NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: The Construction Water, Sewer, Storm, Paving to Serve Nursery Lane
City Project No.: 101144
Improvement Type(s): ❑ Paving ® Drainage ❑ Street Lights ❑ Traffic Signals
Original Contract Price: $138,115.00
Amount of Approved Change Order(s):
Revised Contract Amount: $138,115.00
Total Cost of Work Complete: $138,115.00
7 nni
Feb 26 2019
Joe Geer(Feb 26,2019`
Contractor Date
CFO/Partner
Title
Rumsey Construction,LLC
Company Name
'"A"k A&InAdt�y
Mark McFadin(Feb 26,% Feb 26, 2019
Project Inspector Date
� � Mar 20, 2019
Fi20,2019)
Project Manager Date
ripil25�0!�eaAlly�r Mar 20 2019_
Janie Scarlett Morales(Mar 20,2019)
CFA Manager Date
Sw Mar 20 2019
Susan Alanis(Mar 20,2019) 5
Asst. City Manager Date
Page 1 of 2
LFT,
wnRTH
Notice of Project Completion
Project Name: The Construction Water, Sewer, Storm, Paving to Serve Nursery Lane
City Project No.: 101144
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 120 CD Days Charged: 78
Work Start Date: 4/8/2018 Work Complete Date: 06/24/2018
Page 2 of 2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN,ST
Contract Limits
Project Type DRAINAGE IMPROVEMENTS
City Project Numbers 101144
DOE Number 1144
Estimate Number 1 Payment Number 1 For Period Ending 1/8/2019
CD
City Secretary Contract Number Contract Time 6ED
Contract Date 1/3/2018 Days Charged to Date 78
Project Manager NA Contract is 100.00 Complete
Contractor RUMSEY CONSTRUCTION,LLC
6617 VILLAGE SPRINGS DRIVE
PLANO, TX 75024
Inspectors CORDOVA / MCFADIN
Monday,February 18,2019 Page 1 of 4
City Project Numbers 101144 DOE Number 1144
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN, Estimate Number I
Contract Limits Payment Number I
Project Type DRAINAGE IMPROVEMENTS For Period Ending 1/8/2019
Project Funding
UNIT III:DRAINAGE IMPROVEMENTS
Item Estimated Estimated Completed Completed
Description of Items Unit Unit Cost �
No. Quanity Total Quanity Total
---------------------------------------
1
---- ------ —
1 REMOVE 21"STORM LINE 6 LF $10.00 $60.00 6 $60.00
2 REMOVE 36"STORM LINE 44 LF $15.00 $660.00 44 $660.00
3 REMOVE 48"STORM LINE 410 LF $21.00 $8,610.00 410 $8,610.00
4 REMOVE 5'STORM JUNCTION BOX 1 EA $450.00 $450.00 1 $450.00
5 REMOVE Y DROP INLET 1 EA $450.00 $450.00 1 $450.00
6 TRENCH SAFETY 1050 LF $0.10 $105.00 1050 $105.00
7 21"RCP CLASS III 86 LF $65.00 $5,590.00 86 $5,590.00
8 30"RCP CLASS 111 58 LF $105.00 $6,090.00 58 $6,090.00
9 48"RCP CLASS III 440 LF $235.00 $103,400.00 440 $103,400.00
10 Y STORM JUNCTION BOX 1 EA $6,850.00 $6,850.00 1 $6,850.00
11 10'CURB INLET 1 EA $5,850.00 $5,850.00 1 $5,850.00
--------------------------------------
Sub-Total of Previous Unit $138,115.00 $138,115.00
--------------------------------------
Monday,February 18,2019 Page 2 of 4
City Project Numbers 101144 DOE Number 1144
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN, Estimate Number I
Contract Limits Payment Number 1
Project Type DRAINAGE IMPROVEMENTS For Period Ending 1/8/2019
Project Funding
Contract Information Summary
Original Contract Amount $138,115.00
Change Orders
Total Contract Price $138,115.00
I
Total Cost of Work Completed $138,115.00
Less %Retained $0.00
Net Earned $138,115.00
Earned This Period $138,115.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $138,115.00
Monday,February 18,2019 Page 3 of 4
I
City Project Numbers 101144 DOE Number 1144
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN, Estimate Number 1
Contract Limits Payment Number I
Project Type DRAINAGE IMPROVEMENTS For Period Ending 1/8/2019
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors CORDOVA / MCFADIN Contract Date 1/3/2018
Contractor RUMSEY CONSTRUCTION,LLC Contract Time 60 CD
6617 VILLAGE SPRINGS DRIVE Days Charged to Date 78 CD
PLANO, TX 75024 Contract is .000000 Complete
I
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------- -----------
Total Cost of Work Completed $138,115.00
Less %Retained $0.00
Net Earned $138,115.00
Earned This Period $138,115.00
i
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $138,115.00
Monday,February 18,2019 Page 4 of 4
FORTWORTH rev 03/05/07
TRANSPORTATION & PUBLIC WORKS
FINAL STATEMENT OF CONTRACT TIME
FINAL STATEMENT NO.:1
NAME OF PROJECT: The Construction of Water,Sewer,Storm,Paving of Nursery Lane
PROJECT NO.: CONTRACTOR: Rumsey Construction
DOE NO.:
PERIOD FROM:04/08/18 TO: 06/24/18 FINAL INSPECTION DATE: 8-Jan-19
WORK ORDER EFFECTIVE:4/8/2018 CONTRACT TIME: _ l� o WD ® CD
DAY OF DAYS REASON FOR DAYS DAY OF DAYS REASON FOR DAYS
MONTH CHARGED CREDITED MONTH CHARGED CREDITED
DURING DURING
1. 16.
