Loading...
HomeMy WebLinkAboutContract 33587 � Y CTARY + T Y"*LE SPECIFICATIONS ' CONTRACT NO t<A::TOR'S BONDING CO. . C�;NSTRUCTION'S COPY AND CLIENT [)EPARTNIENT CONTRACT DOCUMENTS FOR HMAC SURFACE OVERLAY (2006-3) AT VARIOUS LOCATIONS IN THE CITY OF FORT WORTH, TEXAS DOE PROJECT NO. 5202 TPW PROJECT NO. GS93-020930522810 2006 MIKE MONCRIEF CHARLES R. BOSWELL MAYOR CITY MANAGER ROBERT D. GOODE, P.E., DIRECTOR DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS A. DOUGLAS RADEMAK.ER, P.E., DIRECTOR .. DEPARTMENT OF ENGINEERING PREPARED BY DEPARTMENT OF ENGINEERING ENGINEERING SERVICES DIVISIONy EXHIBIT 66A99 ... co ................... o _, . N L SCHWINHG • o r' 69+69 :'e ORIGINAL . 06-06-06 P01 : 24 I ``' C ` zooms r ()x'r WORTH WWWWXFW"_*1t49"___ - ----­­­-......___­_------ .......... Home I Council Agenda I M&C I Employee Directoty I Morning Report I Ads I PRS I IT Online t Departments I Site Map Print M&C COUNCIL ACTION: Approved on 5/9/2006 DATE: 5/9/2006 REFERENCE NO.: C-21449 LOG NAME: 303OHMAC06-3 CODE: C TYPE: NON-CONSENT PUBLIC HEARING: NO SUBJECT: Authorize Execution of Contract with Peachtree Construction, Ltd for HMAC Surface Overlay 2006-3 at Various Locations RECOMMENDATION: It is recommended that the City Council authorize the City Manager to execute a contract with Peachtree Construction, Ltd in the amount of$1,213,496.00 for HMAC Surface Overlay 2006-3 at various locations. DISCUSSION: In the FY2005-2006 Contract Major Maintenance Program, various types of street maintenance techniques are grouped into specific contract packages. HMAC (Hot Mix Asphaltic Concrete) Surface Overlay 2006-3 at various locations provides for surface and base rehabilitation, curb, gutter and valley gutter replacements for asphalt streets funded from the Contract Street Maintenance Fund. The attached list details the limits for each of the streets for this project. The City reserves the right to increase or decrease quantities of individual pay items within the contract, provided that the total contract amount remains within plus or minus 25% of the contract award. This project was advertised for bid on January 26 and February 2, 2006. On March 23, 2006, the following bids were received: BIDDERS AMOUNT Peachtree Construction, Ltd $1,213,496.00 Peachtree Construction, Ltd, is in compliance with the City's M/WBE Ordinance by committing to 19% M/WBE participation. The City's goal on this project is 17%. This project is located in COUNCIL DISTRICTS 2 and 9. FISCAL INFORMATION/CERTIFICATION: The Finance Director certifies that funds are available in the current capital budget, as appropriated, of the Contract Street Maintenance Fund. TO Fund/Account/Centers FROM Fund/Account/Centers GS93 541200 020930522810 $1,213,496.00 Submitted for City Manager's Office by: Marc Ott (8476) Originating Department Head: A. Douglas Rademaker (6157) Additional Information Contact: A. Douglas Rademaker(6157) ATTACHMENTS 3030hmac3.pdf ADDENDUM NO. 1 CITY OF FORT WORTH HMAC 2006-3 AT VARIOUS LOCATIONS DOE No. 5202 TPW PROJECT NO. GS93-020930522810 Addendum No. 1 Issue Date: February 15,2006 Bid Receipt Date: March 16, 2006 This addendum forms part of the contract documents referenced above and modifies the original Contract Documents. Acknowledge receipt of this addendum by signing and attaching it to the Contract Documents (inside). Note receipt of the Addendum in the Bid Proposal and on the outer envelope of your bid. Prospective bidders are hereby informed that the bid opening date has been postponed from March 2, 2006 until March 16, 2006. The pre-bid conference has been postponed from February 15, 2006 to March 1, 2006 at 9:00 a.m. in the Transportation and Public Works Conference Room, 2nd Floor, Municipal Building,RM 270. All other provisions of the plans, specifications and contract document for the project which are not expressly amended herein shall remain in full force and effect. Failure to return a signed copy of the addendum with the Proposal shall be grounds for rendering the bid non-responsive. A signed copy of this addendum shall be placed into the Proposal at the time of bid submittal. Receipt Acknowledged: Department of Engineering A. Douglas Rademaker, P.E. Director Title: PRESIDENT By: Oh S /a Tony 9holola, P.E. Engineering Manager, DOE ADDENDUM NO. 1 . t • 1 t ADDENDUM NO. 2 CITY OF FORT WORTH HMAC 2006-3 AT VARIOUS LOCATIONS DOE No. 5202 TPW PROJECT NO. GS93-020930522810 Addendum No. 2 Issue Date: February 28,2006 Bid Receipt Date: March 16, 2006 This addendum forms part of the contract documents referenced above and modifies the original Contract Documents. Acknowledge receipt of this addendum by signing and attaching it to the Contract Documents (inside). Note receipt of the Addendum in the Bid Proposal and on the outer envelope of your bid. The pre-bid conference has been postponed from March 1, 2006 at 9:00 a.m. to March 8, 2006 at 8:30 a.m. in the Transportation and Public Works Conference Room, 2nd Floor, Municipal Building, RM 270. All other provisions of the plans, specifications and contract document for the project which are not expressly amended herein shall remain in full force and effect. Failure to return a signed copy of the addendum with the Proposal shall be grounds for rendering the bid non-responsive. A signed copy of this addendum shall be placed into the Proposal at the time of bid submittal. Receipt Acknowledged: Department of Engineering A. Douglas Rademaker, P.E. Director By: PRESIDENT Title: By: Tony Sholola, P.E. Engineering Manager, DOE ADDENDUM NO.t MAR-14-2006 TUE 03;20 PM city Of Fw-Enginee;, Dept FAX N0. 817 871 6828 _... . _.._... P. 02/23 Addendum No. 3 (20063) ADDENDUM NO. 3 CITY OF FORT WORTH TTMAC 2006-3 AT VARIOUS LOCATIONS DOE No, 5202 TPW PROJECT NO.GS93-020930522810 Addendum No. 3 Issue Date: March 14,2006 Bid Receipt Date: March 23, 2006 This addendum (forms part of the contract documents referenced above and modifies the original Contract Documents. Acknowledge receipt of this addendum by signing and attaching it to the Contract Documents(inside). Note receipt of the Addendum in the Bid Proposal and on the outer envelope of your bid. 1. Prospective bidders Are hereby informed that the bid opening date has been postponed from March 16,2006 until March 23,2006. The primary purpose of this addendum is to clarify the following: 2. Replace page P-2 of the Proposal in its entirety with the enclosed revised page P-2R (Addendum No. 3) (2006-3). 3. Replace page P-3 of the Proposal in its entirety wi 11 the enclosed revised page P-3R (Addendum No. 3) (20063). 4, Replace page P-4 of the Proposal in its entirety with the enclosed revised page P-4R (Addendum No. 3) (2006-3). 5. Replace page P-5 of the Proposal in its entirety with the enclosed revised page P. (Addendum No. 3) (2006-3). 6. Replace page P-6 of the Proposal in. its entirety with the enclosed revised plage P-6.R (Addendum No. 3) (2006-3). 7. On page SP-6 of the Special.Provisions, Ite-a No. 10, Traffic Control: add the following paragraphs before the last paragraph of this item: On downtown streets, the Contractor may work during the day between 9:00 a,m. until 4 p.m. and/or at night,Monday thru Friday,between 6 p.m.to 6 a.m. and/or Saturday except for couflicling Scheduled events. On Elm St.,the Contractor may work during the day between 7:00 a.m.until 6 p.m. 1 MAR-14-2006 TUE 03:21 PM City Of Fw-Engineer, Dept, FAX N0. 817 871 6828 P. 03/23 Add.endumNo. 3 (2006-3) 8. On.page SP-16 of the Special Provisions, Non.Pay Item No. 8, No Paving Work on Solid Waste Weekly Pick up Day: • From pre-bid meeting discussion, the definition of paving activities is.further chirified to not include construction of concrete flat work. The Contractor,therefore,will be allowed to construct concrete flatwork on the solid waste weekly pick-up day. 9. On.page SP-18 of the Special Provisions, for Pay Iten1 No. 3,Manhole Adjustment: • From pre-bid meeting discussion,the set unit price for manhole adjustment willl remain at$400.00 per each. • replace the following paragraphs: The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch.Work shall be completed and street open to traffic within seven(7)calendar days. If the contractor fails to complete the work within seven (7) calendar days, a $100 dollars liquidated damage will be assessed per each manhole per day. with: The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch.Work shall be completed and street open to traffic within five(5) calendar days. If tate contractor falls to complete the work within five (5) calendar days, a $100 dollars liquidated damage will be assessed per each manhole per day. 10. On page SP-18 and SP-1.9 of the Special Provisions, :for Pay Item No. 4, Water Valve Boxes Adjustment: • From pre-bid meeting discussion,the set unit price for water valve boxes adjustment will remain at$300.00 per each. • replace the following paragraphs. The concrete shall be designed to achieve a inin.imurn compressive strength of 3000 pounds per square inch,Work shall be completed and street open.to traffic within seven(7)calendar days. If the contractor fails to complete the work within. seven. (7) calendar days, a $100 dollars liquidated damage will be assessed per each water valve box per day. with: The concrete shall be designed to achieve a minimum compressive strenl;th of 3000 pounds per square inch.Work shall be completed and street open to traffic within five(5) calendar days. 2 MAR-14-2006 TUE 03:21 PM City Of Fw-Engineer, Dept FAX N0, 817 871 6828 P. 04/23 Addendum No. 3 (2006-3) If the contractor fails to complete the work within five (5) calendar days, a $100 dollars liquidated damage will be assessed per each water valve box per day. 11. On page SP-20 of the Special Provisions, Pay Item No. 7, Removal and Replacement of 6" Concrete Driveways: o add the following paragraph before the last paragraph of this item: o The concrete driveways shall be complete within Seven (7)calendar days from the day of demolition to date of cninpletion. If the contractor fails to complete the work within seven (7) calendar days, a $100 dollar liquidated damage will be assessed per block per day. 12. On page SP-20 of the Special Provisions, Pay Item No. 8, Removal and Replacement of 4" Concrete Sidewalk: • add the following paragraph before the last paragraph of this item: a The concrete sidewalks shall be complete within seven (7) calendar days from the day of demolition to date of completion. If the contractor fails to complete the work within seven (7) calendar days, a$100 dollar liquidated damage will be assessed per block per day. 13. On page SP-21 of the Special,Provisions,Pay Itern No. 9, Removal and Replacement of H.M:.A.C. Pavement and Base: o add the following paragraph before the last paragraph of this item: a The 11M.A.C. pavement and base shall be complete within seven (7) calendar days from the day of demolition to date of completion. If the contractor fails to complete the work within seven (7) calendar days, a $100 dollar liquidated damage will be assessed per block per day. 14. On page SP-22 of the Special Provisions, Pay Item. No. 11, Wedge Milling 2" To 0" :Depth 5.0"Wide, 1. Description; add the following paragraph before the last paragraph of this section: • If the existing base is brick and cannot be wedge milled, then the existing brief base,of 5-foot in width, shall be removed ander Pay Item No. 24 "UNCLASSIFIED STREET EXCAVATION", and replaced under Pay Item No. 13 "U MAC LEVEL UP', prior to placing H.M.A.C, surface course. See Pay Item No. 24 "UNCLASSIFIED STREET EXCAVATION",for further description of work. 3 hIAR-14-2006 TUE 03 21 11 PM City Of. Fw-Eneineer, Dept FAX N0, 817 871 6828 P. 05/23 Addendum No. 3 (2006-3) 15. O4tge SP-23 of the Special Provisions,Pay Item No, 12, Butt Joints—.Milled: From pre-hid meeting discussion,the butt,joints shall be milled in lieu of saw cul.. 16. On page SP-24 of the Special Provisions,Pay Item No. 13, H.M.A.C.Level Up: • replace the following paragraphs: This item shall be used to fill ruts, depressions, level up pavement section with J:ype "p" stir-face mix (PG 64-22) prior to placing the asphalt surface overlay and where needed as directed by the;Engineer in the field_ with: This item shall be used to till ruts,depressions,level up pavement section with Type°°n" surface mix(PG 76-22)prior to placing the asphalt surface overlay and where needed as directed by the Engineer in the field. 17. On page SP-25 of the Special Provisions, for Pay Item No. 1.4, 2" H.M.A.C. (Type"D" Mix)Asphalt Cement Surface Course: second paragraph from bottom of the page, • replace the following paragraph: • Under Item 340.2,Materials,U. Asphalt Binder: Furnish performance-graded. PG 64-22 for H.M.A.C. surface course, level up and pavement base repair or replacement. with: • Under Item 340.2,Materials,P. Asolialt Binder: Furnish performance-graded PG 76-22 for H.M.A.C. surface course and level up. Furnish performance-graded PG 64-22 for H M.A.C. pavement and base repair or replacement. o add the following paragraph on page SP-27 as the hast paragraph of this item: The H,M.A.C. pavement and base shall be complete within seven (7) calendar days from the day of demolition to date of completion. If the contractor fails to complete the work within seven (7) calendar days, a $100 dollar liquidated damage will be assessed per block per day. 18. On page SP-27 of the Special Provisions, for Pay Item No. 15, Removal and Replacement of 7"Concrete Valley Gutter: a replace the following paragraphs: Contractor may substitute 5" non-reinforced (2:27) Concrete Base in lieu. of Crushed Stone at no additional.cost. See Item No. 360 "Concrete Pavement(enclosed). 4 MAR-14-2006 TUE 03;21 PM City Of Fw-Engineer, Dept FAX N0, 817 871 6828 P. 06/23 _ . U - it Addendum No. 3 (2006-3) The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch.Contractor shall work on one-half of Valley Gutter at a time, and the other?half shall be open to traffic.Work shall,be completed on each hal.:f within seven(7)calendar days. If the contractor :Fails to complete the work on each half within seven (7) calendar days, a $100 dollars liquidated damage will be assessed per each half of valley gutter per day. with: Contractor may Substitute 5" non-reinforced (2:27) Concrete Base in lieu of Crushed Stone at no additional cost. See Item No. 360 "Concrete Pavement (enclosed). Surface texturing shall be made with a medium broom in lien of carpet drug or metal tining. The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch.Contractor snail work on orae-half of Valley Gutter at a time,and the other half shall be open to traffic.Work shall be completed on each half within three(3)calendar days, If the contractor fails to complete the work on each half within three (3) calendar days, a $100 dollars liquidated damage will be assessed per each half of valley gutter per daffy. 19. On page SP-28 of the Special, Provisions, for Pay Item No. 16, New 7" Concrete Valley Gutter: * replace the following paragraphs. Contractor .may substitute 5" .non-reinforced (2:27) Concrete Base in lieu. of Crushed. Stone at no additional cost. See Item No. 360 "Concrete Pavement(enclosed). The concrete shall be desilmed to achieve a minimum compressive strength of 3000 pounds per square inch.Contractor shall work on one-half of Valley Gutter at a time,and the othi.-r half shall be open to traffic. Work shall be completed on each half within seven(7)calendar days. 1f the contractor fails to complete the work on each half within seven (7) calendar days, a $100 dollars liquidated damage will be assessed.Per each half of valley gutter per day. With: Contractor may substitute 5" non-reinforced (2:27) Concrete Base in lieu of Crushed Stone at no additional cost. See Item No. 360 "Concrete Pavement (enclosed). Surface texturing shall be made with a medium broom in lieu of carpet drag or metal Lining. The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch. Contractor shall work on one-half of Valley Gutter at a time, and the other half shall be open to traffic. 'Work shall be completed on each half within three (3) calendar days. S �W-14-2006 TUE 03;22 PM City Of Fw-Engineer, Dept , FAX NO. 817 871 6828 P. 07/23 Addendum No.3 (2046-3) If the contractor rails to complete the work on each half within three(3) calendar, days, a $100 dollars liquidated damage will be assessed per each half of valley gutter per day. 20. On. page SP-29 of the Special Provisions, for pay Item No. 17, New 4" �,'tandard 'Wheelchair Ramp: • add the following paragraphs before the last paragraph of this item; The wheel chair ramps shall be complete within seven (7)calendar days from the day of demolition to date of completion. If the contractor fails to complete the work within seven (7) calendar days, a $100 dollar liquidated damage will be assessed per uilock per day, 21. On. page SP-33 of the Special Provisions, for Pay Item No. 24, Unclassified Street Excavation: • add the following paragraphs as the last paragraph of this item: This item shall also be used for removing and disposing the existing brick base., if the existing brick base cannot be wedge or surfaced milled, prior to placing 2" HMAC Type °`D" surface course. The void created by removing the existing brick base shall be filled to the proper grade,with Pay Item No. 13—IIHMAC LEVEL IJP", before placing 2" I MAC Type"D"surface course. For wedge milling, the measurement for estimating the removal and disposal of the existing brick material shall be a width of 5-feet, a length of curb and gutter and a depth of 3-inches. For surface milling, the measurement for estimating the removal and disposal of the existing brick material shall be the surface area and the depth of 3-inches. These measurements shall be under Item No. 106 "UNCLASSIFIED STREET EXCAVATION". 22. On page SP-34 of.the Special Provisions,:Pay Item No. 25, 2" Surface Milling: • add the following paragraph as the second last paragraph of this item: If the existing base is brick and cannot be surfaced milled,then the existing brick base shall be removed under Pay Item No. 24 "UNCLASSITIED STREET EXCAVATION", and replaced under Pay Item No. 13 11H.MAC LEVEL IJP", prior to placing H.M.A.C. surface course. See Pay Item No. 24 "UNCLASSIFIED STREET EXCAVATION", 'W further description of work- 6 _MAR-14-2006 TUE 03:22 PM City Of Fw—Engineer. Dept FAX N0. 817 871 6828 P. 08/23 Addendum No. 3 (2006-3) 23. On page SP-34 of the Special Provisions, for Pay Item No, 26, Removal and Replacement of 6"Exposed Concrete Driveway: • replace the following- PAY-ITEM NO. 26 - REMOVAL AND REPLACEMENT OF 6" EXPOSED CONCRETE DRIVEWAYS: This item shall include the removal and replacement of existing concrete; driveway;, due to deterioration or in situations where curb and gutter is replaced to adjust grades to eliminate ponding water with same day haul-off of the removed material to a suitable dump site. For specifications governing this item see Item No. 104 "Removing Old Concrete", Item No, 504" Concrete Sidewalk and Driveways". Pay limits for concrete driveway are as shown in Drawing No. S-SS of the Standard Specifications. The unit price bid per square yard shall be full compensation for all labor, material, equipment, supplies,said incidentals necessary to complete the work. with.. PAY-ITEM NO. 26 - REMOVAL AND RE,PLACEME OF 6" EXPOSED CONCRETE AGGREGATE DRIVEWAYS ANDSIDEWALK: This item shall include the removal and replacement of existing exposed aggregate concrete driveways and sidewalk, due to deterioration or in situations where curb and gutter is replaced to adjust grades to eliminate ponding water,with same day haul-oil of the removed material, to a suitable dump site. For specifications governing this item see Item No. 104 "Removing Old Concrete", Item No. 504" Concrete Sidewalk and Driveways". Pay limits for concrete driveway are as shown in Drawing No.S-S5 of the Standard Specifications. The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch and the driveway surface shall be seeded with pea gravel. The exposed aggregate concrete driveways and sidewalks,shall be complete within seven(7) calendar days from the day of demolition to slate of completion. If the contractor fails to complete the worts within seven (7) calendar days,a $100 dollar liquidated damage will.be assessed per block per day. The unit price bid per square yard shall be full compensation for all labor, material, equipment,supplies,and incidentals necessary to complete the work. All other provisions of the plans, specifications and contract document for the project„ which are not expressly vnen.ded herein, shall remain in:full force and effect. 7 .,.NAR-14-2006 TUE U:22 TPM City Of Fw—Engineer, Dept FAX h10. 817 871 6828 P. 09/23 Addendum No. 3 (2006-3.) Failure to return a signed copy of the addendum with.the Proposal shall be grounds for rendering the bid non-responsive. A signed copy of this addend«m shall be placed into the Proposal at the time of bid submittal. Receipt Acknowledged: Departm.eat of Engvieering A. Douglas RaderaWcer,P.E. Director By: Title:_ _ PRESIDENT _ By: on a Gj Tony Sholola, P.E. Engineering Manager, DOE SPECIFICATIONS AND CONTRACT DOCUMENTS FOR HMAC SURFACE OVERLAY(2006-3) AT VARIOUS LOCATIONS IN THE CITY OF FORT WORTH,TEXAS DOE PROJECT NO. 5202 TPW PROJECT NO. GS93-0209305522810 A.DOUGLAS RADEMAKER,P.E. r S DATE - DIRECTOR,DEPARTMENT OF ENGINEERING 1 AJIB S,P.E. DATE INFRA TRUCTURE MANAGER TRANSPORTATION AND PUBLIC WORKS DEPARTMENT �. :- 3 Gtp 0O KIM,P.E. DATE ENGINEER MANAGER WATER DEPARTMENT CITY i►� . TABLE OF CONTENTS 1. Notice to Bidders 2. Special Instructions to Bidders 3. Prevailing Wage Rates 4. Proposal 5. Vendor Compliance 6. Disadvantaged Business Enterprise 7. Special Provisions 8. Item 360,Concrete Pavement(Modified Specification) 9. Contractor Compliance with Worker's Compensation Law 10. Certificate of Insurance 11. Performance Bond 12. Payment Bond 13. Maintenance Bond 14. Contract 15. Notice of Construction Detail 16. Project Designation Sign Detail 17. Other Details 18. Street Locations 19. Street by Street Paving Quantity Determination Spreadsheet Sealed Proposals for the following: HMAC SURFACE OVERLAY(2006-3) AT VARIOUS LOCATIONS DOE No. 5202 TPW PROJECT NO. GS93-020930522810 Addressed to Mr.Charles R.Boswell, City Manager of the City of Fort Worth,Texas,will be received at the Purchasing Office, City of Fort Worth, in the lower level of the Municipal Building, 1000 Throckmorton, Fort Worth, Texas 76102 until 1:30 p.m., Thursday, March 02, 2006, and then publicly read aloud at 2:00 p.m.,in the Council Chambers. Plans, Specifications and Contract Documents for this project.may be obtained at the office of the .. Department of Engineering, Municipal Office Building, 1000 Throckmorton Street, Fort Worth, Texas 76102. One set of documents will be provided to prospective bidders for a deposit of twenty dollars($20.00), such deposit is non-refundable. Additional sets may be purchased on a non-refundable basis for twenty dollars ($20.00) per set. These documents contain additional information for prospective bidders. A pre-bid conference will be held at 9:00 A.M. February 15, 2006, in the Transportation and Public Works Conference Room,2nd Floor,Municipal Building,RM 270. The major work on the above-referenced project shall consist of the following: Paving Improvements: 8,250 L.F. Removal and Replacement of Concrete Curb and Gutter 23,000 L.F. Wedge Milling 2"to 0"Depth 5' Width 90,000 S.Y. 2"H.M.A.C. Surface Course (Type "D"Mix) v 13,500 S.Y. 8"Pavement Pulverization 176 TON Cement Included in the above will be all other miscellaneous items of construction as outlined in the Plans and Specifications. For additional information, please contact Susan L. Schwinger, P.E., Project Manager at (817) 392- 6529. Advertising Dates: January 26 2006 February 02, 2006 COMPREHENSIVE NOTICE TO BIDDERS Sealed Proposals for the following: w HMAC SURFACE OVERLAY(2006-3) AT VARIOUS LOCATIONS -- DOE No. 5202 TPW PROJECT NO. GS93-020930522810 Addressed to Mr.Charles R. Boswell,City Manager of the City of Fort Worth,Texas,will be received at the Purchasing Office, City of Fort Worth, in the lower level of the Municipal Building, 1000 Throckmorton, Fort Worth, Texas 76102 until 1:30 p.m., Thursday, March 02, 2006, and then publicly read aloud at 2:00 p.m.,in the Council Chambers. Plans, Specifications and Contract Documents for this project may be obtained at the office of the w Department of Engineering, Municipal Office Building, 1000 Throckmorton Street, Fort Worth, Texas 76102. One set of documents will be provided to prospective bidders for a deposit of twenty dollars($20.00), such deposit is non-refundable.Additional sets may be purchased on a non-refundable basis for twenty dollars ($20.00) per set. These documents contain additional information for prospective bidders. A pre-bid conference will be held at 9:00 A.M. February 15, 2006 in the Transportation and Public Works Conference Room,2nd Floor,Municipal Building,RM 270. All bidders will be required to comply with Provision 5159a of"Vernon's Annotated Civil Statutes" of the State of Texas with respect to the payment of prevailing wage rates and City Ordinance No. 7278, as amended by City Ordinance No. 7400(Fort Worth City Code Sections 13-A-21 through 13- A-29),prohibiting discrimination in employment practices. Bid security is required in accordance with Paragraph 1 of the Special Instructions to Bidders. The major work on the above-referenced project shall consist of the following Paving Improvements: 8,250 L.F. Removal and Replacement of Concrete Curb and Gutter 23,000 L.F. Wedge Milling 2"to 0"Depth 5' Width 90,000 S.Y. 2"H.M.A.C. Surface Course(Type"D"Mix) 13,500 S.Y. 8"Pavement Pulverization 176 TON Cement Included in the above will be all other miscellaneous items of construction as outlined in the Plans and Specifications. COMPREHENSIVE NOTICE TO BIDDERS (CONTD.) The City reserves the right to reject any/or all bids and waive any and/or all formalities. Bidders shall not separate, detach, or remove any portion, segment, or sheets from the contract document at any time. Bidders must complete the proposal sections and submit the complete specification book or face rejection of the bid as non-responsive. AWARD OF CONTRACT: No bid may be withdrawn until the expiration of ninety (90) days from the date the M/WBE UTILIZATION FORM, PRIME CONTRACTOR WAVIER FORM, and/or the GOOD " FAITH EFFORT FORM ("Documentation") as appropriate is received by the City. The award of contract, if made, will be within ninety (90) days after this documentation is received,but in no case will the award be made until all necessary investigations are made as to the responsibility of the bidder to whom it is proposed to award the contract. Bidders are responsible for obtaining all addenda to the contract documents prior to the bid receipt time and acknowledging them at the time of the bid receipt. Information regarding the status of addenda may be obtained by contacting the Department of Engineering at (817) 392-7910. Bids that do not acknowledge all applicable addenda may be rejected as non-responsive. In accordance with the City of Fort Worth Ordinance No.15530, the City of Fort Worth has goals for the participation of minority business enterprises and women business enterprises in City contracts. A copy of the Ordinances can be obtained from the Office of the City Secretary. The bidder shall submit the i' M/WBE UTILIZATION FORM, PRIME CONTRACTOR WAVIER FORM, and/or the GOOD FAITH EFFORT FORM ("Documentation"), as appropriate. The Documentation must be received by the contracting department no later than 5:00 p.m., five (5) City business days after the bid opening date. T The bidder shall obtain a receipt from the appropriate employee of the contracting department to whom delivery was made. Such receipt shall be evidence that the Documentation was received by the City. The Managing Department for this project is the Department of Engineering. For additional information, please contact Susan L. Schwinger,P.E.,Project Manager at(817) 392-6529. CHARLES R.BOSWELL MARTHA HENDRIX CITY MANAGER CITY SECRETARY A.DOUGLAS RADEMAKER,P.E. DIRECTOR DEPARTMENT OF ENGINEERING Advertising Dates: By: January 26 2006 Tony Sholola,P.E. February 02,2006 Manager, Consulting Services SPECIAL INSTRUCTIONS TO BIDDERS 1. BID SECURITY: Cashier's check or an acceptable bidder's bond payable to the City of _ Fort Worth, in an amount of not less than 5 percent of the largest possible total of the bid submitted must accompany the bid, and is subject to forfeit in the event the successful bidder fails to execute the contract documents within ten days after the contract has been .. awarded. To be an acceptable surety on the bid bond, the surety must be authorized to do business in the state of Texas. In addition, the surety must (1) hold a certificate of authority from the Untied States secretary of the treasury to qualify as a surety on obligations permitted or required under federal law; or (2) have obtained reinsurance for any liability in excess .