HomeMy WebLinkAboutContract 45846-A3 C"'ECR'TgRy
CONTRACT N0._ S$�(�
AMENDMENT No. 2
pFFp EP TO CITY SECRETARY CONTRACT No. 45846
WHEREAS, the City of Fort Worth (CITY) and Half Associates, Inc. ,
(ENGINEER) made and entered into City Secretary Contract No. 45846, (the
CONTRACT) which was authorized by M&C C-26834 on the 10th day of June,
2014 in the amount of $850, 000 . 00; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment Number
1 in the amount of $110, 000 . 00 which was authorized by M&C C-27925 on the
20th day of September, 2016; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
City Project No. 2239 Design of Risinger Road from Crowley Road to
McCart Avenue; and
WHEREAS, it has become necessary to execute Amendment No. 2 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the additional
engineering services specified in a proposal dated June 4, 2018, a copy
of which is attached hereto and incorporated herein. The cost to City
for the additional design services to be performed by Engineer totals
$29, 600 . 00 (See Attached Funding Breakdown Sheet, Page -3-)
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $986, 600 . 00 .
3 .
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
City of Fort Worth
Professional Services Agreement Amendment Template
CFW Official Release 9/19/2017 FOFFICIAL RECORD
Page 1 of 4
SECRETAR
WORTH,TX
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED:
City of Fort Worth ENGINEER
Halff Associates, Inc.
C� 5e.. Z _A/
Stan Alan Be aurin L. M ahey, P.E.
Assistant City Manager
DATE: �' 16 DATE:
APP VAL RECOMMENDED:
Doug-giersig, P.E
Dire r Transportation and Public Works Department
APPROVED AS TO FORM AND LEGALITY: M&C:
Date:
Douglas W. Black
Assistant City Attorney
ATTEST.
O��ORr'�O
WAY J. Kay4dfr U
City Secretar
jEXpS
LO'FFICIALORDARYCity of Fort WorthProfessional Services Agreement Amendment Template TX
CFW Official Release 9/19/2017 _ --- --
Pape 2 of 4
CS45846 Amendment No. 2
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements .
WWN
Name of Employee
S,Cvnior PrJ-Lss;wtist �n h�t•r
Title
City of Fort Worth
Professional Services Agreement Amendment Template
CFW Official Release 9/19/2017
Page 3 of 4
FUNDING BREAKDOWN SHEET
City Secretary No. 45846
Amendment No. 2
Department FID Amount
TPW 34014 0200431 5330500 CO2239 CO2330 $29, 600 . 00
Total : $29, 600 . 00
City of Fort Worth
Professional Services Agreement Amendment Template
CFW Official Release 9/19/2017
Page 4 of 4
p;p HALFF
June 4,2018
AVO 30431
Mr.Leon Wilson,Jr.,P.E.
Senior Professional Engineer
Transportation and Public Works Department
1000 Throckmorton Street
Fort Worth,Texas 76102
Re: Risinger Road from Crowley Road(FM 73 1)to McCart Avenue
City Project No. 02239
Dear Mr. Wilson:
Please accept this letter proposal to provide median landscaping design and additional construction
administration necessary to complete the Risinger Road project. We are requesting payment for
these additional services in the amount of$29,600.00.
The original contract amount for this project was $850,000.00. With approval of Engineering
Amendment No. 1 the contract amount increased to $960,000.00. With approval of Engineering
Amendment No.2 the contract will increase to$989,600.00. The original SBE fee for this project
was $177,551.00 (20.89%). Engineering Amendment No. 1 increased the SBE fee to $202,551
(21.10%). With approval of Engineering Amendment No. 2 the SBE fee will remain $202,551
(20.47%).
If you have any questions,please call me at 817-764-7471.
Sincerely,
HALFF ASSOCIATES,INC.
Benjamin L.McGahey,P.E.
