CITY OF FORT WORTH CITY OF FORT WORTH, TEXAS
CITY SECRETi''
STANDARD AGREEMENT FOR ENGINEERING RELATED PROFESSIONAL
SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home-rule
municipality ("CITY"), and Kimley-Horn and Associates, Inc., authorized to do business in
Texas, ("ENGINEER"), for a PROJECT generally described as: UPRR Kellis Group Quiet
Zone Improvements.
Article I
Scope of Services
The Scope of Services is set forth in Attachment A.
Article II
Compensation and Term of Agreement
A. The ENGINEER's compensation shall be in the amount up to $95,120.00 as set
forth in Attachment B.
B. Unless otherwise terminated pursuant to Article VI. D. herein, this Agreement
shall be for a term beginning upon the effective date, as described below, and
shall continue until the expiration of the funds or completion of the subject
matter contemplated herein, whichever occurs first.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
(1) The Engineer shall provide the City sufficient documentation, including but
not limited to meeting the requirements set forth in Attachment D to this
AGREEMENT, to reasonably substantiate the invoices.
(2) The ENGINEER will issue monthly invoices for all work performed under this
AGREEMENT. Invoices are due and payable within 30 days of receipt.
City of Fort Worth,Texas OFFICIAL RECORD
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 1 of 17 CITY SECRETARY
FT, WORTH,TX
(3) Upon completion of services enumerated in Article I, the final payment of
any balance will be due within 30 days of receipt of the final invoice.
(4) In the event of a disputed or contested billing, only that portion so contested
will be withheld from payment, and the undisputed portion will be paid. The
CITY will exercise reasonableness in contesting any bill or portion thereof.
No interest will accrue on any contested portion of the billing until mutually
resolved.
(5) If the CITY fails to make payment in full to ENGINEER for billings contested
in good faith within 60 days of the amount due, the ENGINEER may, after
giving 7 days' written notice to CITY, suspend services under this
AGREEMENT until paid in full. In the event of suspension of services, the
ENGINEER shall have no liability to CITY for delays or damages caused the
CITY because of such suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental
thereto.
B. Standard of Care
The ENGINEER shall perform its services:
(1) with the professional skill and care ordinarily provided by competent
engineers practicing in the same or similar locality and under the same or
similar circumstances and professional license; and
(2) as expeditiously as is prudent considering the ordinary professional
skill and care of a competent engineer.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 2 of 17
work to be performed hereunder. The ENGINEER shall also advise
the CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that
could affect the total PROJECT cost and/or execution. These
conditions and cost/execution effects are not the responsibility of the
ENGINEER.
D. Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in .pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires; provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on-site representatives or otherwise, do not make the
ENGINEER or its personnel in any way responsible for those duties that
belong to the CITY and/or the CITY's construction contractors or other
entities, and do not relieve the construction contractors or any other entity of
their obligations, duties, and responsibilities, including, but not limited to, all
construction methods, means, techniques, sequences, and procedures
necessary for coordinating and completing all portions of the construction
work in accordance with the Contract Documents and any health or safety
precautions required by such construction work. The ENGINEER and its
personnel have no authority to exercise any control over any construction
contractor or other entity or their employees in connection with their work or
any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the
progress or quality of the completed work on the PROJECT or to determine,
in general, if the work on the PROJECT is being performed in a manner
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 3 of 17
indicating that the PROJECT, when completed, will be in accordance with
the Contract Documents, nor shall anything in the Contract Documents or
this AGREEMENT between CITY and ENGINEER be construed as requiring
ENGINEER to make exhaustive or continuous on-site inspections to
discover latent defects in the work or otherwise check the quality or quantity
of the work on the PROJECT. If the ENGINEER makes on-site
observation(s) of a deviation from the Contract Documents, the ENGINEER
shall inform the CITY.
(3) When professional certification of performance or characteristics of
materials, systems or equipment is reasonably required to perform the
services set forth in the Scope of Services, the ENGINEER shall be entitled
to rely upon such certification to establish materials, systems or equipment
and performance criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs; competitive bidding procedures and market
conditions; time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate
PROJECT cost or schedule. Therefore, the ENGINEER makes no
warranty that the CITY's actual PROJECT costs, financial aspects,
economic feasibility, or schedules will not vary from the ENGINEER's
opinions, analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling
and observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects; that the
ENGINEER has made an examination to ascertain how or for what purpose
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Dale:11-17.17
Page 4 of 17
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are not other
matters at issue between the CITY and the construction contractor that
affect the amount that should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed. The ENGINEER is not responsible for
any errors or omissions in the information from others that is incorporated
into the record drawings.
I. Minority Business and Small Business Enterprise (MBE)(SBE)
Participation
In accord with the City of Fort Worth Business Diversity goals (Chapter 20,
Article X of the City's Code of Ordinances a/k/a Ordinance No. 20020-12-
2011, as amended), the City has goals for the participation of minority
business enterprises and/or small business enterprises in City contracts.
Engineer acknowledges the MBE and SBE goals established for this
contract and its accepted written commitment to MBE and SBE
participation. Any misrepresentation of facts (other than a negligent
misrepresentation) and/or the commission of fraud by the Engineer may
result in the termination of this Agreement and debarment from participating
in City contracts for a period of time of not less than three (3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers
and records of the ENGINEER involving transactions relating to this
contract. ENGINEER agrees that the CITY shall have access during normal
working hours to all necessary ENGINEER facilities and shall be provided
adequate and appropriate work space in order to conduct audits in
compliance with the provisions of this section. The CITY shall give
ENGINEER reasonable advance notice of intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the
CITY shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 5of17
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
facilities, and shall be provided adequate and appropriate work space, in
order to conduct audits in compliance with the provisions of this article
together with subsection (3) hereof. CITY shall give subconsultant
reasonable advance notice of intended audits.
(3) ENGINEER and subconsultant agree to photocopy such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for
the cost of copies at the rate published in the Texas Administrative Code in
effect as of the time copying is performed.
K. INSURANCE
(1) ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain
commercial general liability (CGL) and, if necessary, commercial
umbrella insurance with a limit of not less than $1,000,000.00 per each
occurrence with a $2,000,000.00 aggregate. If such Commercial General
Liability insurance contains a general aggregate limit, it shall apply
separately to this PROJECT or location.
i. The CITY shall be included as an additional insured with all rights
of defense under the CGL, using ISO additional insured
endorsement or a substitute providing equivalent coverage, and
under the commercial umbrella, if any. This insurance shall apply
as primary insurance with respect to any other insurance or self-
insurance programs afforded to the CITY. The Commercial
General Liability insurance policy shall have no exclusions or
endorsements that would alter or nullify: premises/operations,
products/completed operations, contractual, personal injury, or
advertising injury, which are normally contained within the policy,
unless the CITY specifically approves such exclusions in writing.
ii. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b. Business Auto — the ENGINEER shall maintain business auto liability
and, if necessary, commercial umbrella liability insurance with a limit of
not less than $1,000,000 each accident. Such insurance shall cover
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 6 of 17
liability arising out of "any auto", including owned, hired, and non-owned
autos, when said vehicle is used in the course of the PROJECT. If the
engineer owns no vehicles, coverage for hired or non-owned is
acceptable.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation — ENGINEER shall maintain workers
compensation and employers liability insurance and, if necessary,
commercial umbrella liability insurance with a limit of not less than
$100,000.00 each accident for bodily injury by accident or $100,000.00
each employee for bodily injury by disease, with $500,000.00 policy limit.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability — ENGINEER shall maintain professional liability, a
claims-made policy, with a minimum of $1,000,000.00 per claim and
aggregate. The policy shall contain a retroactive date prior to the date of
the contract or the first date of services to be performed, whichever is
earlier. Coverage shall be maintained for a period of 5 years following the
completion of the contract. An annual certificate of insurance specifically
referencing this project shall be submitted to the CITY for each year
following completion of the contract.
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be attached to this AGREEMENT prior to its
execution.
b. Applicable policies shall be endorsed to name the CITY an Additional
Insured thereon, subject to any defense provided by the policy, as its
interests may appear. The term CITY shall include its employees,
officers, officials, agents, and volunteers as respects the contracted
services.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 7 of 17
c. Certificate(s) of insurance shall document that insurance coverage
specified in this agreement are provided under applicable policies
documented thereon.
d. Any failure on part of the CITY to attach the required insurance
documentation hereto shall not constitute a waiver of the insurance
requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent
to the respective Department Director (by name), City of Fort Worth,
1000 Throckmorton, Fort Worth, Texas 76102.
f. Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of A:V or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management.
g. Any deductible or self insured retention in excess of $25,000.00 that
would change or alter the requirements herein is subject to approval by
the CITY in writing, if coverage is not provided on a first-dollar basis. The
CITY, at it sole discretion, may consent to alternative coverage
maintained through insurance pools or risk retention groups. Dedicated
financial resources or letters of credit may also be acceptable to the
CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation
in favor of the CITY as respects the PROJECT.
i. The CITY shall be entitled, upon its request and without incurring
expense, to review the ENGINEER's insurance policies including
endorsements thereto and, at the CITY's discretion; the ENGINEER may
be required to provide proof of insurance premium payments.
j. Lines of coverage, other than Professional Liability, underwritten on a
claims-made basis, shall contain a retroactive date coincident with or
prior to the date of the contractual agreement. The certificate of
insurance shall state both the retroactive date and that the coverage is
claims-made.
k. Coverages, whether written on an occurrence or claims-made basis,
shall be maintained without interruption nor restrictive modification or
changes from date of commencement of the PROJECT until final
payment and termination of any coverage required to be maintained after
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 8 of 17
final payments.
I. The CITY shall not be responsible for the direct payment of any
insurance premiums required by this agreement.
m. Sub consultants and subcontractors to/of the ENGINEER shall be
required by the ENGINEER to maintain the same or reasonably
equivalent insurance coverage as required for the ENGINEER. When
sub consultants/subcontractors maintain insurance coverage,
ENGINEER shall provide CITY with documentation thereof on a
certificate of insurance.
L. Independent Consultant
The ENGINEER agrees to perform all services as an independent
consultant and not as a subcontractor, agent, or employee of the CITY.
The doctrine of respondeat superior shall not apply.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure
in writing of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing
of any conflicts of interest that develop subsequent to the signing of this
contract and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities - Design Changes
If permitting authorities require design changes so as to comply with
published design criteria and/or current engineering practice standards
which the ENGINEER should have been aware of at the time this
Agreement was executed, the ENGINEER shall revise plans and
specifications, as required, at its own cost and expense. However, if design
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 9 of 17
changes are required due to the changes in the permitting authorities'
published design criteria and/or practice standards criteria which are
published after the date of this Agreement which the ENGINEER could not
have been reasonably aware of, the ENGINEER shall notify the CITY of
such changes and an adjustment in compensation will be made through an
amendment to this AGREEMENT.
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City-Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of
the information provided by the CITY.
B. Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services. The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of
the CITY's personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses
required by local, state, or federal authorities; and land, easements, rights-
of-way, and access necessary for the ENGINEER's services or PROJECT
construction.
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches,
drawings, specifications, proposals, and other documents; obtain advice of
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 10 of 17
an attorney, insurance counselor, accountant, auditor, bond and financial
advisors, and other consultants as the CITY deems appropriate; and render
in writing decisions required by the CITY in a timely manner in accordance
with the project schedule prepared in accordance with Attachment D.
E. Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of
such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos
is a result of ENGINEER's negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto the project.
G. Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of
Article IV.E. regarding the ENGINEER's Personnel at Construction Site, and
provisions providing for contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
H. Contractor Claims and Third-Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering
services performed. Only the CITY will be the beneficiary
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 11 of 17
of any undertaking by the ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third-party beneficiaries.
(3) The CITY will include in each agreement it enters into with any other entity
or person regarding the PROJECT a provision that such entity or person
shall have no third-party beneficiary rights under this Agreement.
(4) Nothing contained in this Section H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER.
I. CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY may secure Builders Risk/Installation insurance at the
replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3) The CITY will specify that the Builders Risk/Installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of the ENGINEER, this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
K. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for performance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 12 of 17
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed from the CITY.