� of$100,000 from a reinsurer that is authorized and admitted as a reinsurer in the state of Texas and is the holder of a certificate of authority from the Untied States secretary of the treasury to qualify as a surety on obligations permitted or required under federal law. .. Satisfactory proof of any such reinsurance shall be provided to the City upon request. The City, in its sole discretion,will determine the adequacy of the proof required herein. .. 2. PROPOSAL: After proposals have been opened and read aloud, the proposals will be tabulated on the basis of the quoted prices,the quantities shown in the proposal, and the application of such formulas or other methods of bringing items to a common basis as may be established in the Contract Documents. The total obtained by taking the sum of the products of unit prices quoted and the .. estimated quantities plus any lump sum items and such other quoted amounts as may enter into the cost of the completed project will be considered as the amount of the bid. Until the award of the contract is made by the Owner,the right will be reserved to reject any or all proposals and waive technicalities, to re-advertise for new proposals, or to proceed with the work in any manner as maybe considered for the best interest of the Owner. The quantities of work and materials to be furnished as may be listed in the proposal forms or other parts of the Contract Documents will be considered as approximate only and will be used for the purpose of comparing bids on a uniform basis. Payment will be made to the Contractor for only the actual quantities of work performed or materials furnished in strict accordance with the Contract Documents and Plans. The quantities of work to be performed and materials to be furnished may be increased or decreased as hereinafter provided,without in any way invalidating the unit prices bid or any other requirements of the Contract Documents. 3. ADDENDA: Bidders are responsible for obtaining all addenda to the Contract .. Documents prior to the bid receipt. Information regarding the status of addenda may be obtained by contacting the Department of Engineering Construction Division at(817) _ 871-7910. Bids that do not acknowledge all applicable addenda will be rejected as non- responsive. .r SPECIAL INSTRUCTIONS TO BIDDERS - I - i _ 4. AWARD OF CONTRACT: The contract, if awarded, will be awarded to the lowest responsive bidder. The City reserves the right to reject any or all bids and waive any or all irregularities. No bid may be withdrawn until the expiration of forty-nine (49)City _ business days from the date that the M/WBE UTILIZATION FORM, PRIME CONTRACTOR WAIVER FORM and/or the GOOD FAITH EFFORT FORM ("Documentation")is received by the City. 5. PAYMENT, PERFORMANCE AND MAINTENANCE BONDS: The successful bidder entering into a contract for the work will be required to give the City surety in a sum equal to the amount of the contract awarded. The successful bidder shall be required to furnish bonding as applicable in a sum equal to the amount of the contract awarded. The form of the bond shall be as herein provided and the surety shall be acceptable to the City. All bonds furnished hereunder shall meet the requirements of Chapter 2253 of the Texas Government Code, as amended. A. If the total contract price is$25,000 or less,payment to the contractor shall be made in one lump sum. Payment shall not be made for a period of 45 calendar days from the date the work has been completed and accepted by the City. B. If the contract amount is in excess of$25,000, a Payment Bond shall be executed, in the amount of the contract, solely for the protection of all claimants supplying labor and material in the prosecution of the work. C. If the contract amount is in excess of$100,000, a Performance Bond shall be executed, in the amount of the contract conditioned on the faithful performance of the work in accordance with the plans, specifications, and contract documents. Said bond shall solely be for the protection of the City of Fort Worth. i D. A Two-year Maintenance Bond is required for all projects to insure the prompt, full and faithful performance of the general guarantee as set forth in Paragraph 7 of the Special Provisions. To be an acceptable surety on the performance, payment and maintenance bonds, the surety must be authorized to do business in the state of Texas and meet all requirements of Texas Insurance Code, section 7.19-1. In addition, the surety must (1) hold a certificate of authority from the Untied States secretary of the treasury to qualify as a surety on obligations permitted or required under federal law; or (2) have obtained reinsurance for any liability in excess of$100,000 from a reinsurer that is authorized and admitted as a reinsurer in the state of Texas and is the holder of a certificate of authority from the Untied States secretary of the treasury to qualify as a surety on obligations permitted or required under federal law. Satisfactory proof of any such reinsurance shall be provided to the City upon request. The City, in its sole discretion, will determine the adequacy of the proof required herein. _ No sureties will be accepted by the City that are at the time in default or delinquent on any bonds or which are interested in any litigation against the City. Should any surety on the contract be determined unsatisfactory at any time by the City, notice will be given to the contractor to that effect and the contractor shall immediately provide a new surety i satisfactory to the City SPECIAL INSTRUCTIONS TO BIDDERS -2- 6. LIQUIDATED DAMAGES: The Contractor's attention is called to Part 1 - General Provisions, Item 8,Paragraph 8.6, Standard Specifications for Street and Storm Drain Construction of the City of Fort Worth, Texas, concerning liquidated damages for late completion of projects. 7. EMPLOYMENT AND NON-DISCRIMINATION: The Contractor shall not discriminate against any person(s)because of sex,race,religion, color or national origin and shall comply with the provisions of sections 13A-21 through 13A-29 of the Code of the City of Fort Worth(1986), as amended,prohibiting discrimination in employment practices. 8 WAGE RATES: All bidders will be required to comply with provision 5159a of "Vernons Annotated Civil Statutes" of the State of Texas with respect to the payment of prevailing wage rates as established by the City of Fort Worth, Texas, and set forth in Contract Documents for this project. 9. FINANCIAL STATEMENT: A current certified financial statement may be required by the Department of Engineering Director for use by the CITY OF FORT WORTH in determining the successful bidder. This statement,if required, is to be prepared by an independent Public Accountant holding a valid permit issued by an appropriate State Licensing Agency. 10. INSURANCE: Within ten days of receipt of notice of award of contract, the Contractor must provide, along with executed contract documents and appropriate bonds,proof of insurance for Workers Compensation(statutory); Comprehensive General Liability ($1,000,000 per occurrence, $2,000,000 aggregate); and Automobile Insurance ($1,000,000 each accident on a combined single basis or$250,000 property .. damage/$500,000 bodily injury per person per occurrence. A commercial business policy shall provide coverage on"any auto", defined as autos owned, hired, and non- owned). Additional lines of coverage may be requested. If such a request is made after bid opening, Contractor shall be entitled to additional compensation equal to 110%of the additional premium cost. For worker's compensation insurance requirements,see Special Instructions to Bidders -Item 16. ADDITIONAL INSURANCE REQUIREMENTS: A. The City, its officers, employees and servants shall be endorsed as an additional insured on Contractor's insurance policies excepting employer's liability insurance coverage under Contractor's workers'compensation insurance policy. B. Certificates of insurance shall be delivered to the City of Fort Worth, contract administrator in the respective department as specified in the bid documents, 1000 Throckmorton Street, Fort Worth, TX 76102, prior to commencement of work on the contracted project. C. Any failure on part of the City to request required insurance documentation shall not constitute a waiver of the insurance requirements specified herein. D. Each insurance policy shall be endorsed to provide the City a minimum thirty days notice of cancellation, non-renewal, and/or material change in policy terms SPECIAL INSTRUCTIONS TO BIDDERS -3- _ or coverage. A ten days notice shall be acceptable in the event of non-payment of premium. _ E. Insurers must be authorized to do business in the State of Texas and have a current A.M. Best rating of A: VII or equivalent measure of financial strength and solvency. F. Deductible limits, or self-funded retention limits, on each policy must not exceed $10,000.00 per occurrence unless otherwise approved by the City. G. Other than worker's compensation insurance, in lieu of traditional insurance, City may consider alternative coverage or risk treatment measures through insurance pools or risk retention groups. The City must approve in writing any alternative coverage. .. H. Workers' compensation insurance policy(s) covering employees employed on the project shall be endorsed with a waiver of subrogation providing rights of recovery in favor of the City. I. City shall not be responsible for the direct payment of insurance premium costs for contractor's insurance. J. Contractor's insurance policies shall each be endorsed to provide that such insurance is primary protection and any self-funded or commercial coverage .. maintained by City shall not be called upon to contribute to loss recovery. K. In the course of the project, Contractor shall report, in a timely manner, to City's officially designated contract administrator any known loss occurrence which could give rise to a liability claim or lawsuit or which could result in a property loss. L. Contractor's liability shall not be limited to the specified amounts of insurance required herein. M. Upon the request of City, Contractor shall provide complete copies of all insurance policies required by these contract documents. 11. NON-RESIDENT BIDDERS: Pursuant to Texas Government Code, art. 2252.002,the City of Fort Worth will not award this contract to a non-resident bidder unless the non- resident's bid is lower than the lowest bid submitted by a responsible Texas resident bidder by the same amount that a Texas resident bidder would be required to underbid a non-resident bidder to obtain a comparable contract in the state in which the non- resident's principal place of business is located. _ "Non-resident bidder" means a bidder whose principal place of business is not in this state,but excludes a contractor whose ultimate parent company of majority owner has its principal place of business in this state. �jnJ(�98 SIER SPECIAL INSTRUCTIONS TO BIDDERS u UEua u -4- FT. wi-oEITH, TEX. _ "Texas resident bidder"means a bidder whose principal place of business is in this state, and includes a contractor whose ultimate parent company or majority owner has its principal place of business in this state. This provision does not apply if the project is funded in whole or in part with federal funds. The appropriate blanks of the Proposal must be filled out by all non-resident bidders in order for its bid to meet specifications. The failure of a non-resident contractor to do so will automatically disqualify that bidder. 12. MINORITY/WOMEN BUSINESS ENTERPRISE: In accordance with City of Fort .,, Worth Ordinance No. 11923, as amended by Ordinance No. 13471,the City of Fort Worth has goals for the participation of minority business enterprises and women business enterprises in City contracts. You may obtain a copy of the Ordinance from the .. Office of the City Secretary. The M/WBE Utilization Form, Prime Contractor Waiver Form and the Good Faith Effort •• Form, as applicable,must be submitted no later than 5:00 p. in. five(5) City business days after the bid opening date, exclusive of the bid opening date. The bidder shall submit the documentation at the reception area of the Department of Engineering .. ("Managing Department"),2nd floor, City Hall, and shall obtain a receipt. Failure to comply shall render your bid non-responsive. .. Upon contract execution between the City of Fort Worth and the successful bidder, now known as Contractor, a pre-construction meeting will be scheduled at which time the Contractor is required to submit either Letters of Intent or executed agreements with the M/WBE firm(s)to be utilized on this project. Such Letters of Intent or executed agreements shall include the following information: 1. Name of Contract 2. Name of M/WBE firm utilized 3. Scope of Work to be performed by the M/WBE firm 4. Monetary amount of work to be performed by the M/WBE firm 5. Signatures of all parties .. A notice to proceed will not be issued until the signed letter(s) or executed agreement(s) have been received. .. Throughout the duration of this project,the Contractor comply with the M/WBE Ordinance by complying with the following procedures: • A M/WBE Participation Report Form must be submitted monthly until the contract is completed. The first report will be due 30 days after commencement of work. The _ monthly report MUST have an original signature to ensure accountability for audit purposes. • Reports are to be submitted monthly to the M/WBE Office, regardless of whether or not the M/WBE firm has been utilized. If there was no activity by an M/WBE in a particular month,place a "0" or"no participation" in the spaces provided, and provide SPECIAL INSTRUCTIONS TO BIDDERS -5- a brief explanation. • The Contractor shall provide the M/WBE Office proof of payment to the M/WBE subcontractors and suppliers only. The M/WBE Office will accept the following as proof of payment: 1. Copies of submitted invoices with front and back copies of canceled check(s), OR 2. A notarized letter explaining, in detail: a Subcontractor/supplier Scope of Work b. Date when services were received from subcontractor/supplier c. Amounts paid to the subcontractor/supplier d. Original signatures from both parties must be included on this letter. • If the Contractor foresees a problem with submitting participation reports and/or proof of payment on a monthly basis,the M/WBE Office should be notified. If the Contractor wishes to change or delete an M/WBE subcontractor or supplier, adhere to the following: 1. Immediately submit a Request for Approval of Change Form to the M/WBE Office explaining the request for the change or deletion. 2. If the change affects the committed M/WBE participation goal, state clearly how and why in documentation. a. All requests for changes must be reviewed and pre-approved by the M/WBE Office. b. If the Contractor makes change(s)prior to approval, the change will not be considered when performing a post compliance review on this project. • Upon the Contractor's successful completion of this project, and within ten days after .. receipt of final payment from the City of Fort Worth, The Contractor will provide the M/WBE Office with a Final Participation Report Form to reflect the total participation from ALL subcontractors/suppliers utilized on the project. • All forms are available at the M/WBE Office, 3rd floor- City Hall. For additional information regarding compliance to the M/WBE Ordinance, call (817) 871-6104. Upon request, Contractor agrees to provide to Owner Complete and accurate information regarding actual work performed by a Minority/Women Business Enterprise(M/WBE) on the contract and payment therefore. Contractor further agrees to permit an audit and/or examination of any books,records or files in its possession that will substantiate the ., actual work performed by an M/WBE. The misrepresentation of facts (other than a negligent misrepresentation) and/or the commission of fraud by the Contractor will be grounds for termination of the contract and/or initiating action under appropriate federal, .. state or local laws or ordinances relating to false statements; further, any such misrepresentation(other than a negligent misrepresentation) and/or commission of fraud SPECIAL INSTRUCTIONS TO BIDDERS -6- am will result on the Contractor being determined to be irresponsible and barred from .m participating in City work for a period of time of not less than three years. _ 13. AMBIGUITY: In case of ambiguity or lack of clearness in stating process in the proposal, the City reserves the right to adopt the most advantageous construction thereof or to reject the proposal. 14. PROGRESS PAYMENTS FINAL PAYMENT PROJECT ACCEPTANCE AND WARRANTY: a. The contractor will receive full payment(less 5%retainage) from the city for each pay period. b. Payment of the retainage will be included with the final payment after acceptance of the project as being complete. c. The project shall be deemed complete and accepted by the City as of the date the final punch list has been completed, as evidenced by a written statement signed by the .. contractor and the City. d. The warranty period shall begin as of the date that the final punch list has been .. completed. e. Bills Paid Affidavit and Consent of Surety shall be required prior to final payment becoming due and payable. f. In the event that the Bills Paid Affidavit and Consent of Surety have been delivered to the city and there is a dispute regarding(i) final quantities, or(ii) liquidated damages, city shall make a progress payment in the amount that city deems due and payable. g. In the event of a dispute regarding either final quantities or liquidated damages,the parties shall attempt to resolve the differences within 30 calendar days. 15. AIR POLLUTION WATCH DAYS: The Contractor shall be required to observe the following guidelines relating to working on City construction sites on days designated as "AIR POLLUTION WATCH DAYS". Typically, the OZONE SEASON, within the Metroplex area,runs from May 1, through October 31,with 6:00 a.m. - 10:00 a.m.being critical because emissions from this time period have enough time to bake in the hot atmosphere that leads to early afternoon ozone formation. The Texas Commission on Environmental Quality(TCEQ), in coordination with the National Weather Service,will issue the AIR POLLUTION WATCH by 3:00 p.m. on the afternoon prior to the WATCH day. On designated AIR POLLUTION WATCH DAYS, the Contractor shall bear the responsibility of being aware that such days have been designated AIR POLLUTION WATCH DAYS and as such shall not begin work until 10:00 a.m. whenever construction phasing requires the use of motorized equipment for periods in excess of 1 hour. However, the Contractor may begin work prior to 10:00 a.m.if use of motorized equipment is less than 1-hour,or if equipment is new and certified by EPA as"Low SPECIAL INSTRUCTIONS TO BIDDERS -7- Emittin "g or equipment burns Ultra Low Sulfur Diesel(ULSD),diesel emulsions, or alternative fuels such as CNG. If the Contractor is unable to perform continuous work for a period of at least seven hours between the hours of 7:00 a.m. - 6:00 p.m., on a designated AIR POLLUTION WATCH DAY, that day will be considered as a weather day and added onto the allowable weather days of a given month. 16. WORKERS COMPENSATION INSURANCE COVERAGE: Contractors compliance ., with Workers Compensation shall be as follows: A. Definitions: Certificate of coverage("certificate") -A copy of a certificate of insurance, a certificate of authority to self-insure issued by the commission, or a coverage .. agreement(TWCC-81, TWCC-82, TWCC-83, or TWCC-84), showing statutory workers'compensation insurance coverage for the person's or entity employees providing services on a project, for the duration of the project. Duration of the project- includes the time from the beginning of the work on the project until the contractor's/person's work on the project has been completed and .. accepted by the governmental entity. Persons providing services on the project("subcontractor" in 406.096) -includes all .. persons or entities performing all or part of the services the contractor has undertaken to perform on the project, regardless of whether that person has employees. This includes,without limitation, independent contractors, subcontractors, leasing companies, motor carriers, owner-operators, employees of any such entity, or employees of any entity which furnishes persons to provide services on the project. "Services" include,without limitation,providing,hauling, or delivering equipment or materials,or providing labor,transportation, or other service related to a project. "Services" does not include activities unrelated to the project,such as food/beverage vendors, office supply deliveries, and delivery of portable toilets. B. The contractor shall provide coverage,based on proper reporting of classification codes and payroll amounts and filing of any coverage agreements, which meets the statutory requirements of Texas Labor Code, Section 401.011(44) for all employees of the contractor providing services on the project, for the duration of the project. C. The Contractor must provide a certificate of coverage to the governmental entity prior to being awarded the contract. D. If the coverage period shown on the contractor's current certificate of coverage ends during the duration of the project, the contractor must,prior to the end of the _ coverage period, file a new certificate of coverage with the governmental entity showing that coverage has been extended. .. E. The contractor shall obtain from each person providing services on a project, and provide to the City: SPECIAL INSTRUCTIONS TO BIDDERS -8- _ (1) a certificate of coverage, prior to that person beginning work on the project; so the City will have on file certificates of coverage showing coverage for all persons providing services on the project; and (2) no later than seven days after receipt by the contractor, a new certificate of coverage showing extension of coverage, if the coverage period shown on the current certificate of coverage ends during the duration of the project. E. The contractor shall retain all required certificates of coverage for the duration of the project and for one year thereafter. G. The contractor shall notify the governmental entity in writing by certified mail or ., personal delivery,within ten days after the contractor knew or should have known, of any change that materially affects the provision of coverage of any person providing services on the project. H. The contractor shall post on each project site a notice, in the text, form and manner prescribed by the Texas Workers'Compensation Commission, informing all persons •• providing services on the project that they are required to be covered, and stating how a person may verify coverage and report lack of coverage. I. The contractor shall contractually require each person with whom it contracts to provide services on a project, to: (1) provide coverage, based on proper reporting on classification codes and payroll amounts and filing of any coverage agreements,which meets the statutory requirements of Texas Labor Code, Section 401.011(44) for all of its employees providing services on the project, for the duration of the project; (2) provide to the contractor,prior to that person beginning work on the project, a certificate of coverage showing that coverage is being provided for all employees of the person providing services on the project, for the duration of the project; (3) provide the contractor,prior to the end of the coverage period, a new certificate of coverage showing extension of coverage, if the coverage period shown on the current certificate of coverage ends during the duration of the project; (4) obtain from each other person or entity with whom it contracts, and provide to the contractor: (a) a certificate of coverage,prior to the other person or entity beginning work on the project; and (b) a new certificate of coverage showing extension of coverage,prior to the end of the coverage period, if the coverage period shown on the current certificate of coverage ends during the duration of the project; (5) retain all required certificates of coverage on file for the duration of the project and for one year thereafter. SPECIAL INSTRUCTIONS TO BIDDERS -9- .. (6) notify the governmental entity in writing by certified mail or personal delivery, within ten days after the person knew or should have known, of any change that materially affects the provision of coverage of any person providing services on the project; and (7) contractually require each person with whom it contracts,to perform as required by paragraphs (1) - (7), with the certificates of coverage to be provided to the person for whom they are providing services. J. By signing this contract or providing or causing to be provided a certificate of coverage, the contractor is representing to the governmental entity that all employees of the contractor who will provide services on the project will be covered by workers' compensation coverage for the duration of the project, that the coverage will be based on proper reporting of classification codes and payroll amounts, and that all coverage agreements will be filed with the appropriate insurance carrier or, in the case of a self- insured, with the commission's Division of Self-Insurance Regulation. Providing false of misleading information may subject the contractor to administrative penalties, criminal penalties,civil penalties or other civil actions. K. The contractor's failure to comply with any of these provisions is a breach of contract by the contractor which entitles the City to declare the contract void if the contractor .. does not remedy the breach within ten days after receipt of notice of breach from the City. "The contractor shall post a notice on each project site informing all persons providing services on the project that they are required to be covered, and stating how a person may verify current coverage and report failure to provide coverage. This notice does not satisfy other posting requirements imposed by the Texas Workers' Compensation Act or other Texas Workers'Compensation commission rules. This notice must be printed with a title in at least 30 point bold type and text in at least 19 point normal type, and shall be in both English and Spanish and any other language common to the worker population. The text for the notices shall be the following text,without any additional words or changes: REQUIRED WORKERS' COMPENSATION COVERAGE .. "The law requires that each person working on this site or providing services related to this construction project must be covered by workers'compensation insurance. This includes persons providing,hauling, or delivering equipment or materials, or .. providing labor or transportation or other service related to the project,regardless of the identity of their employer or status as an employee." "Call the Texas Workers'Compensation Commission at(512)440-3789 to receive information on the legal requirement for coverage, to verify whether your employer .. has provided the required coverage, or to report an employer's failure to provide coverage." „M 17. AGE DISCRIMINATION: In accordance with the policy("Policy") of the Executive Branch of the federal government, contractor covenants that neither it nor any officers, members, agents or employees who engage in the performance of this contract sh%, SPECIAL INSTRUCTIONS TO BIDDERS #QC9 �g4Gl(ol(,,. a — 10— [ Ff.