HomeMy WebLinkAboutContract 48212-A1 AMENDMENT No . 1 CITY SECRETARY _ C®NTRACT N0. 4tau-L TO CITY SECRETARY CONTRACT WHEREAS, the City of Fort Worth (CITY) and Kennedy/Jenks Consultants, Inc. , (ENGINEER) made and entered into City Secretary Contract No. 48212, (the CONTRACT) which was authorized by M&C C-27917 on the 13th day of September, 2016 in the amount of $256, 616.00; and WHEREAS, the CONTRACT involves engineering services for the following project: Sanitary Sewer Rehabilitation, Contract 97 (City Project No. CO2739) ; and WHEREAS, it has become necessary to execute Amendment No. 1 to the CONTRACT to include an increased scope of work and revised fee. NOWTHEREFORE, CITY and ENGINEER, acting herein by and through their duly authorized representatives, enter into the following agreement, which amends the CONTRACT: 1 . Article I of the CONTRACT is amended to include the additional engineering services specified in a proposal dated February 15, 2018, a copy of which is attached hereto and incorporated herein. The cost to City for the additional design services to be performed by Engineer totals $87 ,785 .00 . 2 . Article II of the CONTRACT is amended to provide for an increase in the fee to be paid to Engineer for all work and services performed under the Contract, as amended, so that the total fee paid by the City for all work and services shall be an amount of $346,401 . 00 3. All other provisions of the Contract, which are not expressly amended herein, shall remain in full force and effect. EXECUTED and EFFECTIVE as of the date last written by a signatory, below. OFFICIAL,RECORD c��rsF�9rr�,o CITY 80CRIKTARY Page -1- FT�WOR 111 TX APPROVED: ENGINEER City of Fort Worth Kennedy/Jenks Consultants, Inc. , Jesus J. Chapa Kathy Fre 11, P.E. Assistant City Manager Principal DATE: DATE: APPROVAL RECOMMENDED: Christopher Harder, P.E. Assistant Director, Water Department Contract Compliance Manager: By signing, I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Name of Emplo Title: Project Manager APPROVED AS TO FORM AND LEGALITY: M&C: N/A Qvla�-- Date N/A Douglas W. Black Senior Assistant City At ��-�w ATTEST: A. �� r` U Z�' M r J. ys r City SecretaryAS OFFICIAL RECORD CITY SECRETARY Page -2- WORTHs TX Kennedy/Jenks Consultants Engineers&Scientists Texas Registration Number F-1341 777 Main Street,Suite 600 Fort Worth,TX 76102 817-887-8051 15 February 2018 Robert Sauceda, P.E. City of Fort Worth, Water Department 1000 Throckmorton Street Fort Worth, TX 76102 Subject: Sanitary Sewer Rehabilitation Contract 97 Amendment Request, CS#48212 City Project No.: 02739 K/J 1645003.00 Dear Mr. Sauceda, Kennedy/Jenks and our subconsultant have completed the conceptual design and survey tasks for the aforementioned project executed under City of Fort Worth Project No. 01793, and agreement executed on 27 September 2016. We verbally discussed the prospect for a budget amendment to cover out-of-scope work identified during the conceptual design. As discussed at our 30 percent design review meeting,we are hereby submitting a formai request for a budget augmentation. Budget Augmentation A summary of out-of-scope items by task is provided below, Tasks 3.0 and Task 4.0-Additional Plan and Profile Sheets and Additional Design (Sub-tasks 3.1.3, 3.1.5.4, 4.1.1, 4.2.1, 4.3.1) The following additional design effort has been identified for this project. 1. Segment M-191 Village Creek: The City requested approximately 170 additional feet of sewer line rehabilitation to be added to this segment. This request will add an additional plan and profile.sheet and will increase the design effort to complete. Refer to the Conceptual Design Report, Figures 8 and 8A for added length. 