B. Reuse of Project Documents
All designs, drawings, specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the final designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God, strikes, lockouts, accidents, or other events beyond
the control of the ENGINEER that prevent ENGINEER's performance of its
obligations hereunder.
D. Termination
(1) This AGREEMENT may be terminated
a.) by the City for its convenience upon 30 days' written notice to
ENGINEER.
b.) by either the CITY or the ENGINEER for cause if either party fails
substantially to perform through no fault of the other and the
nonperforming party does not commence correction of such
nonperformance within 5 days' written notice or thereafter fails to
diligently complete the correction.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans,
specifications or other forms of ENGINEER'S work product;
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 13 of 17
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
c.) The time requirements for the ENGINEER'S personnel to document
the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all termination expenses. The
CITY'S approval will be obtained in writing prior to proceeding with
termination services.
E. Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER
for the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors,
and ENGINEER's compensation will be made.
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify or hold harmless the CITY against liability
for any damage committed by the ENGINEER or ENGINEER's agent,
consultant under contract, or another entity over which the ENGINEER
exercises control to the extent that the damage is caused by or
resulting from an act of negligence, intentional tort, intellectual
property infringement, or failure to pay a subcontractor or supplier.
CITY is entitled to recover its reasonable attorney's fees in proportion
to the ENGINEER's liability.
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the
prior written consent of the other party.
H. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and performance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 14 of 17
Texas.
I. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any
reason to be invalid, illegal, or unenforceable in any respect, such invalidity,
illegality, or unenforceability will not affect any other provision, and this
AGREEMENT shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained herein. Articles V.F., VI.B., VI.D., VI.F.,
VI.H., and VI.I. shall survive termination of this AGREEMENT for any cause.
J. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in
any way affect this AGREEMENT and the work hereunder, and shall
observe and comply with all orders, laws ordinances and regulations which
may exist or may be enacted later by governing bodies having jurisdiction or
authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. ENGINEER agrees to defend, indemnify and
hold harmless CITY and all of its officers, agents and employees from and
against all claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
K. Immigration Nationality Act
ENGINEER shall verify the identity and employment eligibility of its
employees who perform work under this Agreement, including completing
the Employment Eligibility Verification Form (1-9). Upon request by CITY,
ENGINEER shall provide CITY with copies of all 1-9 forms and supporting
eligibility documentation for each employee who performs work under this
Agreement. ENGINEER shall adhere to all Federal and State laws as well
as establish appropriate procedures and controls so that no services will
be performed by any ENGINEER employee who is not legally eligible to
perform such services. ENGINEER SHALL INDEMNIFY CITY AND
HOLD CITY HARMLESS FROM ANY PENALTIES, LIABILITIES, OR
LOSSES DUE TO VIOLATIONS OF THIS PARAGRAPH BY ENGINEER,
ENGINEER'S EMPLOYEES, SUBCONTRACTORS, AGENTS, OR
LICENSEES. CITY, upon written notice to ENGINEER, shall have the
right to immediately terminate this Agreement for violations of this
provision by ENGINEER.
L. Prohibition On Contracts With Companies Boycotting Israel
ENGINEER acknowledges that in accordance with Chapter 2270 of the
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 15 of 17
Texas Government Code, CITY is prohibited from entering into a contract
with a company for goods or services unless the contract contains a
written verification from the company that it: (1) does not boycott Israel;
and (2) will not boycott Israel during the term of the contract. The terms
"boycott Israel" and "company" shall have the meanings ascribed to those
terms in Section 808.001 of the Texas Government Code. By signing
this contract, ENGINEER certifies that ENGINEER'S signature
provides written verification to the CITY that ENGINEER: (1) does not
boycott Israel; and (2) will not boycott Israel during the term of the
contract.
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, which supersedes all prior written or oral understandings, and may only be
changed by a written amendment executed by both parties. This AGREEMENT may be
executed in one or more counterparts and each counterpart shall, for all purposes, be
deemed an original, but all such counterparts shall together constitute but one and the
same instrument. The following attachments and schedules are hereby made a part of
this AGREEMENT:
Attachment A - Scope of Services
Attachment B - Compensation
Attachment C -Amendments to Standard Agreement for Engineering Services
Attachment D - Project Schedule
Attachment E - Location Map
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 16 of 17
Duly executed by each party's designated representative to be effective on the date
subscribed by the City's designated Assistant City Manager.
BY: BY:
CITY OF FORT WORTH ENGINEER
Kimley-Hom and Associates, Inc.
LV
an Alanis
zsistant City Manager Scott R. Arnold, P.E.
Assistant Secretary
Date:
Date:
APPR L RECOMMENDED:
By: f, L - Cj
DouglasOW. Wiersig, P.E.
Director, Department of Transportation
and Public Works
Contract Compliance Manager:
By signing, I acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including
ensuring II performa a and reporting
require nts.
Clint Hoover, P.El"S.E.
Senior Professional Engineer
APPROVED AS TO FORM AND LEGALITY
By:
Douglas W. Black FORT
Assistant City Attorne �O�
%
AT S tj z :Form 1295 No. n/a
Mary J. Kays ( p� M&C No.: n/a
City Secretary
M&C Date: n/a
OFFICIAL RECORD
City of Fort Worth,Texas �/
Standard Agreement for Engineering Related Design Services CI 1 y SECRETARY
Revised Date:11.17.17 @ ��y
Page 17 of 17 K WOR"rH, X
FORT WORTH.
ATTACHMENT "A"
Scope for Engineering Design Related Services for
UPRR Kellis Group Quiet Zone Improvements
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
OBJECTIVE
The objective of the UPRR Kellis Group Quiet Zone Improvements project is to install safety
measures to allow each of the five (5) crossings to become quiet zones which will reduce
train horn noise in the surrounding neighborhoods.
WORK TO BE PERFORMED
Task 1. Design Management
Task 2. Final Design (90% and 100°/x)
Task 3. Construction Phase Services
Task 4. Permitting
Task 5. Quality Control/ Quality Assurance
Task 6. On-Call Railroad Program Services
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 1 of 12
FORT WORTH.