�i1�b' 151UJbSU Wolf TEX. _ connection with such employment, advancement or discharge of employees or in connection with the terms, conditions or privileges of their employment, discriminate against any person because of their age except on the basis of a bona fide occupational qualification,retirement plan or statutory requirement. Contractor further covenants that neither it nor its officers, members, agents or employees acting on their behalf, shall specify in solicitations or advertisements for employees to work on those contract a maximum age limit for such employment unless the specified maximum age limit is based upon a bona fide occupational qualification,retirement plan .. or statutory requirement. Contractor warrants that it will fully comply with the Policy and will defend, indemnify .. and hold City harmless against any and all claims or allegations filed by third parties against City arising out of Contractor's alleged failure to comply with the Policy in the performance of this contract. 18. DISCRIMINATION DUE TO DISABILITY: In accordance with the provisions of the Americans with Disabilities Act of 1990("ADA'), Contractor warrants that it will not unlawfully discriminate on the basis of disability in the provision of services to the general public, nor in the availability, terms or conditions of employment for applicants for employment with, or current employees of, Contractor. Contractor warrants that it will fully comply with the ADA's provisions and any other applicable federal, state, or local laws concerning disability and will defend, indemnify and hold City harmless against any and all claims or allegations filed by third parties against City arising out of Contractor's alleged failure to comply with the ADA in the performance of this contract. END OF SECTION SPECIAL INSTRUCTIONS TO BIDDERS - 11 - Classifications Hourly Rates Classifications Hrly Rts Air Tool Operator $10.06 Scraper Operator $11.42 Asphalt Raker $11.01 Servicer $12.32 Asphalt Shoveler $8.80 Slip Form Machine Operator $12.33 Asphalt Distributor Operator $13.99 Spreader Box Operator $10.92 + .Asphalt Paving Machine Operator $12.78 Tractor operator, Crawler Type $12.60 Batching Plant Weigher $14.15 Tractor operator, Pneumatic $12.91 Broom or Sweeper Operator $9.88 Traveling Mixer Operator $12.03 Bulldozer operator $13.22 Truck Driver-Single Axle(Light) $10.91 Carpenter(Rough) $12.80 Truck Driver-Single Axle(Heavy) $11.47 Concrete Finisher-Paving $12.85 Truck Driver-Tandem Axle Semi-Trailer $11.75 Concrete Finisher-Structures $13.27 Truck Driver-Lowboy/Float $14.93 Concrete Paving Curbing Mach. O er. $12.00 Truck Driver-Transit Mix $12.08 Wagon Drill, Boring Machine, Post Hole Concrete Paving Finishing Mach.O er. $13.63 Driller $14.00 Concrete Paving Joint Sealer O er. $12.50 Welder $13.57 Concrete PavingSaw O er. $13.56 Work Zone Barricade Servicer $10.09 Concrete Paving Spreader Oper. $14.50 Concrete Rubber $10.61 Crane, Clamshell, Backhoe, Derrick, Dragline,Shovel $14.12 Electrician $18.12 Flagger $8.43 Form Builder-Structures $11.63 Form Setter-Paving&Curbs $11.83 Foundation Drill Operator, Crawler Mounted $13.67 Foundation Drill Operator,Truck Mounted $16.30 Front End Loader $12.62 Laborer-Common $9.18 Laborer-Utility $10.65 _. Mechanic $16.97 Milling Machine Operator, Fine Grade $11.83 Mixer Operator $11.58 Motor Grader Operator Fine Grade $15.20 Motor Grader Operator, Rough Oiler $14.50 Painter,Structures $13.17 Pavement Marking Machine O er. $10.04 Pie Layer $11.04 Roller,Steel Wheel Plant-Mix Pavements $11.28 Roller,Steel Wheel Other Flatwheel or Tamping $10.92 Roller, Pneumatic,Self-Propelled Scraper $11.07 Reinforcing Steel Setter(Paving) $14.86 Reinforcing Steel Setter Structure $16.29 Source is AGC of Texas (Hwy, Hvy, Utilities Industrial Branch) www.access.gpogov/davisbacon/ 2/2/2006 r. ATTACHMENT 1A Page 1 of 4 FORT WORTH City of Fort Worth Subcontractors/Suppliers Utilization Form PRIME COMPANY NAME: Check applicable block to describe prime PROJECT NAME: M/W/DBE NON-MM/DBE l BI DATE City's MNVBE Project Goal: Prime's MIWBE Project Utilization: PROJECT NUMBER / 7 % GS93-d�og3 os'� X8/0 Identify all subcontractors/suppliers you will use on this project - . .urge ' 'i .ierir agrso .e ,ih:. t Blc. fi�rf r , k4 - is i M/WBEs listed toward meeting the project goal must be located in the nine (9) county marketplace or currently doing business in the marketplace at the time of bid. Marketplace is the geographic area of Tarrant, Parker, Johnson, Collin, Dallas, Denton, Ellis, Kaufman and Rockwall counties. 3r7lla tUV;ue _f i; .p rlmw � ILipv'{ * '+ 5 ,Yla 'bier, 1' Irlr auhr* tr + r tF ALL MIWBEs MUST BE CERTIFIED BEFORE CONTRACT AWARD. Certification means those firms, located or doing business at the time of bid opening within the Marketplace, that have been determined to be bonafide minority or women businesses by the North Central Texas Regional Certification Agency(NCTRCA), or the Texas Department of Transportation (TX DOT), highway division. Disadvantaged Business Enterprise(DBE) is synonymous with Minority/Women Business Enterprise(M/WBE). LL wY- S y OFFICIA,I END coQif S���� /,UG�U o— F/4nin.,A FOR_T WORTH ATTACHMENT 1A EQVP Page 2 of 4 Primes are required to identify ALL subcontractors/suppliers,regardless of status;i.e.,Minority,Women and non-M/WBEs. Please fist MNVBE firms first,use additional sheets if necessary. Certification SUBCONTRACTORISUPPLIER T (check one) Company Name 1 N T Detail Detail Address e M w C X Subcontracting Work Supplies Purchased Dollar Amount Telephone/Fax r B B T O E E C T A B / C�hST/ZJe.�/d/l CohCreAe /a�s�i w. Gl'-6UrheIS 0 Gr0L J1ey,T)r, 76034, !^vrb '2tC for. l7) .2-qZ —9(oo ! l 7)a29 7— 0`f37 Ac.,ac P�• �>c ���EQffi 2q'a- :2'(9.2- 0 If I—?- P-0 -79390 .. S 7& !7q —b380 ` �l 7) S6`f 7— �s(A Irs,7 g�7— -2-6 9 7.28 �2 �6.z 6 loo, ($l )) eY9/—303 4 o.,., cnnma FORT WORTH ATTAC Page 3 4 Page 3 of A Mal Primes are required to identify ALL subcontractors/suppliers,regardless of status;i.e.,Minority,Women and non-MIWBEs. Please list M/WBE firms first,use additional sheets if necessary. Certification SUBCONTRACTORISUPPLIER T (check one) In Company Name i N T Detail Detail Address 6 M W C X Subcontracting Work Supplies Purchased Dollar Amount dr'- Telephone/Fax r s B R O E E C T A I PERi I �y. ATTACHMENT 1A FORT WORTH Page 4 of 4 Total Dollar Amount of M/WBE Subcontractors/Suppliers $ ,j2, Total Dollar Amount of Non-M/WBE Subcontractors/Suppliers $ O - 60 TOTAL DOLLAR AMOUNT OF ALL SUBCONTRACTORS/SUPPLIERS $ 7 a' ' t - � alf ' .ai# - - �y ftis cerci art�rout'-t -pr/6r`-gr . . '+ i��'`. of. i�r r 44::!Husltl _ fir" s`tgr�2 �rrcu h [4�e Ys rnif��l�_,'�,� .eCC* t t 6l re46in rd _ i h .crdinanca, Thfi. � '�- $�' if�� ki'i . - �;h_ e; dcfifni3 ' e�e# frfect tha C fpl ►a�{ trti't ren a € t�'f��eal ca ,1rilr n. s By affixing a signature to this form, the Offeror further agrees to provide, directly to the City upon request, complete and accurate information regarding actual work performed by all subcontractors, including MM/DBE(s) arrangements submitted with the bid. The Offeror also agrees to allow an audit and/or examination of any books, records and files held by their company. The bidder agrees to allow the transmission of interviews with owners, principals, officers, employees and applicable subcontractors/suppliers/contractors participating on the contract that will substantiate the actual work performed by the M/W/DBE(s) on this contract, by an authorized officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment from City work for a period of not less than three (3) years and for initiating action under Federal, State or Local laws concerning false statements. Any failure to comply with this ordinance and create a material breach of contract may result in a determination of an irresponsible Offeror and barred from participating in �1 City work for a period of time not less than one (1)year. � V Authari d Signature Printed Signature Cll 4rAC4a C-y Tob conted NamNTitie(N different) 7 y -- Company Name l Telephone andlor Faxes S-601 'e6a rAe V"'-{ ..fy rc;c,e l�-0E)eetC-' �E"E'C®i�., CorLl Address Etndl Address k 8//er cKpVtatefZip pate 1. x Rev.5/30/03 ATTACHMENT 1B FORT WORTH Page 1 of 1 City of Fort Worth Prime Contractor Waiver Form PRIME COMPANY NAME: Check applicable block to describe rime -T PROJECT NAME: (WW/DBE NON-MM/DBE BID DATE HMS 5Uf�rCAlp OVcf 302 0 City's MIWBE Project Goal: PROJECT UMBER f 7 C-Sg3ro.za9 8/0 If both answers to this form are YES,do not complete ATTACHMENT 1C(Good Faith Effort Form). All questions on this form must be completed and a detailed explanation provided, if applicable. If the answer to either question is NO, then you must complete ATTACHMENT 1 C. This form is only applicable if both answers are yes. Will you perform this entire contract without subcontractors? YES If yes, please provide a detailed explanation that proves based on the size and scope of this project, NO this is your normal business practice and provide an operational grofile of your business. Will you perform this entire contract without suppliers? YES If yes, please provide a detailed explanation that proves based on the size and scope of this project, this is your normal business practice and provide an inventory profile of your business. NO The bidder further agrees to provide, directly to the City upon request, complete and accurate information ' regarding actual work performed by all subcontractors, including M/WBE(s)on this contract,the payment therefore and any proposed changes to the original M/WBE(s) arrangements submitted with this bid. The bidder also agrees to allow an audit and/or examination of any books, records and files held by their company that will substantiate the actual work performed by the M/WBEs on this contract, by an authorized officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment from City work for a period of not less than three (3)years and for initiating action under Federal, State or Local laws concerning false statements. Any failure to comply with this ordinance creates a material breach of contract may result in a determination of an irresponsible offeror and barred from participating in City work for a period of time ndt less than one(1)year. Authirized Signature Printed Signature P— eSi Title CoMad Name Of different) pE-a cc ,f.-E•►e Cir s'�r�of A b L 1 kl 7)7`f L y&U (S/7) Company Name Phone Number Fax Number Address Email Address K.el/gr � Cr -76��% 3L,30/00 r Clty/Stabop We Rev.5/30/03 PROPOSAL TO: MR.CHARLES R.BOSWELL Fort Worth,Texas City Manager Fort Worth,Texas FOR: H.M.A.C.SURFACE OVERLAY(2006-3) AT VARIOUS LOCATIONS DOE PROJECT NO.5202 TPW PROJECT NO. GS93-020930522810 Pursuant to the foregoing "Notice to Bidders", the undersigned has thoroughly examined the plans, specifications and the site,understands the amount of work to be done, and hereby proposes to do all the work and furnish all labor, equipment, and materials necessary to fully complete all the work as provided in the plans and specifications, and subject to the inspection and approval of the Director of the Department of Engineering of the City of Fort Worth. Total quantities given in the bid proposal may not reflect actual quantities; however, they are given for the purpose of bidding on and awarding the contract.The City also reserves the right to increase or decrease quantities of individual pay items within the contract provided that the total contract amount remains within plus or minus (f) 25% of the contract award. The contractor is not entitled to any additional compensation or renegotiation of individual pay item bid prices. Upon acceptance of this proposal by the City Council, the bidder is bound to execute a contract and furnish Performance, Payment and Maintenance Bonds acceptable to and approved by the City of Fort Worth for performing and completing the said work within the time stated and for the following sums,to-wit: SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL ITEM ITEM QIJANTiTY PRICES WRITTEN IN WORDS PRICE AMOUNT BID S.P. 1 2 EA. Project Designation Sign @ Two Hundred Dollars & No Cents Per EA. $ 200.00 $ 400.00 S.P. 2 LUMP SUM Utility Adjustment @ Six Thousand Dollars & No Cents Per L.S. $ 6,000.0011 , P-1 MAR-14-2006 TUE_03:22 PM City Of Fw—EngiReer, Dept FAX N0. 817 871 6828 P. 10/23 SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH IUD UNIT 'TOTAL ITEM LT C Q]TANT T PTEs IMIMISIN IYRDS PRTCF ,AMOT :IIID 406 3 36 EA. Manhole Adjustment a 450 Fntir=ffylildrM Dollars& S.P. _No_,Cent's Per EA. $ 400.00 $1.4,400 406 4 39 EA, Water Valve Boxes Adjustment @ 450 Thrpg-i in(Jm,d____Dollars& S.P. NO __Cents Per EA. $ 300.00 $11,700 S.P. 5 2 EA. Water Meter Boxes Adjustment @ Tl�is-l -T� _»ollars& Nn —Cents Per EA. S 35.00 $70.00 104 6 8,250 L.F. Removal and Replacement of 502 Concrete Curb and Cutter @ S.F. -P-)F R✓2 Dollars& r`aD Cents Per L.F. $ 25 9F $ ICIS=.CO 104 7 960 S.Y. Removal and Replacement of 6" 504 Concrete Driveway @ S.P. 1b¢.N- 1114 tri' Dollars& wo —Cents Per S.Y. $ qe 104 8 450 S.Y. Removal and Replacement of 4" 504 Concrete Sidewalks @ S.P. ­ *`'o Dollars& Nv Cents Per S.Y. $ 32 Or $ I4,ge�aQo 300 9 200 C.Y. Removal and Replacement of 310 II.M.A.C.Pavement and 340 Base(Base Repair)(PG 64-22)[x3 S.P. T''A H✓Np Qti� Dollars& ^'Cents Per C.Y. $ 2oo'e $ 4v,ew.co 208 t0 200 C.Y. Graded Crushed Stones @ S.P. E-Pnollars& �?Cents Per C.Y. $ Z-1 W $ S40-0-00 P-2R(Addendum No.3)(2006-3) SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE AMO NT BM 406 3 36 EA. Manhole Adjustment @ / I 450 Four-Hundred Dollars& S.P. No Cents Per EA. $ 400.00 $ 1 ,400 406 4 39 EA. Water Valve Boxes Adjustment @ 450 Three-Hundred Dollars& S.P. No Cents Per EA. $ 300.00 $11,700 S.P. 5 2 EA. Water Meter Boxes Adjustment @ Thirty-Five Dollars& No Cents Per EA. $ .00 $70.00 104 6 8,250 L.F. Removal and Replacement of 502 Concrete Curb and Gutter @ S.P. Dollars& Cents Per L.F. $ $ 104 7 960 S.Y. Removal and Replacement of A4 504 Concrete Driveway @ ' S.P. Dollars& Cents Per S.Y,, $ $ 104 8 450 S.Y. Removal and Re cement of 4" 504 Concrete SidewAlks @ S.P. Dollars& Ce is Per S.Y. $ $ 300 9 200 C.Y. Removal and Replacement of 304 H.M.A.C.Pavement and 312 Base(Base Repair)@ S.P. Dollars& Cents Per C.Y. $ $ 208 10 200 C.Y. Graded Crushed Stones @ S.P. Dollars& Cents Per C.Y. $ $ P-2 MSR-14. .— TUE 03;23 PM City Of FW-Eng.. eer, lwpt FAX N0. 817 871 6828 P. 11/23 SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT 'TOTAL TTM ITEM 01TANT.ITY ERIrFS W-11111EN INWORDS PRICE 9MOIjhjT_ ;13I12 S.P. 1.1 23,000 L.F. 'Wedge Milling 2"to 0"Depth 5.0'Wide @ No Dollars& NIP 4 rlCents Per L.F. S O S 2o,7o4L aio S.P. 12 40 EA. Butt Joint-Milled a@ T.►o WvN024D;'ri1`' Dollars& $ $ No Cents Per EA. 210 _ _ e400,00 300 13 100 TON ILM..A.C.Level-Up(111G 76-22)@ 340 006 } 1DETfiW Dollars& S.P Cents Per TON $ Ito* $ 1140=civ 300 14 90,000 S.Y. 21114..M.A.C. Surface Course 310 (Type"D"Mix) (PG 76-22)@ 340 SE Vim''Dollars& $ $ SY FN'r-1- F ISE.CentsPer S.Y. ��foo.ora 104 15 80 S.Y. Removal and Replacement of 7" 360 Concrete Valley Gutter C3a S.P. 51X111 . Fi vis Dollars& N' Cents Per S.Y. $ 6 5 $ G, Zoo.ao 360 16 100 S.Y. New 7"Concrete Valley Gutter @ S.P. Dollars& kJO Cents Per S.Y. $ bS x $ 6 goaao 104 17 130 S.Y. Standard 4"Reinforced Concrete 505 Wheelchair Ramps @ S.P. S No Cent&Per S.Y. $ LS 5 G-0.00 402 is 800 L.F. 6"PVC Perforated Pipe 500 Subdrain @ 620 56 u OW 1ll01lars& S.P. .. c -Cents Per L.F. S , $ S,600.00 P-3R(Addenduin No.3)(2006-3) � V SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL ITEM ITEM QJJANTITY PRICES WRITTEN IN WORDS PRICE AMOUNT SlD S.P. 11 23,000 L.F. Wedge Milling 2"to 0"Depth 5.0' Wide @ Dollars& Cents Per L.F. $ $ S.P. 12 40 EA. Butt Joint-Milled @ Dollars& $ $ Cents Per EA. 300 13 100 TON H.M.A.C.Level-Up @ 312 Dollars& S.P. Cents Per TON $ $ 312 14 90,000 S.Y. 2"H.M.A.C.Surface Course S.P. (Type"D"Mix)@ Dollars& $ $ Cents Per S.Y 104 15 80 S.Y. Removal and Repl cement of 7" 314 Concrete Valley utter @ S.P. D ars& Ce s Per S.Y. $ $ 314 16 100 S.Y. New 7" oncrete Valley Gutter @ S.P. Dollars& Cents Per S.Y. $ $ 104 17 130 S.Y. Standard 4"Reinforced Concrete 505 Wheelchair Ramps @ - S.P. Dollars& Cents Per S.Y. $ $ 402 18 800 L.F. 6"PVC Perforated Pipe 500 Subdrain @ 620 Dollars& S.P. Cents Per L.F. $ $ P-3 MAR-14-2006 TUE_ 03;23 PM City Of Fw-Enginur, De, , FAX NO. 817 871 6828 P. 12/23 SPEC PAY APPROX. DESCRIPTION OF ITEMS WITII BID UNIT TOTAL ITEM ITEM ITS 'liy 'TTV P]RICF...r,WRITTEN_Nl RIDS PRICE Il MQ1INT 502 19 400 L.F. New Concrete Curb and Gutter @ lWf NTY-Two Dollars& Cents Per L.F. 2Z 81800.00 504 20 100 S.Y, New 4"Concrete Sidewalk @ TNte-1 --wv Dollars& .FJO �Cents Per S.Y. acao:00 275 21 13,500 S.Y. $"Pavement Pulverization @ S.P. 174At BB Dollars& N 1 N cry- F,%,E Cents Per S.Y. $ ys ss"52s.'00 275 22 176 TON Cement @ 0M & !"o Cents Per TON S MS V $ Z?,2Qa oo S,P. 23 5 EA. Remobilixation @ Five Hun reel Dollars& _No .—Cents Per EA. $ 500.00 $2,500.00 106 24 1.00 C.Y. Unclassified Street Excavation S.P. M%Q-_Ty= 'w1 Dollars& h!4_Cents Per C.Y. $ 35�' $ 3,SoO.vo S.P. 25 6,300 S.Y. 2"Surface Milling Q ON�Dollars& f!R Cents Per S.Y. $ 4! $ c�82o.Oo 104 26 11 S.Y. Removal and Replacement of Exposed 504 Concrete Aggregate S.P. Driveway/Sidewalk @ f 14 uYY-SAX Dollars& h!' Cents Per S.Y. $ $ Q�,ap P-4R(Addendum No.3) (2006-3) SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL ITEM ITEM QJJANTITY PRICES WRITTEN IN WORDS PRICE AMOUNT BID 502 19 400 L.F. New Concrete Curb and Gutter @ Dollars& Cents Per L.F. $ $ 504 20 100 S.Y. New 4"Concrete Sidewalk @ Dollars& Cents Per S.Y. $ 214 21 13,500 S.Y. 8"Pavement Pulverization @ _ S.P. Dollars& Cents Per S.Y. $ $ 214 22 176 TON Cement @ Dollars& Cents Per TO $ $ S.P. 23 5 EA. Remobilization @ Dollars& No Cent Per EA. $ 500.00 $2,500.00 106 24 100 C.Y. Unclassifi Street Excavation S.P. ollars& Cents Per C.Y. $ $ S.P. 25 6,300 S.Y. "Surface Milling @ Dollars& Cents Per S.Y. 104 26 11 S.Y. Removal and Replacement of Exposed 504 Concrete Driveway @ Dollars& Cents Per S.Y. P-4 MAR-14-2006 TUE 03:23 PM City Of Fw-Engineer, Dept FAX NO. 817 871 6828 P. 13/23 SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH IIID UNIT TOTAL IT 'Y ITS (JUAN11T'V PRiCrig MMI 'Y'�'NJN'c QRnS PRICF AMOTINI S.P. 27 38,250 L.F. Crack Sealing of Existing Pavement @ tJo Dollars& Q PIY Cents Per L.F. $ G 'a l 12S.ao S.P. 28 1 EA. Removal and Replacement of Top of 5-foot Drainage Inlot @ 1,04.%,u4. NuM72fADollars& R Cents Per EA, 1�2 O 20 S + zoo—w S.P. 29 1.EA. Removal and Replacement of Top of 10-foot Drainage Inlet @ r t P* t t-wnry f i rs& ,*� Cents 1'Cr EA. S I6,Soo x S I,S ao-ao S.P. 30 1 TaA. Specd Cushion(30' Wide Street) a) FiPTTfN W-$-Pa D Dollars& "n Cents Per EA. S t�SOo°r $ Soa.aa TOTAL BID $ 1121 3�9 94.0o P-SR(Addendurn No.3) (2006-3) SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE AMOITNT DM S.P. 27 38,250 L.F. Crack Sealing of Existing Pavement @ Dollars& Cents Per L.F. S.P. 28 1 EA. Removal and Replaceme of Top of = 5-foot Drainage Inlet Dollars& Cents Per E . S.P. 29 1 EA. Removal an eplacement of Top of 10-foot Dra' age Inlet @ Dollars& ents Per EA. S.P. 30 1 EA. S ed Cushion(30' Wide Street) @ ollars& Cents Per EA. TOTAL BID P-5 _ MAR-14-2006 TUE 03:23 PM City Of Fw-Engineer, Dept FAX N0, 817 871 6828 P. 14/23 This contract is issued by an organization which qualifies for exemption pursuant to the provisions or Article 20.04(1+)of the Texas Limited Sales,Excise and Use Tax Act. fixes. All equipment and materials not consumed by or incorporated into the project construction, are subject to State sales taxes under Mouse.Bill 11,enacted August 15,1991. The Contractor shall comply with City Ordinance 7278, as Amended by City Ordinance 7400 (Fort Worth City Code Sections 13-A-21 through 13-A-29), prohibiting discrimination in, employment practices. The undersigned agrees to complete all work covered by these contract documents within One Hundred- Five(IM Working Days from and after the date for commencing work as set'forth in the written Work order to be issued by the Owner, and to pity not less than the "Prevailing Wage Rates for Street,Drainage and Utility Construction" as established by the City of Fort Worth,Texas. Within Ten (10) Calendar Days of receipt of notice of acceptance of this bid, the undersigned will execute the formal contract and will deliver an approved Surety Bond for the faithful performance of this contract.The attached deposit check in the sum of FW E PeVC'f Nr A mo L)t:a: g io _Dollars($ ) is Ito become the properly of the City of Fort Worth,Texas,or the attached Bidder's Bond is to be'forfeitM in the event the contract and bond are not executed within the time set forth,as liquidated damages for delay and additional work caused thereby. The Contraetnr shall Mob9l*ze MobilizeWithin tell (,1n) ale8 lam r days of the nn 'ee given by the Cangtrliction_ ],nginepr forty of thel►catipns. If flip, contract9r Mis t0 begin the wnrk Within tQn (l0calendar day%,Un d llarg liquidated da> ilge null he assessed pgr Tilnric per d". I (we), acluiowledge receipt of the following addenda to the plans and specifications, all of the provisions and requirements or which have been taken into consideration in preparation of the foregoing bid; Respectfully E CONSTRUCTION,LTD. Addendum No.1 (Initials) Addendum No.2(Initials) Company N�7tle Addendum No.3(Initials) Sy: _ , L— . Signature (Seal) J.BARRY CLARK Printed Name of Principal Address: 5801 PAR:t VISTA CIR. KELLER,TX 76248 E-mail Address: ooc.lo eie. -. p a%CM PACCon. CAM Date:. 3-23-6L Telephone: ice-81,7141-4658 SUM P-6H(Addendum o. *@AR:!1 QY This contract is issued by an organization which qualifies for exemption pursuant to the provisions of Article 20.04(F)of the Texas Limited Sales,Excise and Use Tax Act. Taxes. All equipment and materials not consumed by or incorporated into the project construction, •• are subject to State sales taxes under House Bill 11,enacted August 15,1991. The Contractor shall comply with City Ordinance 7278, as amended by City Or finance 7400 (Fort Worth City Code Sections 13-A-21 through 13-A-29), prohibiting discrimin ion in, employment practices. The undersigned agrees to complete all work covered by these contract currents within Eighty-Five Working Days from and after the date for commencing work a set forth in the written Work order to be issued by the Owner, and to pay not less than the "P evailing Wage Rates for Street, Drainage and Utility Construction" as established by the City of rt Worth,Texas. Within Ten (10) Calendar Days of receipt of notice of acce,�tance of this bid, the undersigned will execute the formal contract and will deliver an approved S rety Bond for the faithful performance of this contract.The attached deposit check in the sum of ollars( ) is to become the property of the City of Fort Worth,Texas,or a attached Bidder's Bond is to be forfeited in the event the contract and bond are not executed wi in the time set forth,as liquidated damages for delay and additional work caused thereby. The Contractor shall mobilize wit i- I fil cakadar days of the notice g*ven by the Construction Fng*neer for any of the locations, IF*u/- --ractor fails tfl beg*n the work with in ten (10) calendar days, a $200 dollars liquidated damage/will be acqeSsed per Block per day, I (we), acknowledge receipt of t e following addenda to the plans and specifications, all of the provisions and requirements o which have been taken into consideration in preparation of the -� foregoing bid: Respectfully submitted, Addendum No.1 (Initials) Addendum No.2(Initials) Company Name Addendum No.3(Initials _ By: Signature (Seal) Printed Name of Principal Address: E-mail Address: Date: Telephone: P-6 VENDOR COMPLIANCE TO STATE LAW The 1985 Session of the Texas Legislature passed House Bill 620 relative to the award of contracts to non-resident bidders. This law provides that, in order to be awarded a contract as low bidder, non-resident bidders (out-of-state contractors whose corporate offices or principal place of business are outside of the State of Texas) bid projects for construction, improvements, supplies or services in Texas at an amount lower than the lowest Texas resident bidder by the same amount that a Texas resident bidder would be required too underbid a non-resident bidder in order to obtain a comparable contract in the State in which the non-resident's principal place of business is located. The appropriate blanks in Section A must be filled out by all out-of-state or non-resident bidders in order for your bid to meet specifications. The failure of out-of-state or non- resident contractors to do so will automatically disqualify that bidder. Resident bidders must check the box in Section B. _ A. Non-resident vendors in (give State), our principal place of business, are required to be percent lower than resident bidders by State law. A copy of the Statute is attached. Non-resident vendors in (give State), our principal place of business, are not required to underbid resident bidders. B. Our principal place of business or corporate offices are in the State of Texas. Bidder: PEACHTREE CONSTRUCTION,LTD. • J.BARRY C" Company By: (Please print) 5801 PAR::VISTA CIR. Address Sigiature KELLER,TX 76246 PRESIDENT City State Zip Title(Please print) THIS FORM MUST BE RETURNED WITH YOUR QUOTATION SPECIAL PROVISIONS FOR: H.M.A.C.SURFACE OVERLAY(2006-3) AT VARIOUS LOCATIONS DOE PROJECT NO.5202 TPW PROJECT NO.GS93-020930522810 1. SCOPE OF WORK: The work covered by these details and specifications consists of the removal (only) of all existing traffic buttons, removal and replacement of existing concrete curb and gutter and driveways and existing base repair and the addition of a new surface layer of H.M.A.C. for those streets designated as Mill Overlay (MOL). For those-streets designated as-Pulverized Overlay (POL), the work consists of the same removal and replacement items as described above, surface & base rehabilitation of existing pavement with cement and the addition of a new surface layer of H.M.A.C. These items are described in the Special Provisions of these - specifications. The work also consists of all other miscellaneous items of construction to be performed as outlined in the details and specifications which are necessary to satisfactorily complete the work. The Contractor shall mobilize within ten (10) calendar days of the notice given by the Construction Engineer for any locations. If the contractor fails to begin the work within ten (10)calendar days,a $200 dollars liquidated damage will be assessed per Block per day. It shall be the responsibility of the prospective bidder to visit the project sites and make such examinations and explorations as may be necessary to determine all conditions that may affect construction of this project. Particular attention should be given to methods of providing ingress and egress to adjacent private and public properties, procedures for protecting existing improvements and disposition of all materials to be removed. Proper consideration should be given to these details during preparation of the Proposal and all unusual conditions that may give rise to later contingencies should be brought to the attention of the City prior to the submission of the Proposal. The contractor shall verify these locations with the Construction Engineer. For street locations see list at the back of this document. At the sole discretion of the City, the City reserves the right to add, delete or substitute streets in this contract. The City also reserves the right to increase or decrease quantities of individual pay items within the contract provided that the total contract amount remains within plus or minus (f) 25% of the contract award. The contractor is not entitled to any additional compensation or renegotiation of individual pay item bid prices. SP-1 All short turnouts that intersect with a street to be repaired shall be included in this contract, even though they may not be listed with the street locations at the back of this document due to their size. The contractor shall verify these locations with the Construction Engineer prior to construction. The construction of these turnouts includes; but, is not limited to, milling, cleaning,tack coating,overlaying and facility adjusting. Total quantities given in the bid proposal may not reflect actual quantities, but represent the best estimate based on a reasonable effort of investigation; however, they are given for the purpose of bidding on and awarding the contract. 2. AWARD OF CONTRACT: Contract will be awarded to the lowest responsible bidder. 