HomeMy WebLinkAboutContract 28006-A7 RECEIVED CITY SECRETARY
REC
AUG E I E AMENDMENT No.7 CONTRACT NO.
CITYOFFORTWORTH TO CITY SECRETARY CONTRACT
CITYSECRETARY
WHEREAS, the City of Fort Worth (CITY) and Dannenbaum
Engineering Corporation, (ENGINEER) made and entered into City
Secretary Contract No. 28006, (the CONTRACT) which was authorized
by M&C C-19172 on the 30th day of July, 2002 in theamount of
$721,899.76; and
WHEREAS, the CONTRACT was subsequently revised by:
Amendment Number 1 in the amount of $111,800 .52 which was
authorized by M&C C-19936 on January 20 , 2004, Amendment No.2 in
the amount of $329,406.00 which was authorized by M&C C-22535 on
November 27 , 2007 , Amendment No. 3 in the amount of $96,825 .00
which was authorized by M&C C-23578 on June 9, 2009 and Amendment
No. 4 in the amount of $60,835.00 which was authorized by M&C C-
24794 on March 22, 2011, Amendment No. 5 in the amount of
$149,012.00 which was authorized by M&C C -28110 on February 14,
2017, Amendment No. 6 in the amount of $63,751 .00 which was
administratively authorized on October 11 , 2017; and
WHEREAS, the CONTRACT involves engineering services for
the following project:
Sanitary Sewer Main 257 and 325 Middle and Upper Village Creek
Parallel Relief Alignment Study and Design; and
WHEREAS, it has become necessary to execute Amendment No.
7 to the CONTRACT to include an increased scope of work and
revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and
through their duly authorized representatives, enter into the
following agreement, which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the
additional engineering services specified in a proposal dated
June 12 , 2018, a copy of which is attached hereto and incorporated
herein. The cost to City for the additional design services to
be performed by Engineer totals $21,860 .00.
2 .
Article II of the CONTRACT is amended to provide for an
increase in the fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall bean
amount of $1,555,389.28.
3. OFFICIAL.RECORD
CITY SECRETARY
+r,WOIRTH,TX
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED: ENGINEER
City of Fort Worth MDanneum Engineerin Corporation,
Jesus J. Chapa Wayn G. Ahrens, P.E.
Assistant City Manager Executive Vice-President
DATE: 7-1 DATE:
APPROVAL RECOMMENDED:
C(- a L
Christopher Harder, P.E.
Acting Director, Water Department
APPROVED AS TO FORM AND LEGALITY:
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring
all performance and reporting requirements.
Name of Employee
tle: Project Manager
MSC: N/A
96�2k Date N/A
Douglas W. Black
Senior Assistant City Attorney `. ,.
AT ,
ry J. Kayser
City Secretary
TEA �..
OFFICIAL.RECORD
CITY SECRETARY
FT.WORTH,TX
DANNENBAUM ENGINEERING CORPORATION
2501 PARKVIEW DRIVE,SUITE 670, FORT WORTH,TEXAS 76102
June 12, 2018
Mr.John Kasavich, P.E.
City of Fort Worth
Water Department
1000 Throckmorton Street
Fort Worth,TX 76102
Re:Sanitary Sewer M-257&325 Middle&Upper Village Creek Parallel Relief Alignment Study&Design
City Secretary Contract No. 28006-Amendment No.7
City Project No. 01333
DEC Project No. 3642-32
Dear Mr. Kasavich:
Dannenbaum Engineering Corporation, (Dannenbaum or ENGINEER) is pleased to provide the City of Fort Worth
(CITY) with Amendment No.7 for the Sanitary Sewer Main 257 & 325 Middle and Upper Village Creek Parallel
Relief Alignment Study contract (the PROJECT). The CITY has asked Dannenbaum to perform additional services
under this contract for:
1) Additional Tree Survey — Preparing additional tree survey within Deer Creek Park to cover alignment
adjustments made within the Park since the original contract design survey.
