HomeMy WebLinkAboutOrdinance 23236-06-2018 Ordinance No. 23236-06-2018
AN ORDINANCE REDUCING UNALLOCATED RECEIPTS AND APPROPRIATIONS IN
THE AMOUNT OF $255,030.00 IN THE WATER AND SEWER COMMERCIAL PAPER
FUND, FOR SYCAMORE CREEK DRAINAGE BASIN PARALLEL INTERCEPTOR
IMPROVEMENTS PROJECT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING
THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL
ORDINANCES IN CONFLICT HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2017-2018 in the
Budget of the City Manager,there shall also be reduced unallocated receipts and appropriations in the amount
of$255,030.00 in the Water and Sewer Commercial Paper Fund,for Sycamore Creek Drainage Basin Parallel
Interceptor Improvements project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 22928-09-2017 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
7
Douglas W Black miry J. K ys '
Sr. Assistant City Attorney
ADOPTED AND EFFECTIVE: June 5. 2018
MAYOR AND COUNCIL COMMUNICATION MAP
60SCM275VARA3 - LAN
Sycamore Cr 7 -.
,t
WL-gt ,C)r-k Tri III i f r
30
30 .
mW Ld
Y
A�::�,.;m
B OMAR AYE
AN STER AVE' _ _ i= co-1 h —�F
_
BOMAR AVE
I — ,w
LJL
CK � � i � -��' � 1:• gam'
r
LLJ
Lu
jzi
VALKUS_ST — R
C7
SYCAMOREREEK '
NI
,4771 ST
C` E
of t' � TA ST
FT ie�` f 5 'w M
10
F L E LI D
E, lCKERY',BLV0
1L
0 +f
= C
a.
FORTWORTH
MORE PARK
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 6/5/2018 - Ordinance No. 23236-06-2018 & Resolution No.
4943-06-2018
DATE: Tuesday, June 5, 2018 REFERENCE NO.: **C-28712
LOG NAME: 60SCM275VARA3 - LAN
SUBJECT:
Authorize Execution of Amendment No. 3 to City Secretary Contract No. 45280, an Engineering Agreement
with Lockwood, Andrews & Newnam, Inc., in the Amount of$215,030.00 for a Revised Contract Amount of
$1,798,884.00 for Sycamore Creek Drainage Basin Parallel Interceptor Improvements at Various Locations
within the Sycamore Creek Drainage Basin, Adopt Resolution Expressing Official Intent to Reimburse
Expenditures with Proceeds of Future Enterprise Fund Debt and Adopt Appropriation Ordinance
(COUNCIL DISTRICT 8)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Resolution expressing official intent to reimburse expenditures with proceeds of
future enterprise fund debt for the Sycamore Creek Drainage Basin Parallel Interceptor
Improvements Project;
2. Adopt the attached Appropriation Ordinance reducing unallocated receipts and appropriations in the
Water and Sewer Commercial Paper Fund in the amount of$255,030.00, for the Sycamore Creek
Drainage Basin Parallel Interceptor Improvements Project; and
3. Authorize execution of Amendment No. 3, in the amount of$215,030.00, to City Secretary Contract
No. 45280, an Engineering Agreement with Lockwood, Andrews & Newnam, Inc., for Sycamore
Creek Drainage Basin Parallel Interceptor Improvements at various locations thereby increasing the
contract amount to $1,798,884.00. (City Project No. 02200)
DISCUSSION:
On November 19, 2013, (M&C C-26567) City Council authorized an Engineering Agreement with
Lockwood, Andrews & Newnam Inc., in the amount of$575,828.00 for the Sycamore Creek Drainage
Basin Parallel Interceptor Improvements at various locations within the Sycamore Creek Drainage Basin.
The Agreement was subsequently revised by Amendment No.1 (M&C C-26964) September 9, 2014 in the
amount of$168,311.00 and Amendment No. 2 (M&C C-27884) August 23, 2016 in the amount of
$839,715.00.
Amendment No. 3 will provide for the following:
Redesign of the portion of the sewer main across Sycamore Golf Course as requested by the Park and
Recreation Department.
