HomeMy WebLinkAboutContract 49694-CO1 FORT WORTH. City of Fort Worth CITY ACT No. �!Legq-(O 1
`�� Change Order Request Breakdown CONTRACT
N0.
Project Namel 2014 CIP Year 3 Contract 6 City Sec# 1 49694
Client Project#(s) c02695
Contractorl ARK Contracting Services,LLC PM Mary Hanna Inspectorl Alan Hugh Kingsmore
Change Order Submittal# Date 2/27/2018
Dept. TPW TPW/Street Water Sewer Contract Time
Maintenance Totals CD
Original Contract Amount $1,113,879.00 $332,520.00 $1,284,945.00 $818,747.00 $3,550,091.00 300
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,113,879.00 $332,520.00 $1,284,945.00 $818,747.00 $3,550,091.00 300
Amount of Proposed Change Order $513,365.00 $0.00 $0.00 $0.00 $513,365.00 180
Revised Contract Amount 1,627,244.00 $332,520.00 $1,284,945.00 $818,747.00 $4,063,456.00 480
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00 $0.00 $0.00 $0.00
Additional Funding(if necessary) $513,365.00 1 1 $513,365.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 14.46%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $4,437,613.75
This change oder adds Lafayette Avenue from Owasso Street to Clover Lane(0.85 LM)to this contract scope since the original contract includes paving improvements near
Lafayette Avenue.
kt�by:
CL�L
onald P. Gonzales,ASW. City SeMdaty
OF'FRT
Q O
* 7y0
OFFICIAL RECORD
CITY SECRETARY
FT.W 01m,TX
T City of Fort worth
Change Order Additions
Project Name 2014 CIP Year 3 Contract 6 City Sec# 49694
Client Project# c02695
Contractorl ARK Contracting Services,LLC PM= Mary Hanna Inspector
Change Order Submittal Date 2 27/2018
ADDITIONS
I I EM DESCRIPTION DEPT Qty Unit Unit Cost Total
remove Concrete Curb and Gutter
77—6"Concrete Curb and Gutter TPW 000 LF 5.
Remove Concrete Driveway TPW 5,000.00000000
6""Concrete TPW 5,000.00000000----91F
Remove Concrete Sidewalk TPW 6,320.00000000 F
"concrete idewalk TPW 8,000. 000 F 8.00
Concrete Retaining Wall w/Sidewalk TPW 25.0000 000 SF $30.00
77—Remove Existing Wheelchair Ramp TPW 4.00000000 EA 00.0
32 Install New ADA Wheelchair Ramp(w/detectable warning dome-tile surface) TPW 13.00 00000 EA2,0 .00
Remove Existing oncrete Valley utter TPW 1,400.0 00000 F 5.
77—Install New Concrete Valley Gutter TPW 85.00000000 F 5.
11-Inch Pavement Pulverization TPW 5,500.00000000Y 7.
TFIF-sy- em—ent Modification TPW 75.00000000 TN 1 .
37 Inch Surface Course Type"D"Mix TPW 5,500.00000Y 15.0
Water Valve Box Adjustment with Concrete ollar TPW &00000000 EA
Water Meter Box Adjustment TPW 24.00000000 EA 25.
Manhole Adjustment With Concrete Collar TPW 7.00000000 EA 5 .
77—Inlet top remove and replace TPW 7.00000 00 EA 750 . 0
Painting House Addresses TPW 0 EA 5 .
43 Top Soil TPW 10.00000000Y ____T1500
44 Block Sod Replacement TPW 1, O. Y $5.00
Remobilization TPW 1.00000000 LS $15,000.00
TPW $513,365.00
TPW/Street Maintenance $0.00
Water $0.00
Sewer $0.00
Sub Total Additions $513,365.00
Change Order Additions Page 1 of 1
FORT WORTH City of Fort Worth
- Ir-- Change Order Deletions
Project Name 2014 CIP Year 3 Contract 6 City Sec# 49694
Client Project# c02695
Contractor ARK Contracting Services,LLC PM Mary Hanna nspecto-
Change Order Submittal# Date 2/27/2018
DELETIONS
ITEM DESCRIPTION UEF I Qty Unit Unit Cost Total
TPW $0.00
TPW/Street Maintenance $0.00
Water $0.00
Sewer $0.00
Sub Total Deletions 0
Change Order Deletions Page 1 of 1
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for this CO
Granados Trucking Hauling by dump trucks $72,040.00
Total $72,040.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 4/17/2018
DATE: Tuesday,April 17,2018 REFERENCE NO.: **C-28663
LOG NAME: 20LAFAYETTE AVENUE SCOPE REALLOCATION VARIOUS CONTRACTS
SUBJECT:
Authorize Execution of Change Order No.4 to City Secretary Contract No.
47874 with Advanced Paving Acquisition,Ltd.,to Remove Lafayette Avenue,
from Owasso Street to Clover Lane,from the Contract Scope,Approve the
Transfer of Previously Appropriated Surplus Funding in the Approximate
Amount of$545,000.00 from HMAC 2014-4 Street Rehabilitation to W&SS
Replacement Contract 2016 WSM-C,and Authorize Execution of Change Order
No.1 to City Secretary Contract No.49694 with ARK Contracting Services,
LLC,in the Amount of$513,365.00 and the Addition of 180 Calendar Days to
Rehabilitate Lafayette Avenue,from Owasso Street to Clover Lane,for a
Revised Contract Amount of$4,063,456.00(COUNCIL DISTRICT 7)
RECOMMEI`DATION:
It is recommended that the City Council:
1. Authorize the execution of Change Order
No.4 to City Secretary Contract No.47874
with Advanced Paving Acquisition,Ltd.,to
remove Lafayette Avenue, from Owasso Street to
Clover Lane,from the contract scope;
2. Approve the transfer of all previously
appropriated surplus funding from HMAC 2014-4
Street Rehabilitation(City Project No.
