HomeMy WebLinkAboutContract 51395-CO1 CITY SECRETAR Y
CONTRACT No., 5 139 J-CC I
FORT WORTH. City of Fort Worth
Change Order Request
Project Namel Brick Pavement Rehabilitation 2019 at Various Locations City Sec# s'
Client Project#(s)l 101610
Project Description Brick Paver Repair
Contractorl C.Green Scaping,LP Change Order# Date 3/1412019
City Project Mgr.J Shammi Rahman City Inspector F Oden Weyman
Dept. TPW-Storm Contract Time
Water Totals (WD)
Original Contract Amount $306,250.00 $306,250.00 210
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $306,250.00 $306,250.00 210
Amount of Proposed Change Order $1,825.21 $1,825.21 5
Revised Contract Amount $308,075.21 $308,075.21 215
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary) $1,825.21 $1,825.21
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.60%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+255.1) $382,812.50
JUSTIFICATION FOR CHANGE ORDER
Change order request to install white pavers in lieu of white paint in crosswalk location on 8th and Main Street.
• ci= _1.
Mary J. , ity Secretary .
�LXAS
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
s Name Contractorftpq Contract Date
C.Green Scaping,LP Stacy Geigenmiller 3/14/1
D Date
_ o
�t it ctor(pept} , ` "`� _ _ - - vat" ��,''�j
ICMAA
Dade
Council Action If qqo"
M&C Number L M&C Date Approved
RECURD
CITY SECRETARY
I FT: WORTH,TX
Fox_ T WORTH City of Fort Worth
Change Order Additions
Project Name Brick Pavement Rehabilitation 2019 at Various Locations City Sec
Client Project# 101610
Project Description Brick Paver Repair
Contractor C.Green Scalping,LP Change Order# Date 3/14/2019
City Project Mgr. Shammi Rahman City Inspector F Oden Weyman
ADDITIONS
ty Unit Unitcost I ota
Furnish Deliver White 8 CM Pavestone Concrete Pavers to torm =ter
Profit and Overhead- o - form ater
Sand,Portland,Etc.and Labor to Install New Pavestone Concrete Pavers - torm =ter
TPW-Storm Water 1,825.21
Sub TotalAdditions 5.
Change Order Additions Page 2 of 4
FORT WORTH City of Fort Worth
- V-- Change Order Deletions
Project Name Brick Pavement Rehabilitation 2019 at Various Locations City Sec#
Client Project# 101610
Project Description Brick Paver Repair
Contractor C.Green Scalping,LP Change Order# Date 3114/2019
City Project Mgr. Shammi Rahman City Inspector Oden Weyman
DELETION5
Unit Unit s o,a
Ti Water i
bun I ota etions
Change Order Deletions Page 3 of 4
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
N/A
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
None
Total $0.00
i
i
1
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Shammi Rahman
Project Manager
Title
❑ This form is N/A as No City Funds are associated with this Contract
I
Printed Name Signature
I
OFFdAL RECORD
0TY SECRETARY
FT. WORTH,TX
Soto, Vania Elizabeth
From: West,Jennifer
Sent: Wednesday,April 10, 2019 4:23 PM
To: Black, Doug
Cc: TPW Contracts; Soto,Vania Elizabeth
Subject: RE: 101610, Brick Rehabilitation Contract Compliance
Attachments: 101610-Contract Compliance Manager.pdf,Contract 51395-COl.pdf, FW: Missing
signature
Yes,anything related to contracts must be approved by you prior to any documents being changed.
Vania...please accept the email below as written approval from Doug. The contract compliance form labelled
101610_Contract Compliance Manger.pdf is signed by the Project Manager and should be attached to the contract.
Thank you,
Jennifer West
Capital Delivery Contract Coordinator
Transportation and Public Works
200 Texas Street
Fort Worth,Texas 76102
817.392.7233 Phone
817.392.8092 Fax
Jennifer.West@fortworthtexas.gov
City of Fort Worth—Working together to build a strong community.
-----Original Message-----
From: Black,Doug
Sent: Wednesday,April 10,2019 4:13 PM
To: West,Jennifer<Iennifer.West@fortworthtexas.gov>
Cc: TPW Contracts<TPWContracts@fortworthtexas.gov>
Subject:RE: 101610,Brick Rehabilitation Contract Compliance
I have to approve this for CSO to swap the pages?If so,this is ministerial and law has no objections to the change.
Approved.
db
-----Original Message-----
From: West,Jennifer
Sent: Wednesday,April 10,2019 16:00
To: Black,Doug<Douglas.Black@fortworthtexas.gov>
Cc: TPW Contracts<TPWContracts@fortworthtexas.gov>
Subject: 101610, Brick Rehabilitation Contract Compliance
Doug,
I want to follow-up on this email. It looks like the PM had the contractor sign the contract compliance page- see attached
email string. I would like to update the Contract Compliance page with one containing a City employee's name; however,
you have to sign off on the change.
Will you please approve this change?
Thank you,
Jennifer West
Capital Delivery Contract Coordinator
Transportation and Public Works
200 Texas Street
Fort Worth,Texas 76102
817.392.7233 Phone
817.392.8092 Fax
Jennifer.West@fortworthtexas.gov
City of Fort Worth—Working together to build a strong community.
-----Original Message-----
From: West,Jennifer
Sent: Wednesday,April 3,2019 11:59 AM
To: Black,Doug<Douglas.Black@fortworthtexas.gov>
Cc: TPW Contracts<TPWContracts@fortworthtexas.gov>; Rahman, Shammi <Shammi.Rahman@fortworthtexas.gov>
Subject: FW:Message from "TPW-D13758"
Doug,
The attached change order contains the incorrect Contract Compliance Manager page. We would like to replace page 5 of
the change order with the attached Contract Compliance Manager signature block. If this is acceptable,please let me
know how you want to handle.
Thank you,
Jennifer West
Capital Delivery Contract Coordinator
Transportation and Public Works
200 Texas Street
Fort Worth,Texas 76102
817.392.7233 Phone
817.392.8092 Fax
Jennifer.West@fortworthtexas.gov
City of Fort Worth—Working together to build a strong community.
-----Original Message-----
From: Rahman, Shammi
Sent: Wednesday,April 3,2019 11:30 AM
To: West,Jennifer<Jennifer.West@fortworthtexas.gov>
Subject: FW: Message from "TPW-D13758"
Will this online do?
thanks
-----Original Message-----
2
From: printeradmins@fortworthgov.org [mailto:printeradmins@fortworthgov.org]
Sent: Wednesday, April 03,2019 10:16 AM
To: Rahman, Shammi
Subject: Message from "TPW-D13758"
This E-mail was sent from "TPW-D13758"(MP C4504).
Scan Date: 04.03.2019 11:16:22(-0400)
Queries to: printeradmins@fortworthgov.org
3