all matters pertaining to the work governed by the Contract whether it be administrative or otherwise and as such shall be empowered, thus delegated and directed, to settle all material, labor or other expenditures, all claims against the work or any -other C3-3 (7) matter associated such as maintaining adequate and appropriate insurance or security coverage for the project. Such local authority for administration of the work under the Contract shall be maintained until all business transactions executed as part of the Contract are complete. Should the Contractor ' s principal base of operations be other than in the Fort Worth-Dallas metropolitan area, notification of the Contractor ' s assignment of local authority shall be made in writing to the Engineer in advance of any work on the project, all appropriately signed and sealed, as applicable, _ by the Contractor ' s responsible officers with the understanding that this written assignment of authority to a local representative shall become part of the project Contract as though bound directly into the project documents . The intent of these requirements is that all matters associated with the Contractor ' s administration , whether it be oriented• _ in furthering the work, or other, be governed direct by local authority. This same requirement is imposed on insurance and surety coverage. Should the Contractor 's local representative fail to perform to the satisfaction of Engineer', the Engineer, at his sole discretion , may demand that such local representative be replaced and the Engineer may, at his sole discretion , stop all work until a new local authority satisfactory to the Engineer is assigned . No credit of working time will be for periods in which work stoppages are in effect for this reason. _ C3-3 . 15 VENUE : Venue of any action hereinunder, s.hall be exclusively in Tarrant County, Texas. C3-3 (8 ) PART C - GENERAL CONDITIONS C4-4 SCOPE OF WORK SECTION C4-4 SCOPE OF WORK C4-4 . 1 INTENT OF CONTRACT DOCUMENTS : It is the definite intention of these Contract Documents to provide for a complete, useful project which the Contractor undertakes to construct or furnish, all in full compliance with the requirements and intent of the Contract Documents . It is definitely understood that the Contractor shall do all work as provided for in the Contract Documents, shall do all extra or special work as may be considered by the Owner as necessary to complete the project in a satisfactory and acceptable manner. The Contractor shall, unless otherwise specifically stated in these Contract Documents, furnish all labor, tools, materials, machinery, equipment , special services , and incidentals necessary to the prosecution and completion of the project. C4-4 . 2 SPECIAL PROVISIONS : Should any work or conditions which are not thoroughly and satisfactorily stipulated or covered by General or Special Conditions of these Contract Documents be anticipated, or should there be any additional proposed work which is not covered by these Contract Documents, then "Special Provisions" covering all such work will be prepared by the Owner previous to the time of receiving bids or proposals for such work and furnished to the Bidder in the form of Addenda. All such "Special Provisions" shall be considered to be a part of the Contract Documents just as though they were originally written therein. C4-4 . 3 INCREASED OR DECREASED QUANTITIES: The Owner reserves the right to alter the quantities of the work to be performed or to extend or shorten the improvements at any time when and .as found to be necessary, and the Contractor shall perform the work as altered, increased or decreased at the unit prices. Such increased. or decreased quantity shall not be more than 25 percent of the contemplated quantity of such item or items. - When such changes increase or decrease the original quantity of any item or items of -work to be done or materials to be furnished by the 25 `percent or more, then either party to the contract shall .upon, written request to the other party be entitled to a revised consideration upon that portion of the work above or below the 25 percent of the original quantity stated in the proposal; such revised consideration to be determined by special agreement or as hereinafter provided for "Extra Work. " No allowance will be made for any changes in anticipated profits nor shall such changes be considered as C4-4 (1 ) waiving or invalidating any conditions or provisions of the Contract Documents . Variations in quantities of sanitary sewer pipes in depth - categories, shall be interpreted herein as applying to the overall quantities or sanitary sewer pipe in each pipe size, but not to the various depth categories. C4-4 . 4 ALTERATION OF CONTRACT DOCUMENTS: By Change Order, the Owner reserves the right to make such changes in the Contract Documents and in the character or quantities of the work as may be necessary or desirable to insure completion in the most satisfactory manner, provided such changes do not materially alter the original Contract Documents or change the general nature of the project as a whole. Such changes shall not be considered as waiving or invalidating any condition or provision of the Contract Documents. C4-4 . 5 EXTRA WORK: Additional work -made necessary by changes and alterat'i-o-n-s-o-T the Contract Documents or of quantities or for other reasons for which no prices are provided in the Contract Documents, shall be defined as "Extra Work" and shall be performed by the Contractor in accordance with these Contract Documents or approved additions thereto; provided, however, that before any extra work is begun a "Change Order" shall be executed or written order issued by the Owner to do the work for payments or credits as shall be determined by one or more combination of the following methods: a. Unit bid price previously approved. b. An agreed lump sum. C. The actual reasonable cost of (1) labor, (2) rental of equipment used on the extra work for the time so used at Associated General Contractors of America current equipment rental rates ; ( 3 ) materials entering permanently into the project, and (4 ) ,actual cost of insurance , bonds , and social security as determined by the Owner, plus a fixed fee to be agreed upon but not to exceed 10% of the actual cost of such extra work. The fixed fee, is not to include any additional profit to the Contractor for rental of equipment owned by him and - used for the extra work. The fee shall be full and complete compensation to cover the cost of superintendence., overhead, other profit, general and all other expense not included in (1 ) , ( 2 ) , ( 3 ) , and ( 4 ) above. The Contractor shall keep accurate cost records on the form and in the method C4-4 (2) suggested by the Owner and shall give the Owner • access to all accounts , bills , vouchers , and records relating to the Extra Work. No "Change Order" shall become effective until it has been approved and signed by each of the Contracting parties. No claim for Extra Work of any kind will be allowed unless ordered in writing by the Owner . In case any orders- or... instructions , either oral or written, appear to -the Contractor - to involve Extra Work for which he should receive compensation, he shall make written request to the Engineer for written orders authorizing such Extra Work, prior to beginning such work. Should a difference arise as to what does or does not constitute Extra Work, or as to the payment thereof , and the Engineer insists upon its performance, the Contractor shall proceed with the work after making written request for written orders and shall keep .an accurate account of the actual - reasonable cost thereof as provided under method ( Item C ) . Claims for extra work will not be paid unless the Contractor shall file his claim with the Owner within five ( 5 ) days before the time for making the first estimate after such work is done and unless the claim is supported by satisfactory vouchers and certified payrolls covering all labor and materials expended upon the said Extra Work. The Contractor shall furnish the Owner such installation records of all deviations from the original Contract Documents as may be necessary to enable the Own.er to prepare for permanent record a corrected set of plans showing the actual installation. The compensation agreed upon for ' extra work' whether or not iniitiated by a ' change order ' shall be a full, complete and final payment for all costs Contractor incurs as a result or relating to the change or extra work, whether said costs are known, unknown, foreseen or unforeseen at that time, including without limitation, any costs for delay, extended overhead, ripple- or impact cost, or any other effect on changed or unchanged work as a result or the change or extra work. C4-4 . 6 SCHEDULE OF OPERATIONS: Before commencing any work under this contract, the Contractor shall submit to the Owner and receive the Owner ' s approval thereof , a "Schedule of Operations , " showing by a .straight line method the date of commencing and finishing each of the major elements of the contract . There shall be also shown the estimated monthly cost of work for which estimates are to be expected. There C4-4 (3) shall be presented also a composite graph showing the anticipated progress of construction with the time being plotted horizontally and the percentage of completion plotted vertically. The progress charts shall be prepared , on 8-1/2" x 11" sheets and at least five black or blue line prints shall be furnished to .the Owner. C4-4 . 