NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: JOHN DAY ROAD—RANCHO CANYON WAY
City Project No.: 100683
Improvement Type(s): ❑ Paving ❑ Drainage ® Street Lights ❑ Traffic Signals
Original Contract Price: $114,875.00
Amount of Approved Change Order(s):
Revised Contract Amount $114,875.00
Total Cost of Work Complete: $114,875.00
JU M=1M Nov 27, 2018
Contractor Date
Project Manager
Title
Conatser Construction Tx Lp
Company Name
he4d,&&Qe I Nov 28 2018
ft9W MaMev U ttwil#W INN2&"12)
Project Inspector Date
awX09&" Nov 29 2018
Project Manager* Date
Dec 3, 2018
iFA Manager Date
S.,ra`A, 7w
Dec 3 2018
SUSan Alanis(0t 1,3018)
Asst. City Manager Date
R
of �� EFT.
C AL R� 2
s�ogT�A/9 SECRETARY
I -Jn WORTH, TX
Notice of Project Completion
Project Name:JOHN DAY ROAD—RANCHO CANYON WAY
City Project No.: 100683
City's Attachments
Final Pay Estimate
Change Order(s): ❑ Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 210 CD Days Charged: 210
Work Start Date: 12/21/2017 Work Complete Date: 11/13/2018
i
Page 2 of 2
l 0 bc6 y 3
City Project Numbers 100683 DOE Number 1750
Contract Name JOHN DAY ROAD-RANCHO CANYON WAY Estimate Number 1
Contract Limits Payment Number 1
Project Type STREET LIGHTS For Period Ending 11/13/2018
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors GREGORY / SUTTERFIELD Contract Date 10/30/2017
Contractor CONATSER CONSTRUCTION TsLP Contract Time 210 CD
5327 WICHITA ST Days Charged to Date 210 CD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $114,875.00
Less %Retained $0.00
Net Earned $114,875.00
Earned This Period $114,875.00
Retainage This Period $0.00
i
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $114,875.00
Monday,November 26,2018 Page 4 of 4
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name JOHN DAY ROAD-RANCHO CANYON WAY
Contract Limits
Project Type STREET LIGHTS
City Project Numbers 100683
DOE Number 1750
Estimate Number 1 Payment Number I For Period Ending 11/13/2018
CD
City Secretary Contract Number Contract Time 21CCD
Contract Date 10/30/2017 Days Charged to Date 210
Project Manager NA Contract is 100.00 Complete
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors GREGORY / SUTTERFIELD
f
i
Monday,November 26,2018 Page 1 of 4
City Project Numbers 100683 DOE Number 1750
Contract Name JOHN DAY ROAD-RANCHO CANYON WAY Estimate Number I
Contract Limits Payment Number 1
Project Type STREET LIGHTS For Period Ending 11/13/2018
Project Funding
UNIT V;STREET LIGHTING RAPROVEMENTS
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 2"CONDT PVC SCH 80(T) 1630 LF $12.00 $19,560.00 1630 $19,560.00
2 RDWY ILLUM ASSEMBLY TY 18,18A,19,AND 9 EA $2,200.00 $19,800.00 9 $19,800.00
D-40
3 LED LIGHTING FIXTURE(137W) 9 EA $600.00 $5,400.00 9 $5,400.00
4 RDWY ILLUM FOUNDATION TY 3,5,6 AND 8 9 EA $1,200.00 $10,800.00 9 $10,800.00
5 6-6-6 TRIPLEX ALUM ELEC CONDUCTOR 1630 LF $3.00 $4,890.00 1630 $4,890.00
W/#10 COPPER GROUND IN POLE ONLY
6 REMOVE AND REUSE EXISTING POLE 1 EA $2,000.00 $2,000.00 1 $2,000.00
7 ELECTRICAL CONTRACTOR VAULT TO BE 1 EA $2,500.00 $2,500.00 1 $2,500.00
ADJUSTED
8 2"CONDT PVC SCH 80(T) 1195 LF $12.00 $14,340.00 1195 $14,340.00
9 RDWY ILLUM ASSEMBLY TY 18,18A,19,AND 8 EA $2,200.00 $17,600.00 8 $17,600.00
D-40
10 LED LIGHTING FIXTURE(13Yw) 8 EA $600.00 $4,800.00 8 $4,800.00
11 RDWY ILLUM FOUNDATION TY 3,5,6 AND 8 8 EA $1,200.00 $9,600.00 8 $9,600.00
12 6-6-6 TRIPLEX ALUM ELEC CONDUCTOR 2/#10 1195 LF $3.00 $3,585.00 1195 $3,585.00
COPPER GROUND IN POLE ONLY
----------------------------------------
Sub-Total of Previous Unit $114,875.00 $114,875.00
--------------------------------------
Monday,November 26,2018 Page 2 of 4
City Project Numbers 100683 DOE Number 1750
Contract Name JOHN DAY ROAD-RANCHO CANYON WAY Estimate Number 1
Contract Limits Payment Number 1
Project Type STREET LIGHTS For Period Ending 11/13/2018
Project Funding
Contract Information Summary
Original Contract Amount $114,875.00
Chante Orders
Total Contract Price $114,875.00