TASK 1. DESIGN MANAGEMENT.
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use
of ENGINEER's and CITY's time and resources. ENGINEER will manage change,
communicate effectively, coordinate internally and externally as needed, and proactively
address issues with the CITY's Project Manager and others as necessary to make progress
on the work.
1.1. Managing the Team:
• Lead, manage and direct design team activities
• Ensure Quality Control / Quality Assurance (QC/QA) is practiced in performance
of the work. Refer to Task 5 for further details.
• Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting:
• Attend one (1)field meeting with CITY representatives prior to the 90% submittal.
• Conduct and document monthly project update meetings with CITY Project
Manager.
• Conduct review meetings with the CITY at the end of each design phase.
• Conduct and document biweekly design team meetings.
• Conduct QC/QA reviews and document those activities. Refer to Task 5 for
further details.
• Prepare invoices, in accordance with Attachment B to this Standard Agreement
and submit monthly in the format requested by the CITY.
• Prepare and submit monthly Project Status Reports in the format provided by the
respective Transportation and Public Works Department.
• Prepare and submit baseline Project Schedule initially, and Project Schedule
updates with a schedule narrative monthly, as required in Attachment D to this
Standard Agreement in compliance with the City's Specification 00 31 15 entitled
Engineer Project Schedule. This PROJECT requires a Tier 3 schedule as
defined in the City's Specification 00 31 15 entitled Engineer Project Schedule.
• Prepare and submit a preliminary Project Risk Register, preliminary Stakeholder
Register, and preliminary Project Communications Plan. CITY to modify and
finalize.
• Complete Monthly M/WBE Report Form and Final Summary Payment Report
Form at the end of the project.
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare
the design.
City of Fort Worth,Texas Page 2 of 12
Attachment A
PMO Release Date:02.06.2015
Page 2 of 12
FORT WORTH
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements
are appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs, and make changes necessary to
meet their requirements, as part of the design scope.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub-consultants shall carry readily visible
information identifying the name of the company and the company
representative.
ASSUMPTIONS
• One (1)field review meeting
• Three (3) monthly project update meetings during design phase
• One (1) plan review meetings
• Six (6) biweekly design team meetings
• All submittals to the City will be Quality checked prior to submission.
• Project design phase is anticipated to take three (3) months.
• Project construction phase is anticipated to take eight (8) months.
• Eleven (11) monthly updates of Project Status Reports, MWBE forms, TPBE,
Risk Register, and project Schedule.
DELIVERABLES
A. Meeting summaries with action items
B. QC/QA documentation
C. Baseline design schedule
D. Preliminary Project Risk Register, preliminary Stakeholder Register, and
preliminary Project Communications Plan
E. Monthly Schedule updates with schedule narrative describing any current or
anticipated schedule changes
F. Monthly Project Status Reports
G. Monthly TPBE spreadsheet updates
H. Monthly Project Risk Register updates
I. Plan Submittal Checklists (See Task 5)
J. Monthly invoices
K. Monthly M/WBE Report Form and Final Summary Payment Report Form
City of Fort Worth,Texas Page 3 of 12
Attachment A
PMO Release Date:02.06.2015
Page 3 of 12
FORT WORTH
TASK 2. FINAL DESIGN (90 PERCENT) AND FINAL CONSTRUCTION DOCUMENTS
(100 PERCENT).
• Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as
follows:
• Final draft construction plans (90%) including specifications shall be submitted to CITY
per the approved Project Schedule.
• The ENGINEER will provide a PDF set of plans with the utility conflicts highlighted and a
Utility Conflicts Table of those conflicts to be included in a Utility Clearance Letter for
final coordination.
• Following a 90% construction plan review meeting with the CITY, the ENGINEER shall
submit Final Plans (100%) to the CITY per the approved Project Schedule. Each plan
sheet shall be stamped, dated, and signed by the ENGINEER registered in State of
Texas.
• A Quantity Summary page will be included in both the 90% and 100% design packages.
Each design sheet of those package shall include a quantity take off table.
• The ENGINEER shall submit a estimate of probable construction cost with both the 90%
and 100% design packages. This estimate shall use standard CITY or TxDOT bid items,
as applicable.
ASSUMPTIONS
• Three (3) sets of 11"x17" size drawings and one (1) set of specifications will be delivered
for the 90% Design package.
• A PDF and DWF file for the 90% Design will be created from design CAD drawings and
will be uploaded to the project folder in Buzzsaw.
• Ten (10) sets of 11"x17" size drawings and two (2) set of specifications will be delivered
for the 100% Design package.
• A PDF and DWF file for the 100% Design will be created from design CAD drawings and
will be uploaded to the project folder in Buzzsaw.
DELIVERABLES
A. 90% construction plans and specifications including QC/QA documentation.
B. Utility Conflict Coordination Package
C. 100% construction plans and specifications including QC/QA documentation.
D. Detailed estimates of probable construction costs including summaries of bid items and
quantities using the CITY's or TxDOT's standard bid items and format, as applicable
E. Original 11"x17" size cover mylar for the signatures of authorized CITY officials.
City of Fort Worth,Texas Page 4 of 12
Attachment A
PMO Release Date:02.06.2015
Page 4 of 12
FORT WORTH
TASK 3. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
3.1. Construction Support
• The ENGINEER shall prepare one (1) task order package for the CITY's Unit
Price Contractor.
• The ENGINEER shall attend the preconstruction conference.
• The ENGINEER shall attend bi-weekly construction progress meetings during the
duration of construction. The ENGINEER will prepare meeting notes with action
items and distribute there to the project team.
• The ENGINEER will prepare a Construction Communication Plan detailing the
procedure for communicating between the Project Delivery Team members and
the Contractors.
• The ENGINEER will meet with concerned citizens as needed.
• The ENGINEER shall review shop drawings, samples and other submittals
submitted by the contractor for general conformance with the design concepts and
general compliance with the requirements of the contract for construction. Such
review shall not relieve the Contractor from its responsibility for performance in
accordance with the contract for construction, nor is such review a guarantee that
the work covered by the shop drawings, samples and submittals is free of errors,
inconsistencies or omissions. The ENGINEER shall log and track all shop
drawings, samples and other submittals in Buzzsaw.