2. Segment M-191 Dillard/Berry(open-cut approach): The scoped design approach for Segment M-191 is rehabilitation utilizing pipe bursting. Based upon the findings summarized in the Conceptual Design Report, the agreed-upon approach for this segment is open-cut to divert the flow from sanitary sewer Segment M-191 to Segment M-170A. The open-cut approach requires more detailed design than the original pipe burst ap roach. The OFFICIAL RECORD p:1201811695003.00_fortwaMconbad97102enhnlvagmts12.0t-rlmeontaftudgetaugemenfetiauq.tlwntrxtemendnenLadditlonaLmw_fnal2.15.18.doc CITY��CRIrrAR I7.WORY'M,TX Kennedy/Jenks Consultants Robert Sauceda, P.E. 15 February 2018 Page 2 Dillard/Berry intersection is highly congested with existing utilities and it is expected additional enlarged plan and/or details will likely be required. 3. Additional Plan and Profile Drawings: The level-of-effort for this project submitted to the City includes preparation of a total of 40 design drawings, including 24 plan and profile drawings. Please note Kennedy/Jenks assumptions included in Design Services Agreement, Attachment A, page 9 of 15. In accordance with the project samples provided during 30 percent, the plan and profile drawings will be set-up at a 20-scale. The anticipated number of plan and profiles sheets required for the project is 37. Please refer to the attached Sheet Index developed for the project. A total of 53 drawing are estimated for the project. Accordingly, the associated effort for the additional 13 plan and profile sheets required for the project is included in this subtask. The level-of-effort associated with the development of 13 additional plan and profile drawings and additional design services is $51,830.This includes effort for preliminary (60 percent, $30,675) and final design (90 and 100 percent, $21,155), additional effort for sheet by sheet opinion of probable construction costs (OPCC), and reproduction costs for additional sheets for each submittal. The City Standard Agreement, Article IV.D, indicates Mylar drawings are required. The level-of- effort (LOE) breakdown (Exhibit B-2) included in our contract does not include reproduction costs to cover Mylar printing of final drawings. As such, the cost to provided final Mylar drawings has been added as Task 4.2.1.1 in the attached Level of Effort spreadsheet. Task 5.1.6- Conformed Specifications and Drawings This task includes incorporating all addenda into the contract document and issuing conformed sets of contract documents. Attachment A of our Design Services contract for this project includes this task item; however, the level-of-effort associated with this task is not accounted for in the level-of-effort(LOE) breakdown (Exhibit B-2) included in our contract. For this reason, the effort associated with issuing confirmed documents (including additional plan and profile sheets) is included in this amendment request. The level-of-effort associated with preparing conformed documents is $3,540 including reproduction costs. Task 6.2.1— Record Drawings(Additional 13 Sheets) This task includes the additional effort associated with preparation of record drawings for an additional 13 sheets. The level-of-effort associated with this task is $740. Task 7.3 Temporary Right-of-Entry Preparation and Submittal The hours and effort included in our agreement for Right-of-Entry Documents, Task 7.1 (refer to Exhibit B-3, Level of Effort Spreadsheet) includes 5 labor hours of effort. This task and associated effort was intended for right-of-entry coordination with our surveyor for the purposes of acquiring right-of-entry from the property owners in order to survey facilities located in residential back yards. The labor hours were not intended to cover the effort required to prepare Temporary Right-of-Entry (TROE) documents to be included in the contract documents for use during construction. Per the City's requirements, the TROE documents for construction require p: 016\1645003.00_fort