7 PROGRESS SCHEDULES FOR WATER AND SEWER PLANT FACILITIES: Within ten ( 10 ) days prior to submission of first monthly progress payment , the Contractor shall prepare and submit to the Owner for approval six copies of the schedule in which the Contractor proposes to carry on the work, the date of which he will start the several major activities ( including procurement of materials, plans, and equipment) and the contemplated dates for completing the same. The schedule shall be in the form of a time schedule PM Critical Path Method (CPM) network diagram. As the work progresses, the Contractor shall enter on the diagram the actual progress at the end of each partial *payment period or at such intervals as directed by the Engineer. The Contractor shall also revise the schedule to reflect any adjustments in contract time approved by the Engineer. Three copies of the updated schedule shall be delivered at such intervals as directed by the Owner. As a minimum, the construction schedule shall incorporate all work elements and activities indicated in the proposal and in the technical specifications. Prior to the final drafting of the detailed construction schedule, the Contractor shall review the draft schedule with the Engineer to ensure the Contractor's understanding of the contract requirements. The following guidelines shall be adhered to in preparing the construction schedule: a. Milestone dates and final project completion dates shall be developed to conform to time constraints , sequencing requirements and completion time. b. The construction process shall be divided into activities with time durations. of approximately fourteen (14 ) days and construction values not to exceed $50 , 000 . Fabrication , delivery and submittal activities are exceptions to this guideline. C4-4 (4 ) C. Durations shall be in calendar days and normal holidays and weather conditions over the duration of the contract shall be accounted for within the duration of each activity. d. one critical path shall be shown on the construction schedule. e. Float time is defined as the amount of time between the earliest start date and the latest start date of a chain of activities of the CPM construction schedule. Float time is not for the exclusive use or benefit of either the Contractor a or the owner. f. Thirty days_ shall be used for submittal review unless otherwise specified. The construction schedule shall as a minimum be divided into general categories as indicated in the Proposal and Technical Specifications and each general category shall be broken down into activities in enough detail to achieve activities of approximately fourteen (14 ) days duration. For each general category, the construction schedule shall identify all trades or subcontracts whose work is represented by activities that follow the guidelines of this Section. For each of the trades or subcontracts , the construction schedule shall indicate the following procurements , construction and preacceptance activities and events in their logical sequence for equipment and materials. 1. Preparation and transmittal of submittals. 2. Submittal review periods. 3. Shop fabrication and delivery. 4. Erection or installation. 5. Transmittal of manufacturer ' s operation and maintenance instructions. 6. Installed equipment and materials testing. 7. Owner's operator instruction (if applicable) . z 8. Final inspection. C4-4 (5 ) 9 . Operational testing. 10. Final inspection. If , in the opinion of the Owner , work accomplished falls behind that scheduled , the Contractor shall take such action as necessary to improve his progress. In addition, the Owner may require the Contractor to submit a revised schedule demonstrating his program and proposed plan to make up lag in scheduled progress. and to insure completion of the work within the contract time. If the Owner finds the proposed plan not acceptable , he may require the Contractor to increase the work force , the construction ' plant and equipment , the number of work shifts or the overtime operations without additional cost to the Owner. Failure of ,the Contractor to comply with these requirements shall be considered grounds for determination by the Owner that the Contractor is failing to prosecute the work with such diligence as will insure its completion within the time specified. C4-4 (6 ) r PART C - GENERAL CONDITIONS C5-5 CONTROL OF WORK AND MATERIALS • SECTION C5-5 CONTROL OF WORK AND MATERIALS C5-5 . 1 AUTHORITY OF ENGINEER: The work shall be performed to the satisfaction of the Engineer and in strict compliance with the Contract Documents . . He shall decide all questions which arise as to the quality and acceptability of materials furnished , work performed, rate of progress of the work, overall sequence of the construction, interpretation of the Contract Documents, acceptable fulfillment of the contract, compensation, mutual rights between Contractor and Owner under these Contract Documents,- supervision of the work, resumption - of operations, and all other questions or disputes which may arise . Engineer will not be responsible for Contractor ' s means , methods , techniques , sequences or procedures of construction, or the safety precaution and programs incident thereto, and he will not be responsible for Contractor ' s failure to perform the work in accordance with the contract documents . He shall determine the amount and quality of the work completed and materials furnished , and his decisions and •- estimates shall be final. His estimates in such event shall be a condition to the right of the Contractor to receive money due him under the Contract. The Owner shall have executive authority to enforce and make effective such necessary decisions and orders as the Contractor fails to carry out promptly. In the event of any dispute between the Engineer and Contractor over the decision of the Engineer on -any such matters , the Engineer must, within a reasonable time , upon written request of the Contractor, render and deliver to both the Owner and Contractor, a written decision on the matter in controversy. C5-5 . 2 CONFORMITY WITH PLANS: The finished project in all cases shall conform with lines , grades , cross-sections , finish , and dimensions shown on the plans or any other requirements otherwise described in the Contract Documents . Any deviation from the approved Contract Documents required by the Engineer during construction will in 'all cases be s determined by the •Engineer and authorized by the Owner by Change Order. �: C5-5 (1) C5-5 . 3 COORDINATION OF CONTRACT DOCUMENTS: The Contract Documents are made up of several sections , which , taken together , are intended to describe and provide for a complete and useful project, and any requirements appearing in one of the sections is as binding as though it occurred in all sections. In case of discrepancies , figured dimension shall _ govern over scaled dimensions , plans shall govern over specifications, special conditions shall govern over general conditions and standard specifications, and quantities shown on the plans shall govern over those shown in the proposal. The Contractor shall not take advantage of any apparent error or omission in -the Contract Documents , and the Owner shall be permitted to make such corrections or interpretations as may be deemed necessary for the fulfillment of the intent of the Contract Documents. In the event the Contractor discovers an apparent error or discrepancy, he shall immediately call this T condition to the attention of the Engineer. In° the event of a conflict in the drawings, specifications, or other portions of the Contract Documents which were not reported prior to the award of Contract, the Contractor shall be deemed to have quoted the most expensive resolution of the conflict. CS-5 . 4 COOPERATION OF CONTRACTOR: The Contractor will be furnished with three sets of the Contract Documents and shall have available on the site of the project at all times one set of such Contract Documents. The Contract shall give to the work the constant attention necessary to facilitate the progress thereof and'4shall cooperate with the Engineer , his inspector , and other PO Contractors in every possible way. The Contractor shall at all times have competent personnel �. available to the project site for proper performance of the work. The Contractor shall provide and maintain at all times- at the site of the project a competent , English-speaking superintendent and an assistant who are fully authorized to act as the Contractor ' s agent on the 'work . Such superintendent and his assistant shall be capable of reading and understanding the Contract Documents and shall receive and fulfill instructions from the Owner, the Engineer, or his authorized representatives . Pursuant to this responsibility of the Contractor, the Contractor shall designate in writing to the project superintendent, to act as the Contractor ' s agent on the work. Such assistant project superintendent shall -be a resident of Tarrant County, Texas and shall be _ subject -to call, as is the project Superintendent, at any time of the day or night on any day of the week on which the Engineer determines that circumstances require the presence on the project site of a representative of the Contractor to _ C5-5 (2) adequately provide for the safety or convenience of the traveling public or the owners of property across which the project extends or the safety of property contiguous to the project routing. The Contractor shall provide all facilities to enable the Engineer and his inspector to examine and inspect the workmanship and materials entering into the work. C5-5 . 