2) Additional TRWD Easement Parcels — Preparing additional permanent sanitary sewer and access
easements and temporary construction easement parcels created as a result of a transfer of property
ownership to Tarrant Regional Water District (TRWD)for a portion of project Parcel 11 west of IH-35W.
This property transfer occurred after the current easement parcel documents had been submitted to the
City.
3) Revised Deer Creek Park Reservation Parcels—Preparing revised permanent and temporary construction
reservation parcels within Deer Creek Park to cover alignment revisions made within the Park to reduce
impacts to existing trees and proposed Park improvements known as "Capital Improvements at Deer
Creek Park, City Project No. 100418" (Park Project).
4) Additional management and design services associated with Deer Creek Park - Additional meetings,
coordination and design revisions related to reducing impacts to existing trees and the proposed Park
Project improvements.
These services are necessary because:
1) Alignment adjustments in Deer Creek Park associated with site visits and discussions with Water
Department and Park & Recreation Department (PARD) staff required that the tree survey be extended
to additional areas within the Park.
2) Additional permanent and temporary construction easement parcels were created as a result of a transfer
of property ownership to Tarrant Regional Water District (TRWD)for a portion of project Parcel 11 west
of IH-35W. This property transfer occurred after Dannenbaum submitted the current easement parcel
documents to the City.
3) Based on meetings and discussions with Park & Recreation Department (PARD) and Water Department
staff, alignment revisions are required in Deer Creek Park to adequately protect existing trees and the
referenced Park Project improvements.
4) A portion of the Park Project's proposed playground and concrete trail improvements that encroach on a
portion of the currently proposed M-325 temporary construction easement alignment as established in
coordination with PARD in September,2012. Dannenbaum was notified on 3/28/18 that the Park Project
was going to bid on 3/29/18 and was provided the Park Project construction plans at that time. PARD with
Sanitary Sewer Main 257&325 Middle and Upper Village Creek Parallel Relief Alignment Study and Design-Amendment No.7
DEC No.3642-32
Page 2 of 4
the Water Department's concurrence asked Dannenbaum to investigate ways to reduce impacts to trees
and the Park Project improvements. Dannenbaum's investigations resulted in meetings with various
construction contractors and PARD and Water Department staff. From these meetings, Dannenbaum
prepared design revisions to reduce Park impacts, which were then presented to and approved by PARD
and Water Department staff.
The additional services required are as follows:
1) Additional Tree Survey - Additional tree survey within Deer Creek Park to cover alignment adjustments
made within the Park since the original contract design survey, is to be performed by ANA Consultants,
LLC (ANA). This work is classified as Special Services under former Part 2-Main 325 Design Phase and
current Work Phase 51 of the contract.The scope of work is described in Attachment A.—Subconsultant's
Scope of Work. Fee=$2,960(Lump Sum).
2) Additional TRWD Easement Parcels — Add permanent sanitary sewer and access easements, and
temporary construction easement parcels created as a result of a transfer of property ownership to
Tarrant Regional Water District (TRWD) for a portion of project Parcel 11 west of IH-35W that occurred
after the current easement parcel documents had been submitted to the City. This work is to be
performed by ANA, and is classified as Special Services under former Part 2-Main 325 Design Phase and
current Work Phase 51 of the contract.The scope of work is described in Attachment A—Subconsultant's
Scope of Work. Fee=$3,200.00(Lump Sum).
3) Revised Deer Creek Park Reservation Parcels—Revise permanent and temporary construction reservation
parcels within Deer Creek Park to cover alignment revisions required to adequately protect existing trees
and referenced proposed Park Project improvements. This work is to be performed by ANA Consultants,
LLC (ANA). This work is classified as Special Services under former Part 2-Main 325 Design Phase and
current Work Phase 51 of the contract.The scope of work is described in Attachment A.—Subconsultant's
Scope of Work. Fee=$700 (Lump Sum).