Attachments
ATTACHMENT "A"
Scope for Engineering Design Related Services for Street Improvements
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
OBJECTIVE
The objective of this project is to prepare schematic landscape plans, contract documents
and specifications for the medians along proposed Risinger Road from east of McCart
Avenue to Crowley Road. The project also includes preparing a detailed construction
phasing plan and construction contract time determination. The landscape design and
construction phasing shall be incorporated into the Risinger Road project currently in design.
WORK TO BE PERFORMED
Task 1. Design Management
Task 2. Conceptual Design
Task 3. Final Design
Task 4. Construction Manager Services
TASK 1. DESIGN MANAGEMENT.
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use
of ENGINEER's and CITY's time and resources. ENGINEER will manage change,
communicate effectively, coordinate internally and externally as needed, and proactively
address issues with the CITY's Project Manager and others as necessary to make progress
on the work.
1.1. Managing the Team
• Lead, manage and direct design team activities
• Ensure quality control is practiced in performance of the work
• Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting
• Attend a pre-design project kickoff/chartering meeting with CITY staff to confirm
and clarify scope, understand CITY objectives, and ensure economical and
functional designs that meet CITY requirements
• Conduct one (1) design review meetings with the CITY
• Prepare invoices, in accordance with Attachment B to this Standard Agreement
and submit monthly in the format requested by the CITY.
• Prepare and submit monthly progress reports in the format provided by the
respective CITY Department.
• Prepare and submit baseline Project Schedule initially, and Project Schedule
updates with a schedule narrative monthly, as required in Attachment D to this
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 1 of 5
Standard Agreement and according to the City of Fort Worth's Schedule Guidance
Document.
• Complete Monthly M/WBE Report Form and Final Summary Payment Report Form
at the end of the project
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare the
design
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs, and make changes necessary to meet
their requirements, as part of the design scope.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub-consultants shall carry readily visible
information identifying the name of the company and the company representative.
DELIVERABLES
A. Meeting summaries with action items
B. Monthly invoices
C. Monthly progress reports
D. Baseline design schedule
E. Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
F. Monthly M/WBE Report Form and Final Summary Payment Report Form
TASK 2. CONCEPTUAL DESIGN (30 PERCENT).
The Conceptual Design shall be submitted to CITY per the approved Project Schedule.
The purpose of the conceptual design is for the ENGINEER to identify, develop,
communicate through the defined deliverables, and recommend the design concept that
successfully addresses the design problem, and to obtain the CITY's endorsement of this
concept. ENGINEER will develop the conceptual design of the infrastructure as follows.
2.1. Site Investigation
• ENGINEER shall initiate and coordinate one (01) site investigation study related to
the site; ingress/egress; available r.o.w.; topography; soils composition and
analysis; utilities; and vegetation areas.
2.3. The Conceptual Design Package shall include the following:
• Based upon the site inventory, site analysis, and the project kick-off meeting,
ENGINEER shall prepare up to two (2) Concept Plan options showing planting
plan layouts to help communicate the design intent and vision of the project.
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 2 of 5
• ENGINEER shall conduct one (1) concept plan review meeting with the City to
present and review the preliminary concept plans.
• Based up on comments received from City staff, ENGINEER shall refine the
concept master plan and develop one (1) preferred alternative. The preferred
alternative shall be the basis for the development of the schematic design.
• Based up on the approved concept and comments received from City staff,
ENGINEER shall prepare a Schematic Plan in Cadd showing plant material
layout, concrete edging, and turf grass areas. Plans shall include planting
details, layout and quantities. The Schematic Plan shall be one strip plot
schematic (no profile) of roadway realignment and landscape areas to illustrate
the potential layout and identify issues and constraints.
• ENGINEER shall conduct one (1) schematic plan review meeting with the City for
final approval.
• Documentation of key design decisions.
• Estimates of probable construction cost.
ASSUMPTIONS
• No irrigation design services are included.
• One (1) design schematic and one (1) digital pdf file will be delivered for the 30%
design.
• ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Conceptual Design Package.
DELIVERABLES
A. Conceptual Design Package
TASK 3. FINAL DESIGN (90 PERCENT) AND FINAL CONSTRUCTION DOCUMENTS
(100 PERCENT).
• Based on the approved Schematic Design, ENGINEER shall prepare, for
approval by the City, a complete set of construction documents and
specifications as defined below. ENGINEER shall prepare and print one (01)
draft set and one (1) digital pdf file copy of drawings for review and comment.
Drawings and specifications will be incorporated into the roadway documents.
ENGINEER shall provide the following drawings for submittal:
• ENGINEER shall design the landscape planting plan. The landscape plan will
show all plantings, arrangement of plant materials, mow and minimal mow areas,
and landscape berms. The quantity, species, size and spacing of all materials will
be specified in a material schedule on the plan. Details for the proper installation
of plants will also be included. Plans will be sealed by a Licensed Landscape
Architect.
• The ENGINEER shall submit one preliminary and one final estimate of probable
construction cost for items to be included in overall project cost estimates.
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 3 of 5
Estimates shall be prepared utilizing standard cost and/or quantity estimate
practices.
• Construction specifications required for items included in the scope of this
proposal will be prepared and provided to the CITY.
ASSUMPTIONS
• Three (3) sets of half-size (11"x17") drawings and one (1) project manual will be
delivered for the 90% Design package.
• Three (3) sets of half-size (11"x17") drawings and one (1) project manual will be
delivered for the 100% Design package.
DELIVERABLES
A. 90% construction plans and specifications.
B. 100% construction plans and specifications.
C. Detailed estimates of probable construction costs including summaries of bid
items and quantities using the CITY's standard bid items and format.
D. Original cover mylar for the signatures of authorized CITY officials.
TASK 4. CONSTRUCTION MANAGER SERVICES.
ENGINEER will provide construction manager services for the project as follows:
• The ENGINEER shall develop a detailed construction sequencing plan for the
project. Plan notes and specifications shall be added/revised to require the
contractor to follow the included sequencing plan.
• The ENGINEER shall analyze the construction sequencing plan and develop a
construction time determination utilizing typical public works production rates for
construction.
• ENGINEER shall conduct one (1) review meeting with the City to present and
review the construction sequencing plan and contract time determination. The
ENGINEER shall revise the construction sequencing and contract time based on
comments from City staff.
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services
described in the tasks above. However, ENGINEER can provide these services, if
needed, upon the CITY's written request. Any additional amounts paid to the
ENGINEER as a result of any material change to the Scope of the Project shall be
agreed upon in writing by both parties before the services are performed. These
additional services include the following:
• Irrigation design.
• Negotiation of easements or property acquisition.
• Services related to development of the CITY's project financing and/or budget.
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 4 of 5
• Services related to disputes over pre-qualification, bid protests, bid rejection
and re-bidding of the contract for construction.
• Construction management and inspection services
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of
God.
• Services related to warranty claims, enforcement and inspection after final
completion.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Performance of miscellaneous and supplemental services related to the project
as requested by the CITY.
City of Fort Worth,Texas
Attachment A
PMO Release Date:02.06.2015
Page 5 of 5
ATTACHMENT B
COMPENSATION
Work Authorization Design Services for
Risinger Road From Crowley Road (FM731)to McCart Avenue
City Project No. 02239
Time and Materials with Rate Schedule Project
I. Compensation
a. The ENGINEER shall be compensated for personnel time, non-labor expenses,and
subcontract expenses in performing services for Task Orders up to$29,600.00 unless
amended. Each Task Order shall be Time and Materials.
I. Personnel Time. Personnel time shall be compensated based upon hours
worked directly in performing the PROJECT multiplied by the appropriate Labor
Category Rate for the ENGINEER's team member performing the work and
includes all direct salaries,overhead,and profit.
