HomeMy WebLinkAboutOrdinance 23545-01-2019Ordinance No. 23545-01-2019
AN ORDINANCE INCREASING APPROPRIATIONS IN THE WATER AND SEWER
COMMERCIAL PAPER FUND, FROM AVAILABLE FUNDS IN THE AMOUNT OF
$3,028,892.00, FOR THE PURPOSE OF FUNDING THE WESTSIDE: V PART 1 ONE
MILLION GALLON ELEVATED WATER STORAGE TANK AND WATER MAIN PROJECT;
PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE
OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2018-2019 in the
Budget of the City Manager, there shall also be increased appropriations in the Water and Sewer Commercial
Paper Fund in the amount of $3,028,892.00, from available funds, for the Westside V Part 1 One Million
Gallon Elevated Water Storage Tank and Water Main Project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 23392-09-2018 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETAR�
Douglas Black ary J. Ka s
Sr Assistant City Attorney 1-1
ADOPTED AND EFFECTIVE: January 29. 2019
MAYOR AND COUNCIL COMMUNICATION MAP
60WSIDEVPIESTANK-LSTRUCTURES1
ui. r
a WHITE SETTLEMENT RD
L
J
J
0
PROPOSED ELEVATED
STORAGE TANK SITE
PROPOSED 24" & 16"
WATER MAIN
(VIAANOTHER CONTRACT)
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 1/29/2019 - Ordinance -No. 23545 a ;919
No. 5036-01-2019
DATE: Tuesday, January 29, 2019
LOG NAME: 60WSIDEVPIESTANK-LSTRUCTURES1
REFERENCE NO.: **C-29015
SUBJECT:
Authorize Execution of Contract with Landmark Structures I, L.P., in the Amount of $2,752,000.00 for
Westside V Part 1 One Million Gallon Elevated Water Storage Tank and Wainer Main Project, Provide for
Project Costs for a Total Project Total in the Amount of $8,206,184.00, Adopt Resolution Expressing
Official Intent to Reimburse Expenditures with Proceeds of Future Debt and ,Adopt Appropriation Ordinance
(COUNCIL DISTRICT 3)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds
of Future Debt for the Westside V Part 1 One Million Gallon Elevated Water Storage Tank and
Water Main Project;
2. Adopt the attached Appropriation Ordinance increasing appropriations in the Water and Sewer
Commercial Paper Fund in amount of $3,028,892.00; and
3. Authorize the execution of a contract with Landmark Structures I, L.P., in the amount of
$2,752,000.00 for the Westside V Part 1 One Million Gallon Elevated Water Storage Tank Project,
located in west Fort Worth and the City's Extra Territorial Jurisdiction (City Project No. 100378)
DISCUSSION:
Growth within west Fort Worth and its Extra Territorial Jurisdiction (ETJ) requires the installation of pump
stations, water storage facilities and transmission mains in order to provide reliable water service to
existing and proposed developments and as required for compliance with state regulatory requirements
related to public water system design and operations. On November 17, 2015, the City Council approved
the construction of a booster pump station to provide service to portions of the Walsh Ranch and
Morningstar developments.
This Mayor and Council Communication provides for the construction of a one million gallon elevated
water storage tank which will be connected to the existing pump station for improved levels of service.
Construction of the project was advertised for bid on November 15, 2018 and November 22, 2018 in the
Fort Worth Star -Telegram. On December 20, 2018 the following bids were received:
BIDDER 1AMOUNT iTIME OF COMPLETION
(Landmark Structures1 LP 1$2,752,000.00 465 Calendar Days
Logname: 60WSIDEVPIESTANK-LSTRUCTURESI Page 1 of 3
Phoenix Fabricators and Erectors, Inc. 1$2,933,560.00
lCaldwell Tanks, Inc. $3,247,000.00
In addition to the contract cost, $194,332.00 is required for Project Management, inspection and material
testing and $82,560.00 is provided for project contingency.
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer Fund.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation
authority authorized under the Callable Commercial Paper Program (CP) will be used to provide interim
financing for this project until debt is issued. To the extent resources other than the Water and Sewer
portfolio are used to provide interim financing, the Water and Sewer Fund w11I be charged interest that is
equivalent to the overall rate of return being earned by the City portfolio (currently approximately one -
percent annually). Should the City's portfolio not support the liquidity needed to provide an interim short-
term financing source, another funding source will be required, which could mean issuance of securities
under the CP Program or earlier issuance of Water and Sewer revenue bonds than is currently planned.
Once debt associated with this project is sold, bond proceeds will be used to reimburse the Water and
Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2018-2022 Five Year Capital Improvement
Plan on September 26, 2017. This City Council adopted plan includes this specific project, with funding
identified through the CP program to be reimbursed with future revenue bonds. In accordance with the
provisions of the Financial Management Policy Statement, Staff anticipates presenting revenue -supported
debt issuances to the City Council for consideration within the next three years. This debt must be issued
within approximately three years to provide reimbursement for these expenses. If that does not occur, the
costs will no longer be reimbursable by issuing tax-exempt debt and the funding source will have to be
made whole through budgetary methods. Adoption of this resolution does not obligate the City to sell
bonds, but preserves the ability to reimburse the City from tax-exempt bond proceeds.
Construction is anticipated to commence in April, 2019 and be completed by April, 2020. This project will
have no impact on the Water Department's Operating Budget when complete.
M/WBE OFFICE: Landmark Structures I, L.P., is in compliance with the City's BDE Ordinance by
committing to five percent MBE participation on this project. The City's MBE goal on this project is five
percent.
The project is located in COUNCIL DISTRICT 3 and the City's Extra Territorial Jurisdiction.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in Water & Sewer Commercial Paper Fund for
the Westside V Part 1 One Million Gallon Elevated Water Storage Tank Project. The Water and Sewer
Commercial Paper Fund includes authority of $150,000,000.00 for the purpose of providing interim
funding for Water and Sewer Capital Projects. After this transfer, the balance will be $80,967,788.00 for
future capital projects. Funding for the Westside V Part 1 One Million Gallon Elevated Water Storage Tank
and Water Main Project is as depicted below:
[FUND
Existing [Appropriations
dditional [Appropriations [Project Total*
Water/Sewer Bond 2016 Fund -
56005
$256,110.00
$0.00
$256,110.00
Logname: 60WSIDEVPIESTANK-LSTRUCTURESI Page 2 of 3
Water & Sewer Bond 2017A +
Fund - 56011 $893,100.00 1$0.00
1$893,100.00
W& S Capital Project 2018
Fund - 56014
1$600,000.00 $0 .00 F$600,000.00
Water & Sewer Commercial
Paper Fund 56016
Project Total
* Numbers rounded for presentation.
FUND IDENTIFIERS (FIDs):
TO
1$3,428,082.00 $3,028,892.00
177,292.00 $3,028,892.00
+$6,456,974.00
$8,206,184.00
FROM
Fundl Department
ccoun
Project
Program
ctivity
Budget
Reference #
moun
7!�7mentart
ID
ID
Year (ChartFeld 2)
Year
(Chartfield 2)
FROM
Fundl Department
ccoun
Project
Program
ctivity
Budget Reference #
moun
I ID
I I
ID
Year (ChartFeld 2)
CERTIFICATIONS:
Submitted for City Manager's Office by:
Originating Department Head:
Additional Information Contact:
Jay Chapa (5804)
Chris Harder (5020)
Rakesh Chaubey (605 1)
Logname: 60WSIDEVPIESTANK-LSTRUCTURESI Page 3 of 3