worth contract 97\02-cntrctsagmts12.01-primcontracttudgetaugementationno.t\contract amendment_additionalsow_final 2.15.18.doc Kennedy/Jenks Consultants Robert Sauceda, P.E. 15 February 2018 Page 3 preparation of forms for each property owner to sign as well as a figure for each TROE document. We anticipatea total of 30 TROE's will be required for this project. The level-of-effort associated with development of 30 TROE documents for construction purposes and associated coordination is $10,560. Task 8.1.1 Additional Design Survey Additional survey requirements for this project have been identified during the conceptual design phase. A summary of the additional design survey items is provided below. 1. Segment M-191 Village Creek: The City requested approximately 170 additional feet of sewer line rehabilitation to be added to this segment. Additional survey to encompass the area added to this segment (extending from the upstream end of initial segment alignment to Burton Avenue) is required. 2. Segment M-191 Dillard/Berry (open-cut approach): The scoped design approach for Segment M-191 is rehabilitation utilizing pipe bursting. As such, the area required for pipe bursting of this segment was surveyed. Based upon the findings summarized in the Conceptual Design Report, the agreed-upon approach for this segment is open-cut to divert the flow from M-191 to Segment M-1 70A. The open-cut approach requires additional survey to encompass the open-cut diversion area in E. Berry Street. For reference refer to the Conceptual Design Report, Figure 14A. 3. Segment L-3289: Arial survey was performed for this segment since it is primarily located in residential back yards. Supplemental on the ground survey for this segment consisted of locating existing manholes within residential backyards and surveying the manhole locations and flow lines. Ground survey efforts were unable to locate a manhole shown on record drawings to be at a critical horizontal bend. The potential absence of this manhole will require a pit to be excavated for CIPP (insertion/extraction pit at the bend) and a manhole to be installed at this horizontal bend location. Additional detailed on the ground survey is required to accurately show existing facilities (fence locations, backyard structures, etc.) where this pit and new manhole will be located. Two (2) large trees have also been identified in close proximity to the anticipated pit location and will likely be impacted. The supplemental survey will include a tree survey of the adjacent trees. Additional on the ground survey for this segment would encompass the area shown on the attached Figure 5A. 4. Survey of Segment L-3291: This segment was added to the overall project by the City on May 9, 2016. The survey costs associated with this additional segment were inadvertently not accounted for in the level-of-effort for the project submitted to the City. 5. Survey of utilities to be potholed: The conceptual design investigations for the project revealed several locations where potholing of existing utilities is recommended; primarily for locating gas lines in close proximity to the segments. A total of 16 potential pothole locations have preliminary been identified. It is expected the location of these requested potholes will be refined during 60 percent design and potholed by the City prior to commencing 90 p:120W1W003.00_fortworth contract 97102-cntrctsagmts12.01-primcontractlbudgetaugementatonno.ticontract amendment_add'itionalsow_final 2.15.18.doc Kennedy/Jenks Consultants Robert Sauceda, P.E. 15 February 2018 Page 4 percent design. The scope-of-work for this survey item includes survey of the exposed utilities once the utilities are exposed. The daily rate for this item is $1,720. A total of three (3) days are budged for this task for a total of$5,160. The