HomeMy WebLinkAboutIR 9022INFORMAL REPORT TO CITY COUNCIL MEMBERS
To the Mayor and Members of the City Council
SUBJECT: Alley Maintenance Services
No. 9022
March 10, 2009
Page 1 of 2
This Informal Report provides a response to the City Council's request for information on the
recent alley maintenance bid award process.
Mr. Bryan Blagg, representing Blagg Building Co., 206 Churchill Court, WeatherFord, Texas,
appeared before the City Council on February 24, 2009, relative to being the low bidder for an
alley maintenance contract. He expressed appreciation for the opportunity, but advised that he
had received some resistance from the Purchasing Division because his bid was too low. He
advised City Council that his bid was $0.16 per foot and $85.00 per alley and that he stood by
that bid. He requested assistance to determine if his bid would be accepted.
The Purchasing Division (Purchasing) along with the Transportation and Public Works
Department (TPW) reviewed the process to date and find that despite Mr. Blagg's concerns, the
process to award this agreement is moving along in a fair, open and expedient manner. This
award process brings the action before City Council in less than one month from the day the bids
were opened and saves the City over $300,000.00, which may be retained or used to complete
additional alley cleanings or other projects. The awarded agreements are expected to also
exceed the five percent M/WBE project goal by at least one percent.
Before any bid is awarded, it is the City's responsibility to exercise due diligence to ensure that
bidders recommended for awards are capable of perForming the agreements and that their bids
meet or exceed the specifications. This confirmation of bids is normally handled by the
requesting City departments, in this case TPW, as the subject matter experts on the goods or
services requested. Purchasing does not normally contact bidders during an evaluation process
unless there are questions about their bids. Purchasing reviews and approves departments' bid
confirmation efforts and recommendations before making a recommendation to the City Council.
The due diligence process began immediately following the opening of the bids for this
agreement.
These alley maintenance bids opened February 12, 2009. The low bidder and other bidders met
with Purchasing the day after the bid opening. The bidders in attendance were informed that the
City would evaluate the bids and staff would try to have an unofficial bid tabulation available by
Friday, February 13, 2009. At this time a meeting was scheduled with the low bidder, Blagg
Building Co. (Blagg), to review several alleys with TPW representatives on Friday, February 13,
2009. The bid tabulation was generated by Purchasing and posted on the City's webpage that
Friday as anticipated.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
To the Mayor and Members of the City Council
SUBJECT: Alley Maintenance Services
No. 9022
March 10, 2009
Page 2 of 2
On February 16, 2009, TPW conducted a site visit of the low bidder's facility to verify that the
bidder's equipment was adequate to perform the specified work. Following its review of the
bidder's equipment and references, TPW recommended Blagg, the low bidder, for award as the
lowest bidder meeting or exceeding specifications on February 18, 2009. In order to ensure
continuity of performance of this important work, Purchasing recommended that the second low
bidder be awarded an agreement as well should additional alleys be added to the scope and
exceed Blagg's capacity. Blagg will be responsible for cleaning the 1,039 alleys specified under
its agreement, if and when awarded.
Purchasing had not had a chance to review the recommendation when Mr. Blagg contacted our
office to follow up on his bid. Purchasing had also not yet received confirmation from the M/WBE
Office that Blagg's bid was in compliance with the M/WBE goal. These processes may take
several days. When Mr. Blagg contacted our office about the award process and status, he was
advised that the typical M&C approval timeframe could result in an award in April 2009 and that
the current agreement may have to be extended to maintain alley cleaning services for TPW
while the award recommendation was routing for approvals.
Purchasing advised Mr. Blagg of its concerns about the award due to the large gap between the
first and second low bids as well as the consequences that his company could suffer if it was
awarded an agreement which it failed to perform. There may have been a misunderstanding at
this point as Purchasing intended only to provide full disclosure of possibilities and did not intend
to offend Mr. Blagg in any way.
Purchasing has been in contact with Mr. Blagg in recent days and has worked to keep him
informed of the upcoming award process. We look forward to a successful business relationship
with Blagg Building Co. following award of today's action.
If you have any questions regarding this information, please contact Jack Dale, Purchasing
Manager, at (817) 392-8357 or Lena Ellis, Financial Management Services Director/CFO, at (817)
392-8517.
Dale A
City Manager
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS