CCONTRACT No. �-q4a 5-42-
��GC AMENDMENT No.2
TO CITY SECRETARY CONTRACT
WHEREAS, the City of Fort Worth (CITY) and Neel-Schaffer,
Inc. , (ENGINEER) made and entered into City Secretary Contract
No. 49485, (the CONTRACT) which was authorized by M&C C-28302
on the 19t day of August, 2017 in the amount of $458,204 . 00;
and
WHEREAS, the CONTRACT was subsequently revised by:
Amendment No. 1 in the amount of $14, 980 . 00 administratively
authorized on May 30, 2018; and
WHEREAS, the CONTRACT involves engineering services for
the following project:
Churchill Road Water and Sanitary Sewer Improvements; and
WHEREAS, it has become necessary to execute Amendment No.
2 to the CONTRACT to include an increased scope of work and
revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and
through their duly authorized representatives, enter into the
following agreement, which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the
additional engineering services specified in a proposal dated
November 9, 2018, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional
design services to be performed by Engineer totals $58,341 . 00
(Water: $47,418 .00; Sewer: $10, 923.00) .
2 .
Article II of the CONTRACT is amended to provide for an
increase in the fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall be
an amount of $531,525 . 00 .
3.
All other provisions of the Contract, which are not
expressly amended herein, shall remain in full force and
effect.
p OFFICIAL RECORD
Page -1- CITY SECRETARY
FT. WORTH,TX
EXECUTED and EFFECTIVE as of the date last written by a
signatory, below.
APPROVED: ENGINEER
City of Fort orth Neel-Schaffer, Inc.
esus J. apa James P. Amick, P.E.
Assistant City Manager Engineer Manager
DATE: DATE: 12 --13 '/?
APPROVAL RECOMMENDED:
1, (t L
Chris Harder, P.E.
Director, Water Department
APPROVED AS TO FORM AND LEGALITY:
Contract Compliance Manager:
By signing, I acknowledge that I am
the person responsible for the
monitoring and administration of
this contract, including ensuring
all performance and reporting
requirements .
aalle of T-1--
J.14 L .Loyee
YoA� '--A- "
M&C: N/A
Title: Project Manager
2Ria'7— Date: N/A
Douglas W. Black
Senior Assistant City Attorney ,., --
.�`��
ATTEST
Mary J. Kayser
City Secretary OFFICIAL RECORD
CITY SECRETARY
Page -2- FT. WORTH,TX
BL HEEL-SCHAFFER
® Solutions you can build upon
November 9,2018
Mr. Lawrence Hamilton,P.E.
Sr. Professional Engineer
City of Fort Worth- Water Department
311 West 10th Street
Fort Worth, Texas 76102
Reference: Churchill Road Water and Sanitary Sewer Improvements Contract Amendment 2
for Additional Services to Revise Alignments of 24" and 8" Water Lines, and 8"
Sewer Lines; and to Study a Proposed 12"Water Line in Jacksboro Highway(SH
199)from Ephriham Avenue(SH 183)to West Long Avenue
Dear Lawrence:
Neel-Schaffer, Inc. offers additional Professional Engineering Services for this project. These
additional services were requested by the City of Fort Worth for four reasons. First, to generally
move the proposed 8"water lines from their designed locations adjacent to the existing 12"or 6"
water lines to locations coinciding with the existing water lines to the extent feasible. Second, to
allow more separation of the proposed 24" water line from water lines operated by the City of
River Oaks. Third, to allow more separation of the proposed 24"water line and the proposed 8"
water line. Fourth, to prepare a preliminary study (feasibility, alignment and tentative
construction cost)for approximately 1,800' of a 12"line for this section.
The study would include: data collection for existing records from Fort Worth (CITY GIS Data,
Aerial Topography, Planimetrics, etc.) of water, sewer, drainage, paving, plats, available
easements; data collection from TxDOT for the State Highways; a site visit; development of
three potential horizontal alignments and typical cross sections; one conceptual plan view
drawing at 40 scale with two plan views that shows the potential alignments; one typical section
sheets that shows the three options; preparing conceptual opinions of probable construction cost
for the alignments; preparing a letter report; and attending a kickoff meeting and a review
meeting.Modeling is not included.
Neel-Schaffer, Inc. proposes to increase the contract amount by $58,340.00 for these additional
services which will include redesign for approximately 6,300' of 24" water line, about 8,000 of
8" water line and around 3,000' of sanitary sewer line; and the study. All additional services will
be performed in accordance with the original contract dated August 9, 2017.
0:Uobs\14056-Churchill Road Water and Sewer\Admin\Contract\Am 2\Amendment 2 Letter-Revised.doc
ARLINGTON • DALLAS • FORT WORTH • HOUSTON
engineers • planners • surveyors • environmental scientists • landscape architects
515 Houston 5t., Ste. 751 • Fort Worth, TX 76102 • ph: 817-870-2422 • fax: 817-870-2489 • www.neel-schaffer.com
Mr. Lawrence Hamilton,P.E.
November 9,2018
Page 2 of 2
Summary of Contract Fee
Original Contract Amount $458,204.00
Amendment No. 1 $14,980.00
Proposed Amendment No. 2
Water $47,418.00
Sewer $10.922.00
Subtotal $58,340.0
Revised Contract Amount $531,524.00
Based on the likely start date of the work contained in this amendment, the original schedule will
be adjusted as follows:
• Final design will be submitted approximately three months after receipt of this approved
amendment.
• The study will also be submitted approximately three months after receipt of this
approved amendment.
The remaining tasks in the schedule will be adjusted accordingly.
If you have any questions or we may be of further service,please call me at 817/870-2422.
Sincerely,
NEEL-SCHAFFER,
r
James P. Amick, P.E.
Engineer Manager
TBPE Finn Reg.No.F-2697