Labor Category Rate as presented in the rate schedule table below is the rate
for each labor category performing the work and includes all direct salaries,
overhead,and profit. Each labor category rate may include a number of
specialties. Labor category specialties are provided below.
Labor Category(Specialty):
Architect
Engineer(Civil,Structural, Mechanical, Electrical,Oil&Gas)
Scientist(Environmental and Geological)
Landscape/Planner
Surveyor
Field Tech (Survey,SUE, Environmental&Construction)
Office Tech (CADD, Designer&Surveyor)
Administrative(Accounting,Assistant, Marketing& Human Resources)
Specialist(GIS, ROW,Visualization & IT)
Intern
Labor Category Level Billing Rate Range
Low High
1 75.00 88.00
11 92.00 126.00
Architect III 149.00 161.00
IV 199.00 213.00
V 226.00 316.00
Engineer 85.00 110.00
II 107.00 145.00
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 1 of 5
B-1
ATTACHMENT B
COMPENSATION
III 142.00 211.00
IV 188.00 239.00
V 232.00 350.00
1 72.00 97.00
II 111.00 128.00
Scientist III 138.00 168.00
IV 170.00 215.00
V 213.00 350.00
1 72.00 88.00
11 88.00 121.00
Landscape/ III 112.00 152.00
Planner
IV 155.00 200.00
V 215.00 316.00
1 92.00 94.00
II 106.00 112.00
Surveyor III 133.00 142.00
IV 140.00 180.00
1 51.00 69.00
11 65.00 85.00
Field Tech III 86.00 102.00
IV 116.00 133.00
V 153.00 210.00
1 43.00 69.00
11 69.00 89.00
Office Tech III 86.00 120.00
IV 112.00 135.00
V 140.00 176.00
1 29.00 69.00
if 67.00 84.00
Administrative III 82.00 112.00
IV 111.00 137.00
V 148.00 350.00
1 66.00 97.00
II 97.00 133.00
Specialist III 124.00 171.00
IV 174.00 208.00
V 223.00 324.00
Intern 44.00 59.00
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 2 of 5
B-2
ATTACHMENT B
COMPENSATION
*The above rates are valid for a twelve month period commencing on City
execution of the contract. All rates are subject to annual adjustment which will
be submitted to City for review no later than thirty(30) days prior to such
escalation becomes effective.
II. Non-Labor Expenses. Non-labor expenses shall be reimbursed as Direct Expenses at invoice or
internal office cost.
Direct Expenses (Non-labor) include, but are not limited to, mileage, travel and lodging,
expenses, mail, supplies, printing and reproduction services, other direct expenses
associated with delivery of the work; plus applicable sales, use, value added, business
transfer,gross receipts, or other similar taxes.
III. Subcontract Expenses. Subcontract expenses and outside services shall be reimbursed at cost
to ENGINEER plus a markup often percent(10%).
IV. Budgets. ENGINEER will make reasonable efforts to complete the work within the budget and
will keep the City informed of progress toward that end so that the budget or work effort
can be adjusted if found necessary.
ENGINEER is not obligated to incur costs beyond the indicated budgets, as may be adjusted,
nor is the City obligated to pay ENGINEER beyond these limits.
If ENGINEER projects, in the course of providing the necessary services that the PROJECT
cost presented in Article 2 of this Agreement will be exceeded, whether by change in scope
of the project, increased costs or other conditions, the ENGINEER shall immediately report
such fact to the City and, if so instructed by the City, shall suspend all work hereunder.
When any budget has been increased, ENGINEER'S excess costs expended prior to such
increase will be allowable to the same extent as is such costs had been incurred after the
approved increase.
The Engineer shall be paid monthly payments as described in Section II — Method of
Payment.