Total Cost of Work Completed $114,875.00
Less %Retained $0.00
Net Earned $114,875.00
Earned This Period $114,875.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $114,875.00
Monday,November 26,2018 Page 3 of 4
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a Notary Public in the state and county aforesaid,
on this day personally appeared Brock Huggins, President of Conatser Management Group, Inc.,
general partner of Conatser Construction TX LP, known to me to be a credible person, who
being by me duly sworn, upon his oath deposed and said:
That all persons, firms, associations, corporations or other organizations furnishing
labor and/or materials have been paid in full;
i
That the wage scale established by the City Council in the City of Fort Worth, has
been paid in full; and
That there are no claims pending for personal injury and/or property damages;
On Contract described as: p
I
SENDERA RANCH EAST JOHN DAY RD.AND
RANCHO CANYON WAY
WATER3 SANITARY SEWER, STORM DRAIN, PAVING
AND STREET LIGHT IMPROVEMENTS
DOE#: N/A
CFA PRJ#:2017-105
CITY PROJCT#: N/A
CITY OF FORT WORTH
STATE OF TEXAS
CONATS R CONSTRUCTION TX, LP
t
Brock Huggins
Subscribed and sworn to before me this 24h day of Se er, 20
-" BERTHA GIANULIS '
Notary Pubiic, state of Texas
My Commission Expires Notary public in Tarrant County, Texas
1 B, 2019
September
CONSENT OF OWNER ❑
SURETY COMPANY ARCHITECT ❑
TO FINAL PAYMENT CONTRACTOR ❑
❑
Conforms with the American Institute of SURETY
OTHER
Architects,AIA Document G707
Bond No 0212173
PROJECT:
(name, address)Sendera Ranch East John Day Rd.&Rancho Canyon Way
Fort Worth,TX
TO (Owner)
CITY OF FORT WORTH AND LENNAR HOMES OF —) ARCHITECT'S PROJECT NO: CGA No.2017-105
TEXAS LAND AND CONSTRUCTION,LTD. CONTRACT FOR:
200 Texas Street Water,Sanitary Sewer,Drainage,Paving,and Street Lighting
Improvements for Sendera Ranch East John Day Road&Rancho
Fort Worth Tx 7sto2 J CONTRACT DATE:
CONTRACTOR:CONATSER CONSTRUCTION TX,L.P.
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above,the
there insert name and address of Surety Company)
BERKLEY INSURANCE COMPANY
475 Steamboat Road
Greenwich CT 06830 , SURETY COMPANY
f on bond of (here insert name and address of Contractor)
CONATSER CONSTRUCTION TX,L.P.
5327 Wichita St.
Fort Worth TX 76119-6035 , CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to (here insert name and address of Owner)
CITY OF FORT WORTH AND LENNAR HOMES OF TEXAS LAND AND CONSTRUCTION, LTD.
200 Texas Street
Fort Worth TX 76102 , OWNER,
as set forth in the said Surety Company's bond.
IN WITNESS, WHEREOF,
the Surety Company has hereunto set its hand this 20th day of September,2018
BERKLEY INSURANCE COMPANY
Surety Company
Attest: Qom' , 2M " Z
(seal): Signature of Authorized Representative
Robbi Morales Attorney-in-Fact
Title
NOTE: This form is to be used as a companion document to AIA DOCUMENT G706, CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIM'',
Current EditionONE PAGE
Green Sheet CPN 100683
Street Lights John Day Rd -
__ :�: Rancho Canyon Way
--- ------- - - Adobe Sign Document History 12/04/2018
---- - - Created: 11/26/2018
By: Etta Bacy(etta.bacy@fortworthtexas.gov)
Status: Signed
Transaction ID: CBJCHBCAABAATu-Jyye3txSfmm1fx378UeKGK4wukfJo
"Green Sheet CPN 100683 Street Lights John Day Rd - Rancho
Canyon Way" History
Document created by Etta Bacy(etta.bacy@fortworthtexas.gov)
11/26/2018-3:18:42 PM CST-IP address:209.194.29.100
E-r Document emailed to Jay Arnell (jay.arnell@conatserconstruction.com)for signature
11/26/2018-3:22:04 PM CST
Document viewed by Jay Arnell (jay.arnell@conatserconstruction.com)
11/27/2018-8:15:28 PM CST-IP address:99.203.23.3
1 Jay Arnell Qay.arnell@conatserconstruction.com) uploaded the following supporting documents:
& File Attachment 1
Ci File Attachment 2
11/27/2018 9:53:45 PM CST
c Document e-signed by Jay Arnell Qay.arnell@conatserconstruction.com)
Signature Date:11/27/2018-9:53:45 PM CST-Time Source:server-IP address:71.86.113.248