5 EMERGENCY AND/OR RECTIFICATION WORK: When , in the opinion of the Owner or Engineer, a condition of emergency exists related to any part of the work, the Contractor, or the Contractor through his designated representative , shall respond with dispatch to a verbal request made by the Owner or Engineer to alleviate the emergency condition . Such a response shall occur day or night, whether the project is scheduled on a calendar-day or on a working-day basis. Should the Contractor fail to respond to a request from the Engineer to rectify any discrepancies , omissions , or s corrections necessary to conform with the requirements of the project specifications or plans , the Engineer shall give the Contractor written notice that such work or changes are to be performed. The written notice shall direct attention to the discrepant condition and request the Contractor to take remedial action to correct the condition. In the event the Contractor does not take positive steps to fulfill this written request, or does not show just cause for not taking- the proper action, within 24 hours , the City may take such remedial action with City forces or by contract. The City shall then deduct an amount equal to the entire costs for such remedial action, plus 25%, from any funds due .the Contractor on the project. C5-5 . 6 FIELD OFFICE: The Contractor shall provide, at no extra compensation, an adequate field office for use of the Engineer , if specifically called for. The field office shall be not less than 10 by 14 feet in floor area, substantially constructed , well heated , air conditioned, lighted, and weather-proof , so that documents will not be damaged by the elements. C5-5 . 7 CONSTRUCTION STARES: The City, through its Engineer, will furnish the Contractor with all lines , grades , and measurements necessary to the proper prosecution and control of the work contracted for under these Contract Documents , and lines , grades and measurements will be established by means of- stakes or other customary method of marking as may be found consistent with good practice. C5-5 (3 ) These stakes or markings shall be set sufficiently in advance of construction operations to avoid delay . Such stakes or markings as may be established for the Contractor ' s use ori guidance shall be preserved by the Contractor until he is authorized by the Engineer to remove them. Whenever, in the opinion of the Engineer , any stakes or markings have been carelessly or willfully destroyed, disturbed, or removed by the Contractor or any of his employees , the full cost of replacing such stakes or marks plus 25% will be charged against the Contractor, and the full amount will be deducted from payment due the Contractor. C5 -5 . 8 AUTHORITY AND DUTIES 'OF CITY INSPECTORS : City �. Inspectors will be authorized to inspect all work done and to be done and all materials furnished. Such inspection may extend to all or any part of the work, and the preparation or manufacturing of the materials to be used or 'equipment to be installed. A City Inspector may be stationed on the work to report to the Engineer as to the progress of the work and the manner in which it is being performed, to report any evidence +� that the materials being furnished or the work being performed by�Ithe Contractor fails to fulfill the requirements of the Contract Documents , and to call the attention of the �. Contractor to any such failure or other infringements . Such inspection 'or lack of inspection will not relieve the Contractor from any obligation to perform the work in accordance with the requirements of the Contract Documents. In case of any dispute arising between the Contractor and the City Inspector as to the materials or equipment. furnished or the manner of performing the work, the City Inspector will have authority to reject materials or equipment to suspend work until the question at issue can be referred to and be decided by the Engineer . The City Inspector will not , however, be authorized to revoke, alter, enlarge, or release any requirement of these Contract Documents, nor to approve or accept any portion or section 'of the work, nor to issue any instructions contrary to the requirements of the Contract - Documerlts. He will in no case act as superintendent or foreman or perform any other duties for the Contractor, or interfere with the management or operation of the work. He will not accept from the Contractor any compensation in any l form for performing any duties . The Contractor shall regard and obey the directions and instructions of the City Inspector s V or Engineer when the same are consistent with the obligations i of the Contract Documents , provided, however, should the Contractor object to any orders or instructions of the City Inspector,., the Contractor may within six days make written appeal to the Engineer for his decision on the matter in controversy. C5-5 (4 ) C5-5 . 9 INSPECTION: The Contractor shall furnish the Engineer with every reasonable facility for ascertaining whether or not the work as performed is in accordance with the requirements of the Contract Documents . If the Engineer so requests , the f' Contractor shall, at any time before acceptance of the work, remove or uncover such portion of the finished work as may be directed. After examination, the Contractor shall restore: said portions of the work to the standard required by the Contract Documents. ` Should the work exposed or examined prove acceptable, the uncovering or removing and replacing of the covering or making good of the parts removed shall be paid for as extra work, but - should be work so exposed or examined prove to be unacceptable, the uncovering or removing and the replacing of all adjacent defective or damaged parts shall be at the Contractor ' s expense. No work shall be done or materials used without suitable supervision or inspection. C5-5 . 10 REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK: All work, materials , or equipment which has been rejected shall be remedied or removed and replaced in an acceptable- manner by the Contractor at his own expense. Work done beyond the lines and grades given or as shown on the plans , except as herein specifically provided, or any Extra Work done without written authority, will be considered as unauthorized and done at the expense of the Contractor and will not be paid for by the Owner . Work so done may be ordered removed at the Contractor ' s expense. Upon the failure on.._the part of the Contractor to comply with any order of the Engineer made under the provisions of this paragraph, the Engineer will have the authority to cause defective work to be remedied or removed and replaced and unauthorized work to be removed, and the cost thereof may be deducted from any money due or, to become due. to the Contractor . Failure to require the removal of any defective or unauthorized work shall . not constitute acceptance of such works. C5 - 5 . 11 SUBSTITUTE MATERIALS OR 'EQUITMENT : If the Specifications , law, ordinance, codes or regulations permit '- Contractor to furnish or use a substitute that is equal to any material or equipment specified, and if Contractor wishes to furnish or use a proposed substitute, he shall, prior to the preconstruction conference , make written application to ENGINEER for approval of such substitute certifying in writing that'-the proposed substitute will perform adequately the _a functions called for by the general design, be similar and of equal substance to that specified and be suited to the same use and capable of performing the same function as that specified; and identifying all variations of the proposed C5-5 (5) substitute from that specified and indicating available maintenance service . No substitute shall be ordered or installed without the written approval of Engineer who will be the judge of the equality and may require Contractor to _ furnish such other data about the proposed substitute as he considers pertinent . No substitute shall be ordered or installed without such performance guarantee and bonds as Owner may require which shall be furnished at Contractor ' s expense. Contractor shall indemnify and hold harmless Owner and Engineer and anyone directly or indirectly employed by either of them from and against the claims, damages, losses and expenses ( including attorneys fees) arising out of the use of substituted materials or equipment. C5-5 . 