• As requested by the CITY, the ENGINEER shall provide necessary interpretations
and clarifications of contract documents, review change orders, and make
recommendations as to the acceptability of the work.
• The ENGIENER will meet with the Project Delivery Team and Contractor on-site
to review any field changes.
• The ENGINEER will coordinate with the TPW department as necessary
• The Engineer will update and submit monthly the Project Status Report, Risk
Register, TPBE and Project Schedule.
• The ENGINEER shall attend the "Final" project walk through and assist with
preparation of final punch list.
3.2. Record Drawings
• The ENGINEER shall prepare record drawings from information provided by the
CITY depicting any changes made to the Final Drawings during construction.
Information provided by the CITY may include, but is not limited to the following:
o As-Built Survey
o Red-Line Markups from the Contractor
o Red-Line Markups from City Inspector
City of Fort Worth,Texas Page 5 of 12
Attachment A
PMO Release Date:02.06.2015
Page 5 of 12
FORT WORTH
o Copies of Approved Change Orders
o Approved Substitutions
• The ENGINEER shall modify the Final Drawings electronically and shall place a
stamp on the plans indicating that they represent Record Drawings of the project
as constructed. The stamp shall be signed and dated by the ENGINEER and
shall be placed on each plan sheet, whether there are any revisions on the sheet
or not. Each sheet shall clearly indicate all changes which apply to that sheet by
clouding and numbering, or other suitable means.
• The following disclaimer shall be included with the Record Drawing stamp:
These Record Drawings were prepared using information
provided by others and represent the as constructed
conditions to the extent that documented changes were
provided for recording. The ENGINEER assumes no liability
for undocumented changes and certifies only that the
documented changes are accurately depicted on these
drawings.
• The ENGINEER shall submit a set of sealed Final Drawings, modified and
stamped as Record Drawings, in Adobe Acrobat PDF format (version 6.0 or
higher) and in DWF format. The ENGINEER may keep copies of the
information provided by the CITY for their files, but all original red-lined drawings
shall be returned to the CITY with the digital files.
• There shall be one (1) PDF file and one (1) DWF file for the TPW plan set and a
separate PDF and DWF file for the Water plan set, if required. Each PDF and
DWF file shall contain all associated sheets of the particular plan set. Singular
PDF and DWF files for each sheet of a plan set will not be accepted.
Both PDF and DWF files shall be uploaded to the project's Record Drawing folder
in Buzzsaw.
For information on the proper manner to submit files and to obtain a file number for
the project, contact the Department of Transportation and Public Works Vault at
telephone number (817) 392-8426. File numbers will not be issued to a project
unless the appropriate project numbers and fund codes have been assigned and
are in the Department of Transportation and Public Works database.
ASSUMPTIONS
• Sixteen (16) site visits are assumed.
• Two (2) submittal reviews are assumed.
• Six (6) RFI's are assumed.
• One (1) Change Order is assumed.
DELIVERABLES
A. Construction Communication Plan
C. Response to Contractor's Request for Information
City of Fort Worth,Texas Page 6 of 12
Attachment A
PMO Release Date:02.06.2015
Page 6 of 12
FOR"T WORTH
D. Review of Change Orders
E. Review of shop drawings
F. Final Punch List items
G. Record Drawings in digital format
City of Fort Worth,Texas Page 7 of 12
Attachment A
PMO Release Date:02.06.2015
Page 7 of 12
FORT WORTH.
TASK 4. PERMITTING.
ENGINEER will provide permitting support for the CITY to obtain any and all agreements
and/or permits normally required for a project of this size and type, as follows
4.1. Railroad Permit
• Meet, negotiate and coordinate to obtain approval of the agency issuing the
agreement and/or permits.
• Completing all forms/applications necessary.
• Submitting forms/applications for CITY review
• Submitting revised forms for agency review
• Responding to agency comments and requests
ASSUMPTIONS
• Permit preparation will begin after approval of the 90% Design.
• One (1) meeting is assumed with UPRR for the railroad permit.
DELIVERABLES
A. Copies of Permit Applications
B. Copies of Approved Permits
City of Fort worth,Texas Page 8 of 12
Attachment A
PMO Release Date:02.06.2015
Page 8 of 12
FORT WORTH
TASK 5. QUALITY CONTROL /QUALITY ASSURANCE
ENGINEER to provide to the City a Quality Control/ Quality Assurance Plan (QC/QA Plan)
outlining the ENGINEER's method of ensuring the highest levels of design and accuracy are
incorporated into the calculations, plans, specifications, and estimates.
ENGINEER is responsible for and shall coordinate all subconsultant activity to include
quality and consistency of plans.
If, at any time, during the course of reviewing a submittal of any item it becomes apparent to
the CITY that the submittal contains errors, omissions, and inconsistencies, the CITY may
cease its review and return the submittal to the ENGINEER immediately for appropriate
action. A submittal returned to the ENGINEER for this reason may be rejected by the CITY
Project Manager.
5.1. QC/QA of Design Documentation
• ENGINEER shall perform a QC/QA review of all documents being submitted for
review at all stages of the design including the 90% and Final Document design
review submittals. QA should be performed by an individual within the firm who
is not on the design team.
• ENGINEER is to acknowledge that each item on the Detailed Checklist has been
included by checking "done" on the checklist. If a checklist item is not applicable,
this should be indicated by checking "N/A". If an entire checklist is not
applicable, this should be indicated by checking every item on the list as "N/A"
and still included with the submittal. The ENGINEER shall use the Detailed
Checklist provided by CITY.
• A Comment Resolution Log must be used to document conflicting comments
between reviewers and to highlight comments made by the CITY that the
ENGINEER is not incorporating into the design documents along with the
associated explanation. The ENGINEER shall use the Comment Resolution Log
provided by CITY.
• The documentation of a QC/QA review includes (1) a copy of the color-coded,
original marked-up document (or"checkprint") developed during the QA checking
process and/or review forms which sequentially list documents and associated
comments; and (2) a QC sign-off sheet with signatures of the personnel involved
in the checking process. Mark-ups may also be documented using the Comment
Resolution Log.
• Evidence of the QC/QA review will be required to accompany all submittals.
