HomeMy WebLinkAboutContract 49576-CO2 CITY SECRETARY FORTWORTH. City of Fort Worth CONTRACT NO.- �'11�� Change Order Request Breakdown Project Namel 2014 CIP Yr 3,Contract 8 City Sec# 1 49576 Client Project#(s) 56011/39411/39412-0600430/0700430/0200431-CO2696 Contractorl Woody Contractors,Inc PM Mary Hanna Inspectorl Ariel Duarte Change Order Submittal# Date 6/1212018 Dept. Water Unit 1 Sewer Unit 2 Paving Unit 3 Totals Contract TimeCD Original Contract Amount $468,223.45 $1,214,135.00 $758,722.50 $2,441,080.95 300 Extras to Date $18,451.00 $18,451.00 30 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $468,223.45 $1,232,586.00 $758,722.50 $2,459,531.95 330 Amount of Proposed Change Order $0.00 $23,700.00 $0.00 $23,700.00 10 Revised Contract Amount $468,223.45 1,256,286.00 $758,722.50 2,483,231.95 340 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 $0.00 $0.00 Additional Funding(if necessary) $23,700.00 $23,700.00 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 1 1.73% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) 1 $3,051,351.19 change order is needed to remobilize and rework 8"SS for CIPP or possible Pipe Bursting.To repair the existing line required moving some existing structures and then moving those structures back to their original location A7 Mary J. K � `, Cify Secr>3twy TEXAS RECEIVED OFFICIAL RECORD JUL 10 2018 CITY SECRETARY CITYOFFORTWORTH CITYSECRETARY FT.WORTH,TX City of Fort Worth Change Order Additions Project Name 2014 CIP Yr 3,Contract 8 City Sec# 49576 Client Project# 56011139411139412-06004301070043010200431-CO2696 Contractor Woody Contractors,Inc PM Mary Hanna nspector Ariel Duarte Change Order Submittal# 0 Date 6/12 2018 ADDITIONS Unit Unit os o a 50 Remobilize ewer ni 5 Rework 8'SS for CIPP Sewer Unit Water Unit 1 $0.00 Sewer Unit 2 $23,700.00 Paving Unit 3 $0.00 Sub ota itEns Change Order Additions Page 2 of 4 FORT WORTH City of Fort Worth 'I- Change Order Deletions Project Name 1 2014 CIP Yr 3,Contract 8 City Sec# 4957fi Client Project# 1 56011/39411/39412-0600430/0700430/0200431-CO2696 Contractor Woody Contractors,Inc PMJ Mary HannaInspectoF Ariel Duarte Change Order Submittal# I�2 Date 6/12 2018 DELETIONS ITEM DESCRIPTION JLFI Qty Unit Unrt Total Water Unit 1 $0.00 Sewer Unit 2 $0.00 Paving Unit 3 $0.00 Sub otaDeletions Change Order Deletions Page 3 of 4 M/SBE Breakdown for this Change Order M/SBE Sub Type of Service Amount for this CO N/A Total $0.00 Previous Change Orders Co# DATE AMOUNT 1 3/7/2018 $18,451.00 Total $18,451.00 CFW Change Order Approval Wa-COApp02 Page 2 of 4 FORT WORTH. city of Fort Worth -�•-••,� --- Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: 2 Change Order No.: Wa-COApp02 Date Started: 6/20/2018 City Sec. No.: 49576 Date Due: 8/9/2018 Project Name: 2014 CIP Year 3 — Contract 8 Project Numbers: 02696 DOE Numbers: Project Paving, water and sanitary sewer replacemnets on Galvaz Ave. (from Description: Denair to Gross St) and 4th St (from Covelo Ave to Denair St) City Project Mgr.: Mary Hanna City Inspector: Ariel Duarte Contractor: Woody Contractors, Inc. COUNCIL ACTION (If Required): M&C Log Name: N/A M&C Number: M&C Date: COST AND DAYS SUMMARY: Department: Cost($) Fund Account Center: Requested Days: Water Department $ 23,700.00 56011-0700430-5740010-c026! 10 Total: $ 23,700.00 Total Requested Days: 10 Approval Status: https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&ProcessI... 7/10/2018 CFW Change Order Approval Wa-COApp02 Page 3 of 4 Approved: Yes Comments: User: Troy Woody Date: 2018-06-21 9:42 AM Approved: Yes Comments: User: Mary Hanna Date: 2018-06-21 11:44 AM Approved: Yes Comments: User: Troy Woody Date: 2018-06-21 4:11 PM Approved: Yes Comments: User: Mary Hanna Date: 2018-06-21 4:19 PM Approved: Yes Comments: User: Walter Norwood Date: 2018-06-21 4:46 PM Approved: Yes Comments: User: John Kasavich Date: 2018-06-21 5:02 PM Approved: Yes Comments: User: Chris Harder Date: 2018-07-06 12:27 PM Approved: Yes Comments: K. Morgan no longer with CFW bypassed by Fred Griffin User: Kenneth Morgan Date: 2018-07-06 1:33 PM Approved: Yes Comments: User: Doug Black Date: 2018-07-10 8:00 PM Approved: Yes Comments: User: Jay Chapa https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&Processl... 7/10/2018 CFW Change Order Approval Wa-COApp02 Page 4 of 4 Date: 2018-07-10 4:07 PM Action Required: Please review and approve https:Hprojectpoint.buzzsaw.com/ bz_web/Forms/FormPrint.aspx?Siteld=51500&ProcessI... 7/10/2018 Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Q✓ Name f Employee/Signature Sr. Title This form is N/A as No City Funds are associated with this Contract Printed Name Signature