2. 17.
3. 18.
4. 19.
5. 20.
6. 21.
7. 22.
8. 23.
9. 24.
10. 25.
11. 26.
12. 27.
13. 28•
14. 29.
15. 30.
31.
SAT,SUN, RAIN,TOO WET, UTILITIES DAYS TOTAL
&HOLIDAYS &TOO COLD RELOCATIONS OTHERS* CHARGED DAYS
THIS
78 78
PERIOD
PREVIOUS
0 0
PERIOD
TOTALS
78 78
TO DATE
*REMARKS:
f
`4.
CONTRACTOR DATE INSPECTOR DATE
ENGINEERING DEPARTMENT
=' The City of Fort Worth•1000 Throckmorton Street•Fort Worth,TX 76012-6311
3 a
(817) 392-7941 •Fax:(817)392-7845
City Secretary
Contract No.
FORTWORTH..) Date Received
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: The Construction Water, Sewer, Storm, Paving to Serve Nursery Lane
City Project No.: 101144
Improvement Type(s): ❑ Paving ❑x Drainage ❑ Street Lights ❑ Traffic Signals
Original Contract Price: $138,115,00
Amount of Approved Change Order(s).-
Revised
rder(s):Revised Contract Amount: $138,115.00
Total Cost of Work Complete: $138,115.00
-2
Contrac r Date
Title
Company Name
Project Inspector Date
Project Manager Date
CFA Manager Date
Asst. City Manager Date
Page 1 of 2
Notice of Project Completion
Project Name:The Construction Water, Sewer, Storm, Paving to Serve Nursery Lane
City Project No.: 101144
City's Attachments
Final Pay Estimate N
Change order(s): ❑ Yes Z NIA
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 120 CD Days Charged: 78
Work Start Date: 4/812018 Work Complete Date: 08/24/2018
Page 2 of 2
FORTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN,ST
Contract Limits
Project Type DRAINAGE IMPROVEMENTS
City Project Numbers 101244
DOE Number 1144
Estimate Number I Payment Number 1 For Period Ending 1/8/2019
CD
City Secretary Contract Number Contract Time 6IED
Contract Date 1/3/2018 Days Charged to Date 78
Project Manager NA Contract is 100.00 Complete
Contractor RUMSEY CONSTRUCTION,LLC
6617 VILLAGE SPRINGS DRIVE
PLANO, TX 75024
Inspectors CORDOVA 1 MCFADIN
Monday,Febmary 18,2019 Page i of4
1.�' 1 /
City Project Numbers 101144 DOE
Number 1144
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN, Estimate Number 1
Contract Limits Payment Number I
Project Type DRAINAGE IMPROVEMENTS For Period Ending 1/8/2019
Project Funding
UNIT M-.DRAINAGE IMPROVEMENTS
Item Description.of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
I REMOVE 21"STORM LINE 6 LF $10.00 $60.00 6 $60.00
2 REMOVE 36"STORM LINE 44 LF $15.00 $660.00 44 $660.00
3 REMOVE 48"STORM LINE 410 LF $21.00 $8,610.00 410 $8,610.00
4 REMOVE 5'STORM!UNCTION BOX I EA $450.00 $450.00 1 $450.00
5 REMOVE T DROP INLET 1 EA $450.00 $450.00 1 $450.00
6 TRENCH SAFETY 1050 LF $0.10 $105.00 1050 $]05.00
7 21"RCP CLASS III 86 LF $65,00 $5,590.00 86 $5,590.00
8 30"RCP CLASS 11] 58 LF $105.00 $6,090.00 58 $6,090.00
9 48"RCF CLASS III 440 LF $235.00 $103,400.00 440 $103,400.00
10 T STORM JUNCTION BOX 1 EA $6,850.00 $6,850.00 1 $6,850.00
11 l0'CURB INLET 1 EA $5,85000 $5,850,00 I $5,850.00
Sub-Total of Previous Unit $138,115.00 $138,115.00
Monday,February 18,2019 Page 2 of 4
City Project Numbers 101144 DOE Number 1144
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN, Estimate Number 1
Contract Limits Payment Number 1
Project Type DRAINAGE Uv1PROVEMENTS For Period Ending 1/8/2019
Project Funding
Contract Information Summa
Original Contract Amount S138,I15.00
Change Orders
Total Contract Price $138,115.00
Total Cost of Work Completed $138,115.00
Less %Retained $0.00
Net Earned $138,115.00