Documentation shall include, but is not limited to, the following items:
- PDF of the completed Detailed Checklists
- PDF of the QC/QA checkprint of the calculations, plans, specifications, and
estimates demonstrating that a review has been undertaken;
- PDF of previous review comments (if any) and the ENGINERR's responses
to those comments in the Comment Resolution Log.
• If any of the above information is missing, is incomplete or if any comments are
not adequately addressed; the CITY may contact the ENGINEER and request
City of Fort Worth,Texas Page 9 of 12
Attachment A
PMO Release Date:02.06.2015
Page 9 of 12
FORT WORTH
the missing information. If the ENGINEER does not respond to the request
within 24 hours, the CITY shall reject the submittal. No additional time will be
granted for a returned submittal.
• If the ENGINEER has not adequately addressed the comments, the submittal
shall be rejected and returned to the ENGINEER immediately to address the
issues.
ASSUMPTIONS
• All submittals to the City will be Quality checked prior to submission.
• A PDF of the QC/QA documentation will be uploaded to the project folder in
Buzzsaw.
DELIVERABLES
A. QC/QA documentation
City of Fort Worth,Texas Page 10 of 12
Attachment A
PMO Release Date:02.06.2015
Page 10 of 12
FORT WORTH
TASK 6. ON-CALL RAILROAD PROGRAM SERVICES
ENGINEER will perform on-call services related to the 2018 Railroad Bond Program as
requested by the City.
City of Fort Worth,Texas Page 11 of 12
Attachment A
PMO Release Date:02.06.2015
Page 11 of 12
FORT WORTH.
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services described in
the tasks above. However, ENGINEER can provide these services, if needed, upon — be
sure to track changes. the CITY's written request. Any additional amounts paid to the
ENGINEER as a result of any material change to the Scope of the Project shall be agreed
upon — be sure to track changes. in writing by both parties before the services are
performed. These additional services include the following:
• Negotiation of easements or property acquisition.
• Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre-qualification, bid protests, bid rejection and re-
bidding of the contract for construction.
• Construction management and inspection services
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of God.
• Services related to warranty claims, enforcement and inspection after final completion.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Performance of miscellaneous and supplemental services related to the project as
requested by the CITY.
City of Fort Worth,Texas Page 12 of 12
Attachment A
PMO Release Date:02.06.2015
Page 12 of 12
ATTACHMENT B
COMPENSATION
UPRR Kellis Group Quiet Zone Improvements
Time and Materials with Rate Schedule Project
I. Compensation
A. The ENGINEER shall be compensated in an hourly amount not-to-exceed
$95,120.00 for personnel time, non-labor expenses, and subcontract expenses in
performing services enumerated in Attachment A as follows:
i. Personnel Time. Personnel time shall be compensated based upon hours
worked directly in performing the PROJECT multiplied by the appropriate
Labor Category Rate for the ENGINEER's team member performing the
work.
Labor Category Rate as presented in the rate schedule table below is the rate for
each labor category performing the work and includes all direct salaries,
overhead, and profit.
Labor Category Rate
($/hour)
Project Director $250
Quality Control Manager $235
Senior Project Manager $205
Project Manager $175
Project Engineer IV $160
EIT III $140
EIT II $130
EIT 1 $125
LA/LP Professional VI $180
LA/LP Professional V $170
LA/LP Professional IV $160
LA/LP Analyst III $135
LA/LP Analyst II $125
LA/LP Analyst 1 $120
Environmental Professional VI $185
Environmental Professional V $175
Environmental Professional IV $155
Environmental Analyst III $130
Environmental Analyst II $125
Environmental Analyst 1 $120
RPLS-Surveyor $180
CADD Operator $110
CADD Designer $155
Project Accountant $160
Administrative $90
Intern $80
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 1 of 4
B-1
ATTACHMENT B
COMPENSATION
ii. Non-Labor Expenses. Non-labor expenses shall be reimbursed as Direct
Expenses at invoice or internal office cost.
Direct Expenses (non-labor) include, but are not limited to, mileage, travel and
lodging expenses, mail, supplies, printing and reproduction services, other direct
expenses associated with delivery of the work; plus applicable sales, use, value
added, business transfer, gross receipts, or other similar taxes.
iii. Subcontract Expenses. Subcontract expenses and outside services shall
be reimbursed at cost to ENGINEER plus a markup of ten percent (10%).
iv. Budgets. ENGINEER will make reasonable efforts to complete the work
within the budget and will keep the City informed of progress toward that end
so that the budget or work effort can be adjusted if found necessary.
ENGINEER is not obligated to incur costs beyond the indicated budgets, as may
be adjusted, nor is the City obligated to pay ENGINEER beyond these limits.
If ENGINEER projects, in the course of providing the necessary services that the
PROJECT cost presented in Article 2 of this Agreement will be exceeded, whether
by change in scope of the project, increased costs or other conditions, the
ENGINEER shall immediately report such fact to the City and, if so instructed by
the City, shall suspend all work hereunder.
When any budget has been increased, ENGINEER's excess costs expended prior
to such increase will be allowable to the same extent as if such costs had been
incurred after the approved increase.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. The ENGINEER shall be paid by the City based upon an invoice created on the
basis of statements prepared from the books and records of account of the
ENGINEER, based on the actual hours and costs expended by the ENGINEER
in performing the work.
B. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
C. ENGINEER shall prepare and submit invoices in the format and including content
as presented in Exhibit B-1.
D. Payment of invoices will be subject to certification by the City that such work has
been performed.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 2 of 4
B-2
ATTACHMENT B
COMPENSATION
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Transportation and Public Works Department monthly progress reports and
schedules in the format required by the City.
IV. Summary of Total Project Fees
Firm Primary Responsibility Fee Amount %
Prime Consultant
Kimley-Horn and Design, bidding, construction $95,120.00 100.0%
Associates, Inc. phase services
Proposed MBE/SBE Sub-Consultants
Non-MBE/SBE Consultants
TOTAL $95,120.00 100.0%
Project Number & Name Total Fee MBE/SBE Fee MBE/SBE
�o
CPN 100751 — UPRR Kellis Group $95,120.00 $0.00 0
Quiet Zone Improvements
City MBE/SBE Goal = 0% Consultant Committed Goal = 0%
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 3 of 4
B-3
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across desired work types and work phases.