3. SUBMITTALS FOR CONTRACT AWARD: The City reserves the right to require contractor who is the apparent low bidder(s) for a project to submit such information as the City, in sole discretion may require, including but not limited to manpower and equipment records, information about key personnel to be assigned to the project, and construction schedule, to assist the City in evaluating and assessing the ability of the apparent low bidder(s) to deliver a quality product and successfully complete projects for the amount bid within the stipulated time frame. Based upon the City's assessment of the submitted information, a recommendation regarding the award of a contract will be made to the City Council. Failure to submit the information if requested may be grounds for rejecting the apparent low bidder as son-responsive.Affected contractors will be notified in writing of a recommendation to the City Council. 4. WORKING DAYS: The Contractor agrees to complete the Contract within the allotted number of days. If the Contractor fails to complete the work within the number of days specified,liquidated damages shall be charged, as outlined in Part 1, Item 8,Paragraph 8.6, of the "General Provisions" of the Standard Specification for Street and Storm Drain Construction of the City of Fort Worth, Texas. The Contractor also agrees to complete the final punch list within ten (10) days after receiving it. If the Contractor fails to complete the work within ten (10) days, the counting of the number of days to complete the Contract will resume and liquidated damages shall be SP-2 charged, as outlined in Part 1, Item 8, Paragraph 8.6, of the "General Provisions" of the Standard Specification for Street and Storm Drain Construction of the City of Fort Worth, Texas. 5. EARLY WARNING SYSTEM FOR CONSTRUCTION: Time is of the essence in the completion of this contract. In order to insure that the contractor is responsive when notified of unsatisfactory performance and/or of failure to maintain the contract schedule,the following process shall be applicable: The work progress on all construction projects will be closely monitored. On a bi-monthly basis the percentage of work completed will be compared to the percentage of time charged to the contract. If the amount of work performed by the contractor is less than the percentage of time allowed by 20% or more (example: 10% of the work completed in 30% of the stated contract time as may be amended by change order), the following proactive measures will be taken: A. A letter will be mailed to the contractor by certified mail, return receipt requested demanding that, within 10 days from the date that the letter is received, it provide sufficient equipment, materials and labor to ensure completion of the work within the contract time. In the event the contractor receives such a letter,the contractor shall provide to the City an updated schedule showing how the project will be completed within the contract time. B. The Project Manager and the Directors of the Department of Engineering, and Department of Transportation and Public Works will be made aware of the situation. If necessary, the City Manager's Office and the appropriate city council members may also be informed. C. Any notice that may, in the City's sole discretion, be required to be provided to interested individuals will distributed by the Engineering Department's Public Information Officer. D. Upon receipt of the contractor's response, the appropriate City departments and directors will be notified. The Engineering Department's Public Information Officer will, if necessary, then forward updated notices to the interested individuals. SP-3 ���� y� VIERn e Lane E. If the contractor fails to provide an acceptable schedule or fails to perform satisfactorily a second time prior to the completion of the contract, the bonding company will be notified appropriately. 6. RIGHT TO ABANDON: The City reserves the right to abandon, without obligation to the Contractor, any part of the project, or the entire project, at any time before the Contractor begins any construction work authorized by the City. 7. CONSTRUCTION SPECIFICATIONS: This contract and project are governed by the two following published specifications,except as modified by these Special Provisions: STANDARD SPECIFICATIONS FOR STREET AND STORM DRAIN CONSTRUCTION- CITY OF FORT WORTH and STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION-NORTH CENTRAL TEXAS.General Provisions shall be those of the Fort Worth document rather than Division 1 of the North Central Texas document. A copy of these specifications may be purchased at the office of the Department of Engineering, 1000 Throckmorton Street, 2nd Floor, Municipal Building, Fort Worth, Texas 76102. The specifications applicable to each pay item are indicated in the call-out for the pay item in the Proposal. If not shown, then applicable published specifications in any of these documents may be followed at the discretion of the Contractor. 8. CONTRACT DOCUMENTS: Bidders shall not separate, detach or remove any portion, segment or sheets from the contract documents at any time. Failure to bid or fully execute contract without retaining contract documents intact may be grounds for designating bids as "non-responsive" and rejecting bids or voiding contract as appropriate and as determined by the Director of the Engineering. 9. MAINTENANCE STATEMENT: The Contractor shall be responsible for defects in this project due to faulty materials and workmanship,or both,for a period of two(2)years from date of final acceptance of this project SP-4 by the City of Fort Worth and will be required to replace at his expense any part or all of the project which becomes defective due to these causes. See Special Instructions to Bidders Item No. 14 for further requirements. 10. TRAFFIC CONTROL: The contractor will be required to obtain a "Street Use Permit" prior to starting work. As part of the "Street Use Permit" a traffic control plan is required. The Contractor shall be responsible for providing traffic control during the construction of this project consistent with the provisions set forth in the "Latest Edition Texas Manual on Uniform Traffic Control Devices for Streets and Highways" issued under the authority of the "State of Texas Uniform Act Regulating Traffic on Highways", codified as Article 6701d Vernon's Civil Statues, pertinent sections being Section Nos.27,29,30 and 31. A traffic control plan shall be submitted for review to Mr. Charles R. Burkett, City Traffic Engineer 00-817-392-8712 at least 10 working days prior to the preconstruction conference. Although work will not begin until the traffic control panel has been reviewed, the Contractor's time will begin in accordance with the time frame established in the Notice to the Contractor. The Contractor will not remove any regulatory sign, instructional sign, street name sign, or other sign which has been erected by the City. If it is determined that a sign must be removed to permit required construction, the Contractor shall contact the Transportation and Public Works Department, Signs and Markings Division (phone number 871-7738), to remove the sign. In the case of regulatory signs, the Contractor must replace the permanent sign with a temporary sign meeting the requirements of the above referenced manual and such temporary sign must be installed prior to the removal of the permanent sign. If the temporary sign is not installed correctly or if it does not meet the required specifications,the permanent sign shall be left in place until the temporary sign requirements are met. When construction work is completed to the extent that the permanent sign can be re-installed,the Contractor shall again contact the Signs and Markings Division to re-install the permanent sign and shall leave his - temporary sign in place until such re-installation is completed. The Contractor shall limit his work within one continuous lane of traffic at a time to minimize Y interruption to the flow of traffic upon the approval of the City Engineer. Work shall not be performed on certain locations/streets during "peak traffic periods" as determined by the City Traffic Engineer and in accordance with the applicable provision of the SP-5 "City of Fort Worth Traffic Control Handbook for Construction and Maintenance Work Areas." See Special Instructions to Bidders Item No. 15, for further work time restrictions on "Air Pollution Watch Days"with substantial use of motorized equipment. 11. PUBLIC NOTIFICATION PRIOR TO BEGINNING CONSTRUCTION: Prior to beginning construction on any street in this contract, the contractor shall, prepare and deliver a notice/flyer of the pending construction to the front door of each residence or business that will be impacted by construction. The notice/flyer shall be posted three (3) days prior to beginning any construction activity along each street (Le. a notice for each phase of construction is required. concrete flatwork, pulverization, milling and asphalt overlay). The flyer shall be prepared on the Contractor's letterheads and shall include the same information as what is in the enclosed detail. The contractor shall submit a schedule showing the construction start and finish dates for each street of the project to the inspector at the pre-construction conference. In addition, a copy of the Notice of Construction/flyer shall be delivered to the City inspector for his ., review prior to being distribution. The contractor will not be allowed to begin construction on any street until the flyer is delivered to all residents of the street. All work involved with the notification flyer shall be considered subsidiary to the contract price and no additional compensation shall be made. The Electronic version of the notification flyer can be obtained from the Construction office at (817)871-8306. 12. PAYMENT: The Contractor will receive bi-weekly payment (minus 5% retainage) from the City for all v work for each pay period. Payment of the remaining amount shall be made with the final payment, and upon acceptance of the project. See Special Instructions to Bidders Item No. 14 for further requirements. V� s � G'' SP-6 YEN, 13. DELAYS: The Contractor shall receive no compensation for delays or hindrances to the work, except when direct and unavoidable extra cost to the Contractor is caused by the failure of the City to provide information or material,if any, which is to be furnished by the City. When such extra compensation is claimed a written statement thereof shall be presented by the Contractor to -- the Engineer and if by him found correct shall be approved and referred by him to the Council for final approval or disapproval; and the action thereon by the Council shall be final and binding. If delay is caused by specific orders given by the Engineers to stop work, or by the performance of extra work, or by the failure of the City to provide material or necessary instructions for carrying on the work, then such delay will entitle the Contractor to an equivalent extension of time, his application for which shall, however, be subject to the approval of the City and no such extension of time shall release the Contractor or the surety on his performance bond from all his obligations hereunder which shall remain in full force until the discharge of the contract. 14. DETOURS AND BARRICADES: The Contractor shall prosecute his work in such a manner as to create a minimum of interruption to traffic and pedestrian facilities and to the flow of vehicular and pedestrian traffic within the project area. Contractor shall protect construction,as required by Engineer, by providing barricades. Barricades, warning and detour signs shall conform to the Standard Specifications "Barriers and Warning and/or Detour Signs",Item 524,and/or as shown on the plans. Construction signing and barricades shall conform with the latest edition of the "Texas Manual on Uniform Traffic Control Devices,Vol.No. 1". 15. DISPOSAL OF SPOIL/FILL MATERIAL: Prior to the disposing of any spoil/fill material,the Contractor shall advise the Director of the Department of Engineering acting as the City of Fort Worth's Flood Plain Administrator ("Administrator"), of the location of all sites where the contractor intends to dispose of such material. Contractor shall not dispose of such material until the proposed sites have been determined by the Administrator to meet the requirements of the Flood Plain Ordinance of the City of Fort Worth (Ordinance No. 10056) and a flood plain permit issued. All disposal sites must be approved by the Administrator to ensure the filling is not occurring within a flood SP-7 plain without a permit. A flood plain permit can be issued upon approval of necessary engineering studies. No fill permit is required if disposal sites are not in a flood plain. Approval of the Contractor's disposal sites shall be evidenced by a letter signed by the Administrator stating that the site is not in a known flood plain or by a Flood Plain Fill Permit authorizing fill within the flood plain. Any expenses associated with obtaining the fill permit, including any necessary engineering studies,shall be at Contractor's expense. In the event that the Contractor disposes of spoil/fill material at a site without a fill permit or a letter from the Administrator approving the disposal site,upon notification by the Director of the Department of Engineering, Contractor shall remove the spoil/fill material at its expense and dispose of such materials in accordance with the Ordinance of the City and this section. No temporary storage of material, rubble, equipment or vehicles within parkway is allowed. Damage to sodded/landscaped areas shall be replaced at Contractor's expense to the satisfaction of City Engineer. 16. ZONING REQUIREMENTS: During the construction of this project, the Contractor shall comply with present zoning requirements of the City of Fort Worth in the use of vacant property for storage purposes. 17. PROPERTY ACCESS: Access to adjacent property shall be maintained at all times unless otherwise directed by the Engineer. 18. CONSTRUCTION SCHEDULE: Contractor shall be responsible for producing a project schedule at the pre-construction conference. This schedule shall detail all phases of construction, including project clean up, and allow the contractor to complete the work in the allotted time. Contractor will not move on to the jobsite nor will work begin until said schedule has been received and approval secured from the Construction Engineer. However, contract time will start even if the project schedule has not been turned in. Contract start date would be outlined in the pre- construction work order notice. Proiect schedule will be updated and resubmitted at the end of every estimating period. All costs involved with producing and maintaining the project schedule shall be considered subsidiary to this contract. SP-8 — 19. SAFETY RESTRICTIONS-WORK NEAR HIGH VOLTAGE LINES: The following procedures will be followed regarding the subject item on this contract: (1) A warning sign not less than five inches by seven inches, painted yellow with black letters that are legible at twelve feet shall be placed inside and outside vehicles such as cranes, derricks, power shovels, drilling rigs, pile drivers, hoisting equipment or similar apparatus. The warning sign shall read as follows: "WARNING —UNLAWFUL TO OPERATE THIS EQUIPMENT WITHIN SIX FEET OF HIGH VOLTAGE LINES." (2) Equipment that may be operated within ten feet of high voltage lines shall have an insulating cage-type of guard about the boom or arm,except back hoes or dippers,and insulator links on the lift hood connections. (3) When necessary to work within six feet of high voltage electric lines, notification shall be given the power company (TXU Electric Delivery) which will erect temporary mechanical barriers, de-energize the line, or raise or lower the line. The work done by the power company shall not be at the expense of the City of Fort Worth.The notifying department shall maintain an accurate log of all such calls to TXU Electric Delivery and shall record action taken in each case. _ (4) The Contractor is required to make arrangements with the TXU Electric Delivery for the temporary relocation or raising of high voltage lines at the Contractor's sole cost and expense. (5) No person shall work within six feet of a high voltage line without protection having been taken as outlined in Paragraph(3). 20. RIGHT TO AUDIT: Contractor agrees that City shall,until the expiration of three (3) years after final payment under this contract is made by City, have access to and the right to examine and photocopy any directly pertinent books, documents, papers and records of Contractor involving transactions relating to this contract. Contractor agrees that City shall have access during normal working hours to all necessary Contractor facilities and shall be provided adequate and appropriate workspace in order to conduct audits in compliance with the provisions of this section. SP-9 Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that City shall, until the expiration of three (3) years after final payment under the subcontract, have access to and the right to examine any directly pertinent books, documents, papers and shall be provided adequate and appropriate work space, in order to conduct audits in compliance with the provisions of this article together with Article VI. City shall give the subcontractor reasonable advance notice of intended audits. Contractor and subcontractor agree to photocopy such documents as may be requested by City. City agrees to reimburse Contractor and/or subcontractor for the cost of copies at the rates as contained in the Texas Administrative Code at the time payment is made. 21. CONTRACTOR'S RESPONSIBILITY FOR DAMAGE CLAIMS: Contractor Covenants and agrees to indemnify City's Engineer and Architect, and their personnel at the project site for Contractor's sole negligence. In addition, Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims or suits for property loss, property damage, personal injury, including death, arising out of, or alleged to arise out of, the work and services to be performed hereunder by Contractor, its officers, agents, employees, subcontractors, licensees or invitees, whether or not any such injury, damage or death is caused, in whole or in part, by the negligence or alleged negligence of City, its officers, servants, or employees. Contractor likewise covenants and agrees to indemnify and hold harmless the City from and against any and all injuries to City's officers, servants and employees and any damage, loss or destruction to property of the City arising from the performance of any of the terms and conditions of this Contract, whether or not any such w injury or damage is caused in whole or in part by the negligence or alleged negligence of City, its officers,servants or employees. In the event City receives a written claim for damages against the Contractor or its subcontractors prior to final payment, final payment shall not be made until Contractor either (a) submits to City satisfactory evidence that the claim has been settled and/or a release from the claimant involved, or (b) provides City with a letter from Contractor's liability insurance carrier that the claim has been referred to the insurance carrier. The Director may, if deemed appropriate, refuse to accept bids on other City of Fort Worth public work from a Contractor against whom a claim for damages is outstanding as a result of work performed under a City Contract. SP-10 22. SUBSTITUTIONS: The specifications for materials set out the minimum standard of quality that the City believes necessary to procure a satisfactory project. No substitutions will be permitted until the Contractor has received written permission of the Engineer to make a substitution for the material that has been specified. Where the term "or equal', or "or approved equal"is used, it is understood that if a material,product, or piece of equipment bearing the name so used is furnished, it will be approvable, as the particular trade name was used for the purpose of establishing a standard of quality acceptable to the City. If a product of any other name is - proposed substitutes is procured by the Contractor. Where the term "or equal', or "approved equal" is not used in the specifications, this does not necessarily exclude alternative items or material or equipment which may accomplish the intended purpose. However, the Contractor shall have the full responsibility of providing that the proposed substitution is, in fact, equal, and the Engineer, as the representative of the City, shall be the sole judge of the acceptability of substitutions. The provisions of the sub-section as related to "substitutions"shall be applicable to all sections of these specifications. 23. WATER FOR CONSTRUCTION: Water for construction will be furnished by the Contractor,at his own expense. 24. SANITARY FACILITIES FOR WORKERS: The Contractor shall provide all necessary conveniences for the use of workers at the project site.Specific attention is directed to this equipment. 25. MATERIAL STORAGE: Material shall not be stored on private property unless the Contractor has obtained permission from the property Owner. 26. PROTECTION OF EXISTING UTILITIES AND IMPROVEMENTS: The Contractor shall take adequate measures to protect all existing structures, improvements and utilities,which may be encountered. SP-11 � a �I ll 27. LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC: The Contractor's particular attention is directed to the requirements of Item 7, "Legal Relations and Responsibilities to the Public" of the "Standard Specifications for Street and Storm Drain Construction". 28. CONSTRUCTION The City of Fort Worth maintains a "CONFINED SPACE ENTRY PROGRAM" for its employees and all contractors and their sub-contractors must comply with this program as a condition of the contract. All active sewer manholes, regardless of depth, are defined, as "permit required confined spaces".Contractors will be required to complete the"CONFINED SPACE ENTRY PERMIT" used by the Fort Worth Water Department (Field Operations Division) for each entry and possess and use the equipment necessary to comply with this program. The cost of complying with this program will be considered subsidiary to the pay items involving work in confined spaces(e.g.vacuum testing,cleaning,televising,construction, etc.). NON-PAY ITEM No. 1 -SPRINKLING FOR DUST CONTROL: All applicable provisions of Standard Specifications Item 200, "Sprinkling for Dust Control"shall apply. However, no direct payment will be made for this item and it shall be considered incidental to this contract. NON-PAY ITEM NO.2-REMOVAL OF TRAFFIC BUTTONS AND TEMPORARY LANE TAPE: All traffic buttons shall be removed from the existing asphalt surface before resurfacing begins. The contractor shall be responsible for the removal of all buttons.Upon completion of the job the City will install new buttons after proper notification. The contractor shall also be responsible for all materials, equipment and labor to place temporary adhesive lane marking tape, at locations as directed by the Construction Engineer, to direct traffic flow until permanent markers are installed. The contractor shall notify the Construction Engineer to arrange for the replacement of the buttons and adhesive lane markers(arrows,etc.).All costs to the contractor shall be figured as subsidiary to this contract. SP-12 NON-PAY ITEM No.3—LOCATION AND EXPOSURE OF MANHOLES AND WATER VALVES: The contractor shall be responsible for locating and marking previously exposed manholes and water valves in each street of this contract before the resurfacing process commences for a particular street. The contractor shall attempt to include the Construction Engineer(if he is available)in the observation and marking activity. In any event a street shall be completely marked a minimum of two (2) working days before resurfacing begins on any street. Marking the curbs with paint is a recommended procedure. It shall be the contractor's responsibility to notify the utility companies that he has commenced work on the project. As the resurfacing is completed (within same day), the contractor shall locate the covered manholes and valves and expose them. Upon completion of a street the contractor shall notify the utilities of this completion and indicate the start of the next one in order for the utilities to adjust facilities accordingly. The following are utility contact persons: Company Telephone Number Contact Person SBC—Telephone 817-338-6202 Mr. Gary Tillory 214-384-3732 Cell TXUElectric Delivery 817-215-6424 Mr. Scott King Downtown 817-215-6688 Mr.Robert Martinez -other than Downtown Atmos Energy(Gas)— 817-215-4306 Mr.Roger Oliver - CFW Street Light and Signal 817-871-8100 Mr.Dwayne Cox Mr. Roger Martin Storm Drain 817-871-8100 Mr. Gordon Couch Water&Sewer 817-212-2686 817-992-0130 Cell Mr. Steve Tackett 817-212-2633 817-991-8102 Cell Mr. Ron Dacus SP-13 CIT EC,PEA i Y FT, r�: RTH, T E K 8 Of course, under the terms of this contract, the contractor shall complete adjustment of the storm drain and Water Department facilities,one traffic lane at a time within five(5)working days after completing the laying of proposed H.M.A.C.overlay adjacent to said facilities. Any deviation from the above procedure and allotted working days may result in the shut down of the resurfacing operation by the Construction Engineer. The contractor shall be responsible for all materials, equipment and labor to perform a most accurate job and all costs to the contractor shall be figured subsidiary to this contract. NON-PAY ITEM No.4-PROTECTION OF TREES,PLANTS AND SOIL: All property along and adjacent to the Contractor's operations including lawns, yards, shrubs, trees, etc. shall be preserved or restored after completion of the work to a condition equal or better than existed prior to start of work. By ordinance, the contractor must obtain a permit from the City Forester before any work (trimming, removal or root pruning) can be done on trees or shrubs growing on public property including street rights-of-way and designated alleys. This permit can be obtained by calling the Forestry Office at 871-5738. All tree work shall be in compliance with pruning standards for Class II Pruning as described by the National Arborist Association. A copy of these standards can be provided by calling the above number. Any damage to public trees due to negligence by the Contractor shall be assessed using the current formula for Shade Tree Evaluation as defined by the International Society of Arboriculture. Payment for negligent damage to public trees shall be made to the City of Fort Worth and may be withheld from funds due to the Contractor by the City. To prevent the spread of the Oak Wilt fungus, all wounds on Live Oak and Red Oak trees shall be immediately sealed using a commercial pruning paint. This is the only instance when pruning paint is recommended. NON-PAY ITEM No.5—PROJECT CLEAN-UP: During the construction of this project, all parkways that are excavated shall be shaped, including bar ditches, and backfilled at the same time the roadway is excavated. Excess excavation will be disposed of at locations approved by the Engineer. The Contractor shall be aware that keeping the project site in a neat and orderly condition is considered an integral part of the contracted work and as such shall be considered subsidiary to the appropriate bid items. Clean up work shall be done as directed by the SP-14 Engineer as the work progresses or as needed. If, in the opinion of the Engineer it is necessary, clean up shall be done on a daily basis. Clean up work shall include, but not be limited to: • Sweeping the street clean of dirt or debris • Storing excess material in appropriate and organized manner • Keeping trash of any kind off of residents' property If the Engineer does not feel that the jobsite has been kept in an orderly condition, on the next estimate payment (and all subsequent payments until completed)of the appropriate bid item(s)will be reduced by 25%. The Contractor shall make a final cleanup of all parts of the work before acceptance by the City or its representative. This cleanup shall include removal of all objectionable rocks, pieces of asphalt or concrete and other construction materials, and in general preparing the site of the work in an orderly manner and appearance. Final cleanup work shall be done for this project as soon as the paving and curb and gutter has been constructed. No more than seven days shall elapse after completion of construction before the roadway and right-of-way is cleaned up to the satisfaction of the Engineer. NON-PAY ITEM NO.6—CRACK SEALING: All cracks that develop after completion of the street resurfacing and until the end of the 2- year warranty period shall be crack