HomeMy WebLinkAboutOrdinance 23234-06-2018 Ordinance No. 23234-06-2018
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN
THE AMOUNT OF $2,456,243.00 IN THE WATER AND SEWER CAPITAL FUND, FROM
AVAILABLE FUNDS, FOR WATER AND SANITARY SEWER MAIN REPLACEMENT
CONTRACT 2016 WSM-F, PART 1; PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL
ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2017-2018 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the amount
of$2,456,243.00 in the Water and Sewer Capital Fund, from available funds, for Water and Sanitary Sewer
Main Replacement Contract 2016 WSM-F, Part 1.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 22928-09-2017 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETA
r
Douglas W Black Mary J. K
Sr. Assistant City Attorney
ADOPTED AND EFFECTIVE: June 5. 2018
SEW 4,;6 41
Pie
J'-A
MIMI
.:t
T rsz: aalvt��s �rw sem-+► m_'. R r I r � ! p
I .
Iff,
.r .
E-"
i C i i I I i
Mt., Mk 11
L' • uf .. • tal
Yr�14
X001
t Ar
I + l I
`` �. � ♦'�� _�_ fir:�" $!e�' { —� { ��
WF
b'- 1 LW
/
JAW Aw
�_ „ .roe �4�� ?!�'Jo�'�'✓� � ' f� �� ���
powwom
e7 Jgo
M''S� 'M;JAMi & '�;qm,g "fit`
NA
+)n1
{ � aYi.;l�:..a E ss'tl- 4{�' A ?i.S� t'i. - tl.iisk k " M •F"
Ay
opt
Z-.—
���� a ! � 1'�' �. • IIS '°.�. �Y„
L '�"3 !�y y[�
i W..TrAM�f 4$'1 i 1 y �i'kitY p..'•.'4 w -'s t r
,he� 1f�1•'ima���kl"'"� �w53'.«st�. '�'�3+� M. $: w• � "i 3'�� mss^"�"
4
.. (AR w �ik•r."�
FORTWORTH'
,
$WSW
x
ris..7:t6ahels�6v.A7A1A75.�'fl a..awha+..4'+F�'aMr rsw
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 6/6/2018 - Ordinance No. 23234-06-2018
DATE: Tuesday, June 5, 2018 REFERENCE NO.: **C-28709
LOG NAME: 602016WSMFPI-GRATEX
SUBJECT:
Authorize Execution of Contract with Gra-Tex Utilities, Inc., in the Amount of$2,767,633.00 for Water and
Sanitary Sewer Main Replacement Contract 2016 WSM-F, Part 1 and Adopt Appropriation Ordinance
(COUNCIL DISTRICT 8)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Appropriation Ordinance increasing estimated receipts and appropriations in the
Water and Sewer Capital Fund in the amount of$2,456,243.00 from available funds; and
2. Authorize execution of a contract with Gra-Tex Utilities, Inc., in the amount of$2,767,633.00 for
Water and Sanitary Sewer Main Replacement Contract 2016 WSM-F, Part 1 (City Project No.
CO2727).
DISCUSSION:
This Mayor and Council Communication is to authorize a construction contract for the replacement of
deteriorated water or sanitary sewer mains located in the West Meadowbrook Neighborhood area and as
identified on the streets, alleys and easements below:
Street [FromFTo
Scope
of Work
Avenue G FCollard Street IS. Ayers Avenue Water
Avenue H Bishop Street Little Street lWater
Haynes Avenue [Hawlet Street E. Lancaster [Water
Fw
Av
Alley Between Avenue H and Avenue S. Ayers Avenue allace Street Sewer
G
Alley between Ave G and E Rosedale [Collard Street FSAyers Avenue [Sewer
Street
Easement Between S. Clairemont 60 feet south of [Ha0w
2feet north of
Avenue and Haynes Avenue Hampshire letStreet [Sewer
Boulevard
Easement between Haynes Avenue [Panola Avenue Hampshire [Sewer
and Perkins Street Boulevard
Easement 120 feet south of 200 feet east of
Logname: 602016WSMFPI-GRATEX Page I of 3
Hampshire Boulevard and between 200 feet west of Clairmont
Hampshire Boulevard and Union Clairmont Avenue Avenue Sewer
Pacific Railroad
In conjunction with replacement of the water mains, all connecting lead service lines will be removed and
replaced. There are a total of 63 lead services that have been identified that will be replaced as part of this
contract. Additionally, asphalt pavement rehabilitation will be conducted on Avenue G, Avenue H and
Haynes Avenue, subsequent to the water main replacement. The Transportation and Public Works
Department's share of this contract is $710,798.00.
The project was advertised for bids on February 22, 2018 and March 1, 2018 in the Fort Worth Star-
Telegram. On March 22, 2018, the following bids were received:
Bidder [AmountITime of Completion
Gra-Tex Utilities, Inc. [$2,767,633.00 [365 Calendar Days
Ark Contracting Services, LLC $2,889,323.00
Jackson Construction, Ltd [$3,205,520.00
Woody Contractors, Inc. `$3,427,680.00
Excel Aircraft dba Excel Trenching [$4,067,818.00
In addition to the contract amount, $483,151.00 (Water: $205,096.00; Sewer: $91,470.00; Paving:
$186,585.00) is required for project management, material testing and inspection $138,382.00 (Water:
$71,106.00; Sewer: $31,736.00; Paving: $35,540.00) is provided for project contingencies.
The sanitary sewer component of this project is part of the Water Department's Sanitary Sewer Overflow
Initiative Program.
This project will have no impact on the Transportation and Public Works' annual operation budget nor on
the Water Department' s operating budget when completed. Construction is expected to start in July 2018
and be completed by July 2019.
M/WBE OFFICE—Gra-Tex Utilities, Inc., is in compliance with the City's Business Diversity Ordinance by
committing to 26 percent MBE participation on this project. The City"s MBE goal on this project is 25
percent.
The project is located in COUNCIL DISTRICT 8, Mapsco 78G, K, L.
FISCAL INFORMATION /CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in the current capital budget, as appropriated, of
the Water and Sewer Capital Fund and the General Capital Projects Fund. The Fiscal year 2018 Water
Operating Budget includes appropriations of$29,069,236.00 for the purpose of providing Pay-As—You-Go
funding for Water Capital Projects. After this transfer for Fiscal Year 2018, the balance will be
Logname: 602016WSMFPI-GRATEX Page 2 of 3
$8,697,911.00. The Fiscal Year 2018 Water Operating Budget includes appropriations of$29,022,689.00
for the purpose of providing Pay-As-You-Go funding for Sewer Capital Fund - Legacy. After this transfer
for Fiscal Year 2018, the balance will be $8,108,440.00.
Appropriations for Water and Sanitary Sewer Main Replacement Contract 2016 WSM-F Part 1:
FUND Existing Additional Project
Appropriations Appropriations Total*
General Capital Projects
Fund 30100 $832,923.00 $0.00 ' $932,923.00
Water & Sewer Capital $0.00 $2,456,243.00 [$2,456,243.00
Fund 56002
Project Total $2,456,243.00 $3,389,166.00
$932,923.00
* Numbers rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID Year Chartfield 2
FROM
Fund Department ccoun Project Program ctivityJ Budget Reference # moun
ID ID Year (Chartfield 2)
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Chris Harder (5020)
Additional Information Contact: Lawrence Hamilton (2626)
Logname: 602016WSMFPI-GRATEX Page 3 of 3