HomeMy WebLinkAboutContract 50567-CO2 CITY SECRETARY FORT WORTH® City of Fort worth CONTRACT NO. 50 5lo- _ � Change Order Request Breakdown Project Name HMAC 2017-5 Street Rehabiliation at Various Locations City Sec# 1 50567 Client Project#(s)l 101265 Contractor JLB Contracting,LLC PM Kristian Sugrim Inspectorl Martina Salinas Change Order Submittal# 0 Date 12/4/2019 Dept. T/PW Contract Time Totals (C D) Original Contract Amount $1,945,950.00 $1,945,950.00 210 Extras to Date $60,604.10 $60,604.10 36 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $2,006,554.10 $2,006,554.10 246 Amount of Proposed Change Order $23,223.80 $23,223.80 48 Revised Contract Amount 2,029,777.90 $2,029,777.90 294 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(ff necessary) F $23,223.80 $23,223.80 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 4,3101 MAXALLOWABLECONTRACTAMOUNT(ORIGINAL CONTRACTCOST+25%) $2,432,437.50 JUSTIFICATION"ONS)FOR OHANG�CRDE This Change Ordef s.-brrim will provide for the removal and replacement.--f broken innhc:c-collars on the milled of OvertoNew pay items were also required for the import of topsoil for backfilling new curb and gutter and sealing the cracks on Grace after the surface aspahlt was milled. The change order also adds flatwork quantities for Marshall,which was added to the project. Additional days are requested for the abnormal weather encountered in August,September and October,as well as the added project Marshall. 6, 56 7 ,891 P OFFICIAL RECORD CITY SECRETARY 681 g 9V�'� FT WORTH,TX City of Fort worth Change Order Additions Project Name HMAC 2017-5 Street Rehabiliation at Various Locations City Sec# 50567 Client Project# 101265 Contractor JLt3 Contracting,LLC PM Kristian Sugrim Inspector Martina Salinas Change Order Submittal# 0 Date 12/4/2019 AUDI l TUNS y Unit Unitos o a new Crack Sealing ---T- 7FFne-w-T Remove&Replace Concrete Manhole CollarI.uuuuuuuu 3TTn-e-wT Topsoilor Backfill ----TY-- Remove Valley Gutter . Valley Gutter Remove ADA Ramp 12 ADA Ramp T/PW $23,223.80 Sub Total Additions 23,223.8 Change Order Additions Page 1 of 1 FORT WORTH City of Fort Worth rte-- Change Order Deletions Project Name HMAC 2017-5 Street Rehabiliation at Various Locations City Sec# 50567 Client Project# 101265 Contractor JLB Contracting,LLC PM Kristian Sugdm Inspector Martina Salinas Change Order Submittal# 0 Date 124/2019 ULLLI IUM Unit Unit os o a T/PW $0.00 Sub Total Deletions $u.u0 Change Order Deletions Page 1 of 1 M/SBE Breakdown for this Change Order M/SBE Sub Type of Service Amount for this CO None Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 CFW Change Order Approval COAppr-02 Page 1 of 3 Routing Assigned To: Due Date: Assigned By: Due Time: Links 1 fortworthgov/Infrastructure Projects/101265 - HMAC (2017-5)/Contractor/Change Orders/change order 2 - marshall & sealing on grace/Change Order Breakdown - co2 mh crack seal marshall.xlsm Attachments(0) No Attachments have been added to this form. https://projectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?SiteId=51500&ProcessI... 1/16/2019 CFW Change Order Approval COAppr-02 Page 2 of 3 FORT WORTH. C'ty of Fort Worth ---. i.-.�- Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: 2 Change Order No.: COAppr-02 Date Started: 2019-01-09 City Sec. No.: 50567 Date Due: 2019-02-28 Project Name: HMAC (2017-5) 101265 DOE Numbers: Project Numbers: Project Removal and replacement of nonfunctional curb and gutter, Description: driveways and sidewalks, followed by the pulverization and stabilization of the existing pavement and a surface overlay of 2" HMAC. Project/Contract Compliance Kristian Sugrim City Inspector: Martina Salinas Manager: Contractor: JLB Contracting, LLC. COUNCIL ACTION (If Required): M&C Log Name: M&C Number: M&C Date: COST AND DAYS SUMMARY: Requested Department: Cost($) Fund Account Center: Days: TPW $ 23,223.80 30100-0200431-5740010-101265-0 48 Total Cost: $ 23,223.80 Total Requested Days: 48 Approval Status: https://proj ectpoint.buzzsaw.com/_bz_web/Forms/FormPrint.aspx?Site1d=51500&ProcessI... 1/16/2019 CFW Change Order Approval COAppr-02 Page 3 of 3 Approved: Yes Comments: User: Sam Davis Date: 2019-01-09 11:20 AM Approved: Yes Comments: User: Kristian Sugrim Date: 2019-01-09 11:46 AM Approved: Yes Comments: User: Lane Zarate Date: 2019-01-09 6:29 PM Approved: Yes Comments: User: Ricardo Matute Date: 2019-01-09 12:58 PM Approved: Yes Comments: User: Signing for TPW Director Role Approvals Date: 2019-01-09 5:36 PM Approved: Yes Comments: User: Doug Black Date: 2019-01-11 9:15 PM �ORri Atte y: _ I v�,• � .•.. Approved: Yes Comments: _ 2 User: Susan Alanisgar� J. y , City eae Date: 2019-01-16 12:48 PM Action Required: 1t0MCIAL RECORD MY SECRETARY 7T. WORTH,TX https://projectpoint.buzzsaw.com/ bz web/Forms/FomiPrint.aspx?SiteId=51500&ProcessI... 1/16/2019 Contract Compliance Manager Re: Change Order No. 2 ($23,223.80) Contractor: JLB Contracting, LLC. Project Name: HMAC 2017-5 Street Rehabilitation City Secretary No.: 50567 Project No.: 101265 By signing, I acknowledge that I am the person responsible for the monitoring and administration of this contract including ensuring all performance and reporting requirerrtents. -` Name of Employee Prolect Manager Title �`)FFICIAL RECORD CITY SECRETARY EI T. WORTH,TX