CO2282)in the approximate amount of
$545,000.00 to W&SS Replacement Contract 2016
WSM-C,(City Project No. CO2695),in the
Street Rehabilitation Fund(City Project No.
39408);and
3. Authorize the execution of Change Order
No. 1 to City Secretary Contract No.49694
with ARK Contracting Services,LLC,in the
amount of$513,365.00 and the addition of 180
calendar days to rehabilitate Lafayette Avenue
from Owasso Street to Clover Lane for a
revised contract amount of$4,063,456.00(City
Project No.02695).
DISCUSSION:
Ork May 17,2016,the City Council authorized
the execution of a contract with Advanced
Paving Acquisition,Ltd., in the amount of
$3,771,301.80 for the Rehabilitation of
Various Street Segments,2014 CIP Year 2
–Contract 4 Street Rehabilitation(City
Project No. 100181,M&C C-27723).During
construction,additional work efforts
associated with poorer than expected street
conditions on multiple street segments
increased the cost of the project,and
required the removal of Lafayette Avenue to
prevent exceeding contract capacity. This
reduction of contract scope necessitated this
Change Order No.4.
On August 1,2017,City Council authorized the
execution of a contract with ARK Contracting
Services,in the amount of$3,550,091.00 for
Combined Street Paving Improvements and Water
and Sanitary Sewer Main Replacement,2014 CIP
Year 3,Contract No. 6(M&C C-28312).This
contract scope includes paving improvements
adjacent to Lafayette Avenue and due to the
close proximity of existing similar work,it
is cost effective to add Lafayette Avenue from
Owasso Street to Clover Lane to this contract
through Change Order No. 1 in the amount of
$513,365.00 and the addition of 180 days.
Staff is requesting the transfer of all
previously appropriated surplus funding from
B 14AC 2014-4 Street Rehabilitation(City
Project No.CO2282,M&C C-26852)in the
approximate amount of$545,000.00,in the
Street Rehabilitation Fund(Project No. 39408)
to provide funding for this change order,
since this project is complete and excess
funding was not utilized as originally
anticipated.
This Change Order will have no impact on the
Transportation and Public Works annual
operation budget.
M/WBE OFFICE-ARK Contracting Services,LLC,
is in compliance with the City's MBE Ordinance
by committing to 14 percent MBE participation
on this Change Order No. 1. The City's MBE
goal on this change order or extra work is 14
percent.
The project is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon
approval of the above recommendations,funds
will be available as appropriated in the
current capital budget, of the Street
Rehabilitation Fund.
FUND IDENTIFIERS (FIDs):
ig
Department Account Project Program Activity Budget Reference Amount
#
Fund ID ID Year (Chartfield 2)
FROM
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year (Chartfield 2)
CERTIFICATIONS:
Submitted for City Manager's Office by: Susan Alanis (8180)
Originating Department Head: Douglas Wiersig (7801)
Additional Information Contact: Mary Hanna (5565)
ATTACHMENTS
1. 1295 form 2014 CIP Year 3 Contract 6 ARK C.O.l.pdf (Public)
2. 2014 CIP Year 3 Contract 6 ARK C.O.1_Man.ndf (Public)
3. 2014 CIP Year 3 Contract 6 C.O.1_MBE Compliance Memo.pdf (CFW Internal)
4. Change Orderl_Breakdown.xlsm (CFW Internal)
5. FID ARK.pdf (CFW Internal)
CFW Change Order Approval COAppr-01 Page 1 of 2
FORT WORTH., city of Fort Worth
..-- Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: 1
Change Order No.: COAppr-01 Date Started: 2018-02-27
City Sec. No.: 49694 Date Due: 2018-04-18
Project Name: 2014 CIP Year 3 - Contract 6
Project Numbers: CO2695 DOE Numbers:
Project ;This is a combined Street Paving Improvements and Water and
Description: ;Sanitary Sewer Main Replacements in the Handley and Crestline
Area Neighborhoods.
Project/Contract
Compliance Mary Hanna City Inspector: Alan Hugh Kingsmore
Manager:
Contractor: ARK Contracting Services, LLC
COUNCIL ACTION (If Required):
M&C Log Name: 202014 CIP YEAR 3 CONTRACT 6 ARK CONSTRUCTION SERVICES C.O.1
M&C Number: M&C Date:
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
r'
TPW $ 513,365.00 39408-0200431-5740010-CO2483 1180
Total Cost: $ 513,365.00. Total Requested Days: 180
Approval Status:
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&Processld... 5/4/2018
CFW Change Order Approval COAppr-01 Page 2 of 2
Approved: Yes
Comments:
User: Mike Plunk
Date: 2018-02-27 3:05 PM
Approved: Yes
Comments:
User: Rakesh Chaubey
Date: 2018-03-05 8:39 AM
Approved: Yes
Comments:
User: Lane Zarate
Date: 2018-04-18 11:47 AM
Approved: Yes
Comments:
User: Ricardo Matute
Date: 2018-04-23 12:37 PM
Approved: Yes
Comments:
User: Doug Wiersig
Date: 2018-04-26 11:43 PM
,Approved: Yes
Comments:
User: Doug Black
Date: 2018-04-30 11:24 AM
Action Required: Review and Approve
Approved:Yes
Comments:
User:Susan Alani
Date: