Construction Allowance Request CONTRACTNO., ._ - a
Project Namel Northside 11 48"Water Main Phase II,Part I City Sec No. 48783
Project No.(s) 56011-0600430/0700430-CO 1788 M&C: C-28106 City Proj.No. 2304
Project Description: 48-inch Water Main installation from Heritage Trace Parkway/Harmon Road Intersection to Wagley Robertson Road
Contractor: S.J. Louis Construction of Texas, LTD Allowance No: 0 Date: 1/8/2019
City Project Mgr.1 John Kasavich City Inspector: Raymond Brice
Phone Number: 817-392-8480 Phone Number: 817-392-8452
Dept. Unit I NS II Water Unit 11 36"Water Unit III Sewer Totals Contract Time
(Calender days)
Original Contract Amount $8,920,223.00 $438,130.00 $523,777.00 $9,882,130.00 620
Previous Allowances Allocated $0.00 $11,200.57 $0.00 $11,200.57
Amount of Proposed Allocation $40,000.02 $40,000.02
Original Allowance Available for Allocation $300,000.00 $50,000.00 $50,000.00 $400,000.00
Remaining Funds Available for this Allocation $300,000.00 $38,799.43 $50,000.00 $388,799.43
Revised Contract Time 620
STIFICATION (REASONS)FOR ALLOWANC -
Allowance No. 2 will reimburse the contractor for having to demobilize and remobilize of the project site
until a permanent easement was acquired for a large tract property located close to the end of the project.
Staff had anticipated that the easement would be acquired shortly after bids were received on the project,
however, it took over a year to secure the easement.
0R7,
�0
RECEIVED tnald
JAN 18 2019CITY OF FORT WORTHCiTYSFCRru,e� A s City Se6>net8ly';
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and satisfaction and
Contractor's Name Contractor Name - --
S.J.Louis Construction of Texas,LTD Adam Lunsford u
Itmeft
r
Date - Date
Date Date
_l6�
�.�. W.
FORT WORTHCity of Fort Worth
vl'"l- _ Construction Allowance Request
Project Name Northside 1148"Water Main Phase ll,Part I I City Sec No. 48783
Project No.(s) 56011-0600430/0700430-C01788 M&C: C-28106 City Proj.No. 2304
Project Description 48-inch Water Main installation from Heritage Trace Parkway/Harmon Road Intersection to Wagley Robertson Road
Contractor S.J. Louis Construction of Texas, LTD Allowance No: 0 Date: 11/29/2018
City Project Mgr. John Kasavich City Inspector FRaymond Brice
CONSTRUCTION ALLOWANCE ITEMS TO BE ADDED
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
53 Construction Contingency Unit I NS II Water 0.1333334 LS $300,000.00 $40,000.02
Unit I NS II Water $40,000.02
Additions Sub Total $40,000.02
IE:'—RT WORTH City of Fort Worth
Construction Allowance Request
Project Name Northside 1148"Water Main Phase II, Part I City Sec No. 48783
Project No.(s) 56011-0600430/0700430-CO1788 M&C: F C-28106 City Proj.No. 2304
Project Description 48-inch Water Main installation from Heritage Trace Parkway/Harmon Road Intersection to Wagley Robertson Road
Contractor S.J.Louis Construction of Texas, LTD Allowance No: 0 Date: 11/29/2018
City Project Mgr.1 John Kasavich City Inspector FRaymond Brice
CONSTRUCTION ALLOWANCE ITEMS TO BE ADDED
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
0.0000000 $0.00 $0.00
$0.00
Additions Sub Total $0.00
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
Signature
J
Name of Employee
Title
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH,TX