HomeMy WebLinkAboutContract 33970 COMMUNITY FACILITIES AGREEMENT THE STATE OF TEXAS § City Secretary �n� COUNTY OF TARRANT § Contract No. 7 lJ WHEREAS, Hillwood Alliance Services, L.P. hereinafter called "Developer", desires to make certain improvements to Heritage Trace Parkway, an addition to the City of Fort Worth, Texas; and WHEREAS, the said Developer has requested the City of Fort Worth, a municipal corporation of Tarrant, Denton and Wise Counties, Texas, hereinafter called "City", to do certain work in connection with said improvements. NOW, THEREFORE, KNOW ALL BY THESE PRESENTS: For and in consideration of the covenants and conditions contained herein, the City and the Developer do hereby agree as follows: I. General Requirements A. The Policy for the Installation of Community Facilities ("Policy") dated March 2001, approved by the City Council of the City of Fort Worth and subsequently amended, is hereby incorporated into this Community Facilities Agreement as if copied herein verbatim. Developer agrees to comply with all provisions of said Policy in the performance of its duties and obligations hereunder. B. The requirements of the Policy shall govern this Community Facilities Agreement, provided, however, that any conflict between the terms of this Community Facilities Agreement and the Policy shall be resolved in favor of this Agreement. C. Developer shall provide financial security in conformance with paragraph 6, Section II, of the Policy. D. Developer acknowledges that there shall be no reduction in the amount of financial security prior to project completion and acceptance by the City. E. The Developer shall award all contracts for the construction of community facilities in accordance with Section II, paragraph 7 of the Policy. ���K1C^^1A ROD F. The contracts for the construction of the public infrastructure shall be administered in conformance with paragraph 8, Section II, of the Policy. G. The Developer further covenants and agrees to, and by these presents does hereby, fully indemnify, hold harmless and defend the City, its officers, agents and employees from all suits, actions or claims of any character, whether real or asserted, brought for or on account of any injuries or damages sustained by any persons (including death) or to any property, resulting from or in connection with the construction, design, performance or completion of any work to be performed by said Developer, his contractors, subcontractors, officers, agents or employees, or in consequence of any failure to properly safeguard the work, or on account of any act, intentional or otherwise, neglect or misconduct of said DEVELOPER, his contractors, sub-contractors, officers, agents or employees, whether or not such injuries, death or damages are caused, in whole or in Part, by the alleged negligence of the City of Fort Worth, its officers, servants, or employees. H. Developer shall install or adjust all of the required utilities to serve the development or to construct the improvements required herein. I. In the event that City participation exceeds $25,000, Developer agrees that no street construction or storm drainage will begin prior to City Council approval of this Community Facilities Agreement. (Article 104.100, Ordinance 7234). J. Developer agrees that no lot shall be occupied under a certificate of occupancy until the improvements required herein have been constructed (Article 104.100, Ordinance 7234). K. Developer hereby releases and agrees to indemnify and hold the City harmless for any inadequacies in the