12 SAMPLES AND TESTS OR MATERIALS: Where, in the opinion s of the Engineer, or as called for in the Contract Documents , tests of materials or equipment are necessary, such tests will be made at the expense of and paid for direct to the testing agency by the Owner unless otherwise specifically provided. The failure of the Owner to make any tests of materials shall be in no way relieve the Contractor of his responsibility of furnishing materials and equipment fully conforming to the requirements of the Contract Documents. Tests and sampling of materials , unless otherwise specified , will be made in accordance with the latest methods prescribed by the American Society for Testing Materials or specific requirements of the Owner . The Contractor shall provide such facilities as the Engineer may require for collecting and forwarding samples and shall not , without specific written permission of the Engineer, use the materials represented by the samples until tests have been made and the materials approved for use. The _ Contractor will furnish adequate samples without charge to the Owner. In case of concrete, the aggregates , design minimum, and the mixing and transporting equipment shall be approved by the Engineer before any concrete is placed, and the Contactor shall be responsible for replacing any concrete which does not meet the requirements of the Contract Documents. Tests shall be made at least 9 days prior to the placing of concrete , using samples from the same aggregate, cement, and mortar which are to be used later in the concrete. Should the source of supply change, new tests shall be made prior to the use of the new materials. C5-5 . 13 STORAGE OF MATERIALS: All materials which are to be used in the construction operation shall be stored so as to insure the preservation of the quality and fitness of the work. When directed by the Engineer, they shall be placed on wooden platforms or other hard, clean durable surfaces and not on the C5-5 (6 ) ground, and shall be placed under cover when directed. Stored materials shall be placed and located so as to facilitate prompt inspection. C5-5 . 14 EXISTING STRUCTURES AND UTILITIES: The location and dimensions shown on the Plans relative to existing utilities are based on the best information available. Omission from, or the inclusion of utility locations on the Plans is not to be- considered as the nonexistence of, or a definite location of, existing underground utilities . The location of many gas mains , water mains, conduits , sewer lines and service lines for all utilities, etc. , is unknown to the Owner , and the Owner assumes no responsibility for failure to show any or all such structures and utilities on the plans or to show them in their exact location. It is mutually agreed that such failure will not be considered sufficient basis for claims for additional compensation for Extra Work or for increasing the pay quantities in any manner whatsoever, unless an obstruction encountered is such as to necessitate changes in the lines and grades of considerable magnitude or requires the building of special works, provision for which is not made in the Contract Documents , in which case the , provision in these Contract Documents for Extra Work shall apply. It shall be the Contractors responsibility to verify locations of adjacent and/or conflicting utilities sufficiently in advance of construction in order that he may negotiate such. - local adjustments as necessary in the construction process to provide adequate clearances . The Contractor shall take all necessary precautions in order to protect all existing utilities , structures and service lines . Verification of existing utilities, structures and service lines shall include notification of all utility companies at least forty eight _. (48 ) hours in advance of construction including exploratory excavation if necessary. All verification of existing utilities and their adjustment shall be considered as subsidiary work. C5-5.15 INTERRUPTION OF SERVICE:. a. Normal Prosecution: In the normal prosectuion of work where the interruption of service is necessary, the Contractor, at least 24 hours in advance, shall be required to: 1. Notify the Water Department ' s Distribution' Division as to location, time, and schedule of _ service interruption. C5-5 (7 ) 2. Notify each customer. personally through responsible personnel as to time and schedule of the interruption of their service, or 3. In the event that personal notification of a _.. customer cannot be made, a prepared tag form shall be attached to the customer ' s entrance door knob . The tag shall be durable in composition, and in large bold type shall say: "NOTICE" Due to Utility Improvement in your neighborhood, your (water) — (sewer) service will be inter- rupted on between the hours of and This inconvenience will be as short as possible. Thank you, Contractor Address Phone b. Emergency: In the event that an unforeseen service interruption occurs , notice shall be as above,but immediate. C5-5 . 16 MUTUAL RESPONSIBILITY OF CONTRACTORS: If , through acts or.. neglect on the part of the Contractor , any other Contractor or any sub-contractor shall suffer loss or damage on the work, the Contractor agrees to settle with such other Contractor or sub-contractor by agreement or arbitration. If such other Contractor or sub-contractor shall assert any claim against the Owner on account of any damage alleged to have been sustained, the Owner will notify the Contractor , who shall indemnify and save harmless the Owner against any such claim. C5-5 . 17 CLEAN-UP: Clean-up of surplus and/or waste materials accumulated on the job site during the prosecution of the work — under these Contract Documents shall be accomplished in keeping with a daily routine established to the the satisfaction of the Engineer . Twenty-fours fours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the Engineer , if the Contractor fails to correct the C5-5 (8) unsatisfactory procedure, the City may take such direct action as the Engineer deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice, -, and the costs of such direct action , plus 25% of such costs , shall be deducted from monies due or to become due to the Contractor. Upon the completion of the project as a whole as- covered by these Contract Documents , and before final acceptance and final payment will be made, the Contractor shall clean and remove from the site of the project all surplus and discarded materials , temporary structures, and debris of every kind. He shall leave the site of all work in a neat and orderly condition equal to. that which originally existed. Surplus and waste materials removed from the site of the work shall be disposed of at locations satisfactory to the Engineer. The Contractor shall thoroughly clean all equipment and materials installed by him and shall deliver over such materials and equipment in a bright , clean , polished and new appearing condition . No extra compensation will be made to the Contractor for any clean-up required on the project. C5-5 . 18 FINAL INSPECTION: Whenever the work provided for in and contemplated under the Contract Documents has been satisfactorily completed and final cleanup .performed, the Engineer will notify the proper officials of the Owner and request that the Final inspection be made. Such inspection will be made within 10 days after such notification. After such final inspection, if the work and materials and equipment are found satisfactory, the Contractor will be notified in writing of the acceptance of the same after the proper resolution has been passed by the City Council . No time charge will be made against the Contractor between said date of notification of the Engineer and the date of final inspection of the work. C5-5 (9 ) PART C - GENERAL CONDITIONS C6-6 LEGAL RELATIONS AND PUBLIC RESPONSIBILITY _ SECTION C6-6 LEGAL RELATIONS AND PUBLIC RESPONSIBILITY C6-6.1 LAWS TO BE OBSERVED: The Contractor shall at all times observe and comply with all Federal and State Laws and City ordinances and regulations which in any way affect the conduct of the work or his operations, and shall observe and comply with all orders, laws, ordinances and regulations which exist or which may be enacted later by bodies having jurisdiction or _ authority for such enactment. No plea of misunderstanding or ignorance thereof will be considered. The Contractor and his Sureties shall indemnify and save harmless the City and all of its officers , agents, and employees against any and all claims or liability arising from or based on the violation of any such law, ordinance, regulation , or order, whether it be by himself or his employees. C6-6 . 2 PERMITS AND LICENSES: The Contractor shall procure all permits and licenses , pay all charges, costs and fees , and give all notices necessary and incident to the 'due and lawful prosecution of the work. _ C6-6 . 