sealed with Rubber Asphalt Crack Sealer, as per the latest edition of the TxDOT Specifications for Construction and Maintenance of Highways, Streets,and Bridges,Item 300,"Asphalts,Oils,and Emulsions". The contractor shall be responsible for all materials, equipment and labor to perform a most accurate job and all costs to the contractor shall be figured subsidiary to this contract. NON-PAY ITEM NO.7—STORM DRAIN INLET PROTECTION: All pulverization and overlay streets with storm drain inlets shall use inlet protection for sediment control, in accordance with the Standard Specifications for Public Works Construction-North Central Texas. The contractor shall be responsible for all materials, equipment and labor to perform a most accurate job and all costs to the contractor shall be figured subsidiary to this contract. SP-15 NON-PAY ITEM NO. 8 - NO PAVING WORK ON SOLID WASTE WEEKLY PICK-UP DAY In order to eliminate potential rutting of the pavement from solid waste trucks while paving operations are underway, the contractor shall schedule construction on all the identified project streets so that no paving activities are scheduled on the weekly solid waste pick-up day for each street. The solid waste weekly pick-up day for each project street is identified on the "STREET BY STREET PAVING QUANTITY DETERMINATION SPREADSHEET" located at the end of the contract documents. On the spreadsheet,the solid waste weekly pick-up is listed as the day of the week under the column heading, "Garbage, Recycling, Yard Trimmings & Brush Weekly Pickup". No paving activities shall be scheduled on this day. Also on the spreadsheet,the solid waste monthly pick-up is listed as the week of the month under the column heading, "Monthly Pickup of Bulky Items". During this week,the day of pick up varies from Monday to Saturday afternoon. The Contractor will be allowed to pave the week of the solid waste monthly pickup. The Contractor, however, will be responsible for any coordination with the City Environmental Dept. concerning when the monthly pickup day occurs. If new pavement is placed and damaged by the solid waste monthly pickup trucks; then, the Contractor will be responsible for any repairs required, at no cost to the City. Assessment of damage will be determined by the Construction Engineer,or,his authorized representative. The weekly and monthly solid waste pick up schedules are made available to the Contractor, for bid preparation and construction use. All cost associated with scheduling pavement installation around "solid waste pick-up days" shall be considered incidental to the project contract amount and no additional compensation shall be allowed. PAY ITEM No. 1 -PROJECT DESIGNATION SIGN: The contractor shall construct and install two (2) Project Designation Signs and it will be the responsibility of the contractor to maintain the signs in a presentable condition at all times on each project under construction. Maintenance will include painting and repairs as directed by the Engineer. SP-16 It will be the responsibility of the Contractor to have the individual project signs lettered and painted in accordance with the enclosed detail. The quality of the paint, painting and lettering on the signs shall be approved by the Engineer. The height and arrangement of the lettering shall be in accordance with the enclosed detail. The sign shall be constructed of '/4" fir plywood, grade A-C (exterior) or better. These signs shall be installed on barricades or as directed by the Engineer and in place at the project site upon commencement of construction. The work, which includes the painting of the signs, installing and removing the signs, furnishing the materials, supports and connections to the support and maintenance shall be to the satisfaction of the Engineer. The unit price bid per each will be full payment for materials including all labor, equipment,tools and incidentals necessary to complete the work. PAY ITEM NO.2-UTILITY ADJUSTMENT: This item is included for the basic purpose of establishing a contract price which will be comparable to the final cost of making necessary adjustments required due to street improvements to water,sanitary sewer,and natural gas service lines and appurtenances where such service lines and appurtenances are the property owner's responsibility to maintain. An arbitrary figure has been placed in the Proposal; however, this does not guarantee any payment for utility adjustments, neither does it confine utility adjustments to the amount shown in the Proposal. It shall be the Contractor's responsibility to provide the services of a licensed plumber to make the utility adjustments determined necessary by the Engineer. No payment will be made for utility adjustments except those adjustments determined necessary by the Engineer. Should the Contractor damage service lines due to his negligence,where-such lines would not have required adjustment or repair otherwise,the lines shall be repaired and adjusted by the Contractor at the Contractor's expense. The payment to the Contractor for utility adjustments shall be the actual cost of the adjustments plus ten percent (10%) to cover the cost of bond and overhead incurred by the Contractor in handling the utility adjustments. PAY ITEM NO.3-MANHOLE ADJUSTMENT: This item shall include adjusting the tops of existing manhole with concrete collar to match proposed grade as shown on the plans, in the detail at the back of this document or as directed SP-17 by the Engineer. Standard Specification Item Nos. 450 "Adjusting Manholes and Inlets" and - 406"Concrete for Structures" shall apply except as herein modified. The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch.Work shall be completed and street open to traffic within seven (7)calendar days. If the contractor fails to complete the work within seven (7) calendar days, a $100 dollars liquidated damage will be assessed per each manhole per day. Prior to beginning of work,the Contractor shall make an inventory of the condition of existing manholes. The Engineer will field verify this inventory and provide the Contractor replacements for broken manhole covers. The contractor shall replace the manhole covers which are damaged during construction at no cost to the City. Included as part of this pay item shall be the application of a cold-applied preformed flexible butyl rubber or plastic sealing compound for sealing interior and/or exterior joints on concrete manhole sections,as per current City Water Department Special Conditions. The unit price pre bid per each will be full compensation for all labor, materials, equipment, tools,and incidentals necessary to complete the work. PAY ITEM NO.4-WATER VALVE BOXES ADJUSTMENT: This item shall include adjusting the tops of existing water valve with concrete collar to match proposed grade as shown on the detail at the back of this document or as directed by the Engineer. Standard Specification Item Nos. 450 "Adjusting Manholes and Inlets" and 406 "Concrete for Structures" shall apply except as herein modified. Contractor will be responsible for adjusting water valve boxes to match new pavement grade. The water valves themselves will be adjusted by City of Fort Worth Water Department forces. Prior to beginning of work,the Contractor shall make an inventory of the condition of existing water valve boxes. The Engineer will field verify this inventory and provide the Contractor replacements for broken valve boxes. The contractor shall replace the valve boxes which are damaged during construction at no cost to the City. The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch.Work shall be completed and street open to traffic within seven(7)calendar days. SP-18 If the contractor fails to complete the work within seven (7) calendar days, a $100 dollar liquidated damage will be assessed per each water valve box per day. The unit price pre bid per each will be full compensation for all labor, materials, equipment, tools,and incidentals necessary to complete the work. PAY ITEM NO.5-WATER METER BOX ADJUSTMENT: This item only apply when the adjacent curb and gutter has been determined to be removed and replaced as directed by the Engineer.The adjustment shall include raising or lowering the existing water meter box to the proper grade. The unit price pre bid per each will be full compensation for all labor, materials, equipment, tools,and incidentals necessary to complete the work. ~ PAY ITEM NO. 6 - REMOVAL AND REPLACEMENT OF CONCRETE CURB AND GUTTER: These provisions require the contractor to remove all failed existing curb and gutter, as designated by the Construction Engineer, and replace with standard concrete curb and gutter, laydown curb and gutter,or in like kind,as governed by the standard City Specifications,Item No. 104 "Removing Old Concrete", Item No. 502 "Concrete Curb and Gutter", and Drawing Nos. S-S2 through S-S4. Pay limits for laydown curb and gutter are as shown in Drawing No. S-S5 of the Standard Specifications.Contractor shall sawcut the curb and gutter and pavement prior to removal. Included, and figured subsidiary to this unit price, will be the required sawcut excavation, as per specification Item No. 106 "Unclassified Street Excavation", into the street to aid in the construction of the curb and gutter.The pay limit will be 9" out from the gutter lip,with same day haul-off of the removed material to a suitable dump site. The street void shall be filled with H.M.A.C. Type "D" mix (PG 6422) in accordance with all applicable provisions of TxDOT's "Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges" Item Nos. 300 "Asphalts, Oils, and Emulsions",310 "Prime Coat" (referenced), and 340 "Dense-Graded Hot-Mix Asphalt (Method)"(referenced) and compacted to standard densities. Top soil as per specification Item No. 116 "Top Soil", if needed, shall be added and leveled to grade behind the curb. Existing improvements within the parkway such as water meters, sprinkler system, etc. damaged during construction shall be replaced with same or better at no cost to the City. SP-19 - Backfill for curb and gutter shall be completed within seven (7) calendar days from the day of completion of the curb and gutter. If the contractor fails to complete the work within seven(7) calendar days,a$100 dollar liquidated damage will be assessed per block per day. For those streets designated as Mill Overlay on the street list in the back of this contract document book, the wedge milling shall begin within fourteen (14) calendar days from the completion of the curb and gutter. If the contractor fails to complete the work within fourteen (14)calendar days,a$100 dollar liquidated damage will be assessed per block per day. The unit price bid per linear foot shall be full compensation for all materials,labor,equipment and incidentals necessary to complete the work. PAY-ITEM NO.7-REMOVAL AND REPLACEMENT OF 6" CONCRETE DRIVEWAYS: This item shall include the removal and replacement of existing concrete driveways, due to deterioration or in situations where curb and gutter is replaced to adjust grades to eliminate ponding water with same day haul-off of the removed material to a suitable dump site. For specifications governing this item see Item No. 104 "Removing Old Concrete",Item No. 504" Concrete Sidewalk and Driveways".Pay limits for concrete driveway are as shown in Drawing No.S-S5 of the Standard Specifications. The unit price bid per square yard shall be full compensation for all labor, material, equipment,supplies, and incidentals necessary to complete the work. PAY-ITEM NO.8-REMOVAL AND REPLACEMENT OF 4" CONCRETE SIDEWALK: This item shall include the removal and replacement of existing concrete sidewalk due to failure or in situation where curb and gutter is replaced to adjust grades to eliminate ponding water with same day haul-off of the removed material to a suitable dump site. For specifications governing this item see Item No. 104 "Removing Old Concrete", and Item No. 504 "Concrete Sidewalk and Driveways". The unit price bid per square yard shall be full compensation for all labor, material, equipment,supplies,and incidentals necessary to complete the removal and replacement work. SP-20 PAY ITEM NO. 9 - REMOVAL AND REPLACEMENT OF H.M.A.C. PAVEMENT AND BASE: The contractor is to remove all existing deformed H.M.A.C. pavement and/or bad base material that shows surface deterioration and/or complete failure. The Construction Engineer will identify these areas upon which time the contractor will begin work. The failed area shall be saw cut, or other similar means, out of the existing pavement in square or rectangular fashion.The side faces shall be cut vertically and all failed and loose material excavated. As a part of the excavation process, all unsatisfactory base material shall be removed, if required, to a depth sufficient to obtain stable sub-base. The total depth of excavation could range from a couple of inches to include the surface-base-some sub-base removal for which the Construction Engineer will select the necessary depth. The remaining good material shall be leveled and uniformly made ready to accept the fill material. All excavated material shall be hauled off site, the same day as excavated, to a suitable dump site. After satisfactory completion of removal as outlined above, the contractor shall place the permanent pavement patch, with Type "D" surface mix (PG 6422). This item will always be used even if no base improvements are required. The proposed H.M.A.C. repair shall match the existing pavement section or the depth of the failed material, whichever is greater. However,the patch thickness shall be a minimum of 2 inches. Generally the existing H.M.A.C. pavement thickness will not exceed 6".Before the patch layers are applied,any loose material, mud and/or water shall be removed. A liquid asphalt tack coat shall be applied to all exposed surfaces.Placement of the surface mix lifts shall not exceed 3 inches with vibrator compactions to follow each lift. Compactions of the mix shall be to standard densities of the City of Fort Worth,made in preparation to accept the recycling process. All applicable provisions of TxDOT's "Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges" Item Nos. 300 "Asphalts, Oils, and Emulsions", 310 "Prime Coat" (referenced), and 340 "Dense-Graded Hot-Mix Asphalt - (Method)"(referenced)shall govern work. The unit price bid per cubic yard shall be full compensation for all materials,labor, equipment and incidentals necessary to complete the work. SP-21 PAY-ITEM NO. 10-GRADED CRUSHED STONES: This item shall be used to repair the failed base material in areas exceed 8" deep as directed by the Engineer.The material shall be graded crushed stone. For City specifications governing this item see Item No.208 "Flexible Base". The unit price bid per cubic yard shall be full compensation for all materials,labor,equipment and incidentals necessary to complete the work. PAY-ITEM NO. 11-WEDGE MILLING 2" TO 0"DEPTH 5.0'WIDE: 1. Description This item shall consist of milling the existing pavement from the lip of gutter at a depth of 2" and transitioning to match the existing pavement (0" cut) at a minimum width of 51. The existing pavement to be milled will either be asphalt, concrete, or brick pavement. The removal and disposal of the milled materials shall be as directed by the Engineer. - The milled surface shall provide a smooth surface free from gouges, ridges, oil film, and other imperfections of workmanship and shall have a uniform textured appearance.In all situations where the existing H.M.A.C. surface contacts the curb face, the wedge milling shall include the removal of the existing asphalt covering the gutter up to and along the face of curb. The wedge milling operations for this project will be performed in a continuous manner along both sides of the street.Details of milling locations are at the back of this document. Contractor is required to begin the overlay,within five(5)calendar days from the date of the wedge milling completion of any one street. Should the contractor fail to meet this condition,the wedge milling will be shut down,and liquidated damage of$500.00 per day per street will be assessed until all wedge milled streets are overlayed. The overlay, once begun on a street shall continue uninterrupted until complete. The Contractor shall haul-off the removed material to a suitable dumpsite. 2. Equipment The equipment for removing the pavement surface shall be a power operated milling machine or other equal or better mechanical means capable of removing, in either one pass or two passes, the necessary pavement thickness in a five-foot minimum width. The SP-22 equipment shall be self-propelled with sufficient power,traction and stability to maintain accurate depth of cut and slope. The machine shall be equipped with an integral loading and reclaiming means to immediately remove material being cut from the surface of the roadway and discharge the cuttings into a truck, all in one operation. Adequate back-up equipment (mechanical street sweepers, loaders, water truck, etc.) and personnel will also be provided to keep flying dust to a minimum and to insure that all cuttings are removed from street surface daily. Stockpiling of planed material will not be permitted on the project site unless designated by the Engineer. The machine shall be equipped with means to control dust created by the cutting action and shall have a manual system providing for uniformly varying the depth of cut while the machine is in motion thereby making it possible to cut flush to all inlets,manholes,or other obstructions within the paved area. The speed of the machine shall be variable in order to leave the desired grid pattern specified under Surface Texture. For those streets designated as Mill Overlay on the street list in the back of this contract document book,the wedge milling shall begin within fourteen(14)calendar days from the completion of the curb and gutter. If the contractor fails to complete the work within fourteen (14) calendar days, a $100 dollar liquidated damage will be assessed per block per day. The unit price bid per linear feet shall be full compensation for all labor, material, equipment,tools,and incidentals necessary to complete the work. PAY-ITEM NO. 12-BUTT JOINTS-MILLED: Description: This item requires the contractor to mill "butt joints" into the existing surface, in association with the wedge milling operation (PAY ITEM NO. 11) to the depth and at locations as described below. The butt joint will provide a full width transition section, whereby the new overlay shall maintain constant depth at the point the new overlay is terminated and the new surface elevation matches the existing pavement. The construction activities, performance standards and equipment needed for the butt joints milling operations shall be governed by the special provisions of Pay Item No. 11 - Wedge Milling. The configuration of the butt joints is described in more detail below. General details of butt joint locations - along with wedge milling in general-are shown in plan form at the back of this document. SP-23 Construction Details: _ Prior to the milling of the butt joints, the contractor shall consult with the construction Engineer for proper location of these joints and verify that the selected limits of the projects street are correct. The general locations for butt joints are at all beginning and ending points of streets listed in the project and as more graphically detailed at the back of this specification book. The joints are also required on both sides of all railroad tracks and concrete valley gutters, bridge decks and culverts and all other items which transverse the street and end the continuity of the asphalt surface. Each butt joint shall be 20 feet long and milled out across the full width of the street section to a tapered depth of 2". This milled area shall be tapered within the 20 feet to a depth from 0" to 2" at a line adjacent to the beginning and ending points or intermediate transverse items. This butt joint- when overlayed-will consist of an asphalt section that will transition the new overlay to match the existing pavement elevation. The contractor shall provide a temporary wedge of asphalt at all butt joints to provide a smooth ride over the bump. Measurement and Payment: Butt joints as prescribed above, will be measured by the unit of each butt joint milled. The disposal of excess material involved will not be measured for payment. Each butt joint-milled, measured as above, complete-in place-in accordance with these specifications, will be paid for at the unit price shown in the proposal for 'Butt Joints". The unit price bid per each shall be full compensation for all milling, including material haul-off, tools,labor,equipment and incidentals necessary to complete the required work. PAY ITEM NO. 13-H.M.A.C.LEVEL UP: This item shall be used to fill ruts, depressions, level up pavement section with Type "D" surface mix (PG 64-22) prior to placing the asphalt surface overlay and where needed as directed by the Engineer in the field. SP-24 All applicable provisions of TxDOT's "Standard Specifications for Construction and - Maintenance of Highways, Streets, and Bridges" Item Nos. 300 "Asphalts, Oils, and Emulsions" (referenced), 310 "Prime Coat" (referenced), and 340 "Dense-Graded Hot-Mix Asphalt(Method)"(referenced),shall govern work. The unit price bid per ton shall be full compensation for all materials, labor, placing, equipment,cleaning and incidentals necessary to complete the work. PAY-ITEM NO. 14 - 2" H.M.A.C. (TYPE "D" MIX) ASPHALT CEMENT SURFACE COURSE: All applicable provisions of TxDOT's "Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges" Item Nos. 300 "Asphalts, Oils, and Emulsions" (referenced), 310 "Prime Coat" (referenced), and 340 "Dense—Graded Hot-Mix Asphalt(Method)"(referenced)shall govern work. The following amendments to the above TxDOT's specifications shall govern, take precedence and shall include: Item No. 340 "Dense—Graded Hot-Mix Asphalt(Method)"(referenced): • Under Item 340.2,Materials,A. Aggregates: The surface aggregate classification (SAC) shall be Class B. The Contractor shall perform the Los Angeles abrasion, magnesium sulfate soundness,Micro-Deval and all other aggregate quality tests listed in Table 1. 2.RAP will not be allowed,for use,in surface course Type"D"mix. T • Under Item 340.2,Materials,D. Asphalt Binder: Furnish performance-graded PG 64-22 for H.M.A.C. surface course, level up and pavementlbase repair or replacement. • Under Item 340.4,Construction, The City of Fort Worth, Texas will perform quality assurance tests and checks on the paving project materials during construction, to ensure compliance with the specifications and approved mixture design. SP-25 The sampling and testing of the materials shall be made at the expense of the City. In the event the sampling and testing does not comply with the specifications, all subsequent testing of the material,in order to determine if the material is acceptable, shall be furnished and paid by the contractor,as directed by the Engineer. Samples will be taken daily for determination of asphalt content, aggregate gradation,maximum theoretical specific gravity and stability. For each hot mix asphalt surface course placed, nuclear gauge in-place density testing will be performed at each 50-ft station,with a minimum of one test per lane width at each 50-ft station. For each hot mix asphalt surface course placed, cores will be obtained to determine in-place density and thickness. The cores will be taken at the maximum interval of 300-ft(to coincide with field density locations). • Under Item 340.4, Construction,A.Mixture Design: The contractor shall furnish mixture design of the proposed hot mix asphalt, at or before the pre-construction meeting. The Contractor shall submit to the Engineer a mixture design prepared by a AASHTO accredited laboratory,for the materials to be used in the project. Using the typical weight design example in Tex-204-F,Part I, the mixture design shall meet the requirements contained in Tables 1 through Table 5 of Item 340. The Indirect Tensile-Dry (Tex-226-F) and the Hamburg Wheel-tracking (Tex-242-F) tests shall be waived. The mixture design report must be certified and signed by a Level II Specialist and submitted on TxDOT's software forms. The Engineer may verify the mixture design at optimum asphalt content. • Under Item 340.4, Construction,B. Job-Mix Formula Approval: The Contractor will perform the Boil Test(Tex-530-C). • Under Item 340.4, Construction,J.Ride Ouality: - The Ride Quality Surface Type A(Tex-1001-S)test shall be waived. • Under Item 340.5 Measurement: Hot mix will be measured by the square yard of the composite hot mix, which includes asphalt, aggregate and additives. SP-26 ■ Under Item 340.6 Payment: The work performed and materials furnished in accordance with this Item and measured as provided under "Measurement", will be paid for at the unit price bid per square yard,for"Dense-Graded Hot Mix Asphalt (Method)". PAY ITEM NO. 15 - REMOVAL AND REPLACEMENT OF 7" CONCRETE VALLEY GUTTER: This item shall include the removal and reconstruction of existing concrete valley gutters at locations to be determined in field by the Construction Engineer. Removal of existing concrete valley, asphalt pavement, concrete base, curb and gutter, and necessary excavation to install the concrete valley gutters all shall be subsidiary to this pay item. Furnishing and placing of 2:27 concrete base and crushed limestone to a depth as directed by the Engineer and necessary asphalt transitions as shown in the concrete valley gutter details,shall be subsidiary to this Pay Item. See City standard specifications Item No. 104, "Removing Old Concrete", Item No. 106, R "Unclassified Street Excavation" Item No. 208 "Flexible Base", Drawing No. S-S6 and detail enclosed, TxDOT's "Standard Specifications for Construction and Maintenance of Highways, Streets,and Bridges" Item Nos. 300 "Asphalts, Oils, and Emulsions" (referenced),310 "Prime Coat" (referenced), and 340 "Dense-Graded Hot-Mix Asphalt (Method)" (referenced) and Item No. 360 "Concrete Pavement" (enclosed). Measurement for final quantities of valley gutter will be by the square yard of concrete pavement and the curb and gutter section will be included. Contractor may substitute 5" non-reinforced (2:27) Concrete Base in lieu of Crushed Stone at no additional cost.See Item No.360"Concrete Pavement"(enclosed). The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch. Contractor shall work on one-half of Valley Gutter at a time, and the other half shall be open to traffic.Work shall be completed on each half within seven(7)calendar days. If the contractor fails to complete the work on each half within seven (7)calendar days, a$100 dollars liquidated damage will be assessed per each half of valley gutter per day. The unit price bid per square yard for Concrete Valley as shown on the proposal will be full compensation for materials, labor, equipment, tools and incidentals necessary to complete the work. SP-27 PAY-ITEM NO. 16-NEW 7" CONCRETE VALLEY GUTTER: This item shall include the construction of concrete valley gutters at various locations to be determined in field by the Construction Engineer. Removal of existing, asphalt pavement, concrete base, curb and gutter, and necessary excavation to install the concrete valley gutters all shall be subsidiary to this pay item. Furnishing and placing of 2:27 concrete base and crushed limestone to a depth as directed by the Engineer and necessary asphalt transitions as shown in the concrete valley gutter details shall be subsidiary to this Pay Item. See City standard specifications Item No. 104, "Removing Old Concrete", Item No. 106, "Unclassified Street Excavation" Item No. 208 "Flexible Base", Drawing No. S-S6 and detail enclosed, TxDOT's "Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges"Item Nos.300 "Asphalts, Oils, and Emulsions" (referenced),310 "Prime Coat" (referenced), and 340 "Dense-Graded Hot-Mix Asphalt (Method)" (referenced) and Item No. 360 "Concrete Pavement" (enclosed). Measurement for final quantities of valley gutter will be by the square yard of concrete pavement and the curb and gutter section will be included. Contractor may substitute 5" non-reinforced (2:27) Concrete Base in lieu of Crushed Stone at no additional cost. See Item No.360"Concrete Pavement"(enclosed). The concrete shall be designed to achieve a minimum compressive strength of 3000 pounds per square inch. Contractor