4) Additional management and design services associated with Deer Creek Park — Additional meetings,
design studies,correspondence,exhibits,easement and design changes associated with reducing impacts
to existing trees and the proposed Project Park improvements within Deer Creek Park. Fee=$15,000.00
(Time &Materials).
Dannenbaum will perform/manage the work described in the items above forthis Amendment in accordance with
the original Contract.
We recommend that the City increase the budget by$21,860 for these additional services as follows:
The recommended breakdown for survey Items, 1)through 3),for subconsultant ANA is:
Description Fee %Amend No. 7
Additional Tree Survey $2,960 14.33%
Easement Revisions $3,900 17.84%
Total(Work Phase 51) $6,860 31.38%
The recommended breakdown for engineering design and management services, Item 4),for Dannenbaum is:
Description Fee
Design/Mgmt/Coord. $15,000
Total (Work Phase 33) $15,000
Overall M/WBE Fees and%of Contract are also presented in attached Exhibit B,Tab Exhibit B-3A Fee Summary.
\\us-ftw-fs01\data\ftwdata\projects\1210\3642-32\admin\agreement\supplemental#7\amendment exhibits\main 325 sa7 cover letter rev04.docx
Sanitary Sewer Main 257&325 Middle and Upper Village Creek Parallel Relief Alignment Study and Design-Amendment No.7
DEC No.3642-32
Page 3 of 4
The following table summarizes the Fee per Work Phase breakdown:
Work Phase Fee
33 (Design/Coordination) $15,000
51(Survey) $6,860
Total $21,860
These Services are presented in further detail in attached Exhibit B,Tab Exhibit B-3.
The following table summarizes our recommended budget revisions and shows the revised contract amount:
Current Contract Through Revised Contract
Amend No.6
Description Amend No.7
Original Work New Work Original Work New Work
Phase Phase Phase Phase
Part 1-Alignment Study $145,727.46 $145,727.46 - $145,727.46 $145,727.46
Part 2-Main 325 Design $1,072,879.99 $860,116.99 $1,072,879.99 $860,116.99
Work Phase 51(Survey) $44,000.00 $6,860.00 - $50,860.00
Work Phase 33(Design,Design Support) - $168,763.00 $15,000.00 $183,763.00
Part 3—Village Creek Basin Rehab Part 4 $231,929.54 $231,929.54
Part4—Main 238 Basin Rehab $82,992.29 $82,992.29
Total Project $1,533,529.28 $21,860.00 $1,555,389.28
The following table summarizes original and supplemental agreement dates,fee and scope for this contract:
Contract Summary to date:
Description Date Amount Description
Original Agreement 7/30/2002 $721,899.76
1 Supplemental Agreement#1 1/20/2004 $111,800.52 Addition&Modification of Various Lines
2 Supplemental Agreement#2 12/26/2007 $329,406.00 Main 325 Design
3 Supplemental Agreement#3 9/1/2009 $96,825.00 Addition and Modification of Alignment
4 Supplemental Agreement#4 4/12/2011 $60,835.00 Revise Align.East of Huguley(Surv,Esmt,EID)
5 Supplemental Agreement#5 3/5/2017 $149,012.00 Realignment of 7075 LF of Main 325
6 Supplemental Agreement#6 10/11/2017 $63,751.00 Incr.Pipe Size to 48",Util.Locates,Access Esmts.
7 Supplemental Agreement#7 Pending $21,860.00 Revise Deer Creek Park Esmt Parcels,Add TRWD Esmt Parcels
Mgmt/Dgn Revisions-Deer Creek Park
Total 1 $1,555,389.28
It is proposed that fu nding for this amendment be drawn from the previously approved contract Amendment
No. 5 (dated 3/5/2017) budget for the acquisition of Easement Parcels 15PE(r01) and 15CE(r01) (Reference
Exhibit C—Amendment 5—Exhibits 4 and 5 )which are located on Deer Creek Park, property owned by the City
of Fort Worth. A cost of$123,954 was inadvertently assigned to cover acquisition costs for these two
reservation parcels and is included in the Amendment No. 5 budget (Reference Exhibit D—City Council Action
Ref No.C-28110,dated 2/14/2017).
Since the two reservation parcels are located on City property,there is no easement acquisition cost associated
with them, and the$123,954 amount is available to cover the contract budget increase for this amendment(No.
7)of$21,860, plus the previous Amendment No. 6 (dated 10/11/2017)fee of$63,751.
\\us-ftw-fs01\data\ftwdata\projects\1210\3642-32\admin\agreement\supplemental#7\amend ment exhibits\main 325 sa7 cover letter rev04.docx
Sanitary Sewer Main 257&325 Middle and Upper Village Creek Parallel Relief Alignment Study and Design-Amendment No.7
DEC No.3642-32
Page 4 of 4
We appreciate the opportunity to be of continued service to the City. Please contact us if we need to provide
any further information.
Very truly yours,
Dannenbaum Engineering Corporation
Digitally signed by Douglas E Guinn
Date:2018.06.12 13:39:03-05'00'
Douglas E. Guinn, P.E.
Sr. Project Manager
DEG/JCP
Attachments:
Attachment A—Subconsultants'Scope of Work
Exhibit B—Summary of Manhours and Project Fees
Exhibit C—Amendment 5—Exhibits 4 and 5
Exhibit D—City Council Action Ref No. C-28110,dated 2/14/2017
\\us-ftw-fs01\data\ftwdata\projects\1210\3642-32\admin\agreement\supplemental#7\amendment exhibits\main 325 sa7 cover letter rev04.docx
ATTACHMENT A
\\us-ftw-fs01\data\ftwdata\projects\1210\3642-32\admin\agreement\supplemental#7\amendment exhibits\main 325 sa7 cover letter rev04.docx
Attchment A—Subconsultant's Scope of Work
ADDITIONAL TREE SURVEY(DEER CREEK PARK)
Scope of Work -Field tie and show tree locations,species and trunk diameters within the noted
boundary on the attached exhibit (within the Temporary Construction and Permanent Easements),for
all trees trunk sizes 6" and larger. Deliverable shall consist of an AutoCAD design base file on Main 325
Parallel Relief Sewer project datum and using the same project symbology as provided in prior CADD
submittals.
Tree Survey Field Work- 16 hours @ $160/Hour= $2,560.00
Tree Survey Office Work-4 hours @ $100/Hour= $400.00
ADDITIONAL EASEMENT PARCEL(TRWD)
Scope of Work -Provide documents necessary for the acquisition of one (1)additional permanent
sanitary sewer easement,one (1)additional access easement and one(1)additional temporary
construction easements, located west of IH-35W owned by Tarrant Regional Water District, and
revisions to one (1) permanent sanitary sewer easement,one (1)access easement and one (1)
temporary construction easement, previously prepared for property owned by W1 & LL Luck.
Provide two (2) signed and sealed real property descriptions and maps of survey for each easement to
be acquired.
Two (3) new easements +Two (3) revised easements=$3,200.00
REVISED RESERVATION PARCEL(DEER CREEK PARK)
Scope of Work -Revise one (1)temporary construction and one (1) permanent sanitary sewer
reservation documents within Deer Creek Park to coincide with sanitary sewer alignment revisions made
to reduce impacts to existing trees and proposed improvements within Deer Creek Park, identified as
City Project No. 100418.
Provide two (2)signed and sealed real property descriptions and maps of survey for each easement to
be dedicated.
