HomeMy WebLinkAboutContract 51012-AR1 CITY SECRETARY FORT WORTH City of Fort Worth CONTRACTNO. Construction Allowance Request Breakdown Construction CA# 0 Date 12/3/2018 City Sec# 1 51012 Client Project#(s)l 101333 FAC#(s) Project Name HMAC(2018-4)HIR Street Rehabilitation Description Contractorl Cutler Repaving, Inc. City Inspector Jarad Souders Funding TPW Select Day Type Allocation Account Totals Original Contract Amount $1,865,363.60 $1,865,363.60 Extras to Date Credits to Date Current Contract Amount $1,865,363.60 $1,865,363.60 Amount of Proposed Allocation $48,750.00 $48,750.00 Original Allowance Available for Allocation $102,443.00 $102,443.00 Allowance Funds Previously Allocated Remaining Funds Available for this Allocation $102,443.00 $102,443.00 _ JUSTIFICATION SUMMARY The City requested Surface Milling be performed on International Plaza. The original bid sheet only has an item for Wedge Milling.This Construction Allowance add the bid item for Surface Millling It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and satisfaction and represents payment in full for all costs arising out of,or incidental to,the above Construction Allowance Request.Contract Time will be adjusted on the basis of the time shown on this Construction Allowance Request by a later Change Order,if necessary. pEC \-00 circ�r S�caEta��c FORT WORTH® City of Fort Worth Construction Allowance Request Breakdown Construction FOA# 1 Date 12/3/2018 Client Project#(s) 101333 FAC#(s) Project Name HMAC(2018-4)HIR Street Rehabilitation Description Contractorl Cutler Repaving, Inc. City Inspector C ADDITIONS ITEM MCPIPTIM ep yUnit' Surface Milling Change Order Additions Page 1 of 4 Sub' Change Order Additions Page 2 of 4 City Sec# 51012 Jarad Souders Unit os o a Change Order Additions Page 3 of 4 TPW $48,750.00 Total Additions 75 .0 Change Order Additions Page 4 of 4 75 0 N O L N O O C N U O C Cn (d _T (O U � c `o C ❑ Q W U O U LiJ N ami m L � m 00 7 c,4 W V) O rt= o L Li c Q O 3 o U Q z C D_ s U V — � }1 L _ Z V D � U = C O) �Y C 06 (O co 2 U m Q m Q UQLL U)c U d o C O d �T 2 U wo cn 0 U C) 0 0 0 c 0 Cl ia_ Fz H 0 F- CO N O N N OA f0 d C O .I- _v v ttov v C co L U MIWBE Breakdown for this Construction Allowance Request MWBE Sub Type of Service Amount for this FOA N/A Total $0.00 Previous Construction Allowance Requests CO# DATE AMOUNT N/A Total $0.00 CFW Construction Allowance Request Approval CAAppr-01 Page 1 of 3 Routing Assigned To: Due Date: Assigned By: Due Time: Links 1 fortworthgov/Infrastructure Projects/101333 - HMAC 2018-04 HIR Street Rehab/Contractor/Change Orders/Constr Allow Request Breakdown #1R 2018-4.xlsm Attachments(0) No Attachments have been added to this form. https://projectpoint.buzzsaw.com/ bz_web/Forms/FonnPrint.aspx?Siteld=51500&Proces... 12/31/2018 CFW Construction Allowance Request Approval CAAppr-01 Page 2 of 3 FORT WORTH., City of Fort Worth Construction Allowance Request Approval (Construction Allowance Breakdown Available in Links) For Construction Allowance Submittal No.: 1 Construction Allowance Request Approval No.: CAAppr-01 Date Started: 2018-12-04 Date Due: 2019-01-23 City Sec. No.: 51012 Project Name: 101333 - HMAC 2018-04 HIR Street Rehab Project Numbers: 101333 DOE Numbers: Project Removal and replacement of non-functional curb&gutter, Description: driveways sidewalks and pavement remarkings, followed by a HIR overlay of 1" HMAC. Project/Contract Compliance Kristian Sugrim City Inspector: Jarad Souders Manager: Contractor: Cutler Repaving, Inc. COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: TPW $ 48,750.00 30100-0200431-5740010-101333-0 Total Cost: $ 48,750.00 Total Requested Days: 0 Approval Status: https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&Proces... 12/31/2018 CFW Construction Allowance Request Approval CAAppr-01 Page 3 of 3 Approved: Yes Comments: User: Lane Zarate Date: 2018-12-05 3:59 PM Approved: Yes Comments: User: Ricardo Matute Date: 2018-12-10 10:59 AM Approved: Yes Comments: User: Signing for TPW Director Role Approvals Date: 2018-12-10 1:18 PM Approved: Yes Comments: User: Doug Black Date: 2018-12-17 6:35 PM OF FO�T A7 C) Approved: Yes Comments: User: Susan Alanis 94ar� S8 , City Secr4q " Date: 2018-12-28 2:50 PM Action Required: OFFICIAL RECORD f CITY SECRETARY FT. WORTH,TX https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?SiteId=51500&Proces... 12/31/2018 Contract Compliance Manager: By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Kristian Sugrim /Name of of Employee/Signature Project Manager Title ❑ This form is N/A as No City Funds are associated with this Contract Kristian Sugrim /Printed Name Name Signature OFFICIAL RECORD CITY SECRETARY FT. WORTH,TX