shall work on one-half of valley gutter at a time, and the other half shall be open to traffic.Work shall be completed on each half within seven (7) calendar days. If the Contractor fails to complete the work on each half within seven(7)calendar days,a$100 dollars liquidated damage will be assessed per each half of valley gutter per day. The unit price bid per square yard for Concrete Valley as shown on the proposal will be full compensation for materials, labor, equipment, tools and incidentals necessary to complete the work. SP-28 PAY-ITEM NO. 17-NEW 4" STANDARD WHEELCHAIR RAMP: This item shall include the construction of standard concrete wheelchair ramps at various locations to be determined in field by the Construction Engineer. The Contractor shall construct standard concrete wheelchair ramps as shown on the enclosed details,or as directed by the Engineer. The removal of existing substandard wheelchair ramps and sidewalk as required for the installation of new wheelchair ramps shall be subsidiary to this pay item. The removal and replacement of existing curb and gutter as required for the installation of new wheelchair ramps shall be included in Pay Item 6 (Removal and Replacement of Curb and Gutter). Pay limits for laydown curb and gutter are as shown in the Standard Pay Limit Detail(WR-1).The pay limit will extend from 9" outside the lip of gutter to 15" back from the face of curb. Any asphalt tie-in shall be subsidiary to the curb and gutter pay item. Pay limits for "Standard Wheelchair Ramp" will start 15" back from the face of curb and encompass the remainder of the ramp and sidewalk. All applicable provision of standard Specifications Item 104 "Removing Old Concrete" and Item 504 "Concrete Sidewalk Driveways" shall apply except as herein modified. All concrete flared surface shall be colored with LITHOCHROME color hardener as manufactured by L.M. Scofield Company or equal.The color hardener shall be brick red color and dry-shake type,and shall be used in accordance with manufactures instructions. Concrete stain may be applied after concrete is poured(Product sold by BAER). "Contractor shall provide a colored sample concrete panel of one foot by one foot by three inches dimension, or other dimension approved by the Engineer, meeting the aforementioned specification. The sample, upon approval by the Engineer, shall be the acceptable standard to be applied for all construction covered in the scope of this pay item. The method of application shall be by screen, sifter, sieve or other means in order to provide for a uniform color distribution." The unit price bid per square yard for 4" standard wheelchair ramp as shown on the proposal will be full compensation for materials, labor, equipment, tools and incidentals necessary to compete the work. SP-29Gi�iSpM���p�r1l�i 6`1�P5Qi�,1USu FT. W."O.019, M. PAY-ITEM NO. 18-6" PERFORATED PIPE SUBDRAIN: This item shall consist of furnishing and installing 6" perforated subdrain and filter material all as shown on the enclosed details,or as directed by the Engineer. All applicable provision of standard Specifications Item 500 "SUBDRAINS" shall apply except as herein modified. The pipe material shall be poly vinyl chloride (PVC) with the standard dimensional ratio of 35 (SDR35) and meet the ASTM D 1784. Filter fabric shall have the capability of passing ground water without transporting the soil placed around the filter fabric. The fabric shall be constructed exclusively of synthetic thermoplastic fibers and may be either woven or non-woven to form a mat of uniform quality. Fabric fibers may be either continuous or discontinuous and oriented in either a random or a aligned pattern throughout the fabric. The fabric shall be mildew resistant,rot proof,shall be satisfactory for use in a wet soil and aggregate environment,contain ultraviolet stabilizers and have non-raveling edges. The fabric shall meet the following requirements when sampled and tested in accordance with the methods indicated: Test Original Physical Properties Method Requirements Fabric weight, on an ambient SDHPT Test Method Tex- 4.0 minimum for under temperature air-dried tension free 616-J"Testing of drains and Slope sample,expressed in oz/sq.yd. Construction Fibers" Stabilization, 6.0 minimum for Gabions Revetment Water flow rate by falling head Tex-6164 80 minimum method, 7.9 inches (20 cm) to 3.9 inches(10 cm)on 2 inch ID cylinder with 1 inch diameter orifice, with flow rate expressed in gal/sq. ft/minute. Breaking load in either machine or ASTM Designation: D 1682 100 minimum cross-machine direction, expressed in grab method G as modified pounds. by Tex--6164 Equivalent opening size (US Standard CW-02215, US Army Corps 70 to 100 sieve no.) of Engineers, Civil Works Construction Guide SP-30 Specification. "Plastic Filter Fabric",Nov. 1977. "Apparent elongation" at breaking ASTM Designation: D 1682 100 maximum load in either machine or cross- grab method G as modified machine direction, expressed as by Tex-616-J percent. The "Filter Fabric" shall be installed in accordance with the manufacturer's recommendations, as indicated or as directed by the Engineer.When lapping is required,it shall be in accordance with the manufacturer's recommendations. Backfilling around the Filter Fabric shall be done in such a way as not to damage the Filter Fabric material during the placement. The unit price bid per L.F. shall be full compensation for all labor, materials, equipments, tools,and incidentals necessary to complete the work. PAY-ITEM NO.21-8" PAVEMENT PULVERIZATION: All applicable provisions of TxDOT's "Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges" Item No. 275 "Cement Treatment (Road Mixed)" (referenced) shall govern work. (Soil reports for this project will be available at the pre-construction meeting.) The City of Fort Worth,Texas will perform quality assurance tests and checks on the paving project materials during construction,to ensure compliance with the specifications. The sampling and testing of the materials shall be made at the expense of the City. In the event the sampling and testing does not comply with the specifications, all subsequent testing of the material, in order to determine if the material is acceptable, shall be furnished and paid by the contractor,as directed by the Engineer. Contractor shall pulverize the existing pavement to a depth of 8". After pulverization is completed, contractor shall temporarily remove and store the 8" deep pulverized material, then cut the base 2" to provide place for the new 2" H.M.A.C. surface. The 2" base cut shall start at a depth of 8" from the existing pulverized surface. After the undercut operation is completed, the temporarily stored 8" deep pulverized material shall be returned to the excavation for mixing with cement. SP-31 If the existing pavement has a combination of 10" H.M.A.0 and crushed stone/gravel, undercut will not be required,the contractor will pulverize 10" inches,the 2" inch cut will be taken from the 10" pulverized material. Pulverization shall start within (ten) 10 calendar days after all concrete work has been completed on a street. If the contractor fails to begin the work within ten (10) calendar days, $200 dollars liquidated damage will be assessed per block per day. The maximum amount of existing asphalt concrete pavement in the mixture shall be at the discretion of the Engineer. The contractor shall spread, mix,blade to grade and compact the pulverized material to 95% of the maximum density as determined in accordance with TxDOT's Standard Specifications stated above or as directed by the Engineer in the field. A 3.5% portland cement shall be used to mix the pulverized material. - The Engineer or his authorized representative will observe the cement treatment and collect delivery tickets from each transport truck. Cement quantities used will be verified, with respect to areas being treated. From the pulverized cement treated mixture,samples will be collected and tested for gradation requirements. Testing will be at a minimum of one test per 150 linear feet per lane width per each 8-inches of treated depth,with a minimum of 2 tests per area. After the cement treated base has cured for 48 hours,provide machinery to roll the surface of the cement treated material to induce hairline cracks "micro-cracks". Micro-cracking will be used to reduce shrinkage cracking in the cement treated material and reduce reflective cracking through the asphalt cement surface overlay. Rollers shall be in accordance with TxDOT's "Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges" Item Nos. 210 "Rolling" (referenced). Operate rollers at walking speed. Generally one(1)to four(4)passes of the roller are required to create the micro-cracks. The contractor shall then prime and immediately overlay the micro-cracked surface with 2" H.M.A.C. surface course. The work shall be in accordance with TxDOT's "Standard Specifications for Construction and Maintenance of Highways,Streets,and Bridges"Item Nos. 300 "Asphalts, Oils, and Emulsions" (referenced), 310 "Prime Coat" (referenced), and 340 "Dense-Graded Hot-Mix Asphalt(Method)"(referenced). SP-32 If the contractor fails to begin the HMAC 2" H.M.A.C. surface course work within three (3) calendar days, a $200 dollars liquidated damage will be assessed per block per day. The 2" H.M.A.C. surface will be paid under PAY-ITEM NO. 14 - 2" H.M.A.C. (TYPE "D" MIX) ASPHALT CEMENT SURFACE COURSE. On pulverized and overlay streets that do not have existing curb and gutter, the Contractor shall finish the parkway with backfill. The backfill shall begin at the edge and elevation of the new HMAC 2" H.M.A.C. surface course and extend within the parkway, to existing ground surface, at the grade of one-fourth (1/4)inch per foot. There should be no voids in the backfill material,to the satisfaction of the Engineer. The unit price bid per square yard shall be full compensation for all labor, material, equipment, tools, and incidentals necessary to pulverize, remove and store the pulverized material, undercut the base, mixing, compaction, haul off, sweep, dispose of the undercut material and backfill the parkway. PAY-ITEM NO.23—REMOBILIZATION: This item shall compensate the Contractor to remobilize personnel, equipment, supplies, and material to perform an additional work as directed by the Engineer. Remobilization will be considered when concrete "Flat-work" has been completed, personnel and equipments were demobilized, and the street is clean and ready for the overlay. Remobilization shall be determined by the Engineer. Any Remobilization without the approval of the Engineer will not be compensated. The unit price per bid per each will be full compensation for all labor, equipment,material, tools, and all incidentals necessary to complete the work. J PAY-ITEM NO.24—UNCLASSIFIED STREET EXCAVATION: This item will be used if additional excavation is needed that is not covered by Pay Item No.21 - "$" PAVEMENT PULVERIZATION".Additional Excavation is the removal of the excessive crown and base to bring the new base to proper grade& City standard specifications for street reconstruction. All applicable provisions of Item No. 106 "Unclassified Street Excavation" shall apply,work shall be paid per cubic yard. SP-33 CITY Efli ff PAY ITEM NO.25-2" SURFACE MILLING: This item shall consist of milling the existing pavement at a depth of 211. All applicable provisions of Pay Item No. 11 "Wedge Milling" shall apply. The unit price bid per square yard shall be full compensation for all materials,labor, equipment and incidentals necessary to complete the work. PAY-ITEM NO. 26 - REMOVAL AND REPLACEMENT OF 6" EXPOSED CONCRETE DRIVEWAYS: This item shall include the removal and replacement of existing concrete driveways, due to deterioration or in situations where curb and gutter is replaced to adjust grades to eliminate ponding water with same day haul-off of the removed material to a suitable dump site. For specifications governing this item see Item No. 104 "Removing Old Concrete",Item No. 504" Concrete Sidewalk and Driveways".Pay limits for concrete driveway are as shown in Drawing No.S-S5 of the Standard Specifications. The unit price bid per square yard shall be full compensation for all labor, material, equipment,supplies,and incidentals necessary to complete the work. PAY ITEM NO.27—CRACK SEALING: Contractor shall seal existing cracks '/a" and greater, by using cold poured crack sealer Polymer Modified Ashpalt Emulsion Crack Sealer, as directed by the Engineer. TxDOT's "Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges"Item Nos.300 "Asphalts,Oils,and Emulsions",shall apply. The inside of the cracks shall be cleaned with an air compressor or approved equipment,prior to sealing. Sealant shall be applied with a rubber "V" shaped squeegee where applicable. Provide adequate traffic control during set up and cure time of sealant. The unit price bid per linear foot shall be full compensation for all labor,material,equipment, supplies,and incidentals necessary to complete the work. SP-34 PAY ITEM NOS. 28 & 29- REMOVAL AND REPLACEMENT OF TOP OF 5' and 10' DRAINAGE INLETS: This item shall include the removal and replacement of a 7" thick drainage inlet top of 5 -foot and 10' drainage inlet openings. The removal and replacement of the drainage inlet top shall be in accordance with Standard Specification Item No. 450 "Adjusting Manholes and Inlets", as shown in the Drawing S-S02 and as directed by the construction engineer. The unit price per bid per each will be full compensation for all labor, equipment, material, tools,and all incidentals necessary to complete the work. PAY ITEM NOS.30&31 -H.M.A.C. Sneed Cushions(30' & 40'wide Street): This item shall consist of removing existing and installing new H.M.A.0 Speed Cushions according to the plan and profile as shown on the detail sheet.All excavated material shall be hauled off site the same day as excavated,to a suitable dumpsite. Contractor shall notify the Construction Engineer 72 hours prior to installing any speed - cushions. Contractor shall install pavement markings. If the roadway is damaged during existing marker removal, the work shall be temporarily halted until consultation with the Construction Engineer. The pavement shall be repaired prior to new HMAC overlay. MATERIALS AND QUALITY REQUIREMENTS: 1. Speed Cushions The speed cushions shall consist of H.M.A.C. Type D surface course with tack coat (SS-1) and compacted with vibratory hand roller.All applicable provisions of TxDOT's"Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges" Item Nos.300 "Asphalts,Oils,and Emulsions" (referenced),310 "Prime Coat" (referenced),and 340 "Dense-Graded Hot-Mix Asphalt (Method)" (referenced) shall apply. Kraft brown paper-36" wide 40-1b paper shall be used to keep curb &gutter clean. 2. Pavement Markings Raised Pavement Markings SP-35 All materials used shall be pre-approved prior to placement. The brand name and specifications of the materials shall be included in submittal for approval. The approved materials must be used throughout the duration of the contract. In the event that substitute materials need to be used, they must be equal to or exceed the quality of those currently in use and be approved the Construction Engineer. All markers shall be 4"and be installed with epoxy; bituminous adhesive is not approved. A chalk line, chain, or equivalent shall be used during layout to insure that individual markers are properly aligned. All markers shall be placed uniformly along the line to achieve a smooth continuous appearance. Preformed Pavement Markings All materials used under this agreement shall be pre-approved prior to awarding of the bid. Materials used shall meet TXDOT specifications Item 666 Type II. The approved materials must be used throughout the duration of the bid. In the event that substitute materials need to be used, they must be equal to or exceed the quality of those currently in use, and be approved by Construction Engineer. All material must be equal to or exceed the following: Pre Mark brand Hot Tape which is manufactured by Stimsonite. Stamark A420,which is manufactured by 3M. Stamark A380,which is manufactured by 3M. All applications shall be in strict compliance with all manufacturer recommendations. Surface Preparation and Application of Pavement Markings Roadway surface shall be clean, dry and free from dirt, grease, and other forms of contamination. All surfaces must be air blasted prior to application of paint. Surface preparation and application shall be in strict compliance with manufacturer recommendations. Equipment and methods used for surface preparation shall not damage the pavement or present a hazard to motorists. T Installation of Pavement Markings SP-36 Contractor's personnel shall be knowledgeable and sufficiently skilled in the installation v of raised pavement markings and preformed pavement markings. Markings that are not properly applied due to faulty application methods or defective product, and markings, which are placed in the wrong position or alignment, shall be removed and replaced by the contractor at the contractor's expense. If the mistake is such that it would be confusing or hazardous to motorists it shall be remedied the same day of notification. Notification will be made by phone and confirmed by fax. Other mistakes shall be remedied within five days of written notification. Traffic Control of Pavement Markings When markings are applied on roadways open to traffic care will be taken to ensure that proper safety precautions are followed, including the use of signs, cones, barricades, flaggers, etc. Work shall be performed with as little disruption to traffic as possible,and freshly applied markings shall be protected from traffic damage and disfigurement. 3. Measurement and Payment The unit price bid per each shall be full compensation for removal of existing pavement markings,H.M.A.C.Type D surface course,tack coat(SS-1),vibratory hand roller,surface preparation,preformed and raised pavement markings,kraft brown paper-36" wide 40-1b paper to keep curb & gutter clean, and all materials, labor, equipment and incidentals necessary to complete the work. The unit price per bid per each will be full compensation for all labor, equipment, material,tools,and all incidentals necessary to complete the work. END OF SECTION SP-37 E-`0e1G;U1 :Yr2ji NOTE: THIS SPECIFICATION HAS BEEN MODIFIED TO DELETE NON- APPLICABLE ITEMS FOR USE AS A GUIDE SPECIFICATION FOR CITY STREETS. Item 360 CONCRETE PAVEMENT 300.1. Description. Construct Portland cement concrete pavement with or without curbs on the concrete pavement. 300.2. Materials. A. Portland Cement Concrete. Provide Portland cement concrete to meet a minimum compressive strength.of 3,000 psi at 28 days, unless shown otherwise in the contract documents. Use Class A concrete for curbs that are placed separately from the pavement. Provide concrete that is workable and cohesive, possesses satisfactory finishing qualities, and conforms to the mix design and mix design slump. B. Reinforcing Steel. Provide Grade 60 deformed steel for bar reinforcement. Provide approved positioning and supporting devices(baskets and chairs) capable of securing and holding the reinforcing steel in proper position before and during _. paving. Provide corrosion protection when shown on the plans. 1. Dowels. Provide Grade 60 smooth, straight dowels of the size shown on the plans, free of burrs or deformations. Coat dowels with a thin film of grease or - other approved de-bonding material. Provide dowel caps.on the lubricated end of each dowel bar used in an expansion joint. Provide dowel caps filled with a.soft compressible material with enough range of movement to allow complete closure of the expansion joint. 2. Tie Bars. Provide straight deformed steel tie bars. Provide either multiple-piece tie bars or single-piece tie bars as shown on the plans. Provide multiple-piece tie bars composed of 2 pieces of deformed reinforcing steel with a coupling capable of developing a minimum tensile strength of 125% of the design yield strength of the deformed steel when tensile-tested in the assembled configuration. Provide a minimum length of 33 diameters of the deformed steel in each piece. C. Curing Materials. Provide Type 2 membrane curing compound conforming to DMS-4650, °Portland Cement Concrete Curing Materials and Evaporation Retardants." D. Epoxy. Provide Type III epoxy in accordance with DMS-6100, "Epoxies and Adhesives,"for installing all drilled-in reinforcing steel. -� E. Evaporation Retardant. Provide evaporation retardant conforming to DMS-4650, "Portland Cement Concrete Curing Materials and Evaporation Retardants.' F. Joint Sealants and Fillers. Provide Class 5 or Class 8 joint-sealant materials and fillers unless otherwise shown on the plans or approved and other sealant materials of the size,shape, and type shown on the plans in accordance with DMS-6310, "Joint Sealants and Fillers." 300.3. Equipment. Furnish and maintain all equipment in good working condition. Use measuring, mixing, and delivery equipment conforming to the requirements of Item 421, "Portland Cement Concrete." Obtain approval for other equipment used. A. Placing, Consolidating, and Finishing Equipment. Provide approved self- propelled paving equipment that uniformly distributes the concrete with minimal segregation and provides a smooth machine-finished consolidated concrete pavement conforming to plan line and grade. Provide an approved automatic grade control system on slip-forming equipment. Provide approved mechanically operated finishing floats capable of producing a uniformly smooth pavement surface. Provide equipment capable of providing a fine, light water fog mist. Provide mechanically operated vibratory equipment capable of adequately consolidating the concrete. Provide immersion vibrators on the paving equipment at sufficiently close intervals to provide uniform vibration and consolidation of the concrete over the entire width and depth of the pavement and in accordance with the manufacturer's recommendations. Provide immersion vibrator units that operate at a frequency in air of at least 8,000 cycles per minute. Provide enough hand-operated immersion vibrators for timely and proper consolidation of the concrete along fomes, - at joints and in areas not covered by other vibratory equipment. Surface vibrators may be used to supplement equipment-mounted immersion vibrators. Provide tachometers to verify the proper operation of all vibrators. For small or irregular areas or when approved, the paving equipment described in this Section is not required. B. Forming Equipment. 1. Pavement Forms. Provide metal or wood side forms of sufficient cross-section, strength, and rigidity to support the paving equipment and resist the impact and vibration of the operation without visible springing or settlement. Use forms that are free from detrimental kinks, bends, or warps that could affect ride quality or alignment. Provide flexible or curved metal or wood forms for curves of 100-ft. radius or less. .2. Curb Forms. Provide curb forms for separately placed curbs that are not slipformed that conform to the requirements of Item 529, "Concrete Curb, Gutter, and Combined Curb and Gutter." C. Reinforcing Steel Inserting Equipment. Provide inserting equipment that accurately inserts and positions reinforcing steel in the plastic concrete parallel to the profile grade and horizontal alignment in accordance to plan details. D. Texturing Equipment. 1. Carpet Drag. Provide a carpet drag mounted on a work bridge or a moveable _ support system. Provide a single piece of carpet of sufficient transverse length to span the full width of the pavement being placed and adjustable so that a sufficient longitudinal length of carpet is in contact with the concrete being placed to produce the desired texture. Obtain approval to vary the length and width of the carpet to accommodate specific applications. Use an artificial grass-type carpet having a molded polyethylene pile face with a blade length of 5/8 in. to 1 in., a minimum weight of 70 oz. per square yard, and a strong, durable, rot- resistant backing material bonded to the facing. 2. Tining Equipment. Provide a self-propelled transverse metal tine device equipped with 44n.to 64n. steel tines and with cross-section approximately 1/32 in. thick by 1/12 in. wide, spaced at 1 in., center-to-center. Hand-operated tining equipment that produces an equivalent texture may be used only on small or irregularly shaped areas or, when permitted, in emergencies due to equipment breakdown. C P-2- E. Curing Equipment. Provide a self-propelled machine for applying membrane curing compound using mechanically pressurized spraying equipment with atomizing - nozzles. Provide equipment and controls that maintain the required uniform rate of application over the entire paving area. Provide curing equipment that is independent of all other equipment when production rates are such that the first application of membrane curing compound cannot be accomplished immediately after texturing and after free moisture has disappeared. Hand-operated pressurized spraying equipment with atomizing nozzles may only be used on small or irregular areas or, when permitted, in emergencies due to equipment breakdown. F. Sawing Equipment. Provide power-driven concrete saws to saw the joints shown on the plans. Provide standby power-driven concrete saws during concrete sawing operations. Provide adequate illumination for nighttime sawing. G. Grinding Equipment. When required, provide self-propelled powered grinding equipment that is specifically designed to smooth and texture concrete pavement using circular diamond blades. Provide equipment with automatic grade control capable of grinding at least a 3-ft.width longitudinally in each pass without damaging the concrete. 300.4. Construction. Obtain approval for adjustments to plan grade-line to maintain thickness over minor subgrade or base high spots while maintaining clearances and drainage. Maintain subgrade or base in a smooth, clean, compacted condition in conformity with the required section and established grade until the pavement concrete is placed. Keep subgrade or base damp with water sufficiently in advance of placing pavement concrete.Adequately light the active work areas for all nighttime operations, if required. A. Reinforcing Steel and Joint Assemblies.Accurately place and secure in position all reinforcing steel as shown on the plans. Place dowels at mid-depth of the pavement slab, parallel to the surface. Place dowels for transverse contraction joints parallel to the pavement edge. Tolerances for location and alignment of dowels will be shown on the plans. Stagger the longitudinal reinforcement splices to avoid having more than 1/3 of the splices within a 2-ft. longitudinal length of each lane of the pavement. Use multiple-piece tie bars or drill and epoxy grout tie bars at longitudinal construction joints. 1. Manual Placement. Secure reinforcing bars at alternate intersectionswitivwire ties or locking support chairs.Tie all splices with wire. 2.. Mechanical Placement: If mechanical placement of reinforcement results in steel misalignment or improper location, poor concrete consolidation, or other inadequacies, complete the work using manual methods. B. Joints. Install joints as shown on the plans. Clean and seal joints in accordance with Item 438, "Cleaning and Sealing Joints and Cracks (Rigid Pavement and Bridge Decks)." Repair excessive spalling of the joint saw groove using an approved method before installing the sealant. Seal all joints before opening the pavement to all traffic. When placing of concrete is stopped, install a rigid transverse bulkhead, accurately notched for the reinforcing steel and shaped accurately to the cross- section of the pavement. 1. Placing Reinforcement at Joints.Where the plans require an assembly of parts at pavement joints, complete and place the assembly at the required location and elevation with all parts rigidly secured in the required position.Accurately notch joint materials for the reinforcing steel. �P-3 2. Curb Joints. Provide joints in the curb of the same type and location as the adjacent pavement. Use expansion joint material of the same thickness, type, .. and quality required for the pavement and of the section shown for the curb.