Earned This Period S138,115.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
PIus Material on Hand Less 15% $0.00
Balance Due This Payment $138,115.00
Monday,February 18,2019 Page 3 of
City Project Numbers 101144 DOE Number 1144
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN, Estimate Number I
Contract Limits Payment Number I
Project Type DRAINAGE IMPROVEMENTS For Period Ending 118!2019
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors CORDOVA / MCFADIN Contract Date 1/3/2018
Contractor RUNISE'Y CONSTRUCTION,LLC Contract Time 60 CD
6617 VILLAGE SPRINGS DRIVE Days Charged to Date 78 CD
PLANO, TX 75024 Contract is _000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
`fatal Cost of Work Completed $138,1I5.00
Less %Retained $0.00
Net Earned $138,115.00
Earned This Period $138,115.00
Retainage This Period $0.00
!Less Liquidated Damages
0 Days @ S0.00 1 Day $0.00
LessPavement Deficiency $0,00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $138,115.00
Monday,febmary 18,2019 Page of
FORTWORTH rev 03/05/07
TRANSPORTATION& PUBLIC WORKS
FINAL STATEMENT OF CONTRACT TIME
FINAL STATEMENT NO.: l
NAME OF PROJECT: The Construction of Water, Sewer,Storm,Paving of Nursery Lane
PROJECT NO.: _� � CONTRACTOR: Rumsey Construction
DOE NO.:
PERIOD FROM:04/08/18 TO: 06/24/18 FINAL INSPECTION DATE: 8-Ian-19
WORK ORDER EFFECTIVE:4/8/2018 CONTRACT TIME: � e t;� 0 WD 0 Co
DAY OF DAYS REASON FOR DAYS DAY OF DAYS REASON FOR DAYS
MONTH CHARGED DURING CREDITED MONTH CHARGED DURING CREDITED
1.
16.
2. 17.
3. 18,
4. 19.
5. 20.
6. 21.
7. 22.
S. 23.
9. 24.
10. 25.
11. 26.
12. 27.
13. 28.
14. 29.
15, 30.
31.
SAT,SUN, RAIN,TOO WET, UTILITIES DAYS TOTAL
&HOLIDAYS &TOO COLD RELOCATIONS OTHERS* CHARGED DAYS
THIS
PERIOD 78 78
PREVIOUS
PERIOD 0 0
TOTALS
TO DATE 78 78
REMARKS:
C 0R ---DATt INSPECTOR DATE
ENGTI"EER�Dp
E1RTk\IENT`sCity of Fort Worth• 1Q00ThonStretFWth,TY 76012-6311
($17)392-7941ax;($17}392_7845
City Secretary
Contract No.
FORTWORTH..) Date Received
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: The Construction Water, Sewer, Storm, Paving to Serve Nursery Lane
City Project No.: 101144
Improvement Type(s): ❑ Paving ❑x Drainage ❑ Street Lights ❑ Traffic Signals
Original Contract Price: $138,115,00
Amount of Approved Change Order(s).-
Revised
rder(s):Revised Contract Amount: $138,115.00
Total Cost of Work Complete: $138,115.00
-2
Contrac r Date
Title
Company Name
Project Inspector Date
Project Manager Date
CFA Manager Date
Asst. City Manager Date
Page 1 of 2
Notice of Project Completion
Project Name:The Construction Water, Sewer, Storm, Paving to Serve Nursery Lane
City Project No.: 101144
City's Attachments
Final Pay Estimate N
Change order(s): ❑ Yes Z NIA
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 120 CD Days Charged: 78
Work Start Date: 4/812018 Work Complete Date: 08/24/2018
Page 2 of 2
FORTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN,ST
Contract Limits
Project Type DRAINAGE IMPROVEMENTS
City Project Numbers 101244
DOE Number 1144
Estimate Number I Payment Number 1 For Period Ending 1/8/2019
CD
City Secretary Contract Number Contract Time 6IED
Contract Date 1/3/2018 Days Charged to Date 78
Project Manager NA Contract is 100.00 Complete
Contractor RUMSEY CONSTRUCTION,LLC
6617 VILLAGE SPRINGS DRIVE
PLANO, TX 75024
Inspectors CORDOVA 1 MCFADIN
Monday,Febmary 18,2019 Page i of4
1.�' 1 /
City Project Numbers 101144 DOE