3 PATENTED DEVICES , MATERIALS AND PROCESSES: If the Contractor is required or desires to use any design, device, material , or process covered by letter, patent, or copyright, he shall provide for such use by suitable legal agreement with the patentee or owner of such patent, letter, or copyrighted design . It is mutually agreed and understood that without exception the contract prices shall include all royalties or - cost arising from patents, . trade-marks,__and copy rights in any way involved in the work. The Contractor and his sureties shall indemnify and save harmless the Owner from any and all claims for • infringement by reason of the use of any such patented design , device , material or process , or any trade-mark or copy right in connection with the work agreed to be performed under these Contract Documents , and shall a indemnify the Owner. for any cost, expense, or damage which it may be obliged. to pay, by reason of such infringement at any time during the prosecution of the work or after completion of the work, provided, however, that the Owner will assume the responsibility to defend any and all suits brought for the infringement of .any patent claimed to be infringed upon by the design , type of construction or material or equipment specified in the Contract Documents' furnished the Contractor by the Owner , and to hold the Contractor harmless on account of such suits . C6-6 (1) C6-6 . 4 SANITARY PROVISIONS : The Contractor shall establish and enforce among his employees such regulations in regard to cleanliness and disposal of garbage and waste as will tend to prevent the inception and spread of infectious or contagious diseases and to effectively prevent the creation of a nuisance About the work on any property either public or private, and such regulations as are required by Law shall be put into immediate force and effect by the Contractor. The necessary sanitary conveniences for use of laborers on the work , properly secluded from public observation , shall be constructed and maintained by the Contractor and their use shall be strictly enforced by the Contractor . All such _ facilities shall be kept in a clean and sanitary condition,_ free from objectionable odors so as not to cause a nuisance. All sanitary laws and regulations of the State of Texas and the City shall be strictly complied with. C6-6 .5 PUBLIC SAFETY AND CONVENIENCE: Materials or equipment stored about the work shall be so placed and used, and the work shall at all times be so conducted, as to cause no greater obstruction or inconvenience to the public than is considered to be absolutely necessary by the Engineer. The Contractor is required to maintain at all times all phases of his work in such a manner as not to impair the safety or convenience of the public, including, but not limited to, safe and convenient ingress and egress to property contiguous to the work area. The Contractor shall make adequate provisions to render reasonable ingress and egress for normal vehicular traffic, except during actual trenching or pipe installation -- operations, at all driveway crossings . Such provisions may include bridging, placement of crushed stone or gravel or such other means of providing proper ingress and egress for the property served_by__the driveway as the-Engineer may approve as appropriate. Such other means may include the diversion of driveway traffic, with specific approval by the Engineer. If diversion of traffic is approved by the Engineer at any " location, the Contractor shall make arrangements satisfactory to the Engineer at any location , the Contractor shall make arrangements satisfactory to the Engineer for the diversion of traffic, and shall, at his own expense, provide all materials and. perform all work necessary for the "construction and maintenance of roadways and bridges for such diversion of traffic. Sidewalks must not. be obstructed except by special permission of the Engineer. The materials excavated and the construction materials such as pipe used in the construction of the work shall be placed so as not to endanger the work or prevent free access to all fire hydrants, fire alarm boxes , police call boxes , water valves , C6-6 (2) gas valves , or manholes in the vicinity. The Owner reserves the right to remedy any neglect on the part of the Contractor as regards to public convenience and safety which may come to - its attention , after twenty-four hours notice in writing to. the Contractor, save in cases of emergency when it shall have the right to remedy any neglect without notice, and in either. case, the cost of such work done or. materials. furnished by the Owner or by the -City shall be deducted from monies due or to become due to the Contractor. The Contractor, after approval of the Engineer, shall notify the Fire Department Headquarters, Traffic Engineer, and Police Department, when any street or alley is requested to be closed or obstructed or any fire hydrant is to be made inaccessible, and, when so directed by the Engineer, shall keep any street, streets, or highways in condition for unobstructed use by fire apparatus . The Contractor shall promptly notify the Fire Department Headquarters when all such obstructed streets , alleys, or hydrants are again placed back in service. Where the Contractor is required to construct temporary bridges or make other arrangements for crossing over ditches or streams , his responsibility for accidents in connection with such crossings shall include the roadway approaches as well as the structures of such crossings. = The Contractor shall at all times conduct his operation and the use of construction machinery so as not to damage or destroy trees and shrubs located in close proximity to or on the site of the work. Wherever any such damage may be done , the Contractor shall immediately satisfy all claims of property owners, and no payment will be made by the Owner in settlement of such claims. The Contractor shall file with the Engineer a written statement showing all such claims adjusted. C6-6 . 6 PRIVILEGES OF CONTRACTOR IN STREETS , ALLEYS , AND RIGHT-OF-WAY : For the performance of the contract , the Contractor will be permitted to use and occupy such portions of the public streets and alleys , or other public places or other rights-of-way as provided for in the ordinances of the City , as shown in the Contract Documents , or as may be specifically authorized in writing by the Engineer . A reasonable amount of tools , materials , and equipment for construction purposes maybe stored in such space, but no more than is necessary to avoid delay in the construction operations. Excavated and waste materials shall be piled or stacked in such a way as not to interfere with the use of spaces that may be designated to be left free and unobstructed and so as not to inconvenience occupants of adjacent property . If the street is occupied by railway tracks, the work shall be C6-6 (3 ) carried on in such manner as not to interfere with the operation of trains, loading or unloading of cars, etc . Other contractors of the Owner may, for all purposes required by the contract , enter upon the work and premises used by the Contractor and shall be provided all reasonable facilities and assistance for the completion of adjoining work . Any additional grounds desired by the Contractor for his use shall _ be provided by him at his own cost and expense. C6-6 . 7 RAILWAY CROSSINGS: When the work encroaches upon any right-of-way of any railway, the City will secure the necessary easement for the work. Where the railway tracks are to be crossed , the Contractor shall observe all the regulations and instructions of the railway company as to the methods of performing the work and take all precautions for safety of property and the public. Negotiations with the railway companies for permits shall be done by and through the City. The Contractor shall give the City notice not less than five days prior to the time of his intentions to begin work on that portion of the project which is related to the railway properties . The Contractor will not be given extra or additional compensation for such railway crossings unless specifically set forth in the Contract Documents. C6-6 . 8 BARRICADES WARNINGS AND WATCHMEN: Where the work is carried on in or adjacent to any street, alley , or public place, the Contractor shall at his own expense furnish, erect, and maintain such barricades , fences , lights and danger signals , shall provide such watchmen, and shall take all such other precautionary measures for the protection of persons or property and of the work as are necessary. Barricades and fences shall be painted in a color that will be visible at night, • From sunset to sunrise the Contractor shall furnish and maintain--at least one -easily-visible-burning light at each — barricade. A sufficient number of barricades shall be erected and maintained to keep pedestrians away from, ' and vehicles from being driven on or into, any work under construction or being maintained. The Contractor shall furnish watchmen and keep them at their respective assignments in sufficient numbers to protect the work and prevent accident or damage. All installations and procedures shall be consistent with the provisions set forth in the "1980 Texas Manual on Uniform Traffic Control Devices for Streets and Highways" issued under the authority of the "State of Texas Uniform Act Regulating Traffic on Highways" , codified as Article 6701d Veron' s Civil Statutes, pertinent sections being Section Nos. 27 , 29 , 30 and 31. e C6-6 (4 ) The Contractor will not remove any regulatory sign , instructional sign, street name sign, or other sign which has been erected by the City. If it is determined that a sign must be removed to permit required construction , the Contractor shall contact the Transportation and Public Works department , Signs and Markings Division ( phone number 8780-8075 ) , to remove the sign. In the case of regulatory signs, the Contractor must replace the permanent sign with a temporary sign meeting the requirements of the above _a referenced manual and such temporary sign must be installed prior to the removal of the permanent sign. If the temporary sign is not installed correctly or. if it does not meet the required specifications, the permanent sign shall be left in place until the temporary sign requirements are met. When construction work is completed to the extent that the permanent sign can be re-installed, the Contractor shall again contact the- Signs and Markings Division to the permanent sign and shall leave his temporary sign in place until such re-installation is completed. The Contractor will be held responsible for all damage to the work or the public due to failure of barricades , signs , fences , lights , or watchmen to protect them. Whenever evidence is found ,of such damage to the work the Engineer may order the damaged portion immediately removed and replaced by the Contractor at the Contractor ' s own expense . The Contractor ' s responsibility for the maintenance of barricades, signs, fences and lights , and for providing watchmen shall not cease until the project shall have been completed and accepted by the Owner. No compensation , except as specifically provided in these Contract Documents, will be paid to the Contractor for the work and materials involved in the constructing , providing, and maintaining of barricades , signs , fences, and lights or for salaries of watchmen , for the subsequent removal and - disposal of such barricades , signs , or for any other incidentals necessary for the proper protection., safety, and convenience of the public during the contract period, as this work is considered to be subsidiary to the several items for which unit or lump sum prices are requested in the Proposal. C6-6 . 9 USE . OF EXPLOSIVES , DROP WEIGHT, ETC. : Should the Contractor elect to use explosives, drop weight, etc. , in the prosecution of the work, the utmost care shall be exercised at all times so as not to endanger life or property . The v Contractor shall notify the proper representative of any public service corporation , any company , individual , or utility, and the Owner , not less than twenty-four hours in C6-6 (5 ) advance of the use of any activity which might damage or endanger -their or his property along or adjacent to the work. Where the use of explosives is to be permitted on the project, as specified in the Special Contract Documents , or the use of- explosives is requested, the Contractor shall submit notice to the Engineer in writing twenty-four hours prior to commencing - and shall furnish evidence that he has insurance coverage to protect against any damages and/or injuries arising out of such use of explosives. _ All claims arising out of the use of explosives shall be investigated and a written report made by the Contractor ' s insurers to the Engineer within ten (10) days after receipt of ' written notice of the claim to the Contractor from either the City or the claimant. The City shall proceed to give notice to the Contractor of any such claim. The 'use of explosives may be suspended by the Engineer if any -complaint is received and such use shall not be resumed until the cause of the complaint has been addressed. _ Whenever explosives are stored or kept, they shall be stored in a safe and secure manner and all storage places shall be plainly marked "DANGEROUS EXPLOSIVES" and 'shall be under the care of a competent watchman at all times . All vehicles in which explosives are being transported shall be plainly marked as mentioned above and shall , insofar as possible, not use heavy traffic routes. C6-6 . 10 WORK WITHIN EASEMENTS: Where the work passes over, through, or into private property, the Owner will provide such right-of-way or easement privileges as the City may deem necessary for the prosecution of the work. Any additional rights-of-way or__work area--considered necessary by the Contractor shall be provided by him at his own expense. Such additional rights-of-way or work area shall be acquired for the benefit of the City . The City shall be notified in _ writing as to the .rights so acquired before work begins in the affected area. The Contractor shall not enter upon private property for any purpose without having previously obtained permission from the owner of such property. The Contractor will not be allowed to store equipment or material on private property unless and until the specified approval of the property owner has been secured in writing by the Contractor and a copy furnished to the Engineer. Unless specifically provided otherwise , the Contractor shall clear all rights-of-way or easements of obstructions which must be removed to make possible proper prosecution of the work as a part of the project construction operations. The Contractor shall be responsible for the preservation of and shall. use C6-6 (6 ) every precaution to prevent damage to all trees , shrubbery, plants, lawns , fences, culverts , curbing , and all other types of structures or improvements , to all water, sewer, and gas lines, to all conduits, overhead pole lines , or appurtenances thereof, including the construction of temporary fences, and to all other public or private property along adjacent to the work. The Contractor shall notify the proper representatives of owners or occupants of public or private lands or interest in lands which might be affected by the work. Such notice shall be made at least 48 hours in advance of the beginning of the work. Notices shall be applicable to both public and private utility companies or any corporation, company, individual , or other , either as owners or occupants , whose land or interest in land might affected by the work. The Contractor shall be - responsible for all . damage or injury to property of any character resulting from any act , omission , neglect , or misconduct in the manner or method or execution of the work, or at any time due to defective work, material, or equipment. When and where any direct or indirect or injury is done to public or private property on account of any act, omission , neglect, or misconduct in the execution of the work, or in consequence of the non-execution thereof on the part of the Contractor, he shall restore or have restored at his own cost s and expense such property to a condition at least equal to that existing before such damage or injury was done, by repairing, rebuilding, or otherwise replacing and restoring as may be directed by the Owner , or he shall make good such damages or injury in a manner acceptable to the owner of the property and the .Engineer. All fences encountered and removed during construction- of this project shall be restored to the original . or a better than original condition upon completion of this project. When wire fencing, either wire mesh or barbed wire is to be crossed, the Contractor shall set cross braced posts on either side of permanent easement before the fence is cut . Should additional fence cuts be necessary, the Contractor shall provide cross braced posts at point of the proposed cut in addition to the cross braced posts provided at the permanent easements limits, before the fence is cut. Temporary fencing shall be erected in place of the fencing removed whenever the work is not in progress and when the site is vacated overnight, and/or at all times to prevent livestock from entering the construction area. The cost for fence removal, temporary closures and replacement shall be subsidiary to the various items bid in the project C6-6 (7 ) proposal. Therefore, no separate payment shall be allowed for any service associated with this work. In case of failure on the part of the Contractor to restore such property to make good such damage or injury, the Owner may, upon 48 hour written notice under ordinary circumstances, and without notice when a nuisance or hazardous condition results , proceed to repair, rebuild, or otherwise restore such property as may be determined by the Owner to be necessary, and the cost thereby will be deducted from any monies due or to become due to the Contractor under this Contract. C6-6 . 11 INDEPENDENT CONTRACTOR: It is understood and agreed y the parties hereto that Contractor shall perform all work and services hereunder as an independent ,contractor, and not as an officer , agent , servant or employee of the Owner . Contractor shall have exclusive control of and the exclusive right to control the details of all the work and services . performed hereunder, and all persons performing same, and shall be solely responsible for the acts and omissions of its officers , agents , servants , employees , contractors , subcontractors , licensees and invitees . The doctrine of respondeat superior shall not apply as between Owner and Contractor, its officers , agents , employees , contractors and subcontractors , and nothing herein shall be construed as creating a partnership or joint enterprise between Owner and Contractor. C6-6 . 