preliminary plans, specifications and cost estimates supplied by the Developer for this contract. L. Developer agrees to provide, at its expense, all necessary rights of way and easements across property owned by Developer required to 2 construct current and future improvements provided for in this agreement. M. Developer agrees to construct proposed improvements as shown on the exhibits attached hereto. The following exhibits are made a part hereof. Water (A)None; Sewer (A-1) None; Paving (B)Attached Storm Drain (B-1) Attached; Street Lights and Signs (C) Attached. N. City shall not be responsible for any costs that may be incurred by Developer in the relocation of any utilities that are or may be in conflict with any of the community facilities to be installed hereunder. II. Street and Storm Drain Facilities A. The Developer(s) agree to install or to cause to have installed, the street, storm drainage, street lighting, street name sign and other community facilities improvements shown as "current improvements" on the attached Exhibits B, B1, and C. B. As shown below in the "Summary of Cost for Street and Storm Drain Facilities", the Developer shall fund its share of "current improvements" and shall pay to the City for its share of the cost of street, storm drainage, street lighting, street name signs as shown on the attached Exhibits B, B1, and C. The estimated total cost of current improvements and related support services specified in this agreement, including design, construction and inspection is estimated to $942,323.04. SUMMARY OF COST Heritage Trace Parkway Item Developer City Cost Total Cost Cost A. Construction $ - 1. Streets (Includes Sidewalks) $730,228.00 $ 730,228.00 2. Storm Drainage $109,330.00 $ 109,330.00 3. Street Lights(Incl.Pull Boxes) $49,426.00 $49,426.00 4. Street Name Signs $ - $ - B. Engineering Design $ - C. Construction Engineering and Management by DOE 4% $ 35,559.36 $ 35,559.36 D. Materials Testing by DOE 2% $ 17,779.68 $ 17,779.68 TOTALS $ 942,323.04 $ - $ 942,323.04 Notes: 1. All Preliminary Plats filed after July 2000 will require sidewalks on all streets. 2. Developer's column for Item C represents four percent (4%) cost for construction inspection fees. The City will pay additional inspection fee over 4%. 3. City not preparing plans and specifications. 4. Developer's column for Item D represents two percent (2%) of paving and storm drain costs for materials testing. 4 IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be executed in triplicate in its name and on its behalf by its Assistant City Manager, attested by its City Secretary, with the corporate seal of the City affixed, and said Developer has executed this instrument in triplicate, at Fort Worth,Texas this the day of 52006. RECEIVED JUL t y 1006 Approval Recommended: Transportation and Public Works Department Robert Goode, P. E. Director City of ort. Orth NO M&CREQUIRED __..__... Marc Ott Assistant City Manager TTEST: Marty Hendrix City Secretary Approve s to Form: Assistanty ttorney RECEIVED JUL 1 S 20M Hillwood Alliance Services, L.P., a Texas limited partnership By: Hillwood Development Company, LLC, a Texas limited liability company, its general partner By: —kAAL' L, us 1 L ghlin, Senior Vice resident, Properties Division STATE OF TEXAS § COUNTY OF TARRANT § This instrument was acknowledged before me on J 2006, by L. Russell Laughlin, Senior Vice President, Properties Division, of Hillwood Development Company, LLC, a Texas limited liability company, on behalf of said limited liability company, in its capacity as general partner of Hillwood Alliance Services, L.P., a Texas limited partnershi , on behalf of said limited partnership. LORI L. BOWLING �. Notary Public,State of Texas My Commission Expires ;:�'` October», zoos Notary Public, State of Texas p 6 CITY M11-121 1PE Ry FTo R'i05�11Tw, TSI C No.014000.003 .... ...... A-A �k 't C. ............. ::42 N. p N9 81. .......... ................ CFA Estimate for: HERITAGE TRACE PARKWAY JULY, 2006 STREET IMPROVEMENTS (CFA UNIT PRICES) 1Item No. I DESCRIPTION I QTY j UNIT I PRICE I AMOUNTI 1 1 4' Sidewalk 1 5,400 1 LF 1 14.001 75,600.00 TOTAL -STREET IMPROVEMENTS $75,600.00 G:\JOB\014000003\EST\20060710 Sidewalk CFA\Sidewalk CFA EstimateAs 2 of 3 PART B—PROPOSAL �E'/� s v4 DEVELOPER AWARDED CONTRACTS This proposal must not be removed from this book of Contract Documents. TO: Hillwood Alliance Services, L.P. PROPOSAL FOR: PROJECT NAME: Heritage Trace Parkway WATER PROJECT NO. P164-060164015471 SANITARY SEWER NO. P174-070174013491 FILE NO. 1922 X NO. 18296 Includes the furnishing of all materials, except materials specified to be furnished by the City, equipment and labor for the installation of Paving, Drainage, and Utility Improvements and all necessary appurtenances and incidental work to provide a complete and serviceable project designated as: Heritage Trace Parkway Pursuant to the foregoing Notice to Bidders', the undersigned Bidder, having thoroughly examined the Contract Documents, including plans, special contract documents, the General Contract Documents and General Specifications for Water Department Projects, the General Contract Documents and General specifications for Transportation and Public works Projects, the site of the project and understanding the amount of work to be done, and the prevailing conditions, hereby proposes to do all the work, furnish all labor, equipment and material except as specified to be furnished by the City, which is necessary to fully complete the work as provided in the Plans and Contract Documents and subject to the inspection and approval of the Director of the Department of Engineering of the City of Fort Worth, Texas; and binds himself upon acceptance of this Proposal to execute a contract and furnish an approved Performance Bond, Payment Bond, Maintenance Bond, and such other bonds, if any, as may be required by the Contract Documents for the performing and completing of the said work. Contractor proposes to do the work within the time stated and for the following sums: N:\JOB\014000\Spec\014000.003.002.0640.doc B-1 Updated 05/16/2005 UNIT 111: STORM DRAIN PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE BID (Furnish & Install, Including All Appurtenant Work, Complete in Place, The Following Items) 1. 1 EA: Remove & Dispose of Existing 4 —8' x 5' Parallel Wing Wall, Two Thousand Dollars & No Cents per Each $2,000.00 $2,000.00 2. 1 EA. Remove & Dispose of Existing 51" RCP Headwall, Seven Hundred Fifty Dollars & No Cents per Each $750.00 $750.00 3. 53 L.F. 4 —8' x 5' Box Culverts, Thirteen Hundred Dollars & No Cents per Linear Foot $1,300.00 $68,900.00 4. 68 L.F. 51" Class III RCP, One Hundred Forty-Five Dollars & No Cents per Linear Foot $145.00 $9,860.00 5. 14 L.F. 33" Class III RCP, Seventy Dollars & No Cents per Linear Foot $70.00 $980.00 N:\JOB\014000\Spec\014000.003.002.0640.doc B-9 Updated 05/16/2005 6. 83 L.F. 21" Class III RCP, Forty Dollars & No Cents per Linear Foot $40.00 $3,320.00 7. 3 EA. Std. 15' Recessed Curb Inlet, Twenty-Six Hundred Dollars & No Cents per Each $2,600.00 $7,800.00 8. 