f*R ' Project Name: Northside II 48-Inch Water Transmission Main Phase II, Part I City Sec No.: 48783
G -\,'P eC Project No.(s): 56001-0600430/0700430/C01788 DOE No. N/A City Proj.No.: 02304
Project Description: 48-inch Water Main Intersection from Heritage Trace Parkway/Harmon Road Intersection to Wagley Roberston Road
Contractor: S.J. Louis Construction of Texas,Ltd. Change Order# Date: 3/20/2019
City Project Mgr.1 John Kasavich City Inspector: I Raymond Brice
Phone Number: 817-392-8480 Phone Number: 817-392-8452
Dept. NSII 48"Water 36"Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $8,920,223.00 $438,130.00 $523,777.00 $9,882,130.00 470
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $8,920,223.00 $438,130.00 $523,777.00 $9,882,130.00 470
Amount of Proposed Change Order $5,778.08 -$10,778.00 $5,000.00 $0.08 312
Revised Contract Amount $8,926,001.08 $427,352.00 $528,777.00 $9,882,130.08 782
Original Funds Available for Change Orders $474,900.00 $44,300.00 $519,200.00
Remaining Funds Available for this CO $474,900.00 $44,300.00 $519,200.00
Additional Funding(if necessary) i A
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+259'o) $12,352,662.50
JUSTIFICATION(REASONS)FOR CHANGE ORDER _ - � M`.
Change Order No. 1 will provide compensation for the following: u- I
• Removal of fill material placed by a developer over a segment of the water main to be installed. i.
• Demobilization and remobilization due to lack of easement to install a segment of the water main.
• Additional expense incurred to install the water main through landscaped area completed prior to >u
water main installation.
• Concrete thrust blocking on segments of the project water main. ,
• Concrete paving repair of new pavement that was installed prior to construction of a segment of the V
project.
a�
Staff concurs with the contractor's request for an additional 312 calendar days on the project for the c�
length of time it took to acquire easements that were not available at the time of bid opening.The
contractor had to demobilize and remobilize twice in these areas.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name tt _ ctor SJOAtte
S.J. Louis Construction of Texas, Ltd. Adam Lundsford l
1 '" Data Project Manager VDate
'i
D irector Wa er a t) Date, Co struction Supervisor(Water Dept) Date
LtL
Asgjptanf QAtt Date Assistant City Manager Date
CourtcH Action(If Required)
M&C Number N/A M&C Date Approved SECRETARY
FCC RTr'V[7 RT 1E 3 City of Fort Worth
Change Order Additions
Project Name Northside II 48-Inch Water Transmission Main Phase II,Part I City Sec No.: 48783
Project No.(s): 56001-0600430/0700430/C01788 DOE No. N/A City Proj. No.: 02304
Project 48-inch Water Main Intersection from Heritage Trace Parkway/Harmon Road Intersection to Wagley Roberston Road
Description
Contractor S.J.Louis Construction of Texas,Ltd. Change Order:=1 Date: 3/20/2019
City Project Mgr. John Kasavich City Inspector Raymond Brice
ADDITIONS
DEECRIPTION DEPT Qty Unit Unit Cost Total
33 Concrete Paving Repair NSII 48"Water 165.00 SY $89.00 $14,685.00
34 12"Flex Base NSII 48"Water 165.00 SY $10.00 $1,650.00
54 Additional Traffic Control for Star Rock Drive NSII 48"Water 1.00 LS $700.00 $700.00
55 Re-Mobilize Pipe Crew to finish(missing Easements) NSII 48"Water 1.00 LS $25,000.00 $25,000.00
56 JAdditional Labor, Equip.,and Fuel to Install Waterline through Landscap NSII 48"Water 1.00 LS $15,208.34 $15,208.34
57 Sundance Re-Mob/De-Mob cost for missing easements NSII 48"Water 1.00 LS $15,000.00 $15,000.00
58 Concrete Thrust Blocking on 48"B303 Pipe NSII 48"Water 1.00 LS $28,094.74 $28,094.74
59 Rock fill above water line removal NSII 48"Water 1.00 LS $46,000.00 $46,000.00
26 36"Water Line Elevation Change 36"Water 1.00 LS $8,000.00 $8,000.00
33 Restake Sewer&Additional Traffic control cost(Keller Hicks Rd.) Sewer 1.00 LS $5,000.00 $5,000.00
NSII 48"Water $146,338.08
36"Water $8,000.00
Sewer $5,000.00
Page 2 of 4 Additions Sub Total $159,338.08
FORT WoP,TrH City of Fort Worth
Change Order Deletions
Project Name Northside II 48-Inch Water Transmission Main Phase II, Part I City Sec No.: 48783
Project No.(s): 56001-0600430/0700430/C01788 DOE No. N/A City Proj.No.: 02304
Project Description 48-inch Water Main Intersection from Heritage Trace Parkway/Harmon Road Intersection to Wagley Roberston
Road
Contractor S.J.Louis Construction of Texas, Ltd. Change Order: 111 Date 3/20/2019
City Project Mgr. I John Kasavich City Inspector: Raymond Brice
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
16 Temporary Asphalt Paving Repair 36"Water 458.00 LF $41.00 $18,778.00
27 21"RCP Class III NSII 48"Water 4.00 LF $87.00 $348.00
28 24"RCP Class III NSII 48"Water 8.00 LF $96.00 $768.00
29 27"RCP Class III NSII 48"Water 20.00 LF $104.00 $2,080.00
30 30"RCP Class III NSII 48"Water 20.00 LF $110.00 $2,200.00
31 39"RCP Class III NSII 48"Water 20.00 LF $160.00 $3,200.00
32 48"RCP Class III NSII 48"Water 30.00 LF $210.00 $6,300.00
53 Construction Contingency NSII 48"Water 0,41888 LS $300,000.00 $125,664.00
NSII 48"Water $140,560.00
36"Water $18,778.00
rDewletlons
erPage 3 of 4 Sub Total 1$159,338.00
MWWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 4 of 4
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
Signature
Name of Employee
Title
OFFICIAL RECORD
a
CITY SECRETARY
T. WORTH,TX