12 CONTRACTOR ' S RESPONSIBILITY FOR DAMAGE= CLAIMS : Contractor covenants and agrees to, and does hereby indemnify, hold harmless and defend owner , ' its officers , agents , servants, and employees from and against any an all claims or suits for property damage or loss and/or personal injury, - including death, to any and all persons, of -whatsoever kind or .character , whether real or asserted, arising out of or in connection with, directly or indirectly, the work and services to be performed hereunder by Contractor, its officers, agents, employees, contractors, subcontractors, licensees or invitees , whether or not caused , in whole or in part , by alleged negligence on the part of officers , agents , servants , ►� employees, contractors, subcontractors, licensees and invitees of the* owner; and said Contractor does hereby covenant and agree to assume all liability and responsibility of Owner, its officers agents, servants and employees for property damage or loss , and/or. personal injuries, including death, to any and all persons of whatsoever kind or character, whether real or asserted, arising out of or in connection with, directly or indirectly, the work and services to be performed hereunder by Contractor , its officers , agents employees , contractors , subcontractors, licensees and invitees , whether or not caused, C6-6 (8 ) in whole or in part , by alleged negligence of officers , agents , servants , employees , contractors , subcontractors , licensees or invitees of the Owner. Contractor likewise covenants and agrees to, and does hereby, indemnify and hold harmless Owner from and against any and all injuries,loss or damages to property of the Owner during the performance of any _. of the terms and conditions of this Contract, whether arising out of or in connection with or resulting from, in whole or in part , any and all alleged acts or omissions of officers , agents , servants , employees , contractors, subcontractors , licenses, or invitees of the Owner. In the event a written claim for damages against the contractor or its subcontractors remains unsettled at the time all work on the project has been completed to the satisfaction- of the Director of the Water Department, as evidenced by a - final inspection,. final payment to the Contractor shall not be recommended by the Director of the Water Department for a period of 30 days after the date of such final inspection, unless the Contractor shall submit written evidence `- satisfactory to the Director that the claim has been settled and a release has been obtained from the claimant involved. - If the claim concerned remains unsettled as of the expiration of the above 30-day period, . the Contractor may be deemed to be entitled to a semi-final payment for work completed, such - semi-final payment to be in an amount equal to the total dollar amount then due less the dollar value of any written claims pending against the Contractor arising out of the performance of such work, and such semi-final payment may then be recommended by the Director. The Director shall not recommend final payment to a Contractor against whom such a claim for damages is outstanding for a period of six months following the date of the acceptance of the work performed unless the Contractor submits evidence in writing satisfactory to the Director that: 1. The claim has been. settled and a release has been obtained from the claimant. involved, or 2. Good faith efforts have been made to settle such outstanding claims , and such good faith efforts - have failed. If condition (1) above is met at any time within the six month - period, the Director shall recommend that the final payment to the Contractor be made. If condition (2 ) above is met at any time within the six month period, the Director may recommend that the final payment to the Contractor be made. At the C6-6 (9 ) expiration of the six month period the Director may recommend that final payment be made if all other work has been performed and all other obligations of the Contractor have been met to the satisfaction of the Director. The Director may, if he deems it appropriate, refuse to accept on bids on other Water Department Contract work from a Contractor against whom a claim for damages is outstanding as a result of work performed under a City contract. C6-6 . 13 CONTRACTOR'S CLAIM FOR DAMAGES: Should the Contractor claim compensation for any alleged damage by reason of the .. acts or omissions of the Owner, he shall within three days after the actual sustaining of such alleged damage, make 'a written statement to the Engineer, setting out in detail the nature of the alleged damage, and on or before the 25th day of the month succeeding that in which any such .damage is claimed to have been sustained, the Contractor shall file with the Engineer an itemized statement of the details and amount of such alleged damage and, upon request, shall give the Engineer access to all books of account, receipts, vouchers, bills of lading, and other books 'or papers containing any evidence as to the amount of such alleged damage. Unless such statements shall be filed as hereinabove required, the Contractor ' s claim for compensation shall be waived, and. he shall not be entitled to payment on account of such damages. C6-6 . 14 ADJUSTMENT OR RELOCATION OF PUBLIC UTILITIES. ETC. : In case it is necessary to change , move , or alter in any mow manner the property of a public utility or others, the said property shall not be moved or interfered with until orders thereupon have been issued by the Engineer. The right is reserved to the owners of public utilities to enter the ~ geographical--limits of-"the Contract for the purpose of making such changes or repairs to their property that may be necessary by the performance of this contract. C6-6 . 15 TEMPORARY SEWER AND DRAIN CONNECTIONS: When existing sewer lanes have to be taken up or removed, the Contractor shall , at his own expense and cost, provide and maintain temporary outlets and connections for all private or public drains and sewers. The Contractor shall also take care of all sewage and drainage which will be received from these drains and sewers , and for this purpose he shall provide and maintain, at his own cost and expense , adequate pumping facilities and temporary outlets or diversions. The Contractor , at his own cost and expense, shall construct such troughs, pipes, or other structures necessary, and be prepared at all times to dispose of drainage and sewage C6-6 (10) = received from these temporary` connections until such times as the permanent connections are built and are in service. The existing sewers and connections shall be kept in service and maintained under the Contract, except when specified or ordered to be abandoned by the Engineer. All water, sewage, and other waste shall be disposed of in a satisfactory manner so that no nuisance is created and so that the work under- construction will be adequately protected. C6-6 . 16 ARRANGEMENT AND CHARGES FOR WATER FURNISHED BY THE CITY: When the Contractor desires to use City water in connection with any construction work, he shall make complete and satisfactory arrangements with the Fort Worth City Water Department for so doing. City water furnished to the Contractor shall be delivered to the Contractor from a connection on an existing City main . All piping required beyond the point of delivery shall be installed by the Contractor at his own expense. s The Contractor ' s responsibility in the use of all existing fire hydrant and/or valves is detailed in Section E2-1. 2 USE OF FIRE HYDRANTS AND VALVES in these General Contract Documents. When meters are used to measure the water, the charges , if - any, for water will be at the regular established rates . When meters are not used , the charges , if any, will be as prescribed by the City Ordinance , or where no ordinance _ applies , payment shall be made on estimates and rates established by the Director of the Fort Worth Water Department. C6-6 . 17 USE OF A SECTION OR PORTION OF THE WORK:_- Whenever, .-in the opinion of the Engineer, any section or portion of the work or any structure is in suitable condition, it may be put into use upon the written order of the Engineer , and such usage shall not be held to be in any way an acceptance of said work or structure or any part thereof or as a waiver of any of the provisions of these Contract Documents. All necessary repairs and removals of any section of the work so put into use, due to defective materials or workmanship, equipment, or = to deficient operations on the part of the Contractor , shall be performed by the Contractor at his own expense. C6-6 . 18 CONTRACTOR ' S RESPONSIBILITY FOR THE WORK: Until written acceptance by the Owner as provided for in these' Contract Documents , the work shall be under the charge and care of the Contractor, and he shall take every necessary precaution to prevent injury or damage to the work or any part C6-6 (11) thereof by action of the elements or from any cause whatsoever, whether arising from the execution or nonexecution of the work. The Contractor shall rebuild, repair, restore, and make good at his own expense all injuries or damage to any portion of the work occasioned by any of the hereinabove causes. , .C6-6 . 