City of Fort Worth,Texas
Attachment B
PMO Oficial Release Date:8.09.2012
Page 4 of 4
B-4
�
�
fr 04§ � _
� J
�
� -
| 0
2 �
kCA>
¥a.
§ ƒ
a
E
\ k {
E / / #
m 5
/ £ o {
2 & £ 3k \ CL ' k
�2 �J %
Ea ®
B $
\ \ ] | a
\ z
0 Ln Ln
k ) \ - 2
e L) J
ƒ f
% ) / k ) )
/ 2 I 2 /
E { � } d
\ k k
� � g
ƒ k
3 k k
J m 0 E
@ 2 2
/ < k kU)
� ƒ \ cm0 Q R
«
2
CL■ / j \ j LL
\ 0
■ ± ® _ t e
� ) \ ƒ \
} \
■ .. k z : .. .. \
2 & 2 R E a
_ m EE 2 3 ) § 2a2
£ 2 _ ` ! E k
CL
z z
2 = 2 ] a ` § \ d
■ a \
'21, 0 2 `
a v ° u4 { 2 /
CL \ k ) \ \ \ \ \
Kimley-Horn and Associates, Inc. 817-335-6511
817-335-5070 Invoice
801 Cherry Street, Unit 11
Suite 1300
Fort Worth,Texas 76102 Vendor No.
Consultant Project No.
CFW Project Manager Proj.Invoice No.
Invoice date:
Consultant's Project Manager., Scott R.Arnold,P.E.
Consultant's email: scott.amold@kimley-hom.com Period From Date
To Date
Name of Project: UPRR Kellis Group Quiet Zone Improvements City Secretary Contract#:
P.O.Number:
Labor Category Name Hours Rate($/hr) Amount
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Total Labor 0.0 $0.00
Subcontract Service
Subcontractor Subtotal $0.00
10 Percent Markup on Subcontract Services $0.00
Nonlabor Expenses
Nonlabor Expense Subtotal $0.00
Total Expenses(Subcontract Services+Markup+Nonlabor Expenses) $0.00
TOTAL DUE THIS INVOICE $0.00
�
� ]
� | |
—
;� _
CL
�
G /
� \ \
L
\ | | � ` 4)
E3
e3 { ! k
\\ { §
] 9 E g
\\( \ \
) \ \ ) ) k
0. ocol
\ z
|
) ) \ )
| 0
°72 ■ | `
( F- w
\
F-
0)
e
(
E \
� 9 k A7 2
{ � qu )
} \
�\ _
A ƒ co \%
$ \
) ] \
; ! % f « kk
LL , 2 M ) (\ %� 2
gE \ § kf ) aq) LZ
}
■
E kr k
3/ / -
\ a
y
�� J2
! u
3 /
a.
2 } »
E
)
LL k ( a \ j \
\ § 0M
§ / 2\ \
\0 - E )
\ C )
) t E
\
\j [ � \
k \ ) ) k )
) § ) ) \z
) \ 0U-
_ | ! §
° k2 2
( 2 ®
§
�
�
(
� \Cr
� ( \ \ �
k L \ @ } )
t \
ae -!1>1 j ) ƒ
Ln } }
)
, 0
Go ƒ / G /
- ° u �; k - a &
u Co
t; ;;I
C ƒ\ � § & 0 > ol .2
2 // � � � � � � � ° � § -
J Q »� \) ( /a !
ƒk u u G /
0 /
a \ ` a \
3 00000 N
N oao N oNoo pp Nop No ov�v�c� Ib� N MN O 00 rnnoH OH�ac
Mfo M AM Ln MN A NAre- {H MM10N�00 i��ii �b
OI AOA V td r r O IO Ip M N I�f` N N A W N M A IO A f0 N N N A O N
F N N ra N ao N � N 10 N N `p
y
Y
b
m
F
d O 00 00000 O 00 O OOH
N VOf�N ON OH�IA NIA No" N goo N A E -� N E � n0 N
C N HHHHHHH HHH N HNNOON N H N C,.,..`« m
d N H N E_ 7 b 6 a.
Q y y
K N N
H p y m p w
C.
r
wV 'o'o m-g- (p - y
o 'o 0)U) wa
LLj Lu m
c M N N N N M 0 Q m m�Q O
O m m o w
u m
m m
O '
a o
m z
z
0 N NN H N
d Ii
G ~
m
Q o
w m K N N M M N N
C �
+� C
O
C Z
o M N M N N N N
m w
N m
f
O O O O O O N N O O U N O N O O N N O O N O O�M O Q C T N X-O O RE p
O N r M MA Mtp td MN A ODAr Y MMONN I((II IQJ tQO N�[)
M O/r A A V t0r O10M t0 M W AA N N AfONMA Id AM 1p N NN Ar ml
JH HH H H R H 'NHH
b N ml fp aD N N Ip 01 V
W O N H HHRH N H N rH N H H N N N H N N N H M M N
U
C O
d � Q
Q) ; N N O tl tl O tl N
� m N
Z O b
m3 n�
t E E
'�COw do a
L Q O O N M M N O O O O N M V N O tl N N 'M Otl
a W .42' N C :n N
" yZ 'w
t c0 y •i ++
O O O O O O g O N
O V C7
WO pMaO F
C O d w
d Q N U C Z
C O a N cp N M K t0 t0 O O N O O�O N N m r N V N O O N
J L m N t0
o_
Y Q c
J W
N Y'Q tl a NNNON N O O O O CD
a V M N N tp
O c
N I+J N N N M N N t0 N N N IO N r N o ao O O O N
4441 ~tm
r OO O
c
Q m
y�
O d N
c
C!V 10
f
o
o
m _b
'a 3
� 3 ~
m
c b ? O N N N V N C Q Of L O
m
c d ami^ y�o m 9 y `°o rn o m m t o Q co_ N -
m a y��.-�In w a v no�. Z Y L) a U E ao
O „m, U _ m Q 2 N O C ro = m Q N
Y m E 0.11 C ... m p C m '0 m N C Im m OI
c ro c n d ami`.