level-of-effort associated with the additional design survey as described herein is $21,115. This cost includes associated coordination effort and five (5) percent subconsultant mark-up. Attached to this request is our subconsultant's (Shield Engineering Group) cost for the additional survey (please note the cost of survey for potholes in this attachment is a daily rate). A summary of the requested budget augmentation for this project is provided in Table 1 below. TABLE 1 BUDGET AUGMENTATION SUMMARY Task Additional Effort Task 3.0 Preliminary Design (60 Percent) -Additional Plan and $30,675 Profile Sheets and Additional Design Task 4.0 Final Design-Additional Plan and Profile Sheets and $21,155 Additional Design Task 5.1.6 Conformed Specifications and Drawings $3,540 Task 6.2.1 Record Drawings (Additional 13 Sheets) $740 Task 7.3 Temporary Right-of-Entry Preparation and Submittal $10,560 Task 8.1.1 Additional Design Survey $21,115 Requested Budget Augmentation $87,785 Total Adjusted Contract Amount $346,401 The total requested budget augmentation to cover the items included herein is $87,785. Attached to this letter is the revised Exhibit B-2, Level of Effort Spreadsheet. Thank you for giving us the opportunity to serve the City of Fort Worth. We look forward to receiving approval for this request. If you have any questions or require additional information, please contact me at 817-733-0488. Very truly yours, KENNEDYMENKS CONSULTANTS Kathy Fretwell, P.E. Principal cc: Tony Sholola, City of Fort Worth p:1201611645003.00_fort oath contract 9A02cntrctsagmts12.01-primcontrachbudgetaugementabonno.11contract amendment addtonalsow_final 2.15.18.doc 0000000 0 0 muco n �o MMMMMMM <» M ,Itc J m oo� ri a � cn N `o Y r w m H d O O O O O O O O O O O M M M EA M M M O O A N x N w U N 0 OM OM O O a O 00 N !9 M W M M M w J 'O O O. d: p O O O O fA M H N fA d 7 d � N ~ C d a x UJ m0 0 w w 0 c � m c o w 2 U ON N OM a w NCo 3 o 0 0 o 0 0 0 O O m N O EO N O O O a0 tAMMMMM M M N h m h R N 00 o J N cs 2 N O W M W M m U 0 V > w df io i+ C Z O C r3 Urn -�o p a- a �� c-, O O D m(0 N N O m N m 0 N N m C lJ.l V ZO U ►� !n Q' > p XWO O = d) d) d t 41 CO 0 3U m iAo u �mc�i � a N ai m d J Fa- N J w ca Y •N �.Eo0 O O R M.-- N N � N N � d Ery .F.E a c w oU exp .�C7 c Q a` d N 10 a N O. C d Q' L O N ui n w v LU do Crn t in v a O p 3 cn a v a m0 o a 2 c d A c m O M C O w CO n U L V Q In N O ¢ dC r d Y C c O� a m m N d u p 1 °� C N O a N F d 0: O U N jp 0 d rr (n O °a 3 'o a a ma o c ° r0 ` N c O c 14 w o ° m m v o 2 >m w❑ d E c"v U E an d E (p d 0 l9 C T C3 ._ ' .�C C C d y f- d N W c tT O O�C w N d d d c N O C N C C 0 O rO0_.0 O)�OeO Fadi d ?'m� Uza a0i m Ew m aai a and l o w U E C E d m 00 m 0_2 U U a cnO U¢a d _ (V fM tV M < b M D tl!0 0 0 ����t9�'T O `� �� w o w o m e m o u m N r N ip t0 1 , a M m m d m U) c M °' o H X N d W F 2 o E P-- 0 T E O d C E J O c of oN y =J d 7 N a U X O M J N @ d x OO C0 U m U a mO F d N O > > a t° `a ° owm w d a J Lu Lu o U Z a N v u d d o � d H C ~ d Lu w w wo m C mz _d C J O C Z o w uo m a w m m m ) IYl Oi Ci O>' � 0 0 0 0 0 0 0 0 0 o` a vv m my a .nom m U 0 t� f- Q1 O o v vo o v U - t6 W y s � Urn v co, Q m0"-' o co mco m mo om (D Y N;F, O O.11.1 v w p w 0: ,E .:z O U) L d o 00 0o U W Q C1 W w o c = y daz m foo S m 3ror �m o m o oN N o� o00 �rnr dr j N d V a0 O W U3 Vi LL p� o o 47 d Q � 0 mm J H w 3 °'torte n � (q Ito 'd m fA fA b'i •CO `t00 CJ O V V r• � O r N N N.-. O CUi d! d LL TLL o 0000 O a m p d d 0 4 0 0 0 0 O r c a I�- Z Ne 3F»e3 m•(» (»� aw LLLL n o v3 d d W O O O O N J J d d b N LL W a U t9 d N N D_ NM C Q V) Fo- W M co M t!I a` d w ?m U m � o p r R C J N C d C Oco o 0 d O O Od O m a C l o d d O.