HomeMy WebLinkAboutContract 50552-A1 �1 CITY SECRETARY
AMENDMENT No.1 CONTRACT NO. S� �Z
G`�tG EGQ�P�� TO CITY SECRETARY CONTRACT No. 50552
WHEREAS, the City of Fort Worth (CITY) and Kimley-Horn and
Associates, Inc. , (ENGINEER) made and entered into City Secretary
Contract No. 50552, (the CONTRACT) which was administratively authorized
on the 21St day of March, 2018 in the amount of $ 8, 480. 00; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
E. Lancaster at Beach Pedestrian Crossing Improvements; and
WHEREAS, it has become necessary to execute Amendment No. 1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in a proposal dated July 24, 2018, a copy
of which is attached hereto and incorporated herein. The cost to City
for the additional design services to be performed by Engineer totals
$27, 780. 00. (See Attached Funding Breakdown Sheet, Page -3-)
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $36,260. 00.
3.
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED: OFFICIAL RECORD
City of Fort Worth
Professional Services Agreement Amendment Template CITY SKCRETAW
CFW Official Release 9/19/2017
Page 1 of 3 I e WORTHS TX
City of Fort Worth ENGINEER
Kimley-Horn and Associates, Inc.
Su Alanis Scott R. Arnold, P.E.
Assistant City Manager Assistant Secretary
DATE: 13 DATE:
APPROVAL RECOMMENDED:
Z� a C'j,
Douglas 19. Wiersig, P.E.
Director, Transportation and Public Works Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements .
0'4` ..............
Clint Hoover, P.E.
Senior Professional Engineer
APPROVED AS TO FORM AND LEGALITY: M&C:
�-R�x Date:
Douglas W. Black
Assistant City Attorney
ATTEST:
Of �®
Mary J. ays r
City Secretary
S
OFFICIAL RECORD
City of Fort Worth Wry■ SURA '
Professional Services Agreement Amendment Template WoRtif 'tea,
TX
CFW Official Release 9/19/2017 j
Page 2 of 3
FID BREAKDOWN SHEET
City Secretary No. 50552
Amendment No. 1
Department FID Amount
TPW
Total:
City of Fort Worth
Professional Services Agreement Amendment Template
CFW Official Release 9/19/2017
Page 3 of 3
Kimley�7> Horn
July 24, 2018
Clint Hoover, P.E.
City of Fort Worth—Transportation and Public Works Department
200 Texas Street
Fort Worth, Texas 76102
Re: Amendment#1
CSN 50552—Design Services for E. Lancaster at Beach Pedestrian Crossing Improvements
Dear Clint:
Kimley-Horn and Associates, Inc. ("Kimley-Horn"or"Consultant") is pleased to submit this Amendment
#1 to the City of Fort Worth (City) to provide additional services for the design of the E. Lancaster at
Beach Pedestrian Crossing Improvements.
The following Scope of Services has been developed based on our discussions with the City.
Scope of Services
Kimley-Horn will provide the services specifically set forth below.
Task 3—Intersection Schematic and Opinion of Probable Construction Costs (OPCC)
Kimley-Horn will prepare two (2) intersection schematic to depict the two (2) options discussed with
City staff at the coordination meeting held on July 18, 2018. OPCC's for each option will also be
prepared.
Task 4—Pedestrian Crossing Design Plans
Kimley-Horn will prepare 90%and Final plans for the chosen alternative, in accordance with City and/or
TxDOT standards and specifications. The improvements are anticipated to include: median nose
modification on the west side, installation of actuated pedestrian equipment (pedestal poles, conduit,
cable, pedestrian heads, push buttons, etc), and modification of curb ramps and sidewalk.
Kimley-Horn will prepare for and attend one(1) plan review meeting with the City to discuss comments
on the 90% plans.
Kimley-Horn will also coordinate with TxDOT, as necessary, regarding their resurfacing project and to
obtain a driveway permit.
Kimley-Horn will prepare the construction task order package and attend the pre-construction meeting.
