AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
STREET IMPROVEMENTS 2008 FUND, FROM AVAILABLE FUNDS IN THE AMOUNT OF
$100,128.00, FOR FWPA NORTH BEACH CORRIDOR PROJECT; PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND
PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2017-2018 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Street
Improvements 2008 Fund in the amount of$100,128.00, from available funds, for the FWPA North Beach
Corridor Project.
Department Project Amount
Planning & Development FWPA North Beach Corridor Project $100,128.00
Total $100,128.00
Funding Source Street Improvements 2008 Fund $100,128.00
Total $100,128.00
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 22928-09-2017 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROV AS TO FORM AND LEGA CITY SECRET RY.
Jessica 794mWan a J. K y r
Assistartity Attorney
ADOPTED AND EFFECTIVE: June 5. 2018
Ordinance No.23248-06-2018
WYA VA=
FORT WORTH PUBLIC ART
North Beach Corridor
Public Art Project
Narrative Description
The North Beach Corridor will feature a series of up to twelve(12)"whimsical, kinetic"weather vane"sculptures that will
be placed in the center median along a 4-mile stretch of North Beach Street, between Timberland Boulevard and Shriver
Road. Each unique sculpture will have the form of a native animal, bird or reptile, and will be made from locally-sourced
recycled materials. The choice of materials will have a humorous connection with the creature depicted, such as an
armadillo made of truck bumpers and shovel heads. Pivoting with the direction of the wind,the sculptures will be
approximately 30 feet in height, 12 feet in width, and a depth of 2.5 feet.
"The number of sculptures feasible to implement within budget will be determined at the end of the Final Design phase of this
Agreement.
Site
North 1
• I f � f
A �
I � F � � O�AYIr y�M � 1 � •�wrrY
I � J � wwAb �' YVMrIr
f Y..wo r..•
rrnr b
�� � • • `l Y.Y.. � ,�� �° D�' j
i aW IIrM1Y � ll
d..., c� r.r.•r ° ° e e•orot � � ° On� a � ! sf � i o.
+ � t a b �� �� � 1 r,. ""�/ �s�� o� •w��,j � � �G � 6 o.,+�r i ti }a{ rv"++.Yo
}( ♦ � J � S �Yrr�n Sf t ° � y_ 1 � ^� r j �nr�° ! � i cMa..�
�e .,Y.Z YWIo , ♦r..io � � a.,rr s�1 �1 ° d . r...o � �4��
v
`+,e4 �e� �� s j i� j�� mar � fai � � � � � s rrr•�4 w.nya
4\1�,� � `s°"'i`� °�°� i � �1 .T' ° a�� � t� a/ ''e e`er� 1►,'��..° e r
I d"nrP 1 i 1 � i
Map showing possible distribution of artwork along North Beach,between Timberland Blvd.and Shiver Rd.
Artwork Design Images
(Animal: Material Used)
1►.
-.:
Longhorn: Railroad Tracks and Ties Armadillo: Shovel Heads{ind BLImpers Horsy L�iv,cl�s
' F
,y
Bird: Birdhouses Hawk: Sections of Airplane Wings Cow: Lawnmower Blades
Artwork Design Images(Continued)
(Animal: Material Used)
,
a
Rabbit: Automobile Springs Raccoon: Trash Cans Coyote: Chain Link Fence
IL
51
4
am
'r
I
I
Rooster: Baseball Bats Snake: Hubcaps Turtle: Mailboxes
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 6/5/2018 - Ordinance No. 23248-06-2018
DATE: Tuesday, June 5, 2018 REFERENCE NO.: C-28714
LOG NAME: 06NORTH BEACH CORRIDOR PUBLIC ART PROJECT
SUBJECT:
Authorize Execution of a Final Design and Commission Agreement with Christopher Fennell, LLC for Final
Design, Fabrication, Delivery, Installation and Contingencies in an Amount of$793,398.00 for a Series of
Large-Scale Sculptures to be Located Along Four Miles of North Beach Street, Between Timberland
Boulevard and Shiver Road, 76244, Authorize Fund Transfer, and Adopt Appropriation Ordinance
(COUNCIL DISTRICTS 4 and 7)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a Final Design and Commission Agreement with Christopher Fennell, LLC for final design,
fabrication, delivery, installation and contingencies in an amount of$793,398.00 for a series of large-scale sculptures
to be located along four miles of North Beach Street, between Timberland Boulevard and Shiver Road, 76244;
2. Authorize the transfer of$100,128.00 from the Public Art-2008 CIP Programmable Project to the FWPA North
Beach Corridor Project to align with approved project budget as listed in the City Council-Adopted Fort Worth Public
Art Fiscal Year 2018 Annual Work Plan; and
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Street
Improvements 2008 Fund in the amount of$100,128.00 in the FWPA North Beach Corridor Project.
