HomeMy WebLinkAboutContract 33913 AMENDMENT NO. 2
STATE OF TEXAS $ CITY SECRETARY CONTRACT NO.
(No M&C Needed)
COUNTY OF TARRANT 8
WHEREAS, the City of Fort Worth (City) and Brown & Gay Engineer,
Inc. , (Engineer) made and entered into City Secretary Contract No. 33371,
(the Contract) which was authorized by the City Council by M&C C-21348 on
the 21st day of March 2006; and subsequently revised by one previous
amendment; and
WHEREAS, the Contract involves engineering services for the
following project:
Engineering Design Services: Street Reconstruction, Water and Sewer
Replacement on Blackmore Avenue (Provost St to Hervie St) , and Kilpatrick
Avenue (Eldridge St to E Dead End from Hervie St to Bourine St) , 2004 CIP
Contract Year 3, Contract 35, Project No. 00292; DOE No. 5146
Water Project No. P253-6071700292
Sewer Project No. P258-7071700292
WHEREAS, it has become necessary to execute Amendment No. 2 to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their
duly authorized representatives, enter into the following agreement which
amends the Contract:
1.
Article I of the Contract is amended to include the additional
engineering services specified in a proposal letter dated July 6, 2006, a
copy of which is attached hereto and incorporated herein. The cost to
City for the additional design services to be performed by Engineer total
$3,189.25.
2.
Article II of the Contract is amended to provide for an increase in
the maximum fee to be paid to Engineer for all work and services
jRIGINAL
performed under the Contract, as amended, so that the total fee paid by
the City for all work and services shall not exceed the sum of
$107, 636.25.
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the day of m4, 2006, in Fort Worth,
Tarrant County, Texas.
ATTEST:
f)L NO M&C REQUIRED
Marty Hendrix
City Secretary
APPROVAL RECONdENDED: APPROVED:
A. Douglas Rademaker, P.E. Marc A. Ott
Director, Department of Assistant City Manager
Engineering
Brown & Gay Engineers, Inc.
ENGINEER
By:
Name: A. Lee Head, III. P.E.
Vice President
108 West 8t' Street, Suite 200
Fort Worth, Texas 76102
APPROVE TO FO AND GALITY:
Assistant it Attorney
6Ve
BROWN
& G Y
ENGINEERS, INC.
July 6, 2006
Mr. Gopal Sahu, P.E.
Senior Professional Engineer
The City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102
Re: Amendment No. 2 - Sanitary Sewer Extension
2004 CIP Neighborhood Street Project for
Blackmore Avenue (Prevost Street to Hervie Street)
Kilpatrick Avenue (Eldridge Street to East Dead End)
Kilpatrick Avenue (Hervie Street to Bourine Street)
YEAR 3, CONTRACT 35, PROJECT NO. 00292
Dear Mr. Sahu:
With regard to the additional professional services required for the additional sewer line (Laterals 4520
and 4523) added to the scope at the request of the Water Department for the Blackmore-Kilpatrick CIP
project (Contract 35), we are proposing to provide these additional services for a total of$3,189.25.
The breakdown of proposed cost is as follows:
$2,400.00 Brown & Gay Engineers, Inc. - Engineering Services
$ 717.50 ANA Consultants, Inc. - Surveying Services
$ 71.75 10% mark-up
3,189.25
We are available to meet with you at your convenience to discuss this matter further if you desire.
Sincerely,
W- -
Carl J. Krogness, P.E.
Project Manager
Enclosures
cc: Ms. Dena Johnson, P.E., City of Fort Worth, DOE
Mr. A. Lee Head, III, P.E., Brown& Gay Engineers, Inc. RR
ARRPP
CITY �NUHTAPY
U
TO,
+;uw ;
108 West 8th Street Suite 200 Fort Worth,Texas 76102 TEL:817-887-6130 FAX:817-887-6135 EMAIL:bge@browngay.com
BROWN Date: June 23, 2006 -
BGE Job Number: COF 01
& GAY ENGINEER'S PRELIMINARY OPINION OF CONSTRUCTION COST
ENGINEERS, INC. L-4520&L-4523 SEWER REPLACEMENT
PROJECT NAME: YEAR 3 CONTRACT 35-CITY PROJECT NUMBER#00292
Blackmore Ave. (Prevost St. to Hervie St.), Kilpatrick Ave. (Eldridge St. to East
Dead End)&Kilpatrick Avenue(Hervie St. to Bourine St.)
Project Manager: Gopal Sahu, P.E.
ITEM DESCRIPTION UNIT I QUANTITY UNIT TOTAL
NO. PRICE AMOUNT
Sewer Improvements- Kilpatrick Ave.(Eldridge St.to East Dead End)
1 8"PVC Sanitary Sewer-Open Cut(All Depths) LF 401 $ 35.00 14,035
2 8"(DR-26)PVC Sanitary Sewerw/Cement Stabilized Backfill LF 0 $ 34.00 -
3 8"Sanitary Sewer-By Other than Open Cut LF 0 $ 175.00 -
4 6"to 8"HDPE Sanitary Sewer by Pipe Enlargement LF 0 $ 55.00 -
5 Sag Adjustment for Pipe Installed by Pipe Enlargement Method LF 0 $ 95.00 -
6 Standard 4' Diameter Sanitary Sewer Manhole EACH 1 $ 2,400.00 2,400
7 Standard 4'Diameter Sanitary Sewer Drop Manhole EACH 0 $ 3,000.00 -
8 Extra Depth for Sanitary Sewer Manhole VF 0 $ 125.00 -
9 Watertight Manhole Inserts EACH 1 $ 80.00 80
10 Concrete Collars EACH 1 $ 200.00 200
11 Interior Corrosion Protections for SSMH VF 0 $ 150.00 -
12 4"Sanitary Sewer Service Connection EACH 7 $ 250.00 1,750
13 4"Sanitary Sewer Service Lead LF 145 $ 22.00 3,190
14 4"Sanitary Sewer Service Two Way Cleanout w/Housing &Rise EACH 7 $ 150.00 1,050
15 6"Thick Topsoil SY 31 $ 11.00 341
16 Sodding LF 50 $ 12.00 600
17 Remove Existing Manhole EACH 1 $ 200.00 200
18 Vacuum Test Manhole EACH 2 $ 150.00 300
19 Temporary HMAC Pavement Repair LF 0 $ 8.00 -
20 Concrete Pavement Repair(Fig. 1) LF 0 $ 5D.00 -
21 HMAC Pavement Repair(Fig.4) LF 430 $ 35.00 15,050
22 Trench Excavation Safety Protection for Sewer LF 401 $ 2.00 802
23 Pre-Construction TV Inspection LF 401 $ 1D.00 4,010
24 Post-Construction TV Inspection LF 401 $ 10.00 4,010
25 Pre-Construction D-Hole for Sewer EACH 0 $ 450.00 -
26 Remove& Replace Concrete Curb&Gutter LF 15 $ 12.00 180
27 Remove& Replace Existing Fence LF 80 $ 25.00 2,000
28 Crushed Limestone for Misc. Placement CY 10 $ 10.00 100
29 Type E(1500 psi)Concrete for Misc. Placement CY 5 $ 50.00 250
Sewer Improvements Subtotal $ 33,983
Contingencies(10%) $ 3,400
Sewer Improvements Total $ 37,383
- - -- - ($37,383-x-0.075 x-0.85)- Engineering-per-Curve A $ 2,400 - -
Additional Survey $ 717.50
Sub Mark-up $ 71.75
Total Estimated Budget Increase $40,500.50