Two (2) revised easements =$700.00
EXHIBIT B
\\us-ftw-fs01\data\ftwdata\projects\1210\3642-32\admin\agreement\supplemental#7\amendment exhibits\main 325 sal cover letter rev04.docx
EXHIBIT B-3 Page 1 of 4
(SUPPLEMENT TO ATTACHMENT B)
SUMMARY OF TOTAL PROJECT FEES -SUPPLEMENTAL AGREEMENT NO. 7
SANITARY SEWER MAIN 257&325 MIDDLE & UPPER VILLAGE CREEK
PARALLEL RELIEF ALIGNMENT STUDY & DESIGN
CITY PROJECT NO. 01333
DOE NO. 3650
Phase Scope of Services Fee SUBCONSULTANT % M/WBE
I-Design Services
Part 1 Alignment Study,
Part 2 Main 325 Design
Engineering $ 15,000.00 $ - 0.0%
Survey(ANA) $ 2,960.00 $ 2,960.00 100.0%
Easement Adustments(ANA) $ 3,900.00 $ 3,900.00 100.0%
Geotechnical (Geotel) $ - $ - 0.0%
$ - 0.0%
TOTAL $ 21,860.00 $ 6,860.00 31.4%
Proposed M/WBE Subconsultants Fees % M/WBE
TOTALS $ 6,860.00 31.4%
Exhibit B-Summary of Manhours and Project Fees(Amendment 7)r04.x1sx 6/10/2018
EXHIBIT B-3A FEE SUMMARY Page 2 of 4
(SUPPLEMENT TO ATTACHMENT B)
SUMMARY OF TOTAL PROJECT FEES -SUPPLEMENTAL AGREEMENT NO. 7
SANITARY SEWER MAIN 257&325 MIDDLE& UPPER VILLAGE CREEK
PARALLEL RELIEF ALIGNMENT STUDY&DESIGN
CITY PROJECT NO.01333
DOE NO.3650
BASIC ENGINEERING DESIGN FEE: FEE SUBCONSULTANT %M/WBE
Deer Creek Park Coordination/Design Changes $ 15,000.00 $ - 0.0%
SUBTOTAL(BASIC ENGINEERING DESIGN FEE) $ 15,000.00 $ - 0.0%
SPECIAL SERVICES
Field Survey(ANA Consultants) $ 2,960.00 $ 2,960.00 100.0%
Easement Adjustments(ANA Consultants) $ 3,900.00 $ 3,900.00 100.0%
Environmental(Blanton) $ - $ - 0.0%
Geotechnical(Geotel) $ $ 0.0%
0 $ - $ - 0.0%
SUBTOTAL(SPECIAL SERVICES) $ 6,860.00 $ 6,860.00 100.0%
CONSTRUCTION SERVICES
Construction Phase Services $ - $ - 0.0%
As-Built Drawings $ - $ - 0.0%
SUBTOTAL(CONSTRUCTION SERVICES) $ - $ - 0.0%
REPRODUCTION/DIRECT EXPENSES
8 Sets Review Plans $ - $ - 0.0%
16 Sets Preliminary Plans(Utility Clearance) $ - $ - 0.0%
50 Sets Construction Plans $ - $ - 0.0%
50 Sets Specifications $ - $ - 0.0%
As-Built Plans $ - $ - 0.0%
1 Set Mylar Plans $ - $ - 0.0%
AUTO EXPENSE $ - $ - 0.0%
Mounted Exhibits for Public Meetings $ - $ - 0.0%
SUBTOTAL(REPRODUCTION) $ - $ - 0.0%
10%SUB-CONTRACTOR MARK-UP $ -
TOTAL LUMP SUM FEE(THIS ADDENDUM) $ 21,860.00 $ 6,860.00 31.4%
Exhibit B-Summary of Manhours and Project Fees(Amendment 7)r04.xlsx 6/10/2018
EXHIBIT B-3A FEE SUMMARY Page 3 of 4
PROPOSED MIWBE SUBCONSULTANTS
(THIS ADDENDUM) PROPOSED SERVICES FEES %CONTRACT
ANA Consultants Survey $ 6,860.00 31.4%
Blanton&Associates Environmental $ - 0.0%
Geotel Geotechnical $ - 0.0%
TOTAL M/WBE(THIS ADDENDUM) $ 6,860.00 31.4%
PROJECT TOTALS FEE M/WBE %M/WBE
Original Contract $ 721,899.76 $ 203,001.00 28.1%
Amendment#1 $ 111,800.52 $ 26,672.00 23.9%
Amendment#2 $ 329,406.00 $ 130,728.00 39.7%