Task 5—Construction Phase Services
Kimley-Horn will perform the following tasks:
- Attend bi-weekly construction meetings during construction. Up to four (4) meetings are
included.
- Review up to one (1) shop drawing and up to four(4) RFI's.
801 - - 950, Fort Worth, Texas
K i m ey.'O H o r n Page 2
- Schedule and pay for the TDLR inspection of the project. Additional inspections due to
construction deficiencies shall be paid by the Contractor.
- Attend the punch list meeting and the final walk-through meeting.
- Prepare record drawings upon receipt of Contractor red lines.
Additional Services
Any services not specifically provided for in the above scope will be billed as additional services and
performed at our then current hourly rates
Schedule
We will provide our services in a mutually agreed upon schedule following Notice to Proceed from the
City. Additional services, if desired, will be performed in a timely manner upon authorization by the
City.
Fee and Expenses
Kimley-Horn will perform the services in Tasks 3—5 for a not-to-exceed fee of$27,780. All permitting,
application, and similar project fees will be paid directly by the Client.
Kimley-Horn will not exceed the total maximum labor fee shown without authorization from the Client.
We appreciate the opportunity to provide these services to you. Please contact me if you have any
questions.
Very truly yours,
KIMLEY-HORN AND ASSOCIATES, INC.
By: Scott R. Arnold, P.E.
Project Manager, Assistant Secretary
801■iiiWiiilY Cherry Suite •
Level of Effort Spreadsheet
TASKMOUR BREAKDOWN
Design Services for
E.Lancaster at Beach Pedestrian Crosswalk Improvements
City Project No.02670
Labor hours Ex ense
Task Description Project Project Sr.Project Project Total Labor _ Total Expense
Task No. Director Ma na er En ineer En ineer EIT CADD Atlminiatrative Cos[ Subconsultant Travel Fees Cost Tasty Sub Total
Rate $230 $205 $115 $i55 $125 $100 $90 SBE Non-SBE
3.0 Intersection Schematic and OPCC D 2 0 D 14 D D $2160 $0 $0 $0 $0 $0 $2,160
3.1 Prepare Two 2 Schematics 1 10 $1,455 $0 $1,455
3.2 Prepare Two 2 OPCC's 1 4 $705 $0 $705
4.0 Pedestrian CrossingDesign Plans 0 13 4 0 132 0 0 $19,86 $0 $0 $0 $0 $D $19,665
4.1 Pre are 90%plans 2 2 80 $10,760 $0 $10,760
4.2 - Atlend 90%plan review meeting 2 2 $660 $0 $660
4.3 Prepare 100!plans 2 2 40 $5,760 $0 $5,760
4.4 TxDOT Coordination/Permit 6 6 $1,980 $0 $1,980
4.5 Construction Task Order Package 1 4 $705 $0 $705
5.0 Construction Phase Services 0 4 0 0 33 0 0 $4,945 $0 $600 $150 $0 $750 $5,695
5.1 Bi-Week) Construction Meetings(4 each 1 8 $1,205 $100 $100 $1,305
5.2 - Review ShopDrawin 1 $125 $0 $125
5.3 ReviewlRes and to RFPs 4 each) 2 8 $1,410 $0 $1,410
5.4 TDLR Inspection 4 $500 $600 $25 $625 $1,125
5.5 Punch List and Final Walk Throu h Meetings(2) 6 $750 $25 $25 $775
5.6 Record Drawings 1 6 $955 $0 $955
Totals ll 19 4 0 179 0 0 $26,970 $0 $600 $150 SO $750 $27,720
Project Summary
Total Hours 202
Total Labor $26,970
Total Expense $750
MBEISBE Subconsultant $0
Nan-MBE/SBE Subconsultant $600
10% Sub Markup $60
MBEISBE Partici alion 0.0%
Total Project Cost $27,780
City of Fort Worth,Texas
Attachment El-Level of Effort Supplement
PMO Official Release Date:8.09.2012
1 of 1