AMENDMENT No. 2
CITY SECRETARY CONTRACT NO. �_���
(No M&C Needed)
WI�REAS, the City of Fort Worth (City) and RJN Group, Inc., (Engineer) made and
entered into City Secretary Contract No. 29213, (the Contract) which was authorized by the City
Council by M&C C-19775 on the 30th day of September 2003; and
WHEREAS, the Contract involves engineering services for the following project:
Engineering Services For:
2004 Capital Improvement Projects
D.O.E. No. 3910: New York Avenue From Rosedale Rd. to E. Terrell St.
CONTRACT 99JJ: Sewer and Water Line Replacements — Various Locations
CONTRACT 99LL: Sewer and Water Line Replacements — Various Locations
WHEREAS, it has become necessary to execute Amendment No. 2 to said Contract to
include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their duly authorized
representatives, enter into the following agreement which amends the Contract:
1.
Article I of the Contract is amended to include the additional engineering services specified
in a proposal letter dated August 22, 2006, a copy of which is attached hereto and incorporated
herein. The cost to City for the additional services to be performed by Engineer total $11,510.00
2.
Article II of the Contract is amended to provide for an increase in the maximum fee to be
paid to Engineer for all work and services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not exceed the sum of $181,976.55.
y ; • ',
. 3. �'.l�i�,; __.
_ S .. � , r . . " ' . . . �.'..I
�
All other provisions of the Contract which are.not expressly amended herein shk�ll remain in
full force and effect. �'- -
1/12I2007 -1- � O�'�'NQL
EXECUTED on this the
Texas.
APPROVAL RECONIlVIENDED
r� �
oL day of I ,
A. Douglas Rademaker, P.E.
Director, Department of Engineering
RJN GROUP, INC.
By: !.�
Hugh . Kelso
Vice President
APPROVED AS TO
�r��be�ge�- �
Assistant City Attorney
AND LEGALITY:
1/12/2007 -2-
2007 , in Fort Worth, Tarrant County,
�Pr�vED- � �,
� ° � -- _
�
; �
B : , � ,.�,;✓.�_. . _ �
y r
Marc Ott �
Assistant City Manager
ATTEST:
I�� '
Mariy Hendrix, Secretary
�� M��:� ��f���iJ��1��3
�� ��
;;���J���i�`=':l. ����5���"�,;:.:,� �.
c �.�v ::�:,
�jy��� u,'�i,:,'�u�i,;,,,i',t�J;'
� ,... �,� :,1�,
�
� � ; "f;�..� ";�� 7r �12i ,�
Y ���: .. .. .. �. � ' f
SCOPE OF SERVICES
AMENDMENT 2
CITY OF FORT WORTH
SANIARY SEWER AND WATER LINE REPLACEMENTS
CONTRACT 99JJ AND CONTRACT 99LL
2004 CIP — NEW YORK AVENUE RECONSTRUCTION
Original Contract No. — 29213
Date: September 30, 2003
Original Contract Value - $1,46,734.55
Amendment No. 1
Date: February 28, 2005
Amendment Value - $23,732.00
Amended Contract Value - $170,466.55
Reference No.: C-19775
Sewer Project No.:
Water Project No.:
T&PW Project No.
DOE No.'s: 99JJ -
99LL -
PS58-531200-070580175060
PW53-531200-060530175800
C ll 5-531200-020115095502
2981, 2982, 2983, 2984, 2985
2981, 2982, 2983, 2984, 2985
In accordance with direction received from the City of Fort Worth Department of Engineering, RJN
Group is pleased to submit this amendment for additional design services rendered on the above reference
proj ect.
The following is a description of the tasks that the ENGINEER will perform as part of Amendment No. 2.
Work includes:
Preparation of Plan and Pro�le sheets on 1"=20' Horizontal and 1"=4' Vertical scale for replacement of
pavement, including curb, on Medina Avenue, Wosley Drive, and Wessex Avenue. Total length of
improvements is approximately 4,955 LF.
Station 0+00 to station 19+65 Medina Avenue: Provide P&P sheets showing existing top of curb,
right of way and proposed top of curb profiles, proposed top of curb elevations at half and full
stations in profile view and proposed driveway approach replacements in plan view. Maintain
existing top of curb profile, where possible.
Verify all driveway profiles for grade change not to exceed 15 %.
Station 0+70 to Station 14+15 Wessex Avenue: Provide P&P sheets showing existing top of
curb, right of way and proposed top of curb profiles, proposed top of curb elevations at half and
full stations in profile view and proposed driveway approach replacements in plan view.
Maintain existing top of curb proiile, where possible.
Verify all driveway profiles for grade change not to exceed 15 %.
Station 0+35 to Station 16+80 Wosley Avenue: Provide P&P sheets showing existing top of
curb, right of way and proposed top of curb profiles, proposed top of curb elevations at half and
Page 1 of 3
full stations in profile view and proposed driveway approach replacements in plan view.