Amendment#3 $ 96,825.00 $ 48,760.00 50.4%
Amendment#4 $ 60,835.00 $ 31,240.00 51.4%
Amendment#5 $ 149,012.00 $ 99,239.00 66.6%
Amendment#6 $ 63,751.00 $ 7,850.00 12.3%
This Amendment $ 21,860.00 $ 6,860.00 31.4%
TOTAL LUMP SUM FEE(PROJECT TOTAL) $1,555,389.28 $554,350.00 35.6%
TOTAL M/WBE(CITY M/WBE GOAL=18%) $554,350.00 35.6%
Exhibit B-Summary of Manhours and Project Fees(Amendment 7)r04.xlsx 6/10/2018
MANHOURS Page 4 of 4
DANNENBAUM ENGINEERING CORPORATION
SUMMARY OF MANHOURS BY CLASSIFICATION
SUMMARY OF TOTAL PROJECT FEES-SUPPLEMENTAL AGREEMENT NO.7
M-325 ENGINEERING DESIGN&SUPPORT SVCS.-1)SURVEY/EASEMENTS;2)DEER CREEK PARK COORDINATIONIDESIGN CHANGESIMANAGEMENT
AMENDMENT N7
DEC ESTIMATED MANHOURS PER TASK BY CLASSIFICATION TOTAL TOTAL
TASK DESCRIPTION OF WORK TASK QUANTITY PROJ SENIOR STRUCT/ PROJECT SR DGN TECH. QA/Q, MHIs COST
CODE PRINCIPAL MGR ENGR HYOR ENG ENGR TECH. CARD REVIEW SECTY PER PER
QNTY UNIT $270.00 $230.00 $185.00 $150.00 $120.00 $1%00 $60.00 $185.00 $65.00 TASK TASK
DESIGN PHASE ENGINEERING
0120 PROJECT MANAGEMENT 1 LS 12.0 12.0 2,780.00
0103 CONFERENCES/COORDINATION 5 EA 15 15 16 46.0 7,985.00
2400 FINAL DESIGN
COVER SHEET 0 SHEET 0.0 0.00
GENERAL CONSTRUCTION NOTES 0 SHEET 0.0 0.00
GENERAL SEWER NOTES 0 SHEET 0.0 0.00
.FRCP GENERAL NOTES 0 SHEET 0.0 0.00
LOCATION MAP 0 SHEET 0.0 0.00
SHEET LAYOUT&CONTROL 2 SHEET 1.0 4.0 8.0 1.0 14.0 2,035.00
SAN.SEWER PLAN&PROFILE 2 SHEET 1.0 4.0 8.0 2.0 15.0 2,220.00
SAN.SEWER DETAILS 0 SHEET 0.0 0.00
SW3P DETAIL SHEETS 0 SHEET 0.0 0.00
TRAFFIC CONTROL PLANS 0 SHEET 0.0 0.00
OPINION OF PROBABLE CONSTRUCTION COST 0 LS 0.0 0.00
BID PROPOSAUSPECIFICATIONS 0 LS 0.0 0.00
0.0 0.00
0.0 0.00
GRAND TOTAL 4 0.0 29.0 23.0 0.0 0.0 320 0.0 3.0 0.0 87.0 15,000.00
0.00% 33.33% 26.44% 0.00% 0.00°h 36.78% 0.00% 3.4546 0.00% 100.00%
DIRECT LABOR COSTS: $ 15,000.00
SUBCONTRACTORS
FIELD SURVEY(ANA)(MANBE) $ Zs 0.00
EASEMENT ADJUSTMENTS(ANA] (MANSE) $ 3,900.00
ENVIRONMENTAL(BLANTON)(MM/BE) $ -
GEOTECHNICAL(GEOTEL)(MANSEI $ -
MANBE Participation: 31.4% TOTAL SUBCONTRACTOR COSTS $ 6,860.00
0%SUBCONTRACTOR MARKUP $ -
TOTAL DEC COSTS(LABOR+MARKUP) $ 15,000.00
TOTAL COSTS(DEC+SUBS) $21,860.00
Exhibit B-Summary of Manhours and Project Fees(Amendment 7)r04.xlsx 6/10/2018
EXHIBIT C
\\us-ftw-fs01\data\ftwdata\projects\1210\3642-32\admin\agreement\supplemental#7\amendment exhibits\main 325 sa7 cover letter rev04.docx
--PRQP UPDATEIIALLCNM
II I (CONTRA TAMEN MEfyT�10. 5)
II
i
IPL ALIGNSIENT --
103 --
I� PERM ESMT ` `—
I 30'(T1P) A
X41 203B
Inoas
205 B
6ECOPIDCRO68ING , , ,-'Pp I -� 80'(17P) r PROPOSED
2000 ALIGNMENT AIJGNAEPd?r I
105C
106A 206C
PERH Es.HT
40'cryp)
PERM
E6MT /
-�I,r..T. �•�•s rc _ 1 10'(T1P) ••,L,"=EXISTE6.HTJ�� I TOWER 102 , I
20.
