HomeMy WebLinkAboutContract 33912 AMENDMENT NO. 3
STATE OF TEXAS S CITY SECRETARY CONTRACT NO. .
(No M&C Required)
COUNTY OF TARRANT S
WHEREAS, the City of Fort Worth (City) and Carter &
Burgess,Inc. (Engineer) made and entered into City Secretary
Contract No. 30370, (the Contract) which was authorized by the City
Council by M&C C-20200 on the 10th day of August 2004 and
subsequently revised by two previous amendments; and
WHEREAS, the Contract involves engineering services for the
following project:
36-inch Walnut Creek Sanitary Sewer Interceptor
WHEREAS, it has become necessary to execute Amendment No. 3 to
said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly authorized representatives, enter into the following
agreement which amends the Contract:
I
1.
Article I of the Contract is amended to include the additional
engineering services specified in a proposal letter dated July 10,
2006, a copy of which is attached hereto and incorporated herein.
The cost to City for the additional design services to be performed
by Engineer total $12,090.00.
2 .
Article II of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $147,919.00.
RIGINAL
Ell
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
1
EXECUTED on this the eday of 2006, in Fort
Worth, Tarrant County, Texas.
ATTEST:
LL Lk�L�L�-
Marty Hendrix
City Secretary ---- -_�
APPROVAL RECOM[ENDED: OVED:
A. Douglas Rademaker, P.E. rc LA "Ot-t
Director, Department of Assistant City Manager
Engineering
i
CARTER & BURGESS, JNC.
ENGINEER
By:
3y
N to a Veal, P.E. , Vice President
777 Main Street
Fort Worth, TX 76102-5304
APPROVED AS,70 FORM AND LEGALITY:
Assistan i.ey Attorney
I
-2- �mul"ill ROD
CITY MCI AIM
TN. !-1-.;0 7i 27H1 IL
777 Main Street
Fort Worth,TX 76102
Carter'°Burgess P.O.Box 901058
Fort Worth,TX 76101-2058
Phone: 817.735.6000
Fax:817.735.6148
July 10, 2006 www.c-b.corn
Mr. Liam J. Conlon
Project Manager
Engineering Department
City of Fort Worth
900 Monroe Street, Suite 201
Fort Worth, Texas 76102
Ref: Amendment No. 3
36-Inch Walnut Creek Sewer Interceptor
Moving the Sewer to the South Side of Winscott Road
Project No. PS 58-070580176330
D.O.E. No. 4440
Dear Mr. Conlon:
The attached is a man-hour and cost breakdown for additional engineering services
related to:
• Prepare additional exhibits for City of Fort Worth/City of Benbrook Cost
Sharing
• Participate in additional coordination meetings between the City of Fort
Worth and the City of Benbrook
• Prepare additional cost estimates for cost sharing between the City of
Fort Worth and the City
• Prepare additional easements
• Review and approval of submit als for the construction contract
This will amend the contract as following:
• Original contract = $111,509.00
• Amendment No. 1 -' $5,000.00
• Amendment No. 2 = $19,320.00
• Amendment No. 3 = $12,090.00
• TOTAL CONTRACT FEE _ $147,919.00
Please give me a call at 817-735-2889 if you need additional information and/or have
any questions.
Sincerel
Kathy Pontesso, P.E.
Associate
ores, Irc. Ccrtar&Burgess Consultants, Inc.
r.c. C&B Architects/Engineers,P.C. C&B Nevada,Inc. nn 671
t
AMENDMENT NO.3
SERVICES
The following services have been performed by Carter&Burgess,Inc.(ENGINEER)for the City of Fort Worth(CITY). These services appear to be
above the original scope in our original contract.
COMPENSATION
PROJ MGR: Kathy Pontesso, P.E. 07/14/06
JOB-Walnut Creek Sewer Phase 1 T 04:32 PM
MANHOURS TOTAL
TASKS PROJECT I PROJECT TASK
MANAGER ENGINEER CADD TECH. CLERICAL SURVEY COST
SERVICES&COMPENSATION
Pre are additional exhibits for cost sharing 4 8 16 2 $3,630
Coordination Between the City&Benbrook 10 10 2 $3,090
Preparing Cost Estimates Due to Cost Sharing
Material Pricing(minimum 6) 12 6 6 $3,120
Pre are Additional Easement 10 $1,250
Review of submittals ,or project construction 8 $1,000
GRAND TOTAL 26 32 16 10 10 0 $12,090
i
I
TOTAL MAN-HOURS PER DISCIPLINE 26 32 16 10 10 0
AVERAGE HOURLY SALARY RATE PER DISCIPLINI $175.00 $125.00 $115.00 $45.00 $125.00 $0.00
TOTAL JOB COST PER DISCIPLINE $4,550.00 $4,000.00 $1,840.00 $450.00 $1,250.00 $0.00
PERCENT OF TOTAL JOB HOURS PER DISCIPLINE 28% 34% 17% 11% 11% 0%
PERCENT OF TOTAL JOB COST PER DISCIPLINE 38% 33% 15% 4% 10% 0%
TOTAL SALARY COST $12,090.00
TOTAL JOB HOURS 94
�� TES