- Extend expansion joints through the curb. Construct curb joints at all transverse pavement joints. For,non-monolithic curbs, place reinforcing steel into the plastic concrete pavement as shown on the plans unless otherwise approved. Form or saw the weakened plane joint across the full width of concrete pavement and through the monolithic curbs. C. Placing and Removing Forms. Use clean and oiled forms. Secure forms on a base or firm subgrade that is accurately graded and that provides stable support without deflection and movement by form riding equipment. Pin every form at least at the middle and near each end. Tightly join and key form sections together to prevent relative displacement. Set side forms far enough in advance of concrete placement to permit inspection. Check conformity of the grade, alignment, and stability of forms immediately before placing concrete, and matte all necessary corrections. Use a straightedge or other approved method to test the top of forms to ensure that the Fide quatity requirements for the completed pavement will be met. Stop paving operations if forms settle or deflect more than 1/8 in. under finishing operations. Reset forms to line and grade, and refinish the concrete surface to correct grade. _ Avoid damage to the edge of the pavement when removing forms. Repair damage resulting from form removal and honeycombed areas with a mortar mix within 24 hr. after form removal unless otherwise approved. Clean joint face and repair honeycombed or damaged areas within 24 hr. after a bulkhead for a transverse construction joint has been removed unless otherwise approved. When forms are removed before 72 hr. after concrete placement, promptly apply membrane curing compound to the edge of the concrete pavement. Forms that are not the same depth as the pavement but are within 2 in. of that depth are permitted if the subbase is trenched or the full width and length of the form base is supported with a firm material to produce the required pavement thickness, Promptly repair the form trench after use. Use flexible or curved wood or metal forms for curves of 100-ft. radius or less. D. Concrete Delivery. Clean delivery equipment as necessary to prevent accumulation of old concrete before loading fresh concrete. Use agitated delivery equipment for- concrete designed to have a slump of more than 5 in. Segregated concrete is subject to rejection. Place agitated concrete within 60 min. after batching. Place non-agitated concrete within 45 min. after batching. In hot weather or under conditions causing quick setting of the concrete, times may be reduced by the Engineer.Time limitations may be extended if the Contractor can demonstrate that the concrete can be properly placed, consolidated, and finished without the use of additional water. E. Concrete Placement. Do not allow the pavement edge to deviate from the established paving line by more than 1/2 in. at any point. Place the concrete as,near as possible to its final location, and minimize segregation and rehandling.Where , hand spreading is necessary, distribute concrete using shovels. Do not use rakes or vibrators to distribute concrete. 1. Pavement. Consolidate all concrete by approved mechanical vibrators operated on the front of the paving equipment. Use immersion-type vibrators that simultaneously consolidate the full width of the placement when machine finishing. Keep vibrators from dislodging reinforcement. Use hand-operated CITY 6ECU �,�7'01 V FT. '`"ou:TH, T�4�, vibrators to consolidate concrete in areas not accessible to the machine-mounted vibrators. Do not operate machine-mounted vibrators while the paving equipment is stationary. 2. Temperature Restrictions. Place concrete that is between 40°F and 95°F at the time of discharge, except that concrete may be used if it was already in transit when the temperature was found to exceed the allowable maximum. Take immediate corrective action or cease concrete production when the concrete temperature exceeds 95°F. - Do not place concrete when the ambient temperature in the shade is below 40°F and falling unless approved. Concrete may be placed when the ambient temperature in the shade is above 35°F and rising or above 40°F.When temperatures warrant protection against freezing, protect the pavement with an approved insulating material capable of protecting the concrete for the specified curing period. Submit for approval proposed measures to protect the concrete* from anticipated freezing weather for the first 72 hr. after placement. Repair or replace all concrete damaged by freezing. F. Spreading and Finishing. Finish all concrete pavement with approved self- propelled equipment. Use power-driven spreaders, power-driven vibrators, power- driven strike-off, and screed, or approved alternate equipment. Use the transverse finishing equipment to compact and strike off the concrete to the required section and grade without surface voids. Use float equipment for final finishing. Use concrete with a consistency that allows completion of all finishing operations without addition of water to the surface. Use the minimal amount of water fog mist necessary to maintain a moist surface. Reduce fogging if float or straightedge operations result in excess slurry. 1. Finished Surface. Perform sufficient checks with long-handled 10-ft. and 15-ft. straightedges on the plastic concrete to ensure that the final surface is within the tolerances specified in the contract documents. Check with the straight_edge parallel to the centerline. 2. Maintenance of Surface Moisture. Prevent surface drying of the pavement before application of the curing system. Accomplish this by fog applications of evaporation retardant on the pavement surface.Apply evaporation retardant at the rate recommended by the manufacturer. Reapply the evaporation retardant as needed to maintain.the concrete surface in a moist condition until curmg system is applied. Do not use evaporation retardant as a finishing aid. 3. Surface Texturing. Perform surface texturing using a combination of a carpet drag and metal tining, if required by the contract documents. Complete final texturing before the concrete has attained its initial set. Draw the carpet drag longitudinally along the pavement surface with the carpet contact surface area adjusted to provide a satisfactory coarsely textured surface. Operate the metal-tine device to obtain grooves spaced at 1 in., approximately 3/16 in. deep,with a minimum depth of 1/8 in., and approximately 1/12 in.wide. ` Do not overlap a previously fined area. Use manual methods for achieving similar results on ramps and other irregular sections of pavements. Repair damage to' the edge of the slab and joints immediately after texturing. Do not tine pavement - that will be overlaid. 4. Small or Irregular Placements. Where machine placements and finishing of concrete pavement are not practical, use hand equipment and procedures that R produce a consolidated and finished pavement section to the line and grade. CP-rj 5. Emergency Procedures. Use hand-operated equipment for applying texture, evaporation retardant,and cure in the event of equipment breakdown. G. Curing.Keep the concrete pavement surface from drying by water flogging until the curing material has been applied.Maintain and promptly repair damage to curing materials on exposed surfaces of concrete pavement continuously for at least 3 curing days.A curing day is defined as a 24-hr.period when either the temperature taken in the shade away from artificial heat is above SOT for at least 19 hr. or when the surface temperature of the concrete is maintained above 40"F for 24 hr.Curing begins when the concrete curing system has been applied.Stop concrete paving if curing compound is not being applied promptly and maintained adequately. Other methods of curing in accordance with Item 420,`Concrete Structures,'may be used when specified or approved. 1. Membrane Curing.Atter texturing and immediately after the free surface moisture has disappeared, spray the concrete surface uniformly with 2 coats of membrane curing compound at an individual application rate of not more than 180 sq.ft. per gallon.Apply the first coat within 10 min. after completing texturing opamtions.Apply the second coat within 30 min.after completing texturing operations. Before and during application,maintain curing compounds in a uniformly agitated condition,free of settlement. Do not thin or dilute the curing compound. Wherry the coating shows discontinuities or other defects or If rain falls on the newly coated surface before the film has dried enough to resist damage,apply additional compound at the same rate of coverage to correct the damage. Ensure that the curing compound coats the sides of the tining grooves. H. Sawing Joints.Saw joints to the depth shown on the plans as soon as sawing can be accompfinhed without damage to the pavement regardless of time of day or weather conditions. Some minor raveling of the saw cut is acceptable. Use a chalk line, string Ins,sawing template, or other approved method to provide a true joint alignment. Provide enough saws to match the paving production rate to ensure sawing completion at the earliest possible time to avoid uncontrolled cracking. Reduce paving production if necessary to ensure timely sawing of joints.Promptly restore membrane cure damaged within the first 72 hr.of curing. 1. Protection of Pavemeht and Opening to Traffic.Testing for early opening is the responsibi dy of the Contractor regardless of job-control testing responsibilities unless otherwise shown in the plans or directed.Testing result interpretation for opening to tic is subject to the approval of the Engineer. 1. Protection of Pavement Erect and maintain barricades and other standard and approved devices that will exclude all vehicles and equipment from the newly placed pavement for the periods specified. Before opening to traffic,protect the pavement from damage due to crossings using approved methods.Maintain an adequate supply of sheeting or other material to cover and protect fresh concrete surface from weather damage.Apply as needed to protect the pavement surface from weather. 2 Opening Pavement to Traffic. Before opening to traffic, clean pavement, place stable material against the pavement edges, seal joints, and perform all other tmffiic safety related word. C F140 CONTRACTOR COMPLIANCE WITH WORKERS' COMPENSATION LAW Pursuant to V.T.C.A. Labor Code §406.96 (2000), as amended, Contractor certifies that it provides workers' compensation insurance coverage for all of its employees employed on City of Fort Worth Department of Engineering No.5202 and City of Fort Worth Project No. GS93- 020930522818. CONTRACTOR PEACHTREE CONSTRUCTICIN, LTD By: Name: J. BarrY Clark Title: President Date: S STATE OF TEXAS § COUNTY OF TARRANT § Before me, the undersigned authority, on this day personally appeared J. Barry Clark , known to me to be the person whose name is subscribed to the foregoing instrument, and acknowledged to me that he executed the same as the act and deed of PEACHTREE CONSTRUCTION, LTD for the purposes and consideration therein expressed and in the capacity therein stated. Given Under My Hand and Seal of Office this 15- day of A , 20Q(o Notary P lir in and for theStatef Texas aau CHERYL A.HOHENBERGER Notary Public.State of Texas My Comm.Expires July 30,2W8 OFF101141, ROD O 0,2008 O ,M CERTIFICATE OF LIABILITY INSURANCE DATE[MM /8/2/DD/YYYY) 5%8/2006 PRODUCER FAX 817-737-4947 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION K & S Group, Inc. ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR Frank Siddons Insurance Fort ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. 4021 Hwy 377 South Fort Worth Tx 76116 INSURERS AFFORDING COVERAGE NAIC# INSURED INSURER A:Travelers Lloyds Peachtree Construction, Ltd. INSURER B:Travelers Indemnity Co. 5801 Park Vista Cir. INSURERc:Great American Keller, TX 76248 INSURER D: Phone: INSURER E: COVERAGES THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED.NOTWITHSTANDING ANY REQUIREMENT,TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR ADVL POLICY EFFECTIVE POLICY EXPIRATION LTR INSRD TYPE OF INSURANCE POLICY NUMBER DATE MM/DD/YY DATE(MM/DD/YY) MM/DD/YY LIMITS A GENERAL LIABILITY DT-CO-8225A589-TLC 06/30/2005 06/30/2006 EACH OCCURRENCE $ 1,000,000 DAMAGE TO RENTED300 O X COMMERCIAL GENERAL LIABILITY PREMISES Ea occurrence $ , 00 CLAIMS MADE 7 OCCUR MED EXP An one person) $ 5,000 X Per Project Aggr. PERSONAL&ADV INJURY $ 1,000,000 X XCU Coverages GENERAL AGGREGATE $ 2,000,000 GEN'LAGGREGATE LIMIT APPLIES PER: PRODUCTS-COMP/OP AGG $ 2,000,000 POLICY X JE� LOC B AUTOMOBILE LIABILITY CAP-8225A577 06/30/2005 06/30/2006 COMBINED SINGLE LIMIT X ANY AUTO (Ea accident) $ 1,000,000 ALL OWNED AUTOS BODILY INJURY SCHEDULED AUTOS (Per person) $ X HIRED AUTOS BODILY INJURY $ X NON-OWNED AUTOS (Per accident) PROPERTY DAMAGE $ (Per accident) GARAGE LIABILITY AUTO ONLY-EA ACCIDENT $ ANY AUTO OTHER THAN EA ACC $ AUTO ONLY: AGG $ C EXCESS/UMBRELLA LIABILITY TUU6627683-01 06/30/2005 06/30/2006 EACH OCCURRENCE $ 5,000,000 X OCCUR CLAIMS MADE AGGREGATE $ 5,000,000 $ DEDUCTIBLE $ X RETENTION $10,000 $ B WORKERS COMPENSATION AND UB-0014C224 06/30/2005 06/30/2006 Y TORY LIMITS ER EMPLOYERS'LIABILITY ANY PROPRIETOR/PARTNER/EXECUTIVE E.L.EACH ACCIDENT $ 1,000,000 OFFICER/MEMBER EXCLUDED? E.L.DISEASE-EA EMPLOYEE$ 1,000,000 If yes,describe under SPECIAL PROVISIONS below E.L.DISEASE-POLICY LIMIT $ 1,000,000 OTHER DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES/EXCLUSIONS ADDED BY ENDORSEMENT/SPECIAL PROVISIONS Owner: City of Fort Worth Project: En4AC Surface Overlay (2006-3) At Various Locations DOE No.. 5202 TPW Project No. GS93-020930522810 City of Fort Worth is named as an additional insured on general liability & auto liability with a waiver of subrogation on general liability, auto liability & workers compensation as required by written contract. CERTIFICATE HOLDER CANCELLATION SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE City of Fort Worth A14c ,�pE&LU DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 1000 Throckmorton Street 0FF1C 1AL. S WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,BUT Fort Worth, TX 76102 � Ap� 1 DO SO SHALL IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE (Hxn,/(��n(� AGENTS OR REPRESENTATIVES. . wkV Wfl, TREPRESENTATIVE donsISCOTT �— ACORD 25(2001/08) C ACORD CORPORATION 1988 INS025(0108).06 AMS VMP Mortgage Solutions,Inc.(800)327-0545 Page 1 of 2 CERTIFICATE OF INSURANCE TO: CITY OF FORT WORTH Date: dft NAME OF PROJECT: H M A C SURFACE OVERLAY(2006-3)AT VARIOUS LOCATIONS PROJECT NUMBER: GS93-020930522818 IS TO CERTIFY THAT: PEACHTREE CONSTRUCTION,LTD is,at the date of this certificate,Insured by this Company with respect to the business operations hereinafter described,for the type of insurance and accordance with provisions of the standard policies used by this Company,and further hereinafter described. Exceptions to standard policy noted on reverse side hereof. TYPE OF INSURANCE = Policy Effective Expires Limits of Liability Worker's Compensation Comprehensive General Bodily Injury: Liability Insurance(Public Ea.Occurrence: $_ Liability) Property Damage: Ea.Occurrence: $ Blasting Ea.Occurrence: $ Collapse of Building or structures adjacent to Ea.Occurrence: $ excavations Damage to Underground r Utilities Ea.Occurrence: $ Builder's Risk Comprehensive Bodily Injury: _ Automobile Liability Ea.Person: $ Ea.Occurrence:$ Property Damage: Ea.Occurrence:$ Bodily Injury: Contractual Liability Ea.Occurrence: $ Property Damage: Ea.Occurrence: $ Other Locations covered: Description of operations covered: The above policies either in the body thereof or by appropriate endorsement provided that they may not be changed or canceled by the insurer in less than five(5)days after the insured has received written notice of such change/or cancellation. Where applicable local laws or regulations require more than five(5)days actual notice of change or cancellation to be assured,the above policies contain such special requirements,either in the body thereof or by appropriate endorsement thereto attached. The City,its officers,employees and servants shall be endorsed as an additional insured on Contractor's insurance policies excepting employer's liability insurance coverage under Contractor's workers' compensation insurance policy. Agency Insurance Company: r Fort Worth Agent By Address Title Bond No. 104691471 PERFORMANCE BOND THE STATE OF TEXAS § KNOW ALL BY THESE PRESENTS: COUNTY OF TARRANT § _ That we (1) PEACHTREE CONSTRUCTION, LTD as Principal herein, and (2) (2) , a corporation organized under the laws of the State of(3) (3) , and who is authorized to issue surety bonds in the State of Texas, Surety herein, are held and firmly bound unto the City of Fort Worth,a municipal corporation located in Tarrant and Denton Counties,Texas,Obligee herein, in the sum of.- ONE f:ONE MILLION TWO HUNDRED THIRTEEN THOUSAND FOUR HUNDRED NINTY SIX AND NO/ 100................................................................... ($1,213,496.00)Dollars for the payment of which sum we bind ourselves,our heirs,executors,administrators, successors and assigns,jointly and severally, firmly by these presents. - WHEREAS, Principal has entered into a certain contract with the Obligee dated the 09 of MAY, 2005 a copy of which is attached hereto and made a part hereof,for the construction of: H M A C SURFACE OVERLAY(2006-3)AT VARIOUS LOCATIONS NOW THEREFORE, the condition of this obligation is such, if the said Principle shall faithfully perform the work in accordance with the plans, specifications, and contract documents and shall fully indemnify and hold harmless the Obligee from all costs and damages which Obligee may suffer by reason of Principal's default, and reimburse and repay Obligee for all outlay and expense that Obligee may incur in making good such default, then this obligation shall be void;otherwise,to remain in full force and effect. i (2) Travelers Casualty And Surety Company Of America (3) Connecticut PROVIDED, HOWEVER, that this bond is executed pursuant to Chapter 2253 of the Texas Government Code, as amended, and all liabilities on this bond shall be determined in accordance with the provisions of such statute,to the same extent as if it were copied at length herein. IN WITNESS WHEREOF, the duly authorized representatives of the Principal and the Surety have executed this instrument. SIGNED and SEALED this 09of MAY,2005. ATTEST: MPPEACHTREE CONSTRUCTION,LTD (Principal) ecretary PRINCIPAL(41, BY: Mark Title: President (SEAL) 5801 PARK VISTA CIRLCE KELLER,TX 76248 Travelers Casualty And Surety Cneapany of America Witness as to Principa Surety 5801 Park Vista Circle, Keller, TX 76248 Add s BY: ATTEST'" .Lorrie Scott (Attorney-in-fact)(5) • Holly A. Gravenor Surety)Secretary 4021 Hwy 377 South, Fort Worth, TX 76116 (Address) (SEAL) NOTE: Date of Bond must not be prior to date of Contract (1) Correct Name of Contractor (2) Correct name of Surety (3) State of incorporation of Surety Telephone number of surety must be stated. In addition,an original copy of Power of Attorney shall be attached to Bond by Attomey-in-Fact. The date of bond shall not be prior to date of Contract. ess as Surety Billy Pinson 4021 Wy 377 South, Fort Worth, TX 76116 (Address) Bond No. 104691471 PAYMENT BOND THE STATE OF TEXAS § § KNOW ALL BY THESE PRESENTS: COUNTY OF TARRANT § That we,(1)PEACHTREE CONSTRUCTION,LTD,as Principal herein,and(2) (2) + a corporation organized and existing under the laws of the State of(3) (3) as surety, are held and firmly bound unto the City of Fort Worth, a municipal corporation located in Tarrant and Denton Counties, Texas, Obligee herein, in the amount of ONE MILLION, TWO HUNDRED THIRTEEN THOUSAND FOUR HUNDRED NINTY SIX AND NO/ 100................................................................... Dollars ($1,213,496.00) for the payment whereof, the said Principal and Surety bind themselves and their heirs, executors, administrators,successors and assigns,jointly and severally,firmly by these presents: WHEREAS, the Principal has entered into a certain written contract with the Obligee dated the 09 day of MAY, 2006, which contract is hereby referred to and made a part hereof as if fully and to the same extent as if copied at length,for the following project: H M A C SURFACE OVERLAY(2006-3)AT VARIOUS LOCATIONS NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said Principal shall faithfully make payment to each and every claimant(as defined in Chapter 2253, Texas Government Code, as amended)supplying labor or materials in the prosecution of the work under the contract,then this obligation shall be void;otherwise,to remain in full force and effect. PROVIDED, HOWEVER, that this bond is executed pursuant to Chapter 2253 of the Texas Government Code, as amended, and all liabilities on this bond shall be determined in accordance with the provisions of said statute,to the same extent as if it were copied at length herein. IN WITNESS WHEREOF, the duly authorized representatives of the Principal and the Surety have executed this instrument. SIGNED and SEALED this 09 day of.MAY 2006. (2) Travelers Casualty And Surety Company Of America (3) Connecticut PEACHTREE CONSTRUCTION, LTD PRINCIPAL ATTEST: By: _�1 �t C,-- Name: J. Barry Clark (Principal) Secretary Title: President (S E A L) Address: 5801 PARK VISTA CIRLCE —a�k" KELLER, TX 76248 Witness as to Principal Travelers Casualty And Surety Company Of America SURETY ATTEST: . By: Name: Lorrie Scott Secreta Holly A. Gravenor Attorney in Fact (S E A L) Address: 4021 Hwy 377 South Fnrt Worth, TX 76116 Ntm's's as t6 Surety Billy Pinson Telephone Number: (817) 737-4943 NOTE: (1) Correct name of Principal (Contractor). (2) Correct name of Surety. (3) State of incorporation of Surety Telephone number of surety must be stated. In addition, an original copy of Power of Attorney shall be attached to Bond by the Attorney-in-Fact. The date of bond shall not be prior to date of Contract. Bond No. 104691471 f MAINTENANCE BOND THE STATE OF TEXAS § COUNTY OF TARRANT § That PEACHTREE CONSTRUCTION, LTD ("Contractor"), as principal, and 0 ) a corporation organized under the laws of the State of Connecticut , ("Surety"), do hereby acknowledge themselves to be held and bound to pay unto the City of Fort Worth, a Municipal Corporation chartered by virtue of Constitution and laws of the State of Texas, ("City") in Tarrant County, Texas, the sum of ONE MILLION, TWO HUNDRED THIRTEEN THOUSAND, FOUR HUNDRED NINTY SIX AND NO 1100................................................................... Dollars ($1,213,496.00), lawful money of the United States, for payment of which sum well and truly be made unto said City and its successors, said Contractor and Surety do hereby bind themselves, their heirs, executors, administrators, assigns and successors, jointly and severally. This obligation is conditioned, however, that: WHEREAS, said Contractor has this day entered into a written Contract with the City of Fort Worth, dated the 09 of MAY, 2006, a copy of which is hereto attached and made a part hereof, for the performance of the following described public improvements: H M A C SURFACE OVERLAY (2006-3)AT VARIOUS LOCATIONS the same being referred to herein and in said contract as the Work and being designated as project number(s) GS93-020930522818 and said contract, including all of the specifications, conditions, addenda, change orders and written instruments referred to therein as Contract Documents being incorporated herein and being made a part hereof; and, WHEREAS, in said Contract, Contractor binds itself to use such materials and to so construct the work that it will remain in good repair and condition for and during a period of after the date of the final acceptance of the work by the City; and WHEREAS, said Contractor binds itself to maintain said work in good repair and condition for said term of Two (2) years; and WHEREAS, said Contractor binds itself to repair or reconstruct the Work in whole or in part at any time within said period, if in the opinion of the Director of the City of Fort Worth Department of Engineering, it be necessary; and, (1 ) Travelers Casualty And Surety Company Of America WHEREAS, said Contractor binds itself, upon receiving notice of the need therefore to repair or reconstruct said Work as herein provided. NOW THEREFORE, if said Contractor shall keep and perform its said agreement to maintain, repair or reconstruct said Work in accordance with all the terms and conditions of said Contract, these presents shall be null and void, and have no force or effect. Otherwise, this Bond shall be and remain in full force and effect, and the City shall have and recover from Contractor and Surety damages in the premises as prescribed by said Contract. This obligation shall be a continuing one and successive recoveries may be had hereon for successive breaches until the full amount hereof is exhausted. IN WITNESS WHEREOF, this instrument is executed in 8 counterparts, each of which shall be deemed an original, this 09 day of MAY, A.D. 2006. ATTEST: PEACHTREE CONSTRUCTION, LTD (S E A L) Contractor By: Secretary Name: J. &g--ry Clark Title: Presdident Travelers Casualty And Suxety ATTEST: Canpany of America t (S E A L) Surety y. By: Secret4a Holly A. Gravenor Name: Lorrie Scott Title: Attorney-In-Fact 4021 Hwy 377 South Fny+ Worth, TX 76116 Address WAFWING;THIS POWER OF ATTORNEY IS INVALICI WITHOUT THE RED 00,90r=PI STPAUL POWER OF ATTORNEY TRAVELERS Farmington Casualty Company St.Paul Guardian Insurance Company Fidelity and Guaranty Insurance Company St.Paul Mercury Insurance Company Fidelity and Guaranty Insurance Underwriters,Inc. Travelers Casualty and Surety Company Seaboard Surety Company Travelers Casualty and Surety Company of America St.Paul Fire and Marine Insurance Company United States Fidelity and Guaranty Company Attorney-In Fact No. 214420 Certificate No. 000418602 KNOW ALL MEN BY THESE PRESENTS:That Seaboard Surety Company is a corporation duly organized under the laws of the State of New York,that St.Paul Fire and Marine Insurance Company,St.Paul Guardian Insurance Company and St.Paul Mercury Insurance Company are corporations duly organized under the laws of the State of Minnesota,that Farmington Casualty Company,Travelers Casualty and Surety Company,and Travelers Casualty and Surety Company of America are corporations duly organized under the laws of the State of Connecticut,that United States Fidelity and Guaranty Company is a corporation duly organized under the laws of the State of Maryland,that Fidelity and Guaranty Insurance Company is a corporation duly organized under the laws of the State of Iowa,and that Fidelity and Guaranty Insurance Underwriters,Inc.is a corporation duly organized under the laws of the State of Wisconsin(herein collectively called the"Companies"),and that the Companies do hereby make,constitute and appoint Steven B. Siddons, Shirong Chen, Holly A. Gravenor,and Lorrie Scott of the City of Fort Worth State of Texas their true and lawful Attomey(s)-in-Fact, each in their separate capacity if more than one is named above,to sign,execute,seal and acknowledge any and all bonds,recognizances,conditional undertakings and other writings obligatory in the nature thereof on behalf of the Companies in their busyness of,guaranteeing the fidelity of persons,guaranteeing the performance of contracts and egee>?ting%ar,$tTeratiteeing bonds and undertakings required or pei tkd in any##ions o rceedings allowed by law. IN WTTNSSWH-"REO>?_tfre�ompameOsGhave caused this ins'41 td be 4j$n�d d,tl anc�orlporate seals to be hereto affixed,this 16th Februaryday 8f Farmington Casualty Company St.Paul Guardian Insurance Company Fidelity and Guaranty Insurance('"ompaQ F„ St.Paul Mercury Insurance Company Fidelity and Guaranty Insutince Underwl4Cers,Inc. Travelers Casualty and Surety Company Seaboard Surety Company Travelers Casualty and Surety Company of America St.Paul Fire and Marine Insurance Company United States Fidelity and Guaranty Company Fl0.E 4•t.� \�'N.~MS(/ .P'rgV�9^t Jp 1Y 4Nps Iy451fRfTyY ?Opvor�,r ti .moi'oNov�,• �F Q.. .g f,�.,..........,.,y a a� ,� O CT t' �l �f a � 9 rtpRGOR�>F�f� rP�i pPOR n iG 982'o �9/( RATED �.(�G7 K m'� in3Zco 4TF.n; HAFRWRD• J'tNRIFdF., {{ 1896 Q; ' 19J�1 JO r'•SE AL iof j's1yy-,"Nrcr"�'r�a i 1• r� � ~s��uVVs.r+cco �'•••fs�•�NNL'�-f af CON.SALi°s on CONN. Q ria `SOF � 'tau;n� ..„w..