ONCOS �'ONCOH
nM, n^..,.• I 201
—.7 INITLII.
100'(TYP� [ I ie o•. ALIGNMENT
m �
3� 4r .
II LHUGULEY '
I'Sti•I I yt I HOSPITAL I `�
EASEMENT ACQUISITION EXHIBIT CTAT DEPART RTMENTS
WATER DEPARTMENT
FOR UPDATED ALIGNMENT VILI I,AN RA°RARIELI �N
MAN 325TNOPARALLELP1 0-070 SEWER
WATER PROECT NO,P170-O7017074W.10
mTr�Q1°'''V10 Rn THE nx�io•ars DATA SHOWN HERE 15 APPROXIMATE AND SUBJECT TO UPDATED SURVEY 0.0.E PROJECT NO.3550
'2�1_0S TEMPOR TEMPORARY CONSTREPERMANENT UCTIONREASEMENT R ELL516D•I,„DT11 DAN N E N BAU M
SOUARE FOOTAGE IN ACCOMPANYING EXCEL SPREADSHEET. M325 Amendment Nn,5 Proposed E°semenlsaly,EahiElt C-1 ENGINEERING CORPORATION
T.6 P FlRM REGISTRATION W41
°Are°7/L7IIS -
-E d ra, cva,°vw-=."n� .-
NP.
nza
Amendment S-Exhibit S
This spreadsheet is an estimate of square footages for the easements anticipated for the proposed Amendment No.5 revised alignment of Main 32S. Note that this
assumes that where permanent easements are adjacent to the 150'wide TRWD IPL easement,that the closest 60'of the 150'easement width cannot be used as a
temporary construction easement and that this will need to be acquired as temporary construction easement for the Main 325 project.Only easements for this
revised alignment are included.This spreadsheet accompanies the"Exhibit 4-Easement Acquisition Exhibit For Updated(Amendment No.5)Alignment"
Amendment No.5 Permanent Easements
Estimated Estimated
Parcel Owner(At Time of Survey)
SF cost($)*
14PE(r01) 26,627 66,568 Oncor Electric Delivery Co.,VOL 3539 PG 642 and VOL 6175 PG 135,DRTCT
15PF(rol) 37,676 94,190 City of Fort Worth,1000 Throckmorton St.TAD Account#07658680
101 12,013 30,032 Oncor Electric Delivery Co.,VOL 3625 PG 321 and VOL 6597 PG 713,DRTCT
102 36,127 90,318 Adventist Health Systems/Sunbelt Inc. d/b/a Huguley Memorial Medical Center,Tract 1 VOL 9144 PG 1217 DRTCT
103 71,976 179,940 Adventist Health Systems Sunbelt Inc. d/b/a Huguley Memorial Medical Center,TCCI No.D20S351192,OPRTCT
104 22,146 55,365 Sharon R.Luck-4356 Salix Court,Fort Worth,Texas 76109,TCCI No.D214000601,OPRTCT
105 51,683 129,208 William J.Luck&Dorothy Luck Credit Trust, 7108 Camp Bowie Blvd Fort Worth,TX 76116 VOL 12610 PG 60S DRTCT
106 8,238 0 City of Fort Worth,1000 Throckmorton St.TCCI No.D212172218,OPRTCT
107 20,105 S0,263 Lewisville 7 Partners,LTD.,Tract 1(Remainder)VOL 16555,PG 31 DRTCT
Total 286,591 695,882
*Note: Estimated $2.50/51' permanent easement cost used was provided by the Tarrant Regional Water District(TRWD) based on their costs for nearby IP
easement acquisition.Estimated$0.50/SF temporary construction easement costs is based on discussions with the City of Fort Worth Water Department staff as
to a reasonable estimated value of 20%of permanent easement cost.Dannenbaum Engineering makes no warranty on the level of accuracy or applicability of this
unit price to these easement parcels.If a greater level of accuracy and/or applicability of these unit costs is desired,an appraisal should be conducted by a real
estate professional qualified in pipeline appraisals.
Page 1 of 2
Amendment 5-Exhibit 5
Amendment No.5 Temporary Construction Easements
Parcel EstimatedEstimated
Cost aced Owner(At Time of Survey)
SF
14CE(r01) 39,924 19,962 Oncor Electric Delivery Co.,VOL 3539 PG 642 and VOL 6175 PG 135,DRTCT
1SCE(r01) 59,529 29,764 City of Fort Worth,1000 Throckmorton St.TAD Account#07658680
201 18,021 9,010 Oncor Electric Delivery Co.,VOL 3625 PG 321 and VOL 6597 PG 713,DUCT
202 54,352 27,176 Adventist Health Systems/Sunbelt Inc. d/b/a Huguley Memorial Medical Center,Tract 1 Vol 9144 PG 1217 DRTCT
203A 93,537 46,769 Adventist Health Systems Sunbelt Inc. d/b/a Huguley Memorial Medical Center,TCCI No.D205351192,OPRTCT
203B 14,398 7,199 Adventist Health Systems Sunbelt Inc. d/b/a Huguley Memorial Medical Center,TCCI No.D205351192,OPRTCT
204 27,446 13,723 Sharon R.Luck-4356 Salix Court,Fort Worth,Texas 76109,TCCI No.D214000601,OPRTCT
205A 35,371 17,686 William 1.Luck&Dorothy Luck Credit Trust, 7108 Camp Bowie Blvd Fort Worth,TX 76116 VOL 12610 PG 60S DRTCT
205B 46,499 23,250 William J.Luck&Dorothy Luck Credit Trust, 7108 Camp Bowie Blvd Fort Worth,TX 76116 VOL 12610 PG 605 DRTCT
206 1,388 694 City of Fort Worth,1000 Throckmorton St.TCCI No.D212172218,OPRTCT
207A 9,299 4,650 Lewisville 7 Partners,LTD.,Tract 1(Remainder)VOL 16555,PG 31 DRTCT
2078 30,353 15,177 Lewisville 7 Partners,LTD.,Tract 1(Remainder)VOL 16S5S,PG 31 DRTCT
Total 430,117 215,058
Grand Tota! 716,708 910,941
*Note: Estimated $2.50/SF permanent easement cost used was provided by the Tarrant Regional Water District(TRWD) based on their costs for nearby IPL
easement acquisition.Estimated$0.50/SF temporary construction easement costs is based on discussions with the City of Fort Worth Water Department staff as
to a reasonable estimated value of 20%of permanent easement cost.Dannenbaum Engineering makes no warranty on the level of accuracy or applicability of this
unit price to these easement parcels.If a greater level of accuracy and/or applicability of these unit costs is desired,an appraisal should be conducted by a real
estate professional qualified in pipeline appraisals.