1 EA. Parallel Wing for Skewed 4— 8' x 5' Box Culvert, Sixty-Five Hundred Dollars & No Cents per Each $6,500.00 $6,500.00 9. 138 C.Y. Rock Rip Rap, Sixty-Five Dollars & No - Cents per Cubic Yard $65.00 $8,970.00 10. 1 L.S. Trench Safety, Two Hundred Fifty Dollars & No Cents per Lump Sum $250.00 $250.00 TOTAL AMOUNT BID STORM DRAIN $109,330.00 N:\JOB\014000\Spec\014000.003.002.0640.doc B-10 Updated 05/16/2005 UNIT IV: STREET IMPROVEMENTS PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE BID (Furnish & Install, Including All Appurtenant Work, Complete in Place, The Following Items) 7,000 C.Y. Unclassified Excavation, Two Dollars & ent -Five Cents per Cubic Yard .25 $15,750.00 2. 12,500 C.Y. Alternate d—Berm Construction Two lars & Twenty- ' ents per Cubic e CYa $2.25 $28,125.00 3. 12,504 S.Y ine Grading & Subgrade Preparation, One Dollars & No Cents per Square Yard $1.00 $12,504.0 4. 12,504 S.Y. 6" Lime Stabilized Subgrade, One Dollars & Ninety Cents per Square Yard $1.90 $23,757.60 5. 188 Ton Hydrated Lime Subgrade, Ninety-Eight Dollars & No Cents per Ton $98.00 $18,424.00 N:\JOB\014000\Spec\014000.003.002.0640.doc B-11 Updated 05/16/2005 6. 12,150 S.Y. 4" HMAC Base Course, Sixteen Dollars & No Cents per Square Yard $16.00 $194,400.00 7. 11,535 S.Y. 8" Reinforced Concrete Pavement (3600 PSI), Twenty-Eight Dollars & Twenty-Five Cents per Square Yard $28.25 $325,863.75 8. 3,000 C.Y. Respread Topsoil to Depth of 6" One Dollars & Fifty Cents per Cubic Yard $1.50 $4,500.00 9. 2,399 L.F. 7" Concrete Curb One Dollars & Fifty Cents per Linear Foot $1.50 $3,598.50 10. 3,505 L.F. 6" Concrete Curb One Dollars & No Cents per Linear Foot $1.00 $3,505.00 11. 1,240 L.F. Sawcut, Remove & Dispose of Existing Concrete Curb& Gutter, w lk Five 7 Dollars & No Cents per Linear Foot $5.00 $6,200.00 N:\JOB\014000\Spec\014000.003.002.0640.doc B-12 Updated 05/16/2005 12. 828 S.Y. Remove & Dispose of Existing Concrete Pavement, Thirteen Dollars & No Cents per Square Yard $13.00 $10,764.00 13. 310 S.Y. Remove & Dispose of Existing Asphalt Pavement, Ten Dollars & No Cents per Square Yard $10,00 $3,100.00 14. 485 S.Y. Existing Reinforced Concrete Panel Removal, Fifteen Dollars & No Cents per Square Yard $15.00 $7,275.00 15. 485 �5.Y. Replace Reinforced Concrete Panels, Forty-Five Dollars & No Cents per Square Yard $45.00 $21,825.00 16. 50 L.F. Standard White Solid Stop Bar, Twenty Dollars & No Cents per Linear Foot $20.00 $1,000.00 N;\JOB\014000\Spec\014000.003.002.0640.doc B-13 Updated 05/16/2005 17. 2 EA Remove & Relocate Existing Regulatory Street Signs, Two Hundred Fifty Dollars & No Cents per Each $250.00 $500.00 18. 1,510 EA Type W-4 Markers, Three Dollars & No Cents per Each $3.00 $4,530.00 19. 380 EA Type II-CR-4 Markers, Five Dollars & No Cents per Each $5.00 $1,900.00 20: 140 L.F. Irrigation Conduits 2-6" & 4=4" SCH-80 PVC with End Caps, Fifteen Dollars & No Cents per Linear Foot $15.00 $2,100.00 21. 10 EA. Remove & Relocate Irrigation Control Valves, Two Hundred Fifty Dollars & No Cents per Each $250.00 $2,500.00 NAJOB1014000\Spec\014000.003.002.0640.doc B-14 Updated 05/16/2005 22. 2 EA. Construction Entrance, One Thousand Dollars & No Cents per Each $1,000.00 $2,000.00 23. 6 EA. Inlet Protection, Three Hundred Dollars & No Cents per Each $300.00 $1,800.00 24. 3,557 L.F. Silt Fence, One Dollars & Fifty Cents per Linear Foot $1.50 $5,335.50 25. 1 EA. Rock Berm, Seven Hundred Fifty Dollars & No Cents per Each $750.00 $750.00 26. 