DISCUSSION:
Christopher Fennell, LLC will create a series of up to twelve (12) whimsical, kinetic"weather vane"
sculptures that will be placed in the center median along four miles of North Beach Street, between
Timberland Boulevard and Shriver Road. Each unique sculpture will have the form of a native animal, bird
or reptile, and will be made from locally-sourced recycled materials. The choice of materials will have a
humorous connection with the creature depicted, such as an armadillo made of truck bumpers and shovel
heads. Pivoting with the direction of the wind, the sculptures will be approximately 30 feet in height, 12
feet in width, and a depth of 2.5 feet. The number of sculptures feasible to be implemented within budget
will be determined at the end of the final design phase of this Agreement.
On July 26, 2017, Christopher Fennell, LLC was placed under a Preliminary Design Agreement (City
Secretary Contract No. 49441) in the amount of$17,480.00.
Fort Worth Art Commission (FWAC)Action: On February 12, 2018, the FWAC approved the artist's
preliminary design for artwork and recommended the artist be placed under a Final Design and
Commission Contract.
Funding for the final design and commission phases of the project has been allocated from the 2007
Critical Capital Needs Program and the 2008 Bond Program. The project was included in the Fort Worth
Public Art Fiscal Year 2018 Annual Work Plan, adopted by the Fort Worth City Council on October 17,
Logname: 06NORTH BEACH CORRIDOR PUBLIC ART PROJECT Page I of 3
2017, as M&C G-19139. Project budget and funding sources are as follows:
FUNDING SOURCES AMOUNT
2007 Critical Capital Needs Program $364,899.00
2008 Bond Program 1$428,251.00
2008 Bond, Programmable Pot P000071 $100,128.00
Total $893,278.00
PROJECT BUDGET FBUDGET CONTRACT(S)
Workshop and Visioning $ 21,350.00 CSC# 42945-A1
CSC#44549 (Fennell)
CSC#44547 (Klein)
Proposals From Four (4) Artist Finalists $ 21,800.00 CSC# 44548 (Ball-
Nogues)
CSC#44572-A1 (Zweig)
Preliminary Design by Zweig/Maginn 1 $ 39,250.0-01 CSC#46018-A1
Preliminary Design by Fennell 17,480.00$ CSC# 49441-A1
Final Design, Commission and $793,398.00 This M&C
Contingencies
TOTAL $893,278.00
M/WBE OFFICE -The City's overall M/WBE goal for the Fort Worth Public Art Program is 25 percent of
total capital project dollars expended on public art annually.
Council Members Moon and Shingleton concur with the FWAC's recommendation to proceed with final
design, fabrication, delivery, and installation of the North Beach Corridor Art Project.
The project is located in COUNCIL DISTRICT 4 and 7.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds in the amount of$693,270.00 are available in the North Beach
Corridor Public Art Project. Additionally, $100,128.00 in funds are available from the Programmable Pot
P00071 for appropriation to the North Beach Corridor Public Art Project upon M&C approval. This
appropriation will bring the total available funds for the commission phase to $793,398.00. Prior to an
expenditure being incurred, the participating department has the responsibility to validate the availability of
funds.
FUND IDENTIFIERS (FIDs):
TO
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID I I Year Chartfield 2
Logname: 06NORTH BEACH CORRIDOR PUBLIC ART PROJECT Page 2 of 3
FROM
Fund Department ccoun Project Program ctivity Budget Reference # moun
ID ID Year Chartfield 2
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (6122)
Originating Department Head: Randle Harwood (6101)
Additional Information Contact: Martha Peters (8172983025)
Logname: 06NORTH BEACH CORRIDOR PUBLIC ART PROJECT Page 3 of 3