-. a oa adi aNi L E d J U d x co J Oa c c a� O H d d cl �m c > CN Z' y Ud r N o � d m� •2 W WA m 'V N N d O C VJ C m m N L J d N O d o d E m 3 m o `O d wc Y o a _ o o o U c ° E `o L O U� F V7>. Q o gO U Q d 0 Z co Y FO Cff O I O m O m r m City of Fort Worth Sanitary Sewer Rehabilitation, Contract 97 INDEX OF DRAWINGS P&P Sheets Sheet No. Sheet Description 1 COVER SHEET 2 GENERAL NOTES AND LEGEND 3 PROJECT LAYOUT 1 4 PROJECT LAYOUT 11 5 PROJECT LAYOUT III 6 PROJECT LAYOUT III 7 OVERALL WATER LAYOUT 8 OVERALL SEWER LAYOUT 9 L-5653 RE-ALIGMENT LAYOUT 10 M-191 (BERRY) RE-ALIGMENT LAYOUT 1 11 L-5015 PLAN AND PROFILE STA,b+ O END 2 12 L-5016 PLAN AND PROFILE STA.5 TO 0+98 3 15 i.-5017 PLAN AND PROFILE STA.0+00 TO 4+00 4 14 L-50171.501 7A P N- L3 PRF S T+'00 TO 5+18 AND 0 0-0 TO tI#52 5 1 L-5115 PLAN AND PROFILE S�'il &M TO 5+670 6 16 L-5115 PLAN AND PROMLEM 3466TJOiM 7 17, "1 15 PLAN AM P .1 M TU f +00 8 18 -511 PLAN MD- M- S &.15+00 T 75 MD — 9 % L.-5223 PLAN AND PR FI S A.21+07 TO 2+29 10 g2l L-5514 PLAN AND PROFILE S A.0 TO 3+27 11 L-5514 PLAN AND PWOFILE STA.3+27 O 8+00 12 .-5514 PLANA PROFILi I'A.X-M- O'13+00 13 L-5614 PLANA PROF A.13+00M M 14 24 L-5E353 PDkN AND PROFILE TA.X+00 TO 3+30 15 25 L-6605 PLAN AND PROFILE T .O+MT 4+04� 16 26 L-5805 PLAN AND Pf MMIR STA.4+00 TO 6+19 17 27 L-5909 PLAN AND PROFILE STA 7+73 TO 1,2+50 18 2 L-6909 AND L-5911 ON W R OF ILE ST'A 12+50 To 15W33 Alm.0;-06 1+10 19 M34 .-3286 PLAN AND PR FILE STA.0+00 To 4+50 0 L-3286 PLAN AND PROFILE; TAA.,4+ O 9+00 21 L--3286 PLAN AND PRO I ST .§;WTO 14+00 22 L-3285 PLAN AND OFILE§T-A. 4+00 TU 15+73 23 L 3 8 PLAN AND PROFILE A.0+00 TO 4+50 24 L-3289 PLAN AND PROFILE STA.4+50 TO 9+00 25 35 L-3289 PLAN AND PROFILE STA.9+00 TO 14+00 26 36 L-3289 PLAN AND PROFILE STA. 14+00 TO END 27 37 L-3291 AND L-3291A PLAN AND PROFILE STA.0+00 TO 3+48 AND 0+00 TO END 28 38 M-171 PLAN AND PROFILE STA. 17+87 TO 22+00 29 39 M-171 PLAN AND PROFILE STA. 22+00 TO 26+50 30 40 M-171 PLAN AND PROFILE STA.26+50 TO 30+00 31 41 M-171 PLAN AND PROFILE STA. 30+00 TO 33+21 32 42IM-170A PLAN AND PROFILE STYA 33 43 M-191 (BERRY) PLAN AND PROFILE STA.XX+XX TO STA.XX+XX 34 44 M-191 (VC) PLAN AND PROFILE STA. 86+76 TO 90+00 35 45 M-191 C PLAN AND PROFILE STA. 90+00 TO 94+50 36 46 M-191 (VC) PLAN AND PROFILE STA. 94+50+TO 98+00 37 47 M-191 (VC) PLAN AND PROFILE STA. 98+00+TO 99+58 48 TRAFFIC CONTROL 1 49 ITRAFFIC CONTROL II 50 TYPICAL DETAILS I 51 TYPICAL DETAILS II 52 EROSION CONTROL DETAILS 53 POTENTIAL DETAIL SHEET FOR M-191 OPEN-CUT APRIL 2017 CONTRACT 97 ADDITIONALS Hours of effort Rate Cost 1.M-191 to Burton Ave Field Crew Time: 16 $165 $2,640 (EASEMENTS AS NEEDED$1500/each) Survey Tech Time: 6 $100 $600 RPLS Oversight Time: 2 $155 $310 TOTAL=j $3,550 2.M-191 Dillard/Berry open cut Field Crew Time: 24 $165 $3,960 Survey Tech Time: 8 $100 $800 RPLS Oversight Time: 0 $155 $0 TOTAL= $4,760 3.Gas Manholes Will try to open 4.Potholing of utilities Field Crew Time: 8 $165 $1,320 (DAILY RATE) Survey Tech Time: 4 $100 $400 RPLS Oversight Time: 0 $155 $0 TOTAL= $1,720 5.Survey in backyard for L-3289 Field Crew Time: 16 $165 $2,640 (±IF ANY ACCESS ISSUES) Survey Tech Time: 8 $100 $800 RPLS Oversight Time: $155 $0 TOTAL= $3,440 6.L-3291 Added May 9,2016 Field Crew Time: 12 $165 $1,980 (ADDED AFTER INITIAL FEE WAS DETERMINED) Survey Tech Time: 8 $100 $800 RPLS Oversight Time: $155 $0 TOTAL= $2,780 SUM= $16,250 (ITEM#4 IS DAILY RATE) (DOES NOT INCLUDE EASEMENTS FOR ITEM#1) r 3 ® icy,'0 k ®°<,,o / »°o a Lu u) s2 \//�)k\ Lu u5 N z z<Lj \/}§(/ 2 $ 2 ( Irow yqg Ll� ( { 3 3° Ld \ Ld < ° - ��� � a2 � 2 � Pr / � , � . � $� 7 - � . ' , .L S /4 %r 6 { § #�%x � - � u City of Fort Worth, Texas Mayor and Council Communication COUNCIL ACTION: Approved on 3/20/2018 - Ordinance No. 23144-03-2018 DATE: Tuesday, March 20, 2018 REFERENCE NO.: **C-28633 LOG NAME: 60SSR97AKENNEDYJCFUNDING SUBJECT: Adopt Appropriation Ordinance in the Amount of$107,785.00 for Increased Project Management Costs on Sanitary Sewer Rehabilitation, Contract 97 for Various