HomeMy WebLinkAboutContract 49738-CO1 CITY SECRETARY FORT WORTH® City of Fort Worth CONTRACT NO. —e Change Order Request Breakdown ProjectNamel 2014 CIP Year 3 Contract 4 City Sec# 1 49738 Client Pmject#(s)j 02694 Contractorl Stabile&Winn,Inc. PM IMary Hanna Inspector Gary Deyon Change Order Submittal# One Date 4!30!2018 Dept. Water Sewer TPW Contract TimeTotals CD Original Contract Amount $1,251,960.00 $451,210.00 $1,871,200.00 $3,574,370.00 360 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1;251,960.00._. ;$451;210.00= $1,871,200:00" _ $3,574,370.00 - 360 Ga to ADD&DEL Tabs to Enter CO Backup -00 - 0 Revised Contract Amount - 1,251;960.00 $451,210:00_ $1;871;200.00` _ $3,574,370.00 360 .Original Funds Available for Change Orders $62,598.00 $22,561.00 $93,560.00 $178,719.00 Remaining Funds Available for this CO = "$62,598100 $22,561.00, $93,560.00; $178,719.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.007 MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $4,467,962.50 Change order to add temporary ditchline repair for the sewer work on NE 36th. The roadway replacmeent was changed from a MOL to a POL and therefore the ditchline repair needed to be changed from a permanent to a temporary repair. REcev,Eb JUN-5 2018 CnvcF�o�r CITysrcni nye OFFICIAL RECORD CITY SECRETARY FT.WORTH,TX City of Fort worth Change Order Additions Project Name 2014 CIP Year 3 Contract 4 City Sec# 49738 Client Project# 02694 Contractor Stabile&Winn,Inc. PM Mary Hanna Inspectorl Gary Deyon Change Order Submittal# One Date 4/30/2018 ADDITIONS HEM nETRIP I ION DEPT ty Unit UnitGost Total Unit 2 Sanitary Sewer Improvements 25 Temp.Asphalt Paving Repair(2"HMAC on 6"CTB) Sewer 1,050.00000000 LF 29.00 Water $0.00 Sewer $30,450.00 TPW $0.00 Sub Total Additions 30,450.00 Change Order Additions Page 1 of 1 FORT__TH City of Fort Worth Change Order Deletions Project Name 2014 CIP Year 3 Contract 4 City Sec# 49738 Client Project# 02694 Contractor Stabile&Winn,Inc. PM Mary Hanna inspectorl Gary Deyon Change Order Submittal# F--dne7 Date 4/30/2018 DELETIONS Qty Unit Unit Cost Total Unit 2 Sanitary Sewer 12 4'Wide Asphalt Pvmt.Repair,Residential Sewer 435.00000000 LF 7. ----TVT57.ZU Water $0.00 Sewer $30,450.00 TPW $0.00 Sub Total Deletions 30,450.0 Change Order Deletions Page 1 of 1 M/SBE Breakdown for this Change Order M%SBE Sub Type of Service Amount for this CO N/A N/A Total $0.00 Previous Change Orders COW DATE AMOUNT Total $0.00 CFW Change Order Approval COAppr-01 Page 2 of 3 FORT WORTH, city of Fort Worth Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: 1 . .... .. ..._.... .. __. Change Order No.: COAppr-01 Date Started: 2018-05-01 City Sec. No.: 49738 Date Due: 2018-06-20 Project Name: 2014 CIP Year 3 - Contract 4 02694 DOE Numbers: Project Numbers: -- Project This is a combined street paving improvements and water and Description: saintary sewer main replacemenets project in Diamond Hill Jarvis area Project/Contract Compliance Manager: Mary Hanna City Inspector: ;Gary Deyon Contractor: Stabile & Winn, Inc. COUNCIL ACTION (If Required): M&C Log Name: M&C Number: M&C Date: COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: _ Water Department $ 0.00 '59607-0700430-5740010-c02694 c( 0 Total Cost: $ 0.00 Total Requested Days: 0 Approval Status: https://projeetpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&Processld... 6/5/2018 CFW Change Order Approval COAppr-01 Page 3 of 3 Approved: Yes Comments: User: Jerry Henderson Date: 2018-05-01 2:47 PM Approved: Yes Comments: User: Mary Hanna Date: 2018-05-01 3:04 PM Approved: Yes Comments: User: Roberto C. Sauceda Date: 2018-05-07 8:55 AM Approved: Yes Comments: User: Chris Harder Date: 2018-05-24 5:02 PM Approved: Yes Comments: bypass by FG User: Kenneth Morgan Date: 2018-05-31 11:15 AM O�FOR7* Approved: Yes Comments: User: Doug Black * ' ' Date: 2018-06-01 11:00 AM by; .xAs Approved: Yes Comments: User: Jay Chapa J. Kayser, City S Date: 2018-06-01 1:22 PM Action Required: Review and Approve M&C: 1295: OFFICIAL RECORD U'�y`.�'B GRA;"ARY Fla WORTH, TX https://projeetpoint.buzzsaw.com/ bz_web/Forms/FormPrint.aspx?Siteld=51500&Processld... 6/5/2018 Contract Compliance Manager: By signing, I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting.requirements. M an Sr. Project Manager