2-02 cLi b
oE
b owo
Imm
o
A E E ::E ° —
OH
oo 3 U co oa mE
L o�e 3 c L E m— m
o m m U U o
a uLm` Q °d o m m m
f m U❑ t
i� - c'- a ami n n n n E n c m �, n c m'a m E m a d d U t J m
m E m E o m m ai 3 c m > v m p O n m m m o
o 0 3 N N N N p m p m m m m m m c E— m o E n
m oQ�rnmQadQUaU c c a� o 0 oQQm U�K irLL m mm �o o da cc c�!�
Q2a LLLLNLLQU VU w Q(X CY L)CL 6 o m o
p r N M N N n m W r N M Q N cd t�m LLL o
2 cV N N N N N N N N .-•-•-•-•-•- O
Yb r N"r•-r -PP
p r M M M M M M M M N t' �-N
m O O N (V O M M tl V O N N lA O 10 U Q Q
F' CI t+1 V 6 tG
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
UPRR Kellis Group Quiet Zone Improvements
City Project No. 100751
No changes to the Standard Agreement are proposed.
City of Fort Worth,Texas
Attachment C
PMO Release Date:05.19.2010
Page I of 1
FORT WORTH_
ATTACHMENT "D"
PROJECT SCHEDULE
A. Engineer Project Schedule Development
Engineer shall prepare a project schedule for the services to be provided in fulfilling the
requirements of the Agreement and encompassing the Scope of Work defined in
Attachment A to the Agreement.
Engineer shall prepare and maintain project schedule throughout the life of the project
as defined in the Agreement in compliance with the City's Specification 00 31 15 entitled
Engineer Project Schedule.
Engineer's project schedule will follow the Critical Path Methodology (CPM) for planned
sequencing of the work activity and timing of the work.
B. Schedule "Tier" Selection
City has identified three "Tier" levels for project schedules as defined in City's
Specification 00 31 15, to align with the size and complexity of the project as a basis for
schedule development. City's Project Manager will determine the "Tier' level for the
Engineer's project schedule as part of the negotiation of the Agreement.
C. Project Baseline Schedule
Engineer will produce an initial project schedule and submit as a "baseline" for review
and acceptance by City's Project Manager as defined in City's Specification 00 31 15
which will be referred to as the Project Baseline Schedule. Updates to the baseline
schedule follow the requirements of City's Specification 00 31 15.
D. Project Progress Schedule
Engineer will provide to the City, monthly updates to their project schedule indicating
progress of the Work in compliance with the requirements of City's Specification 00 31
15 and said schedule will be referred to as the Project Progress Schedule.
E. Master Project Schedule
City will develop and maintain a master project schedule for the overall project.
Engineer's project baseline and progress schedule submittals will be an integral part of
the development and updating process of City's Master Project Schedule.
City of Fort Worth,Texas
Attachment D
PMO Release Date:02.15.2011
Page 1 of 1
(13
'{ w
App
09
ku
W,L ' R +R 0 11 IM, I .
a ,O'
k
CID
• i cf ` 'I p Isk E van s-Av
■ . YI . 1
kc k
IF
ILI
.ter , _
Ij
• _ +a ` t4 W
__ • • ST t ry a:,. -R 4110 5d •• *C: _ _
` i�• 15 LlIAS - µ r} t" Gt`UIl#.p 1128
City of Fort Worth
Departmental Request for Waiver
Of MBE/SBE Subcontracting/Supplier Goal
Transportation and Public Works $95,120.00 9/24/18
DEPARTMENT NAME: ESTIMATED COST / PROPOSAL DATE
UPRR Kellis Quiet Zone Improvements 100751
NAME OF PROJECT/BID: DOE/PROJECT NO.
Clint Hoover DlgXallyelgnedbyClint Haover 6573 9/24118
Date:7018.10.05 08:13:10-05'00'
SIGNATURE OF /PROJECT MANAGER EXTENSION DATE NIGP CODE
Prior to advertisement, the contracting/managing department shall determine whether the bid/proposal is one which MBE/SBE
requirements should not be applied. MBE/SBE requirements may be waived upon written approval of the M/WBE Manager. If one
of the conditions listed below exists,the contracting/managing department shall notify the Manager via this form, stating the specific
reason(s)for requesting a waiver.
If the contracting/managing department and the Manager are in conflict over the granting of a waiver, either
may appeal to the City Manager, or designee, and his/her decision is final.
Please Check Applicable Reason:
QA. MWBE Office: A waiver of the goal for MBE/SBE subcontracting requirements was requested
by the Department and approved by the MWBE Office, in accordance with the M/WBE or BDE
Ordinance, because the public or administrative emergency exists which requires the goods or
services to be provided with unusual immediacy; or
=13. MWBE Office: A waiver of the goal for MBE/SBE subcontracting requirements was requested
by the Department and approved by the MWBE Office, in accordance with the M/WBE or BDE
Ordinance, because the purchase of goods or services from source(s) where subcontracting or
supplier opportunities are negligible; or
QC. MWBE Office: A waiver of the goal for MBE/SBE subcontracting requirements was requested
by the Department and approved by the MWBE Office, in accordance with the M/WBE or BDE
Ordinance, because the application of the provisions of this ordinance will impose an economic
risk on the City or unduly delay acquisition of the goods or services; or
=D. MWBE Office: A waiver of the goal for MBE/SBE subcontracting requirements was requested
by the Department and approved by the MWBE Office, in accordance with the M/WBE or BDE
Ordinance, because the MWBE Waiver is solicited based on the sole source information
provided to the MWBE Office by the managing department's project manager.
Justify Commodity or Service Waiver Request:
SBE subcontracting opportunities were satisfied under a separate contract. This contract is to complete 90%and Final design plans for the UPRR Kellis Group.
Please use additional sheets,if needed
M WBE OFFICE USE ONLY:
Melani Valle Digitally signed by 814:2 09-0Valle 10/08/18
Dale:2018.10.08 14:22:09-05'00'
Approved Signature of M/WBE Authorized Personnel Date
I Approved Signature of M/WBE Authorized Personnel Date
�. Rev.2-20-13
Cj1