HomeMy WebLinkAboutOrdinance 23544-01-2019Ordinance No. 23544-01-2019
AN ORDINANCE INCREASING APPROPRIATIONS IN THE WATER AND SEWER
COMMERCIAL PAPER FUND, FROM AVAILABLE FUNDS IN THE AMOUNT OF
$3,428,082.00, FOR THE PURPOSE OF FUNDING THE WESTSIDE V PART 2, 16/24 -
INCH WATER MAIN PROJECT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING
THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL
ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1
That in addition to those amounts allocated to the various City departments for Fiscal Year 2018-2019 in the
Budget of the City Manager, there shall also be increased appropriations in the Water and Sewer Commercial
Paper Fund in the amount of $3,428,082.00, from available funds, for the Westside V Part 2, 16/24 -inch Water
Main Project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 23392-09-2018 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
OU96->
Douglas Black
Sr Assistant City Attorney
ADOPTED AND EFFECTIVE: January 29. 2019
CITY SECRET. RY-
ry J. K4yfr
FM
r
n
C�
O
MAYOR AND COUNCIL COMMUNICATION MAP
60WSIDEVP2WMAIN-MOU NTAINC
WHITE SETTLEMENT FCD z�'
u. ,amu
E BANKHEAD HWY
FORTWORT
I
N
no
CIA
1 btD'WFATFiERFORI) RD
uj � EYISTINta WATER MAIN
�1
LSC
¢LL1
1
620
1
1
E 30 W 30
Ca EXISTING PUMP STATION & "
= GROUND STORAGE TANK
4
USGA IbJSGSLuvl a `_.0 er Commur ity
r _ .��rvc Esn Di' italG'IQki,� GeoE�e i.l��,l�i Geo ra hic9, hdF,->:Ad
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 1/29/201.9 - Ordinance No. 23544-01-201.9 & R�sQlutiOn.
No. 5035-Q1-2019
DATE: Tuesday, January 29, 2019
LOG NAME: 60WSIDEVP2WMAIN-MOUNTAINC
REFERENCE NO.: **C-29014
SUBJECT:
Authorize Execution of a Contract with Mountain Cascade of Texas, LLC, in the Amount of $2,972,194.00
for Westside V Part 2, 16/24 -inch Water Main Project, Provide for Project Costs for a Project Total in the
Amount of $5,177,292.00, Adopt Resolution Expressing Official Intent to Reimburse Expenditures with
Proceeds of Future Debt and Adopt Appropriation Ordinance (COUNCIL DISTRICT 3)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds
of Future Debt for the Westside V Part 2, 16/24 -inch Water Main Project;
2. Adopt the attached Appropriation Ordinance increasing estimated receipts and appropriations in the
Water & Sewer Commercial Paper Fund in the amount of $3,428,082.00; and
3. Authorize the execution of a contract with Mountain Cascade of Texas, LLC, in the amount of
$2,972,194.00 for the Westside V Part 2, 16/24 -inch Water Main Project, located in west Fort Worth
and the City's Extra Territorial Jurisdiction (City Project No. 100378)
DISCUSSION:
Growth within west Fort Worth and its Extra Territorial Jurisdiction (ETJ) requires the installation of pump
stations, water storage facilities and transmission mains in order to provide reliable water service to
existing and proposed developments and as required for compliance with state regulatory requirements
related to public water system design and operations. On November 17, 2015, the City Council approved
the construction of a booster pump station to provide service to portions of the Walsh Ranch and
Morningstar developments.
This Mayor and Council Communication provides for the construction of a 16/24 -inch water transmission
main to connect the pump station to a proposed elevated storage tank for improved levels of service.