C'w Document emailed to Hershel Stanley Sutterfield (stanley.sutterfield@fortworthtexas.gov)for signature
11/27/2018-9:53:49 PM CST
Document viewed by Hershel Stanley Sutterfield (stanley.sutterfield@fortworthtexas.gov)
11/28/2018-5:48:06 PM CST-IP address:107.77.198.25
cSQ Document e-signed by Hershel Stanley Sutterfield (stanley.sutterfield@fortworthtexas.gov)
Signature Date:11/28/2018-5:48:58 PM CST-Time Source:server-IP address:107.77.198.25
Document emailed to.Emanuel Nieto (emanuel.nieto@fortworthtexas.gov)for approval
11/28/2018-5:48:59 PM CST
Adobe Sign
Document viewed by Emanuel Nieto (emanuel.nieto@fortworthtexas.gov)
11/29/2018-7:25:56 AM CST-IP address:209.194.29.100
D , Document approved by Emanuel Nieto (emanuel.nieto@fortworthtexas.gov)
Approval Date: 11/29/2018-7:28:46 AM CST-Time Source:server-IP address:209.194.29.100
Document emailed to Khal Jaafari (khal.jaafari@fortworthtexas.gov)for signature
11/29/2018-7:28:47 ANI CST
i� Document viewed by Khal Jaafari (khal.jaafari@fortworthtexas.gov)
11/29/2018-1:37:04 PM CST-IP address:209.194.29.100
Document e-signed by Khal Jaafari (khal.jaafari@fortworthtexas.gov)
Signature Date:11/29/2018-2:01:58 PM CST-Time Source:server-IP address:209.194.29.100
w Document emailed to Janie Scarlett Morales Qanie.morales@fortworthtexas.gov)for signature
11/29/2018-2:01:59 PM CST
Document viewed by Janie Scarlett Morales Qanie.morales@fortworthtexas.gov)
12/03/2018-11:53:17 AM CST-IP address:209.194.29.100
Ge Document e-signed by Janie Scarlett Morales Qanie.morales@fortworthtexas.gov)
Signature Date:12/03/2018-11:53:39 AM CST-Time Source:server-IP address:209.194.29.100
Cr Document emailed to Susan Alanis (susan.alanis@fortworthtexas.gov)for signature
12/03/2018-11:53:41 AM CST
Document viewed by Susan Alanis (susan.alanis@fortworthtexas.gov)
12/03/2018-5:36:39 PM CST-IP address:209.194.29.100
<Ua, Document e-signed by Susan Alanis (susan.alanis@fortworthtexas.gov)
Signature Date:12/03/2018-5:36:54 PM CST-Time Source:server-IP address:209.194.29.100
'► Document emailed to Allison Tidwell (cso_finalpay@fortworthtexas.gov)for filling
12/03/2018-5:36:55 PM CST
Document viewed by Allison Tidwell (cso_finalpay@fortworthtexas.gov)
12/04/2018-7:58:11 AM CST-IP address:209.194.29.100
6@ Form filled by Allison Tidwell (cso_finalpay@fortworthtexas.gov)
Form filling Date:12/04/2018-7:58:31 AM CST-Time Source:server-IP address:209.194.29.100
C' Document emailed to Trudy Brotherton (therese.brotherton@fortworthtexas.gov)for delivery
12/04/2018-7:58:32 AM CST
Document viewed by Trudy Brotherton (therese.brotherton@fortworthtexas.gov)
12/04/2018-7:59:14 AM CST-IP address:209.194.29.100
FORT WORTH.
Adobe sign
f3a Document receipt acknowledged by Trudy Brotherton (therese.brotherton@fortworthtexas.gov)
Receipt Acknowledgement Date:12/04/2018-7:59:29 AM CST-Time Source:server-IP address:209.194.29.100
74 Document emailed to Julie A Geho Oulie.geho@fortworthtexas.gov)for delivery
12/04/2018-7:59:30 AM CST
Document viewed by Julie A Geho Oulie.geho@fortworthtexas.gov)
12/04/2018-8:06:29 AM CST-IP address:209.194.29.100
b4 Document receipt acknowledged by Julie A Geho Oulie.geho@fortworthtexas.gov)
Receipt Acknowledgement Date:12/04/2018-8:06:42 AM CST-Time Source:server-IP address:209.194.29.100
C' Document emailed to TPW Fiscal Staff(tpwcfafiscal@fortworthtexas.gov)for delivery
12/04/2018-8:06:44 AM CST
Document viewed by TPW Fiscal Staff(tpwcfafiscal@fortworthtexas.gov)
12/04/2018-8:09:05 AM CST-IP address:209.194.29.100
a Document receipt acknowledged by TPW Fiscal Staff(tpwcfafiscal@fortworthtexas.gov)
Receipt Acknowledgement Date:12/04/2018-9:11:49 AM CST-Time Source:server-IP address:209.194.29.100
® Signed document emailed to Janie Scarlett Morales Qanie.morales@fortworthtexas.gov), Trudy Brotherton
(therese.brotherton@fortworthtexas.gov), Jay Arnell Qay.arnell@conatserconstruction.com), Susan Aianis
(susan.alanis@fortworthtexas.gov), and 7 more
12/04/2018-9:11:49 AM CST
Foxe I ,
Adobe sign