HomeMy WebLinkAboutContract 49565-CO1 CITY SECRETARY, /n zz
FORT WORTH City of Fort Worth CONTRACT NO. -"1�
Change Order Request
(D P . .
IA)At Name: Marine Creek Interceptor Improvements Phase I,Part 1 City Sec No.: 1 49565
woR�
c\��c FOr {No.(s): 59607-0700430-CO2223-C01783 DOE No. 7214 City Proj.No.: 02223
Project Description: Pipe enlargement to upgrade and replace an existing deteriorated sanitary sewer main located within the Marine Creek Basin beginning
from Bowman Roberts Road/Cromwell Marine Creek Road
Contractor: William J.Schultz,Inc.Circle C Construction,Co. Change Order# Date: 1 3/19/2018
City Project Mgr. Roberto C.Sauceda,P.E. City Inspector: Virginia Garcia
Phone Number: 817-392-2387 Phone Number: 817-223-2259
Dept. Sewer Totals Contract Time
(Calendar days)
Original Contract Amount $1,634,700.00 $1,634,700.00 320
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,634,700.00 $1,634,700.00 320
Amount of Proposed Change Order $56,400.00 $56,400.00 030
Revised Contract Amount $1,691,100.00 $1,691,100.00 350
Original Funds Available for Change Orders $81,800.00 $81,800.00
Remaining Funds Available for this CO $81,800.00 $81,800.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 3.45%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,043,375.00
JUSTIFICATION FOR CHANGE ORDER
The change order will provide for the replacement of a 188 foot segment of a project sewer main by other
than open cut(BOTC) instead of rehabilitating the segment via pipe enlargement. During construction it was
determined that the identified line segment was not contained within the dedicated easement. BOTC will
allow for the main to be installed within the easement.The existing line segment will be grouted and
abandoned once the replacement main is in service.Open cut installation is not feasible due to the location of
the pipe segment on Huffines Boulevard.
Staff concurs with the contractor` equest for 30 additio Iendar days on the change order.
F
A b • off....�!4T
ary J. ay er, ity S
It is understood and agreed that the acceptance of this Change 0 Ctor con es an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or in o e hares
Order.
Contractor's Name Contractor.Name _,Contractor Signa l
William J.Schultz,Inc.Circle C Construction,Co. Teri Skelly
Date Project Ma ger ---
cvt c� 3.do
t., Date on 'tr ion Supervisor Mater CiA
Date Assistantft
(2-3Tf3
Council Acboriffitat to
M&C Number N/A M&C Date Approved IF MOCRETARY
FC�►RT WORTH City of Fort Worth
Change Order Additions
Project Name Marine Creek Interceptor Improvements Phase I,Part 1 City Sec No.: 49565
Project No.(s): 59607-0700430-CO2223-CO1783 DOE No. 7214 City Proj.No.: 1 02223
Project Pipe enlargement to upgrade and replace an existing deteriorated sanitary sewer main located within the Marine Creek
Description Basin beginning from Bowman Roberts Road/Cromwell Marine Creek Road
Contractor William J.Schultz,Inc.Circle C Construction,Co. Change Order:= Date: 3/19/2018
City Project Mgr. Roberto C.Sauceda,P.E. City Inspector Virginia Garcia
ADDITIONS
Tobi,
36 24-inch PVC Sewer Line Installed BOTOC Sewer 188.00 LF $700.00 $131,600.00
Sewer $131,600.00
Page 2 of 4 Additions Sub Total 1$131,600.00
FC►RT WORTH City of Fort Worth
4V WOW— Change Order Deletions
Project Name Marine Creek Interceptor Improvements Phase I, Part 1 City Sec No.: 49565
Project No.(s): 59607-0700430-CO2223-CO1783 DOE No. 7214 City Proj.No.: 02223
Project Description Pipe enlargement to upgrade and replace an existing deteriorated sanitary sewer main located within the Marine
Creek Basin beginning from Bowman Roberts Road/Cromwell Marine Creek Road
Contractor William J. Schultz, Inc.Circle C Construction,Co. Change Order: 0 Date 3/19/2018
City Project Mgr. Roberto C.Sauceda,P.E. City Inspector: Virginia Garcia
DELETIONS
ITEM DESCRIPTION DEPT Unit Unit Cost Total
20 18"to 24"Pipe Enlargement Sewer 188.00 LF $400.00 $75,200.00
Sewer $75,200.00
Page 3 of 4 IDeletions Sub Total $75,200.00
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
Co# DATE AMOUNT
Total $0.00
Page 4 of 4
FORT WORTH
Contract Compliance Manager
By signing I acknowledge that I am the person responsible for the monitoring and administration of this
contract,including ensuring all ormance and reporting requirements.
S'gnature
Roberto C. Sauceda,P.E.
Name of Employee
Water Department-Engineering
Department
Senior Professional Engineer
Title
817-392-2387
Phone
Date
OFFICIAL RECORD
CITY SECRETARY
FT.WORTNI TX