Construction of the project was advertised for bid on November 15, 2018 and November 22, 2018 in the
Fort Worth Star -Telegram. On December 13, 2018 the following bids were received:
BIDDER
Mountain Cascade of Texas, LLC
r
'AMOUNT TIME OF COMPLETION
$2,972,194.00 365 Calendar Days
Logname: 60WSIDEVP2WMAIN-M0UNTAINC Page I of 3
liackson Construction, Ltd _ 1$3,296,623.25
JCondie Construction Company _ $3,352,198.70
Venus Construction Company _ $3,398,593.60
-_.-.________.._.__. _..._T _
Ark Construction Services $3,672,721.00
In addition to the contract cost, $307,278.00 is required for Project Management, inspection and material
testing and $148,610.00 is provided for project contingency.
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer Fund.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation
authority authorized under the Callable Commercial Paper Program (CP) will be used to provide interim
financing for this project until debt is issued. To the extent resources other than the Water and Sewer
portfolio are used to provide interim financing, the Water and Sewer Fund will be charged interest that is
equivalent to the overall rate of return being earned by the City portfolio (currently approximately one -
percent annually). Should the City's portfolio not support the liquidity needed to provide an interim short-
term financing source, another funding source will be required, which could mean issuance of securities
under the CP Program or earlier issuance of Water and Sewer revenue bonds than is currently planned.
Once debt associated with this project is sold, bond proceeds will be used to reimburse the Water and
Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2018-2022 Five Year Capital Improvement
Plan on September 26, 2017. This City Council adopted plan includes this specific project, with funding
identified through the CP program to be reimbursed with future revenue bonds. In accordance with the
provisions of the Financial Management Policy Statement, Staff anticipates presenting revenue -supported
debt issuances to the City Council for consideration within the next three years. This debt must be issued
within approximately three years to provide reimbursement for these expenses. If that does not occur, the
costs will no longer be reimbursable by issuing tax-exempt debt and the funding source will have to be
made whole through budgetary methods. Adoption of this resolution does not obligate the City to sell
bonds, but preserves the ability to reimburse the City from tax-exempt bond proceeds.
Construction is anticipated to commence in March, 2019 and be completed by March, 2020. This project
will have no impact on the Water Department's Operating Budget when complete.
M/WBE OFFICE: Mountain Cascade of Texas, LLC, is in compliance with the City's BDE Ordinance by
committing to seven percent MBE participation on this project. The City's MBE goal on this project is five
percent.
The project is located in COUNCIL DISTRICT 3 and the City's Extra Territorial Jurisdiction.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance, funds will be available in Water & Sewer Commercial Paper Fund for
the Westside V Part 2, 16/24 -inch Water Main Project. The Water and Sewer Commercial Paper Fund
includes authority of $150,000,000.00 for the purpose of providing interim funding for Water and Sewer
Capital Projects. After this transfer, the balance will be $83,996,680.00 for future capital projects. Funding
for the Westside V Part 2, 16/24 -inch Water Main project is as depicted below:
Existing Additional —
Logname: 60WSIDEVP2WMAIN-M0LNTAINC Page 2 of 3
IFUND
JAppropriations Appropriations IProject Total-
Water/Sewer Bond 2016 Fund -
56005
$256,110.00 $0.00 $256,110.00
`Water & Sewer Bond 2017A
[$893,100.00
$0.00
$893,100.00
!Fund - 56011
W& S Capital Proj 2018 Fund -
�56014
$600,000.00 $"0.00 $600,000.00
Water &Sewer Commercial
$0.00 ($3,428,082.00 '$3,428,082.00
jPaper Fund 56016
Project Total
$1,749,210.00
$3,428,082.00 $5,177,292.00
* Numbers rounded for presentation.
FUND IDENTIFIERS (FIDS):
TO
Fund Department ccoun Project Program Activity Budget Reference #
ID ID Year (Chartfield 2'
and Department ccouniq Project IPrograrn ctivity Budget Reference # moun
ID I ID I Year _Chartfield 2
CERTIFICATIONS:
Submitted for City Manager's Office by: Jay Chapa (5804)
Originating Department Head: Chris Harder (5020)
Additional Information Contact: Rakesh Chaubey (6051)
Logname: 60WSIDEVP2WNIAIN-MOL NTAINC Page 3 of 3