Number 1144
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN, Estimate Number 1
Contract Limits Payment Number I
Project Type DRAINAGE IMPROVEMENTS For Period Ending 1/8/2019
Project Funding
UNIT M-.DRAINAGE IMPROVEMENTS
Item Description.of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
I REMOVE 21"STORM LINE 6 LF $10.00 $60.00 6 $60.00
2 REMOVE 36"STORM LINE 44 LF $15.00 $660.00 44 $660.00
3 REMOVE 48"STORM LINE 410 LF $21.00 $8,610.00 410 $8,610.00
4 REMOVE 5'STORM!UNCTION BOX I EA $450.00 $450.00 1 $450.00
5 REMOVE T DROP INLET 1 EA $450.00 $450.00 1 $450.00
6 TRENCH SAFETY 1050 LF $0.10 $105.00 1050 $]05.00
7 21"RCP CLASS III 86 LF $65,00 $5,590.00 86 $5,590.00
8 30"RCP CLASS 11] 58 LF $105.00 $6,090.00 58 $6,090.00
9 48"RCF CLASS III 440 LF $235.00 $103,400.00 440 $103,400.00
10 T STORM JUNCTION BOX 1 EA $6,850.00 $6,850.00 1 $6,850.00
11 l0'CURB INLET 1 EA $5,85000 $5,850,00 I $5,850.00
Sub-Total of Previous Unit $138,115.00 $138,115.00
Monday,February 18,2019 Page 2 of 4
City Project Numbers 101144 DOE Number 1144
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN, Estimate Number 1
Contract Limits Payment Number 1
Project Type DRAINAGE Uv1PROVEMENTS For Period Ending 1/8/2019
Project Funding
Contract Information Summa
Original Contract Amount S138,I15.00
Change Orders
Total Contract Price $138,115.00
Total Cost of Work Completed $138,115.00
Less %Retained $0.00
Net Earned $138,115.00
Earned This Period S138,115.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
PIus Material on Hand Less 15% $0.00
Balance Due This Payment $138,115.00
Monday,February 18,2019 Page 3 of
City Project Numbers 101144 DOE Number 1144
Contract Name THE CONSTRUCTION OF WATER,SEWER,PAVING,STORM DRAIN, Estimate Number I
Contract Limits Payment Number I
Project Type DRAINAGE IMPROVEMENTS For Period Ending 118!2019
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors CORDOVA / MCFADIN Contract Date 1/3/2018
Contractor RUNISE'Y CONSTRUCTION,LLC Contract Time 60 CD
6617 VILLAGE SPRINGS DRIVE Days Charged to Date 78 CD
PLANO, TX 75024 Contract is _000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
`fatal Cost of Work Completed $138,1I5.00
Less %Retained $0.00
Net Earned $138,115.00
Earned This Period $138,115.00
Retainage This Period $0.00
!Less Liquidated Damages
0 Days @ S0.00 1 Day $0.00
LessPavement Deficiency $0,00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $138,115.00
Monday,febmary 18,2019 Page of
FORTWORTH rev 03/05/07
TRANSPORTATION& PUBLIC WORKS
FINAL STATEMENT OF CONTRACT TIME
FINAL STATEMENT NO.: l
NAME OF PROJECT: The Construction of Water, Sewer,Storm,Paving of Nursery Lane
PROJECT NO.: _� � CONTRACTOR: Rumsey Construction
DOE NO.:
PERIOD FROM:04/08/18 TO: 06/24/18 FINAL INSPECTION DATE: 8-Ian-19
WORK ORDER EFFECTIVE:4/8/2018 CONTRACT TIME: � e t;� 0 WD 0 Co
DAY OF DAYS REASON FOR DAYS DAY OF DAYS REASON FOR DAYS
MONTH CHARGED DURING CREDITED MONTH CHARGED DURING CREDITED
1.
16.
2. 17.
3. 18,
4. 19.
5. 20.
6. 21.
7. 22.
S. 23.
9. 24.
10. 25.
11. 26.
12. 27.
13. 28.
14. 29.
15, 30.
31.
SAT,SUN, RAIN,TOO WET, UTILITIES DAYS TOTAL
&HOLIDAYS &TOO COLD RELOCATIONS OTHERS* CHARGED DAYS
THIS
PERIOD 78 78
PREVIOUS
PERIOD 0 0
TOTALS
TO DATE 78 78
REMARKS:
C 0R ---DATt INSPECTOR DATE
ENGTI"EER�Dp
E1RTk\IENT`sCity of Fort Worth• 1Q00ThonStretFWth,TY 76012-6311
($17)392-7941ax;($17}392_7845