Sanitary Sewer Mains Located Within the Historic Rosedale Park, Stop Six/Poly Oversight, Stop Six Sunrise Edition and Fairhaven Neighborhoods (COUNCIL DISTRICT 5) RECOMMENDATION: It is recommended that the City Council adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Sewer Capital Fund-Legacy in the amount of$107,785.00 from available funds for the purpose of funding Sanitary Sewer Rehabilitation, Contract 97 for Various Sanitary Sewer Mains Located Within the Historic Rosedale Park, Stop Six/Poly Oversight, Stop Six Sunrise Edition and Fairhaven Neighborhoods. (City Project No. CO2739) DISCUSSION: On September 13, 2016, Mayor and Council Communication (M&C C-27917), the City Council authorized the execution of an Engineering Agreement with Kennedy/Jenks Consultants, Inc., in the amount of $258,616.00 for the preparation of plans and specifications for the Sanitary Sewer Rehabilitation, Contract 97 project. This project requires additional funding for project management and to cover costs associated with Amendment No. 1 in the amount of$87,785.00 for the necessary design to replace severely deteriorated sanitary sewer mains located immediately upstream or downstream of some project mains. Engineering for Sanitary Sewer Rehabilitation, Contract 97 is one component of the overall project that includes project management, utility coordination, construction, material testing, inspection and contingencies. The overall project budget is$5,000,000.00. Design is expected to be completed by July 2018. Construction is anticipated to commence in November 2018 and be completed by November 2019. This project is part of the Water Department's Sanitary Sewer Overflow Initiative Program. This project will have no impact on Water Department's operating budget. The project is located in COUNCIL DISTRICT 5. This M&C does not request approval of a contract with a business entity. FISCAL INFORMATION/ CERTIFICATION: The Director of Finance certifies that upon approval of the above recommendation and adoption of the attached appropriation ordinance, funds will be available in the current capital budget, as appropriated, of the Water Capital Projects Fund. The Fiscal Year 2018 Water Operating Fund Budget includes appropriations of$29,022,689.00.00 for the purpose of providing Pay-As-You-Go funding for Sewer Capital Projects. After this transfer for Fiscal Year 2018, the balance will be $12,244,510.00. Appropriations for Sanitary Sewer Rehabilitation, Contract 97 as depicted below: http://apps.cfwnet.org/ecouncil/printme.asp?id=25614&print=true&DoeTvne=Print 10 1/?ffl Q Fund Existing Additional Project Appropriations Appropriations Total* Sewer Capital Fund - $394,000.00 $107,785.00 $501,785.00 Legacy 59607 Project Total $394,000.00 $107,785.00 ![_$501,785.00 *Numbers rounded for presentation purposes. FUND IDENTIFIERS (FIDs): TO Fund Departmentccoun Project Program ctivity Budget Reference# rmounl ID 1A ID Year (Chartfield 2) FROM Fund Department ccoun Project Program ctivity Budget Reference# moun ID ID Year (Chartfield 2) CERTIFICATIONS: Submitted for City Manager's Office by: Jay Chapa (5804) Originating Department Head: Kenneth Morgan (8246) Additional Information Contact: Susan Schwinger (6529) ATTACHMENTS 1. 60SSR97AKENNEDYJCFUNDING FID Table.docx (CFW Internal) 2. 60SSR97AKENNEDYJCFUNDING A018r.docx (Public) http://apps.cfwnet.org/ecouncil/printme.asp?id=25614&print=true&DoeTyI)e=Print 3/21/9,019 v N i/ Q X 'X IX F— d a a a i+ - - Y - Ln - - CO 0 co co 0 00 - F, 0I Q QN 00r4 00 d Q Z � L 00 00 i OA N ami N ami ! a W T00 co coW > y `T — — — F ,L m W m W !t yN — — Y — — — — — J — — — 3 u z Q en en en en Z QQ a o n o 0 O Y o - - - .� to - - - C 0 ca c - - - -_ - - 0 -1 LnLL Q _ LL rl LM Q Q d YL — — —en en en — — — = YC C0 0 00 0 0d) Q — — 0 — — —LLJ X � W LLJ — — 0 — — LL Ln Ln Ln LnLL • Gl Yx