. Design of a sanitary sewer interceptor to cross Vickery Boulevard and into Sycamore Park.
. Park conversions for Sycamore Golf Course and Sycamore Park.
. Design survey.
Logname: 60SCM275VARA3 - LAN Page 1 of 3
. Subsurface utility engineering.
. Assistance during construction.
Lockwood, Andrews & Newnam, Inc., proposes to perform the necessary additional work for a lump sum
fee of$215,030.00. Staff considers this fee to be fair and reasonable for the scope of services proposed.
In addition to the contract cost, $40,000.00 is required for project management.
In order to expedite construction, the project was divided into two phases: Phase 1 from Gateway Park
southwards to Union Pacific Railroad Right-of-way has been advertised for bid; Phase 2 from Union
Pacific Railroad Right-of-way will be revised via this amendment. This project is part of the Water
Department' s Sanitary Sewer Overflow Initiative Program.
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer Fund.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation
authority authorized under the Callable Commercial Paper Program (CP) will be used to provide interim
financing for this project until debt is issued. To the extent resources other than the Water and Sewer
portfolio are used to provide interim financing, the Water and Sewer Fund will be charged interest that is
equivalent to the overall rate of return being earned by the City portfolio (currently approximately one-
percent annually). Should the City's portfolio not support the liquidity needed to provide an interim short-
term financing source, another funding source will be required, which could mean issuance of securities
under the CP Program or earlier issuance of Water and Sewer revenue bonds than is currently planned.
Once debt associated with this project is sold, bond proceeds will be used to reimburse the Water and
Sewer portfolio and the City' s portfolio in accordance with the attached Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2018-2022 Five Year Capital Improvement
Plan on December 12, 2017, Mayor and Council Communication (M&C G-19187). This City Council
adopted plan includes this specific project, with funding identified through the CP program to be
reimbursed with future revenue bonds. In accordance with the provisions of the Financial Management
Policy Statement, Staff anticipates presenting revenue-supported debt issuances to the City Council for
consideration within the next three years. This debt must be issued within approximately three years to
provide reimbursement for these expenses. If that does not occur, the costs will no longer be reimbursable
by issuing tax-exempt debt and the funding source will have to be made whole through budgetary
methods. Adoption of this resolution does not obligate the City to sell bonds, but preserves the ability to
reimburse the City from tax-exempt bond proceeds.
This project will have no impact on the Water Department's operating budget when complete. Design for
the Phase 2 project is expected to be complete by May 2019 with construction starting in September 2019
and completion by June 2021.
M/WBE OFFICE: Lockwood, Andrews & Newnam, Inc. is in compliance with the City's BDE Ordinance by
committing to 12 percent SBE participation on this Amendment No. 3. The City's goal on this Amendment
is 8 percent.
The project is located n COUNCIL DISTRICT 8.
FISCAL INFORMATION /CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in Water& Sewer Commercial Paper Fund for
the Sycamore Creek Drainage Basin Parallel Interceptor Improvements Project. The Water and Sewer
Commercial Paper Fund includes authority of$150,000,000.00 for the purpose of providing interim
funding for Water and Sewer Capital Projects. After this transfer, the balance will be $139,589,970.00 for
Logname: 60SCM275VARA3 - LAN Page 2 of 3
future capital projects. Funding for the Sycamore Creek Drainage Basin Parallel Interceptor Improvements
project is as depicted below:
FUND Existing Additional Project Total*
Appropriations Appropriations
Water & Sewer Commercial
Paper Fund 56016 $0.00 $255,030.00 $255,030.00
Sewer Capital Fund - Legacy $1,818,139.00 $0.00 $1,818,139.00
59607
Project Total F$1
,818,139.00 [$255,030.00 [$2,073,169.00
* Numbers rounded for presentation purposes.
FUND IDENTIFIERS (FIDs):
TO
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID Year ChartPield 2
FROM
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID Year Chartfield 2)
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Chris Harder (5020)
Additional Information Contact: Liam Conlon (6824)
Logname: 60SCM275VARA3 - LAN Page 3 of 3