19 NO WAIVER OF LEGAL RIGHTS: Inspection by the Engineer or any order by the Owner by payment of money or any payment for or acceptance of any work, or any extension of time, or any possession taken by the City shall not operate as a waiver of any provision of the Contract Documents. Any waiver of any breach or Contract shall not be held to be a waiver of any other or subsequent breach. ' The Owner reserves the right to correct any error that may be discovered in any estimate that may have been paid and to adjust the same to meet the requirements of the Contract Documents. C6-6. 20 PERSONAL LIABILITY OF PUBLIC OFFICIALS: In carrying out the provisions of these Contract Documents or in exercising any power of authority granted thereunder, there shall be no liability upon the authorized representatives of the Owner , either personally or otherwise as they are agents and representatives of the City. C6--6 . 21 STATE SALES TAX: On a contract awarded by the City of Fort Worth, an organization which qualifies for exemption .pursuant the provisions of Article 20 . 04 (H) of the Texas Limited Sales, excise, and Use Tax Act, the Contractor may purchase, rent or lease all materials, supplies and equipment used or consumed in the performance of th.is contract by issuing to his supplier an exemption certificate in lieu of -tax,--said exemption certificate to comply with State Comptroller ' s Ruling . 007 . Any such exemption certificate / issued by the Contractor in lieu of the tax shall be subject to and shall comply with the provisions of State Comptroller's i Ruling. . 011, and any other applicable State Comptroller ;. rulings pertaining to the Texas Limited Sales, Excise, and Use Tax Act. On a contract awarded by a developer for the construction of a publicly-owned improvement in a street right-of-way or other easement which has been dedicated to the public and the City of Fort Worth, an organization which qualifies for exemption pursuant to the provisions of Article 20.04 (E) of the Texas limited Sales , Excise, and Use Tax Act, the Contractor can probably be exempted in the same manner stated above. C6-6 (12 ) Limited Sale, Excise and Use Tax permits and information can be obtained from: Comptroller of Public Accounts Sale Tax Division Capitol Station Austin, TX C6-6 (13 ) PART C - GENERAL CONDITIONS C7-7 PROSECUTION AND PROGRESS SECTION C7-7 PROSECUTION AND PROGRESS: C7-7 . 1 SUBLETTING: - The Contractor shall perform with his own organization, and with the assistance of workman under his immediate super intendance, work of a value of not less than - fifty (50$) percent of the value embraced in the contract. If the Contractor sublets any part of the work to be done under these Contract Documents, he will not under any circumstances be relieved of the responsibility and obligation assumed under these Contract Documents . All transactions of the Engineer will be with the Contractor . Subcontractors will be considered only in the capacity of employees or workmen of the Contractor and shall be subject to the same requirements as to character and competency. The Owner will not recognize any subcontractor on the work. The Contractor shall at all times, when the work is in operation, be represented either in person or by a superintendent or other designated representatives. �.. C7-7 . 2 ASSIGNMENT OF CONTRACT : The Contractor shall not assign, transfer, sublet, convey, or otherwise dispose of the contract or his rights , title, or interest in or to the same or any part thereof without the previous consent of the Owner expressed by resolution of the City Council and concurred in by the Sureties. . If the Contractor. does, without such previous. consent, assign, transfer, sublet, convey, or otherwise dispose of - the contract or his right, title, or interest therein or any part thereof, to any person or persons, partnership , company , firm, or corporation, or does by bankruptcy, voluntary or involuntary,. or by assignment under the insolvency laws of any state , attempt to dispose of the contract may, at the option of the 4 Owner be.- revoked and. annulled , unless the Sureties shall successfully complete said contract, and in the event of any such revocation or annulment, any monies due or to become due under or by virtue of said contract shall be retained by the Owner as liquidated damages for the reason that it would be " impracticable and extremely difficult to fix .the actual -. damages. C7-7 . 3 -PROSECUTION OF THE WORK: Prior to beginning any construction operation , the Contractor shall submit to the Engineer in five or more copies, if requested by the Engineer, a progress schedule preferably in chart or diagram form, or a brief outlining in detail and step by step the manner of C7-7 (1) prosecuting the work and ordering materials and equipment which he expects to follow in order to complete the project in the scheduled time . There shall also be submitted a. table of estimated amounts to be earned by the Contractor during each monthly estimate period. The Contractor shall commence the work to be performed under this contract within the time limit stated in these Contract Documents and shall conduct the work in a continuous manner and with sufficient equipment, materials , and labor as is necessary to insure its completion within the time limit. The sequence requested of all construction operations shall be at all times as specified in the Special Contract Documents . Any deviation from scuh sequencing shall be submitted to the Engineer for his approval. Contractor shall not proceed with any deviation until he has received written approval from the Engineer. Such specification or approval by the Engineer shall not relieve the Contractor from the full responsibility of .the complete performance of the Contract.- - The contract time may be changed only as set forth in Section C7-7.8 "Extension of Time of Completion" of this Agreement, and a progress schedule shall not constitute a change in the contract time. C7-7 . 4 LIMITATIONS OF OPERATIONS: The working operations shall at all times be conducted by the Contractor so as to create a minimum amount of inconvenience to the public. At any time when, in the judgment of the Engineer, the Contractor has obstructed or closed or is carrying on operations in a portion of a street or public way greater than is necessary for the proper execution .of the work, the Engineer may require the Contractor to finish - the section on which operations are in • progress before the work is commenced on any additional section or street. ;f C7-7 . 5 CHARACTER OF WORKMEN AND EQUIPMENT: Local labor shall be used by the Contractor. is available. The Contractor may bring in from outside the City of Fort Worth his key men and his superintendent. All other workmen, including equipment operators , may be imported only after the local supply is exhausted . The Contractor shall employ only such superintendents , foremen , and workmen who are careful , competent, and fully qualified to perform the duties or tasks assigned to them, and the Engineer may demand and secure the summary dismissal of any person or persons employed by the Contractor in or about or on the work who, in the opinion of the Owner , shall misconduct himself or be found to be incompetent , disrespectful , intemperate , dishonest , or C7-7 (2) otherwise objectionable or neglectful in the proper performance of his or their duties, or who neglects or refuses to comply with or carry out the directions of the Owner, and such person or persons shall not be employed again thereon without written consent of the Engineer. All workmen shall have sufficient skill , ability , and experience to properly perform the work assigned to them and operate any equipment necessary to properly carry out the performance of the assigned duties. The Contractor shall furnish and maintain on the work all such equipment as is considered to be necessary for prosecution of the work in an acceptable manner and at a satisfactory rate of progress . All equipment , tools , and machinery used for handling materials and executing any part of the work shall be subject to the approval of the Engineer and shall be maintained in a satisfactory , safe and efficient working condition. Equipment on any portion of the work shall be such that no injury to the work, workmen or adjacent property will - result from its use. C7-7. 6 WORK SCHEDULE: Elapsed working days shall be computed starting with the first day of work completed as defined in C1-1 . 23 "WORKING DAY"' or the date stipulated in the "WORK . ORDER" for beginning work, whichever comes first. Nothing in these Contract Documents shall be construed as prohibiting the Contractor from working on Saturday, Sunday or Legal Holidays, providing that the following requirements are met: a. A request to work on a specific Saturday, Sunday or Legal Holiday must be made to the Engineer no later than the proceeding Thursday. b. Any work to be done on the project on such a specific Saturday, Sunday or Legal Holiday must be, in the opinion of the Engineer, essential to the timely completion of the project. The Enginee'r ' s decision shall be final in response to such a request for approval to work on a specific Saturday, Sunday or Legal Holiday, and no extra compensation shall be allowed to the Contractor for any work performed on such a specific Saturday, Sunday or Legal Holiday. Calendar Days shall be defined in C1-1. 24 and the Contractor may work as he so desires. C7-7 (3 )