Maintain existing top of curb profile, where possible.
Verify all driveway pro�les for grade change not to exceed 15 %.
In addition, Plan and Profile sheets on 1"=20' Horizontal and 1"=4' Vertical scale for replacement of
asphalt paving on Atkins Street and Riley Street. Total length of improvements is approximately
1,088 LF.
Station 0+44 to station 7+30 Atkins Street: Provide P&P sheets showing existing and proposed
asphalt centerline profiles, existing R.O.W. pro�les, proposed centerline elevations at half and
full stations in profile view and typical cross section of paving with a straight cross slope, in plan
view.
Station 0+39 to station 4+41 Riley Street: Provide P&P sheets showing existing and proposed
asphalt centerline profiles, existing R.O.W. profles, proposed centerline elevations at half and
full stations in proiile view and typical cross section of paving with a crown (City of Ft. Worth
Street Standards, Alternative (ETJ) Local - Option A Figure 11 and Residential Streets Figure
12.), in plan view.
Verify type and condition of 36-inch existing drainage pipe, far reuse in this project.
The following fee proposal is based on the current approved hourly rate schedule on City contracts. Fees
to perform Basic Services and Special Services are as follows:
I : _:j.`Js�l.y���/5�.�
Pavement P&P Sheets
Sta. 0+00 to Sta. 19+65
Sta. 0+70 to Sta. 14+15
Sta. 0+35 to Sta. 16+80
Sta. 0+44 to Sta. 7+30
Sta. 0+39 to Sta. 4+41
Medina Avenue $3,540.00
Wessex Avenue $2,325.00
Woolsey Avenue $2,990.00
Atkins Street $1,125.00
Riley Street $1,230.00
SPECIAL SERVICES:
Other Direct Costs (Printing, postage, mileage, etc.) $280.00
Subconsultant Administration Fee (10% of 200) $20.00
TOTAL FEE PROPOSAL $11,510.00
M/WBE PARTICIPATION (Goa1= 23.00 %)
Task
Printing
M/WBE Firm
LA Blueline
Page 2 of 3
Dollars
$200.00
Participation
Percent
1.74%
M/WBE
Contract
Amendment No. 1
Amendment No. 2
Total
Less Subcontract Fee
Total Value
$146,734.55
$23,732.00
$11,510.00
$181,976.55
$4,224.75
$177,751.80
Page 3 of 3
M/WBE Value
$39,987.50
$2,056.00
$200.00
$0.00
$42,243.50
M/WBE Percent
23.77%
City of Fort Worth, Texas
Mayor and Council
Commun�cation
COUNCIL ACTION: Approved on 4/3/20U7 ��`�
DATE: Tuesday, April 03, 2007 --�-_.,� __
LOG NAME: 3000NTRACT99LL REFERENCE NO.: **C-22035
SUBJECT:
Authorize Amendment No. 2 to Engineering Agreement with RJN Group, Inc., for
Water Department Contract 99 LL, Sanitary Sewer and Water Line
Replacements on Various Streets
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute
Amendment No. 2 to City Secretary Contract No. 29213 with RJN Group, Inc., for the
preparation of paving plans and profiles on Water Department Contract 99 ita
Sewer and Water Line Replacements on various streets in the amount of $11,510.00;',
thereby, increasing the total contract amount to $177,751.80.
��
DISCUSSION:
On September 30, 2003, (M&C C-19775) the City Council authorized the City Manager
to execute an engineering agreement with RJN Group, Inc., for the preparation of paving
plans and profiles on Water Department Contract 99 LL, Sanitary Sewer and Water Line
Replacements on various streets for a fee not to exceed $146,7��_ 55._ This agreement
was previously revised by one amendment.
Amendment No. 1 was administratively approved on February 28, 20�5 in the amount of
$23,732.00 for additional sanitary sewer and water line design requested by the Water
Qepa�ment.
This amendment, No. 2, provides for design of plans and profiles for various streets
under Water Department Contracts 99JJ and 99LL requested by the Water Department
for paving rehabilitation to be constructed under street maintenance program after the
sanitary sewer and the water lines are constructed. These services were not included in
the , original scope.
City staff considers the proposed fee of $11,510.00 to be fair and reasonable for the
scope of additional services � to be performed.
This project is located in COUNCIL DISTRICTS 3,6,8 and 9, Mapsco 77K, T, X and 90E,
J, L , U and 61T and 91 B, C.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current capital budget, as
appropriated, of the Sewer Capital Projects Fund.
TO Fund/Account/Centers FROBA Fund/Account/Centers f,--__
PS58 531200 �70580175060 �$11,510�00 �
__..�—
Submitted for Citv Manaper's Office bv: Marc Ott (5476)
Oriqinatinq Department Head:
A. Douglas Rademaker (6157)
Additional lnfiormation Contact: Gopal Sahu (7949)