✓� � s- State of Connecticut By: City of Hartford ss. Gorge W ompson,Sen(y Vic President On this the 1 6th day of February 2006 before me personally appeared George W.Thompson,who acknowledged himself to be the Senior Vice President of Farmington Casualty Company, Fidelity and Guaranty Insurance Company,Fidelity and Guaranty Insurance Underwriters, Inc.,Seaboard Surety Company,St.Paul Fire and Marine Insurance Company,St.Paul Guardian Insurance Company,St.Paul Mercury Insurance Company,Travelers Casualty and Surety Company,Travelers Casualty and Surety Company of America,and United States Fidelity and Guaranty Company,and that he,as such,being authorized so to do,executed the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer. G-TfR In Witness Whereof,I hereunto set my hand and official seal. My Commission expires the 30th day of June,2006. '°llBUG Marie C.Terreautt,Notary Public 58440-9-05 Printed in U.S.A. WARNING:THIS POWER OF ATTORNEY IS INVALID WITHOUT THE Rid BORDER T WARNING-THIS POWER OFATYORNEY IS INVB,Lip WITHGUTTHt REO�10RDER This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of Farmington Casualty Company,Fidelity and Guaranty Insurance Company,Fidelity and Guaranty Insurance Underwriters,Inc.,Seaboard Surety Company,St.Paul Fire and Marine Insurance Company, St.Paul Guardian Insurance Company,St.Paul Mercury Insurance Company,Travelers Casualty and Surety Company,Travelers Casualty and Surety Company of America,and United States Fidelity and Guaranty Company,which resolutions are now in full force and effect,reading as follows: RESOLVED,that the Chairman,the President,any Vice Chairman,any Executive Vice President,any Senior Vice President,any Vice President,any Second Vice President,the Treasurer,any Assistant Treasurer,the Corporate Secretary or any Assistant Secretary may appoint Attorneys-in-Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the Company's seal bonds,recognizances,contracts of indemnity,and other writings obligatory in the nature of a bond,recognizance,or conditional undertaking,and any I I of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her;and it is FURTHER RESOLVED,that the Chairman,the President,any Vice Chairman,any Executive Vice President,any Senior Vice President or any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company,provided that each such delegation is in writing and a copy thereof is filed in the office of the Secretary;and it is FURTHER RESOLVED,that any bond,recognizance,contract of indemnity,or writing obligatory in the nature of a bond,recognizance,or conditional undertaking shall be valid and binding upon the Company when(a)signed by the President,any Vice Chairman,any Executive Vice President,any Senior Vice President or any Vice I President,any Second Vice President,the Treasurer,any Assistant Treasurer,the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary;or(b)duly executed(under seal,if required)by one or more Attorneys-in-Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is M FURTHER RESOLVED,that the signature of each of the following officers:President,any Executive Vice President,any Senior Vice President,any Vice President, any Assistant Vice President,any Secretary,any Assistant Secretary,and the seal of the Company may be affixed by facsimile to any power of attorney or to any �l^ certificate relating thereto appointing Resident Vice Presidents,Resident Assistant Secretaries or Attorneys-in-Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof,and any such power of attorney or certificate bearing such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached. I,Kori M.Johanson,the undersigned,Assistant Secretary,of Farmington Casualty Company,Fidelity and Guaranty Insurance Company,Fidelity and Guaranty Insurance Underwriters,Inc., Seaboard Surety Company, St. Paul Fire and Marine Insurance Company,St. Paul Guardian Insurance Company,St_P4ru1 Mercury Insurance Company,Travelers Casualty and Surety Company,Travelers Casualty and Surety Company of America;and United States Fidelity and GOaraDty Company do hereby certify that the above and foregoing is a true and correct copy of the Powe;ofAttorney executed by A01tompanies,which is in full fpte4t id-effect and has not been revoked. IN TESTIMONY WHEREOF,I have hereunto set my hand and affixed the seals of said Companies this 9114 day of — v�•� v',20L� Kori M.Johann Assistant Secretary # i�O b�cy�'OP�'vs�uAII•,br�"�an(oi �YA!'sTrn 14`�o NC1dsIPO51t41TEp i Nrvii�OSsF#UA2EI�y�K iJ�t`�f�l^REHeayco 9 rm ��f�I'Oof;`.OS.rR.RN•EG..=.AI..N.N.AS.Li>UFjar�osc�'+,/ •v�>1:•W:P'S•a.'..p.'SpNO�ARs A L1f•a:�:.;,nt�s1°�e�l I WW�yJpTyANA.,,a�, 0jr- -�,it, OCON I To verify the authenticity of this Power of Attorney,call 1-800-421-3880 or contact us at www.stpaultravelersbond.com.Please refer to the Attorney-In-Fact number, the above-named individuals and the details of the bond to which the power is attached. .,r I ' WARNING THIS POVlr:R DF ATTORNEY IS ItiVAI-ID WkTHOLT THE AED 601tQF-Ft CITY OF FORT WORTH,TEXAS CONTRACT THE STATE OF TEXAS KNOW ALL BY THESE PRESENTS COUNTY OF TARRANT This agreement made and entered into this the 9"' day of May A.D., 20063 by and between the CITY OF FORT WORTH, a municipal corporation of Tarrant County, Texas, organized and existing under and by virtue of a special charter adopted by the qualified voters within said City on the I Ph day of December, A.D. 1924, under the authority (vested in said voters by the "Home Rule" provision) of the Constitution of Texas, and in accordance with a resolution duly passed at a regular meeting of the City Council of said city , and the City of Fort Worth being hereinafter termed Owner, Peachtree Construction,Ltd., HEREINAFTER CALLED Contractor. WITNESSETH: That said parties have agreed as follows: 1. That for and in consideration of the payments and agreements hereinafter mentioned to be made and performed by the Owner, and under the conditions expressed in the bond bearing even date herewith, w the said Contractor hereby agrees with the said Owner to commence and complete the construction of certain improvements described as follows: H M A C SURFACE OVERLAY(2006-3)AT VARIOUS LOCATIONS 2. That the work herein contemplated shall consist of furnishing as an independent contractor all labor, tools, appliances and materials necessary for the construction and completion of said project in accordance with the Plans and Specifications and Contract Documents prepared by the Department of Engineering for the Transportation and Public Works Department of the City of Fort Worth adopted by the City Council of the City of Fort Worth, which Plans and Specifications and Contract Documents are hereto attached and made a part of this contract the same as if written herein. 3. The Contractor hereby agrees and binds himself to commence the construction of said work within ten(10) days after being notified in writing to do so by the Department of Engineeri 4 of the City of Fort Worth. O �-I I I �1�y7�1:11 4. v� 391 �IILn b� The Contractor hereby agrees to prosecute said work with reasonable dilig ce ditd'� commencement thereof and to fully complete and finish the same ready for the inspection and approval o the Department of Engineering of the City of Fort Worth and the City Council of the City of Fort Worth within a period of 105 working days. f If the Contractor should fail to complete the work as set forth in the Plans and Specifications and Contract Documents within the time so stipulated, plus any additional time allowed as provided in the General Conditions, there shall be deducted from any monies due or which may thereafter become due him, the sum of$420 Per working day, not as a penalty but as liquidated damages, the Contractor and his Surety shall be liable to the Owner for such deficiency. 5. Should the Contractor fail to begin the work herein provided for within the time herein fixed or to carry on and complete the same according to the true meaning of the intent and terms of said Plans, Specifications and Contract Documents, then the Owner shall have the right to either demand the surety to take over the work and complete same in accordance with the Contract Documents or to take charge of and complete the work in such a manner as it may deem proper, and if in the completion thereof,the cost to the said City shall exceed the contract price or prices set forth in the said plans and specifications made a part hereof, the Contractor and/or its Surety shall pay said City on demand in writing, setting forth and specifying an itemized statement of the total cost thereof, said excess cost. 6 Contractor covenants and agrees to indemnify City's engineer and architect, and their personnel at the project site for Contractor's sole negligence. In addition, Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the Owner, its officers, servants and employees, from and against any and all claims or suits for property loss, property damage, personal injury, including death, arising out of, or alleged to arise out of, the work and services to be performed hereunder by Contractor, its officers, agents, employees, subcontractors, licensees or invitees, whether or not any such injury, damage or death is caused, in whole or in part, by the negligence or alleged negligence of Owner, its officers, servants, or employees. Contractor likewise covenants and agrees to indemnify and hold harmless the Owner from and against any and all injuries to Owner's officers, servants and employees and any damage, loss or destruction to property of the Owner arising from the performance of any of the terms and conditions of this Contract, whether or not any such injury or damage is caused in whole or in part by the negligence or alleged negligence of Owner, its officers, servants or employees.. In the event Owner receives a written claim for damages against the Contractor or its subcontractors prior to final payment, final payment shall not be made until Contractor either (a) submits to Owner satisfactory evidence that the claim has been settled and/or a release from the claimant involved, or (b) provides Owner with a letter from Contractor's liability insurance carrier that the claim has been referred to the insurance carrier. The Director may, if he deems it appropriate, refuse to accept bids on other City of Fort Worth public work from a Contractor against whom a claim for damages is outstanding as a result of work performed under a City Contract. 7. The Contractor agrees, on the execution of this Contract, and before beginning work, to make, execute and deliver to said City of Fort Worth good and sufficient surety bonds for the faithful performance of the terms and stipulations of the Contract and for the payment to all claimants for labor and/or materials furnished in the prosecution of the work, such bonds being as provided and required in Article 5160 of the Revised Civil Statutes of Texas, as amended, in the form included in the Contract Documents, and such bonds shall be for 100 percent of the total contract price, and said surety shall be a surety company duly and legally authorized to do business in the State of Texas, and acceptable to the City Council of the City of Fort Worth. 8. Said City agrees and binds itself to pay, and the said Contractor agrees to receive, for all of the aforesaid work, and for all additions thereto or deductions therefrom, the price shown on the Proposal submitted by the successful bidder hereto attached and made a part hereof. Payment will be made in ` monthly installments upon actual work completed by contractor and accepted by the Owner and receipt of invoice from the Contractor. The agreed upon total contract amount(including/excluding)alternates n/a, shall be One Million Two Hundred Thirteen Thousand Four Hundred Ninety-six and No/100...................Dollars,($1,213,496.00). 9. It is further agreed that the performance of this Contract, either in whole or in part, shall not be sublet or assigned to anyone else by said Contractor without the written consent of the Director of the Department of Engineering. 10. The Contractor agrees to pay at least the minimum wage per hour for all labor as the same is classified, promulgated and set out by the City of Fort Worth, Texas, a copy of which is attached hereto and made a part hereof the same as if it were copied verbatim herein. 11. It is mutually agreed and understood that this agreement is made and entered into by the parties hereto with references to the existing Charter and Ordinances of the City of Fort Worth and the laws of the State of Texas with references to and governing all matters affecting this Contract, and the Contractor agrees to fully comply with all the provisions of the same. IN WITNESS THEREOF, the City of Fort Worth has caused this instrument to be signed in 8 �. counterparts in its name and on its behalf by the City Manager and attested by its Secretary, with the corporate seal of the City of Fort Worth attached. The Contractor has executed this instrument through its duly authorized officers in 8 counterparts with its corporate seal attached. Done in Fort Worth,Texas,this the 91h day of May,A.D., 2006. RECOMMENDED: CITY OF FORT WORTH BY: DIRECTOR, DEPARTMENT OF CITY MANAGER ENGINEERING ('\M APPROVED: /� C " ✓� Marc A. Ott,Assistant City Manager TRANSPORTAT ION/PUBLIC WORKS DIRECTOR ATTEST: PEACHTREE CONSTRUCTION,LTD 5801 PARK VISTA CIRLCE KELLER,TX 76248 CONTRACTOR •� ,/—� CITY SECRETARY (SEAL) Contract Authorization Date BY: PRESIDENT TITLE APPROVED AS TO FORM AND LEGALITY: ADDRESS ASST. Cl�t AyfORNEY November 1960 Revised May 1986 O Revised September 1992 CIY � � R Y� k a (To be printed on Contractor's Letterhead) Date: Project Name: DOE No. : Project No: MAPSCO location: Street Rehabilitation of (StreetName) Project limits from to (StreetName) treet ame NOTICE OF CONSTRUCTION This notification is to inform you that under a contract with the City of Fort Worth, our company will be rehabilitating the named streets. The first phase of construction on the street will begin approximately THREE (3) DAYS FROM THE DATE OF THIS NOTICE: The phases on this project are as follows but not limited to nor will all phases effect your homes frontage: 1-Saw cut to isolate badly broken and/or misaligned curb/gutter, valley gutter or driveway approaches 2-Remove the isolated old concrete, form and pour concrete. 3-Mill the asphalt edge or re-stabilize the streets sub-base. 4-Application of the asphalt overlay. If you have questions concerning this project please call MR. AT (817) ontmebor a Superintendent OR MR. City inspector) AT (817)871-8306 For emergencies after 4:30 P.M. or on Weekends,Please call(817)871-7970 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL. PROJECT DESIGNATION SIGN 41 _ 011 PA FoKTW0RTH.--- PMS 288 PMS 167 3" f 3" ET MAINTENACE w = 3 PROGRAM O 3" 4 d- 1'/2 Contractor: ill„ 2r2 Contractor's Name Y2�� 7 i%2" TELEPHONE NUMBER 16/2" FORT WORTH IN LOGO- CHELTINGHAM BOLD ALL OTHER LETTERING IN ARIAL BOLD LOGO COLORS: FORT WORTH - PMS 288 LONGHORN LOGO- PMS 167 a v O W < ch z — N O O > 7 W C Qjn2 m O J a b Q Z p 1- J F- CJ U C7 a wI-NNZ J mZWCC40 df o W F-OCw!- _ 00 W°` Q?w ~ H W }� aC (DWC a J� F- ZW=F- ` _J W cn w V W nv LLJvi J z y = 3 Q O W Q J 2 . Z Ho V o >- a v� -- V 3 +. 3 a 0. W at • z c �,, m x c� o W o W0 O o (7 F- x I W W m WW ~ i J m ma 0 O H N W < W 1- J i O 2 IIVWINOD Ni ION 12TSIMOD NI ION rr ' V W _ N h_ I > O W e OC z i 2 y O e 1a- Q C to W Q � � Z z -• W J `\ M _J W Q d V J � w WHO = 3 0 � Z W z W _ W O W C W J o O J = - m v N tr O W U W J N N W •� W ►• Nuo z Q F= z O N 1- M• W O r0Z O ~ 00 a. N W V Q a Q W W j m = Q c9 r I.- JZ� z O = O W N •{Zy vt 0 y O J C bi m W 'OFN < o } N W S W Z V O — tcwo0E- Z = 3 P J " N 1-4 = C N rP- = WI--= C _Z` �' 0 N dN > WHqc OZ Wa J W J S J -1 W Z rz� r � �x z � O L- O Q W S_ zN0m¢ NW N Lai 0 v -Q w F- 0 z , � o - m � r W t Q1 1 > O W d W 0 IZ = W Q F r = 4 t W F cr W O1- m 2 Q N W V _ W m _ W O .J a MW 0JQ E'J N 7 3 W z p F m 049 t 2 < W W < u • JW = J O J W !A La O a tlf a < p Z WO C9 ZZ W m ZI I-- _z W O F' O N z F- W d tr Z W Cp- O ZZ o y W— � m W J A O W W !- u • h W t � 1� J i = Q u zujWV �. o v � x W _ }a- 0 .J z > J0 fAU z� c = JW � m0 N►- 1- Z M W V ��. -i IL v =; p ai V � WZ = NF n < Z Wap t� C LrW .� 7 � Wd HOO _ .JCN DW C Q J < O� d e � N e W LLJ a I- aei Z LtJ J e 11� • 1. X11 til ���• '. , r�{� ;�� •' 1� i' •1> it•.> see �� .. • .{{ .... III . � ,,lll ,• .., III ��, I � ►, - • 'r- v 1 ,, I I COLLAR CONFIGURATION COLLAR CONFIGURATION FOR PAVED AREA IN UNPAVED AREA 4'-0" (MANHOLE) 2'-0" (WATER VALVE) (8) #4 BARS, PLACED AS SHOWN. USE CLASS "A" — (3000 LB) ETE. CONCR 3", TYP. uj LLI 0 > Z cr < Ui M F A A do 77.- im PLAN VIEW CASE CASE 3/4" #1 #2CHAMFER GRADE RINGS 3" MIN. TYP. • GROUND COLLAR ---PVMT. THICKNESS 4 VARIES, 8" MIN. SUB �:*:2:27 - I BASE ov�.... RAM NECK, TYP. CASE #1 COLLAR SHALL EXTEND TO BOTTOM OF 2:27 CONCRETE SECTION "A-A" (REBAR REQUIRED). CASE #2 COLLAR, SHALL EXTEND 3" BELOW (MANHOLE COLLAR SHOWN) BOTTOM OF LOWEST GRADE RING (NOT TO SCALE) (REBAR REQUIRED). ORT RT CITY OF FORT WORTH, TEXAS DATE: 09/2004 MANHOLE AND WATER VALVE CONCRETE COLLAR STR-028 • A SOUARC FEET Or VALLEY GUTTER MEASURED FROM SACK-Or•CURe TO SACK-Or-Cults EXPANSION JOINTS TRAJ/i1T1011 ARIIA YRANSITION AREA(WIDTH AS REGUIREW DUMYT ZMATOUETES IMG w JOINTS PLAN VIEW Not to Ste% Aa Iawrt oo more tAae r/e depth *as ie /ess/4oe &V'/# deolk Sri//Oe reeelied/w o//dar/de aro//sp#utters. Tae cotteedor art// of reeulred to lost/Ao puller with eater'before 16#10A Is eccep/ed, T'CONCRETE - rXIST.N.U.A.C. VALLEY rVM'T ! "SrCUTTER 2�N�i4 C "Sr NO.3 f 24'C-C TRANSITION I' d' .N0.3i 16"C-C TRANSITION Exist 2/21 S' ITEM N0.302 T' 2/2T i' rVYY •sA E CONCRETE MSE Crushed CONCRETE MSE Limestone RESIDENTIAL STREETS SECTION 'A-A' Not to Sco% rhe r romorced concrrte ralloyihollreplace the top7~of Ihoporemeairlth theremo/nlag portion of porement to bs constructed/nc%ding s9091-44 lreotmeaf, In accordoaci with the typ/co/por/ng section. Tb♦ concrete Folly,r/ll br porwned according to city standards for concrete curb and guttsf. Tb• concrete skull be of iroshed and screened aggregate rr/th & x/a. of flref5jeacks of cement per cubicyord ofconciete. with a minimum compressive strength of 3,000 pounds per square inch in seven days. CONCRETE WAILLEYDEMILS GROUND LINE 1.5'MIN. FACE OF CURB SUITABLE MATERIAL TAMPED IN LIFTS NOT CURB AND C EXCEEDINC GUTTER �D I O' L O O S E. .r cam+....... TOP OF CURB N _Le WASHED Ro�cK 12" OVERLAP - PER ITEM 402 FILTER FABRIC PER e�, o PAY ITEM NO. 17 0.3' PIPE SHALL BE 6' PERFORATED POLYVINYL CHLORIDE TUBING PER ASTM D-1784 UNLESS SPECIFIED OTHERWISE. SUBDRAIN . CITY OF FORT WORTH,TEXAS-CONSTRUCTION STANDARD DRAWING NO. S—S 11 MODIF. DATE: 3- 7-95- 367 - 7--95367 Addendum 3 ATTENTION: CURB RAMPS SHALL BE CONSTRUCTED PERPENDICULAR TO THE CURB AT STREET CROSSINGS WITH LANDINGS IN LIEU OF DIAGONAL CROSSINGS WHERE FEASIBLE. SEE FIGS. 58, 59 & 60. WH UHAIR - RAMPS STANDARD D- Al S CITY OF FORT WORTH, TEXAS - CONSTRUCTION STANDARD OCTOBER, 1992, REDRAWN OCTOBER 2002 w w N m c z O M N N m O ¢ U Q H Of Y O WQ W r z cr� z i LLI FV U Ul a a Y W Z W M CL -1 J X c� O W p to < WO M rZ� F' ~ VFW U) aa ' g c9 _ Q n X W~ � 0 Z -Z :> X o O z a U T ¢ LLI XZOH. Yw (L a aQc aa. s � W .5Z'* 01 ,o �++ 0 Q 1H9LJ MH "nO W U OT W Z N CL O 2 V) U L-W Cl) N M F- Z] O c=n Y 2 M C) Lu¢ Q a a,y/► O m ^ LL. VI J ip =W H Q ?� z LJ Qva J� A Q � O -- M Lo U J a Wao ¢ m z n aLJ U _ UU nF O a m ow3Q U No Z LLJ p w Z <t W W 0. W o N _ CC opn CL U 6 cF�w O e� Vl W X V)V � O Z\ I �it J ~ [ _ U Z Fit L1. a w m ° r �a) w O U Ld � m 0 0 _ W W U 0 EXISTING 15' R SCALE 1" = 5' = SIDEWALK RAMP W/ COLORED SURFACE t NOTES 1) EXPANSION JOINT AND SILICONE SEALING SHALL BE SUBSIDIARY TO UNIT PRICE BID FOR SIDEWALK. EXISTING CURB AND GUTTER 2j -I GAC RB ATUAL UND GUTTEMIT OF R AND SIDEWALOVAL OF K SHALL BE AS DIRECTED BY THE ENGINEER IN THE FIELD, 3)NSTALHRSRTEPY BE INSTALLED SI OF SLOPES 8" DEPENDING ON THE FIELD CONDITION OR AS DIRECTED BY THE ENGINEER. 4) CURB RAMPS WITH RETURNED CURBS MAY BE •• 18" OR 24' USED WHERE PEDESTRIANS WOULD NOT NORMALLY WALK ACROSS THE RAMP. 5) SLOPE OF CURB RAMP AND/OR SIDEWALK SAWCUT FOR SHALL BE A_MAXIMUM OF 1:12. FLARED SIDES - CONCRETE OF RAMP SHALL HAVE A MAXIMUM SLOPE OF PAVEMENT 1:10, UNLESS PEDESTRIANS COULD WALK ACROSS THE RAMP THEN THE MAXIMUM SLOPE SHALL BE 1:12. SODDING N AS REQUIRED BACK OF 4 nr PROP. CURB MONOLITHIC SIDEWALK CURB qr-c =4CUNRBUOTRIC FLARED (SEE NOTES) 0 ONBO HIC CUROR ED X30 �`t SEE NOTES) 0G6�0'L FLARED SURFACE OR CURB SODDING Jr. AS REQUIRED 'Qy�q CK OF PROP. CURB �- FACE OF PROP. 7' CURB p'NS�ac FRo URe M PAY CMIT SAWCUT FOR HMAC PAVEMENT & G STANDARD PAY LIMIT DETAIL ORT�ORT CIITY OF FORT WORTH, TEXAS DATE: 09/2004 ACCESSABILITY RAMP - PAY LIMITS STR--032 EXISTING 15' R SCALE 1" = 5' SIDEWALK RAMP -� W/ COLORED SURFACE NOTES 1) EXPANSION JOINT AND SILICONE SEALING SHALL BE SUBSIDIARY TO UNIT PRICE BID FOR SIDEWALK. EXISTING CURB AND GUTTER 2) THE ACTUAL AND GUTTER AND SIDEWALKTSHALL t BE AS DIRECTED BY THE ENGINEER IN THE FIELD. 6" 18" OR 24" SAWCUT FOR CONCRETE PAVEMENT SODDING AS REQUIRED ACK OF PROP. CURB MONOLITHIC SIDEWALK CURB GROOVE 1[4" WITH 44INT TOOL,WITH GROOVE ,wry 1 b4" WITH ' J INTING TOOL 'SODDING AS REQUIRED EXPANSION JOINT & SILICONE SEALING CK OF PROP. CURB FACE OF PROP. 7" CURB SAWCUT FOR HMAC PAVEMENT JOINT DETAIL ORT WORTCITY OF FORT WORTH, TEXAS DATE 09/2004 ACCESSABILITY RAMP - JOINT DETAIL STR-033 a PERPENDICULAR PUBLIC SIDEWALK CURB RAMP r (Ib FLARED SIDE PARMA.EL PUBW SIDEWALK CUM RAW t _- is Leval LmdMg Top of PCur�ar PubYc V r COMBPiED(PSIDEWALKCURB RAMP50 PUBLIC Puc Sldsw� bliiM Curb Romp ORT T�4R CITY OF FORT WORTH, TEXAS DATE 09/2004 ACCESSABILITY RAMP - TYPiCAL CROSS SECTION STR--034 ATTENTION: CURB RAMPS SHALL BE CONSTRUCTED PERPENDICULAR TO THE CURB AT STREET CROSSINGS WITH LANDINGS IN LIEU OF DIAGONAL CROSSINGS WHERE FEASIBLE. SEE FIGS. 58, 59 & 60. 14.2.6 Vehicular Ways and Facilities o a U Li 0 cap A (b) Perpendicular public sidewalk curb ramp Perpendicular public sidewalk curb ramp In public sidewalk with parkway in public sidewalk - Q 4 rr O 1 44-44-1 f El � - cap (b) (c) araiiei public sidewalk curb ramp Combination public sidewalk curb ramp Perpendicular public sidewalk curb ramp In public sidewalk in public sidewalk with parkway at prola.ted intemectlan Fig. 60 Public Sidewalk Cirb Ramps at Marked Crossings ORT WORT CIN OF FORT WORTH, TEXAS DATE 09/2004 ACCESSABILITY RAMP — FIGURE 60 STR-035 X Y RUNNING SLOPE RUNNING SLOPE 1:20 MAX 1:12 MAX COUNTER SLOPE 1:20 MAX WALK CURB RAMP STREET NOTE: (1) Slope = y/x where z is a level slope (2) Counter elope shall not exceed 1:20 Fig. B4.7.2 Measurement of Curb Ramp Slope PLANTING OR OTHER NONWALKING SURFACE X FLARED SIDE 110 NOTE: If X < 48" (1220 mm) then the elope of the flared sides shall not exceed 1:12 ' (a) Flared Sides (b) Returned Curb Fig. B4.7.5 Sides of Curb Ramps 36 mi 91 1 10 Fig. B4.7.6 Built—up Curb Ramp OCTOBER, 1992, REDRAWN OCTOBER 2002 ORT yVOR CITY OF FORT WORTH, TEXAS DATE: 09/2004 ACCESSABILITY RAMP - RAMP SLOPE DETAILS STR-036 ATTENTION: CURB RAMPS SHALL BE CONSTRUCTED PERPENDICULAR TO THE CURB AT STREET CROSSINGS WITH LANDINGS IN LIEU OF DIAGONAL CROSSINGS WHERE FEASIBLE. SEE FIGS. 58, 59 & 60. Y_ P I A A Y- OU - S - CITY OF FORT WORTH, TEXAS - CONSTRUCTION STANDARD OCTOBER, 1992, REDRAWN OCTOBER 2002 TYPE I EXISTING 15' R. SCALE 1" = 4' PROP. 4' RAMP WITH COLORED SURFACE z 0 H d z as 0 U T 1:48 1:12 1:12 VARIABLE HEIGHT CURB 1 1/2' R. (TYP) ORT WO CITY OF FORT WORTH, TEXAS DATE: 09/2004 ACCESSABILITY RAMP — TYPE I (W/15' RADIUS) STR-037 TYP E I EXISTING 20' R. r x SCALE 1" = 4' a PROP. 4' RAMP WITH o COLORED SURFACE E- ­4 z va 0 U 1:48 1:12 VARIABLE HEIGHT CURB 1 1/2' R. (TYP) FORT WORTCITY OF FORT WORTH, TEXAS DATE 09/2004 ACCESSABILITY RAMP - TYPE 1 (20' RAD.) STR--038 II EXISTING CURB de GUTTER TYPE III EXISTING 15' R. SCALE 1" = 4' e. ® SIDEWALK RAMP WITH COLORED SURFACE 18" OR 24" ® BROOM FINISH SAWCUT Fox inuc PV1[T. ® HMAC TIE—IN 8" SODDING AS REQUIIW BACK OF PROP. CB. 1:12 MONOLTTBIC CURB 1:38 i tiry 1.48 SODDING -� — AS REQUIRED BACK OF PROP CURB FACS OF 7" CURB E aSPING CURB :Gv:r-.—. SAIPCUT FOR C CM ffl CITY �EVELL OR,I,w�R,I, CITY OF FORT WORTH, TEXAS DATE 09/21004 ACCESSABILITY RAMP - TYPE IQ (15' RADIUS) STR-039 4 i TYPE III EXISTING 20' R. EXISTING CURB SCALE 1" = 4' do GUTTER ® SIDEWA K RAMP WITH COLORED SURFACE 18" OR 24" ® BROOM FINISH FO HMACUPVIMR HMAC TIE-IN 6" 9" SODDING = AS REQUIRED BACK OF PROP. CB. 1:12 VARIABLE HEIGHT CURB 1:36 00 go go 00 00 00 00 10 j go OF 00 1:12 00 OF 0 :4B EXISTING CURB & GUTTER SODDING AS REQUIRED BACK OF PROP CURB FACE OF 7" CURB SAWCUT FOR CONCRETE PAVEMENT ORT WORT CITY OF FORT WORTH, TEXAS DATE: 09/2004 ACCESSABILITY RAMP - TYPE III (20' RADIUS) STR-040 I PLAN VIEW BACK OF BACK OF CURB CURB (Varies) (Min.:30'-Max 40') 2' (Varies) 2'-7.5" 6-1-3" -7.5" (Varies) 2' 112"WHITE HOT TAPE (AVERY DENNISON OR EQUIVALENT) J__ A ZD MINE Chi "S— CO) (DI 1 co IlIMMI N 12"WHITE HOT TAPE (AVERY DENNISON Striping and reflectors to be OR EQUIVALENT) install by the Contractor WHITE TYPE 11 1-SIDED REFLECTORS ........... .............. Overall length Overall width =Height: 3-1/2 inches Ramp Gradient: 8.57 in 1 (30 inches 3-1/2 inches height) DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS CITY OF Side Gradient: 3.43 in 1 (12 inches 3-1/2 inches heigh�TRAFFIC ENGINEERING FORT WORTH SPEED CUSHIONS DRAWN BY, DATE: AJB January I5,2004 APMWZ BY. DRAWING NOT TO SCALE H.M.A.C. SURFACE OVERLAY (2006-3) DOE NO. 5202 TPW NO. GS-93-020930522810 Blk Limits Project Name CS Street Limits S Procedure Quantity CD Map 1 900-1199 BALLINGER ST W 10TH ST -W LANCASTER AVE POL 0.7 LM 9 76D Z 900-1199 COLLIER ST 3 W l OTH ST -W LANCASTER AVE it POL 0.52 LM 9 76D �j 2900-3099 CULLEN ST 4 N WIMBERLY ST-N UNIVERSITY DR 13 POL 0.28 LM 9 62S 1 600-699 E 4TH ST a PECAN ST-TERRY ST 17— MOL 0.14 LM 9 63W Cj 100-599 E BELKNAP ST 1 W BELKNAP ST-N PECAN ST 17— MOL 1.04 LM 9 63W 4, 100-199 E BLUFF ST N MAIN ST-N COMMERCE ST �Z MOL 0.13 LM 9 62Z 1 900-1190 JENNINGS AVE 3 THROCKMORTON ST-W LANCASTER. MOL 0.71 LM 9 77A 900-1149 MONROE ST 3 W 10TH ST-W LANCASTER AVE I 1 MOL 0.45 LM 9 77A 3600-3699 N ELM ST 3 NE 35TH ST-NE 36TH ST I to MOL 0.38 LM 2 48Y 200-299 N HOUSTON ST 2 W BELKNAP ST-W BLUFF ST 13 MOL 0.1 LM 9 62Z i 500-1399 N MAIN ST 2 NE 4TH ST-E CENTRAL AVE 14 MOL 5.44 LM 2 62Q %1- 300-499 PECAN ST 2 E 2ND ST-E 4TH ST 1 MOL 0.3 LM 9 63W \5 2900-3099 SHOTTS ST 1\ N WIMBERLY ST-N UNIVERSITY DR 13 POL 0.29 LM 9 62W 11 300-499 TERRY ST E 2ND ST-E 4TH ST 1 MOL 0.3 LM 9 63W 16 100-199 W BELKNAP ST E BELKNAP ST-N HOUSTON ST 3 MOL 0.17 LM 9 62Z (0 100-199 W BLUFF ST N MAIN ST-N HOUSTON ST 1 MOL 0.14 LM 9 62Z Total Lane Miles for Contract H2O06-3 11.09 w A* CITY SHUE RAPY MOL=Mill Overlay POL=Pulverization and OverlaR ��� 1 Engineering Department Tuesday,February l4,2006 Design Services Division Page l of 1 Pon Garbage, i Recycling,Yard New Trimmings 6 Valley 10' Water Brush Weekly M Gutter 6'Inlet Inlet Manhole Water Meter Boz Monthly Pickup Pickup Day STREET NAME STREET LIMITS LM CD M7 SY Top EA Top EA EA Valve EA EA of Bulky Hems Areas Week Monday of each BALLINGERST W LOTH ST -W LANCASTER AVE 0.7 9 " 0 0 0 7 4i 0 month Tuesday am — -- - Week of 4th Monday of each COLLIER ST W I OTH ST -W LANCASTER AVE 0.52 9 100 0 0 0 2 0 month _ ! Tuesday i Week of 4th Monday of each _ CULLEN ST N WIMBERLY ST-N UNIVERSITY DR 0.28 9 t 0 0 0 0 0� 0 month Tuesday Week of 1 at Monday of each E_4TH ST PECAN ST-TERRY ST 0.14 9 6 0 0 0 7 01 0 month Tuesday Week of 1st Monday of each MP E BELKNAP ST W BELKNAP ST-N PECAN ST 1.04 9 6 0 0 0 5 8 2 month Tuesday —I Week of 1st II Monday of each E BLUFF ST N MAIN ST-N COMMERCE ST 0.13 9 t 0 0 0 1 _1 I _ 0 month _Tuesday Week of 1 st Monday of each JENNINGS AVE THROCKMORTON ST-65'S OF 13TH ST 0.71 9 1 0 0 0 5 7 01 month _ Tuesday Week of 1st Monday of each MONROE ST W 10TH ST-85'S OF 13TH ST 0.45 9 1 0 1 I 0 3I 3 0 month Tuesday Week of 1st (Monday of each N ELM ST NE 35TH ST-NE 36TH ST 0.36 2 4 0 0 0 1 _ 0 01 month Tuesday Week of 1 st Monday of each db N HOUSTON ST W BELKNAP ST-W BLUFF ST 0.1 9 6 0 0 0 0 0 0 month _Tuesday Week of 1 st � N MAIN ST NE 4TH ST-E CENTRAL AVE 5.44 2 I 6 0 0 0 4 11 Monday of each 1 0 month i Tuesday Week of 1 st—� to Monday of each PECAN ST E 2ND ST-E 4TH ST 0.3 9 6. 0 0 0 1 01 0 month Tuesday Week of 4th i I (Monday of each SHOTTS S7 N WIMBERLY ST-N UNIVERSITY DR_ 0.29, 9 L 6;_ 0; _0 0' 2 1 0 month _ Tuesday � I i Week of 1st I ' Monday of each TERRY ST E 2ND ST-E 4TH ST 0.3 9 � 0 1 0' 2; 0 O'month Tuesday Week of 1st W BELKNAP ST E BELKNAP ST-N HOUSTON ST I 0 17 I 9 I 6 0 O 0 Monday of each I 0. 0 0 month Tuesday Week of 1 st W:-LUFF ST �MAISTIN ST I (Monday of each 0.14 9 6 0: 0. 0. 2, 0; 01month j Tuesday 11.09 -- 100,