1 L.S. Phase I Traffic Control & Channeling Devices, Twenty-Five Hundred Dollars & No Cents per Lump Sum $2,500.00 $2,500.00 N:1JOB10140001Spec1014000.003.002.0640.doc B-15 Updated 05/16/2005 27. 1 L.S. Phase II Traffic Control & Channeling Devices, Two Thousand Dollars & No Cents per Lump Sum $2,000.00 $2,000.00 28. 1 L.S. Phase III Traffic Control & Channeling Devices, Two Thousand Dollars & No Cents per Lump Sum $2,000.00 $2,000.00 29. 1 L.S. Compliance with SWPPP, Twenty Five Hundred Dollars & No Cents per Lump Sum $2,500.00 $2,500.00 +TOTAL AMOUNT BID STREET IMPROVEMENTS "UASSWED C-)QAvAT(O�' ALT6ZATE 3tD-�Eeril s�t1c-�o�,r FuIE �rcA�1�&r+S SEr OIFICIAL EEO N:\JOB\014000\Spec\014000.003.002.0640.doc B-16 Updated 05/16/2005 UNIT V: STREET LIGHTING IMPROVEMENTS PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT AMOUNT ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE BID (Furnish & Install, Including All Appurtenant Work, Complete in Place, The Following Items) 1. 6 EA. Relocation of Existing Street Lights (Double Arm Assembly, Davit Type D40- 9T), One Thousand Dollars & No Cents per Each $1,000.00 $6,000.00 2. 622 L.F. 1 —3" SCH 80 PVC Conduit (for Future Signalization), Eight Dollars & No Cents per Linear Foot $8.00 $4,976.00 3. 6 EA. Pull Boxes (for Future Signalization), Three Hundred Seventy-Five Dollars & No Cents per Each $375.00 $2,250.00 4. 6 EA. Type No. 5 Concrete Drilled Shaft Foundation, with Anchor Bolts, with 4'2" Extension for Decorative Bases, Fifteen Hundred Dollars & No Cents per Each $1,500.00 $9,000.00 N:\JOB\014000\Spec\014000.003.002.0640.doc B-17 Updated 05/16/2005 5. 6 EA. Remove Rock & Store for Reuse on Decorative Bases, Five Hundred Dollars & No Cents per Each $500.00 $3,000.00 6. 6 EA. Reconstruct Decorative Rock Bases, One Thousand Dollars & No Cents per Each $1,000.00 $6,000.00 7. 250 L.F. 2" SCH 80 PVC Conduit, Eight Dollars & No Cents per Linear Foot $8.00 $2,000.00 8. 750 L.F. 2° SCH 40 PVC Conduit, Eight Dollars & No Cents per Linear Foot $8.00 $6,000.00 9. 1400 L.F. 3 #4 & 1 #8 Wires, Three Dollars & No Cents per Linear Foot $3.00 $4,200.00 10. 12 EA. Ballast, 200 W HIPS Lamp, Five Hundred Dollars & No Cents per Each $500.00 $6,000.00 TOTAL AMOUNT BID STREET LIGHTING IMPROVEMENTS $49,426.00 N:\JOB\014000\Spec\014000.003.002.0640.doc B-18 Updated 05/16/2005 SUMMARY TOTAL AMOUNT BID WATER $15,075.00 TOTAL AMOUNT BID SEWER $53,020.00 TOTAL AMOUNT BID STORM $109,330.00 TOTAL AMOUNT BID STREET IMPROVEMENTS $�+ 6 (05'4,(.ZS" TOTAL AMOUNT BID STREET LIGHTING IMPROVEMENTS $49,426.00 GRAND TOTAL AMOUNT BID $937,858.35 881,-1-79 ov N:WOB\014000\Spec\014000.003.002.0640.doc B-19 Updated 05/16/2005 PART B -PROPOSAL(Cont.) s After acceptance of this Proposal, the undersigned will execute the formal contract and will deliver an approved Surety Bond and such other bonds as required by the Contract Documents, .for the faithful performance of the Contract. The attached bid security, if required is to become the property of the Developer. The undersigned bidder certified that he has obtained at least one set of the General Contract Documents and General Specifications for Water Department Projects dated January 1, 1978, and that he has read and thoroughly understands all the requirements and conditions of those General Documents and the specific Contract Documents and appurtenant plans. The successful bidder shall be required to perform the work in accord with the following publications, both of which are incorporated herein and made a part hereof for all purposes: 1. The General Contract Documents and General Specifications for Water Department Projects dated January 1, 1978, which may be purchased from the Water Department. 2. The Standard Specifications for Street and Storm Drain Construction which may be purchased from the Department of Transportation & Public Works. The undersigned assures that its employees and applicants for employment and those of any labor organization, subcontractors, or employment agency in either furnishing or referring employee applicants to the undersigned are not discriminated against as prohibited by the terms of City Ordinance No. 7278 as amended by City Ordinance No. 7400. The Bidder agrees to begin construction within 10 calendar days after issue of the work order, and to complete the contract within 120 calendar days after beginning construction as set forth in the written work order to be furnished by the Owner. (Complete A or B below, as applicable:) A. The principal place of business of our company is in the State of Nonresident bidders in the State of , our principal place of business, are required to be percent lower than resident bidders by state law. A copy of the statute is attached. Non resident bidders in the State of , our principal place of business, are not required to underbid resident bidders. --X—B. The principal place of business of our company or our parent company or majority owner is in the State of Texas. N:\JOB\014000\Spec\014000.003.002.0640.doc B-20 Updated 05/16/2005 I (we) acknowledge receipt of the following addenda to the plans and specifications, all of the provisions and requirements of which have been taken into consideration on preparation of the foregoing bid: Addendum No. 1 (Initials) Addendum No. 3 (Initials) Addendum No. 2 (Initials) Addendum No. 4 (Initials) Respectfully submitted, Conatser Constru on X L.P. By: OF Title Mark Pappas,Vice-President Address PO Box 15448 Fort Worth, TX 76119 Telephone: 817-534-1743 (Seal) Date: March 28, 2006 RL P N:\JOB\014000\Spec\014000.003.002.0640.doc B-21 Updated 05/16/2005 O tp M tD c O O • • N .- RECEIVE �@yi st O "' V R rjP O a O ZO O N O N R W r• s m o 0 WZO W �I3 o V c��2 cr w i J Q U P N � O H F-- O _ -00SY77V0 _ Z 'OJ 1NV2/UY1 LU ' O • 09£ W Y J W Z � M O N 4 m m U V � a o- O v oas a a O o u � LL£ 35W F— u U CW7 N C Q W 4• , W W x Woctw � x Ol8 W J w Q iu t \ \ M M _ _ I\ U o CDc J �2� W w w V p,- W m O s o N m = X �a w O W Z1 f7] F O da OCL i I i I , r � I i r� �4 N LJ I Oco "a I i3 Q j W w O o � I a I K F i --- Z X W o N w N W ZO 3� Z W Ld W Cl 11 O > It -O m I (L F N W >- z Z v>LLI LJ (r H I 0 LLJ W a O C O 0 > O O IZ a... IZ '000 V l 4 c ------------------- �� .. L7J anix — N 0 o cn !ll ii f. N t -O W Q = U I V I t Fza: a H ti X W W P S i 1 ,4 I 11 S X r III W ' Ir" Ilr, I'= 11'1 IN.I 'I II't ! j i t fill $ ;' it j i% !k e w j Ld LJ i ji 1 K I' 1 X W 7 i I I' � l a� ! l !I LiJ J J V) W z z w J a a crJ Q W J z i ! ! H O 3 cr- O Er W 2 O O CO O J z a I- z a w N >- F— cr .Fcr ' w a a CL _ -------------- - ------------------------------------_ -------------- --------- o 0 0 0 - o cr cr = x -._'.__ ARSE—HI i'1---._..._--------_-_ ARSE�._----_._..__---- 10 'LIC i i l0 4 C r Lr re) o ` o CD Q � U N WUj = m Zo W I, u. S V) a itt Z t t r fir. z ' N 7 W U t OI; J w wi C6 I w � li > I 'I 0 i w I t I i I Z rl - m ' Fw-- W j +J i dS W I O j it w I ; Q i a � • o � a I F- W off` !i'I 0 a � r,' i w o J J Z i W w W In Z W Z F- Z F- W N Q to W Ln Q C W D ' W p W F- Z W J w J F- W m i J m O m N iz m f i O p p w F- p w N >- i _ _ --------------------..._.___.________--- ------ VI I X O W CL A15£-FII ----_--_----_-.-_ _._._..__...._......_____... F. W W