V. Method of Payment
a. The ENGINEER shall be paid by the City based upon an invoice created on the basis of
statements prepared from the books and records of account of the ENGINEER, based on
the actual hours and costs expended by the ENGINEER in performing the work.
b. Each invoice shall be verified as to its accuracy and compliance with the terms of this
Agreement by an officer of the ENGINEER.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 3 of 5
B-3
ATTACHMENT B
COMPENSATION
c. ENGINEER shall prepare and submit invoices in the format and including content as
presented in Exhibit B-1.
d. Payment of invoices will be subject to certification by the City that such work has been
performed.
VI. Progress Reports. The ENGINEER shall prepare and submit to the designated representative of
the Transportation and Public Works Department monthly progress reports and schedules in
the format required by the City.
VII.A Summary of fees are listed in the following table.
I. Summary of Fees
Firm Primary Responsibility Fee Amount %
Prime Consultant
Halff Associates, Inc. Design & Construction $29,600.00 100%
Proposed MBE/SBE Sub-Consultants
Non-MBE/SBE Consultants
TOTAL $29,600.00 100%
Project Number & Name Total Fee MBE/SBE Fee MBE/SBE
Risinger Road (100%) $29,600.00 $0.00 0%
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 4 of 5
B-4
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across desired work types and work phases.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 5 of 5
B-5
Level of Effort Spreadsheet
TASKMOUR BREAKDOWN
Design Services for
Risinger Road from Crowley Road(FM 731)to McCart Avenue
City Project No.02239
Labor hourc Es e
Task Description Sr.Project Project Landscape Landscape Sr. Total Labor Total Expense
Task No. Principle Mana a Mana a PM Architech EIT CPDD Admin Cost Subconsultant Travel Reproductlan Cost Task Sub Total
Rate $842 $239 $188 $160 f700 $108 $122 $80 SBE 1 SBE 2) 5BE(3) Non-MWBE 8 Other
Landscape and Irrigation Services 00 0 39 1M 0 0 0 $20610 0. $0 $0 $0 $50 $0 $50 $20690
1.0 Desl n Mana ement
1.1.1 Internal Team Meetin s 4 3 $1,440 $0 $1640
1.1.2 Pre-D¢sl,Coordination ,ti,g 4 4 $1,04D $0 $1,040
2.0 Cance taxi Desi n
1.204 5ile lm,es0 atio, 4 4 si 040 $0 $1 Doo
1.22 Conce mPlan 4 16 $z,24D $D $2,240
123 Cit Review Meetin 4 4 $1040 $50 $50 $1,090
1 2,41 Final Gonce t Plan 2 16 1 51.920 1 $0 $1,920
125 Scnem,rl Desitin 16 $1920 $D $1,920
126 Cast Estimatin 2 e $1120 $0 $1,120
3.0 Final Design
1.3.1 Design and CD Sheet S-p 4 40 $4640 $0 $4,640
132 Pop—Estimale of Probable Gesl 2 8 $1,120 $0 $1,120
1.33 Prepare Prows eci6catens 2 8 $1,120 $0 $1,120
1,3 4 DNDC D-g,Review 4 4 $1040 0 $1,040
135 Res and tc DNDG Gommenis 1 8 $960 0 $960
4.0 Canet—ti—Mana er Services 16 8 8 0 0 0 0 0 $6988 $e $0 $0 $0 $22 $0 $22 $8910
4.1 C' Review Meetin 5 2 4 4 4 $3,076 $22 $22 $3,098
62 Consnmclion Se uence Plan 6 2 2 52,906 $0 $2,906
a 3 s 2 2 s2,906 $D $2 Safi
Totals 76 8 8 39 144 0 0 0 529,528 f0 EO SO $0 $72 0 $721 529,800
Project Summary
Total Hours 215
Total Labor $29,528
Tonal Ex en $72
MBDSBE Subcons—nil $0
N—MB ELBE Subconsullant $0
tM Sub Marku $0.00
MBF—Radici atien 0.0°%
Total Pro ect Cost $29,600
City of Fort Worth,Teras
PXechmerd B-Level of Effort Supplement
PMO DAoial Release Date:8.09.2012
lei