Loading...
HomeMy WebLinkAboutContract 49322-CO1 FORT WORTH., City of Fort Worth CITY SECRETARY .� Change Order Request Breakdown CONTRACTNO, ....--- Project Namel Precinct Line Road Streetlight Improvements City Sec# 1 49322 Client Project#(s)l 00147 Change Order Submittal# 0 Date 1/22/2018 Dept. T/PW Water Sewer Contract Time Totals CD Original Contract Amount $77,875.07 $0.00 $0.00 $77,875.07 90 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $77,875.07 $0.00 $0.00 $77,875.07 90 Amount of Proposed Change Order $15,872.29 $0.00 $0.00 $15,872.29 0 Revised Contract Amount $93,747.36 $0.00 $0.00 $93,747.36 90 Original Funds Available for Change Orders $488,154.00 $6,250.00 $5,750.00 $500,154.00 Remaining Funds Available for this CO $488,154.00 $6,250.00 $5,750.00 $500,154.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 20.38% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $97,343.84 JUSTIFICATION (REASONS)FOR CHANGE ORDER - This change order is required to remove and replace 4 piers along Trinity Boulevard west of Precinct Line Road at Station Nos. 107+40.22, 109+43.62, 111+43.93,and 113+49.00.These foundations were previously installed by TxDOT's contractor and have bent anchor bolts. Additional Traffic Control Plans sealed by a professional engineer are also required for this construction work.Plans and details are linked in Buzzsaw. FORT WORTH City of Fort worth Change Order Additions Project Name Precinct Line Road Streetlight Improvements City Sec# 49322 Client Project# 00147 Change Order Submittal# 0 Date 1/22/2018 ADDITIONS ty unit Unit Cost I ota ier ep acements 471.001 Traffic ontrol Plan for Pier Replacement with Engineer Seal T.W 1, 95.00 T/PW $15,872.29 Water $0.00 Sewer $0.00 Sub Total Additions 15,872. Change Order Additions Page 1 of 1 0609#300 L64Z-N 9LZZZ-X SNtl7d NOLLVNIWO77i GVOE HNI7 IONIODUJ QVOZI aRii S,DmDud e 8 o o O z o� WQ �w oP3 O oa uzi iac r$% �� fid" N N �_4w� n W 0 m w� - - O atag W Y ~L J07 Z O H o �a _ ILS 3- L - zF- 0- OF- d o rn w LLjw o_ ax a �zu Om o O v n ¢ vimnm O z IL1 0 ~' o �" mm =rwim LL¢ v "� W _ " �+ aha�^n� >y Q Z, Ma- .2m kE��y o y O O 0- o z L1 - J S�'o mvl _ - n^r�is Fa- R I'- FJ O o Q u wOw N - O " : i.,Nm im S z W LL Q II _ o - pU � WAHP. � L ~ O R 5 �8Zwam � . a� 2'm oux z �O : > 3 U 3m o s �.. om 'a N= J ' o Q o o o 41 1I q cz - z o' 1 OS+OII 3NI1H0.1Vw - W D / I °o _--- ZZ gS 133HS 33S) m ;M +ill 3NIlHO1VW � --- wo s I-- I J L) I I aw w 1 Iz o I ° Z o z F TD d � 2 I moo❑ Ile 1 Sawe4i - o zo o � I I j 0 I - xo OS+OII 3NIlH <o Olyw i o _ w S � Wm �o ° oo QFW Change Order Approval COAppr-01 Page 1 of 3 Routing Assigned To: Due Date: Assigned By: Due Time: Links 2 fortworthgov/Infrastructure Proiects/00147 - Precinct Line Road Streetlight Improvements/Contractor/Change Orders/00147 - Change Order 1 1-22-18.xlsm fortworthgov/Infrastructure Proiects/00147 - Precinct Line Road Streetlight Improvements/Contractor/Change Orders/Precinct Line Road Streetlight Change Order #1 Plans 1-22-18.pdf Attachments(0) F- No Attachments have been added to this form. J QM123CP4 6 o/�°"Fo 2418 'ATS OFFICIAL RECORD `0 ,,,?y CITY�� r CITY SECRETARY FT.WORTH,TX https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessId=5372&ActiveF... 3/26/2018 QFW Change Order Approval COAppr-01 Page 2 of 3 FORT WORTH(,, city of Fort Worth Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.:11 Change Order No.: COAppr-01 Date Started: 2018-03-12 City Sec. No.:149322 �� Date Due: 2018-03-23 —� Project Name:lPrecinct Line Road Streetlight Improvements Project Numbers: 00147 IDOE Numbers: 6090 = Project Construct streetlight improvements on Precinct Line Road from Description: TRE Railroad to Concho Trail and on Trinity Boulevard from Thames Trail to 400 ' east of Precinct Line Road. Project/Contract Compliance Michael Weiss City Inspector:JDarryl Ruffin +-�--f Manager: Contractor:IStandard Utility Construction, Inc. COUNCIL ACTION (If Required): M&C Log Name: M&C Number:I � I M&C Date: COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: TPW $$ 15s 5,872:29 1111139403 0200431 5740010 C00147 C�C� -77 Total Cost: $__15,872291 Total Requested Days:10 Contract Compliance Manager: Approval Status: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. OFFICIAL RECORD gl"e CITY SECRETARY Michael Weiss,P.E. FT.WORTHp TX Senior Professional Engineer https://projeetpoint.buzzsaw.com/ bz web/Forms/FomiPrint.aspx?SiteId=51500&ProcessId=5372&ActiveF... 3/26/2018 QFW Change Order Approval COAppr-01 Page 3 of 3 .Approved: Yes Comments: User: Marc Martinez Date: 2018-03-12 7:45 PM Approved: Yes Comments: User: Michael Weiss Date: 2018-03-12 2:50 PM Approved: Yes Comments: User: Marc Martinez Date: 2018-03-13 1:15 PM Approved: Yes Comments: User: Michael Weiss Date: 2018-03-13 8:17 AM Approved: Yes Comments: User: JoAnne Kamman Date: 2018-03-14 1:22 PM Approved: Yes Comments: .`LZ 'User: Ricardo Matute A.tta-S aby: Date: 2018-03-15 8:50 AM P�H Maty ��. Kay ecru F 0 Approved: Yes 0�• RT� .Comments: �� •.O� User: Doug Wiersig U Date: 2018-03-19 10:55 AM iS Approved: YesA Comments: &C._ - User: Doug Black Date: 2018-03-20 3:23 PM 1295._ Approved: Yes ,Comments: User: Susan Alanis ,Date: 2018-03-26 12:09 PM &OFFICIALECORD ETARY� Action Required: https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessId=5372&ActiveF... 3/26/2018